Contract No. HY/2013/04
HZMB HKBCF – Infrastructure Works Stage II (Southern Portion)

Spill Response Plan

May 2015

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Certification by Environmental Team Leader

 

Verification by Independent Environmental Checker

 

 

 

 


 


 

 

 

Information Class:

Standard

This document is issued for the party which commissioned it and for specific purposes connected with the above-captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

This document contains confidential information and proprietary intellectual property. It should not be shown to other parties without consent from us and from the party which commissioned it.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Contents

 

 

 

Chapter    Title                                                                                                                           Page

1.1______ Background_____________________________________________________________________ 1

1.2______ Project Description_______________________________________________________________ 1

1.3______ Purpose & Scope_________________________________________________________________ 1

1.4______ Report Structure__________________________________________________________________ 2

2.1______ General________________________________________________________________________ 3

2.2______ Responsibilities of Key Personnel____________________________________________________ 3

2.2.1_____ Emergency Team Leader__________________________________________________________ 3

2.2.2_____ Emergency Team Coordinator______________________________________________________ 3

2.2.3_____ Safety Manager (SM) / Safety Officer (SO)______________________________________________ 3

2.2.4_____ Environmental Officer (EO) / Environmental Supervisor (ES)________________________________ 4

2.2.5_____ Foremen_______________________________________________________________________ 4

2.2.6_____ Onsite Workers__________________________________________________________________ 4

2.3______ Emergency Team Organization______________________________________________________ 4

3.1______ General Precautions______________________________________________________________ 6

3.2______ Chemicals, Oils and Fuels__________________________________________________________ 6

4.1______ General________________________________________________________________________ 8

4.2______ Construction Phase Spill Response___________________________________________________ 8

4.2.1_____ Oil or Hazardous Chemicals Spill on Land or on Deck of Marine Vessel_______________________ 8

4.2.2_____ Oil or Hazardous Chemicals Spill into Marine Environment_________________________________ 9

4.3______ Dolphin Contingency Plan_________________________________________________________ 12

4.4______ Sensitive Receivers______________________________________________________________ 12

5.1______ Training_______________________________________________________________________ 13

5.2______ Spill Control Equipment___________________________________________________________ 13

5.3______ Drills_________________________________________________________________________ 14

5.4______ Spillage Incident Report___________________________________________________________ 14

5.5______ Review and Update______________________________________________________________ 14

6.1______ Emergency Contacts_____________________________________________________________ 15

Appendices                                                                                                                                   18

Appendix A. Site Layout Plan________________________________________________________________ 19

Appendix B. Standard Spill Kit Details__________________________________________________________ 20

 

Tables

Table 5.1:__ Spill Related Training Topics 13

Table 6.1:__ Project / Environmental Team Contact List 15

Table 6.2:__ Emergency Team Contact List 15

Table 6.3:__ Government Department Contract List 15

Table 6.4:__ Utility Company Contract List 16

 

Figures

Figure 2.1:_ Emergency Team Organization Chart for Spillage Incidents 5

Figure 4.1:_ Overall Oil / Hazardous Chemicals Spill Response Procedure_ 11

 

 


1             Introduction

 

 

 

1.1            Background

This Spill Response Plan (SRP) is prepared for the Contract No. HY/2013/04Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities Infrastructure Works Stage II (Southern Portion)” (the Contract) for the Highways Departments of HKSAR Government.

The Contract is part of the Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities” (HZMB HKBCF) Project which is a “Designated Project under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009) was prepared and approved. The current Environmental Permit (EP) for HKBCF, namely No. EP-353/2009/H, was issued on 19 January 2015. These documents are available through the Environmental Impact Assessment Ordinance Register. The site layout plan is presented in the Appendix A.

1.2            Project Description

The Proposed works under this Contract comprise the following:

¡  Construction of vehicular bridge and at-grade roads at the southern portion of Hong Kong Boundary Crossing Facilities;

¡  Construction of associated street lighting, street furniture, road marking, road signage, box culverts and outfalls, drainage, sewerage, fresh water and flushing water supply, irrigation, landscape, electrical and mechanical (E&M), utilities and services works;

¡  Provisioning of civil engineering works and power supply for Traffic Control and Surveillance System (TCSS); and

¡  Other works which are shown on the Drawings or specified in the Specification or which may be ordered in accordance with the Contract.

1.3            Purpose & Scope

As specified in Condition 2.7 of the EP:

“The Permit Holder shall deposit with the Director at least 1 month before the commencement of construction of the Protect, three hard copies and one electronic copy of a Spill Response Plan detailing the actions to be taken in the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Project, with specific provisions for protecting marine ecology and the Chinese White Dolphins.”

This SRP is to establish the requirements for effective emergency preparedness and response to spillage incidents and has been prepared in accordance with the EP requirements. The aim of this Plan is to provide the framework for enabling the following:

¡  Identify the responsible parties involved;

¡  Identify the precautionary measures required;

¡  Specify the procedures for timely and effective responses to spill incident;

¡  Specify the requirements for spill cleanup and reporting; and

¡  Specify the measures to protect sensitive receivers from adverse impacts due to spills.

1.4            Report Structure

Following this introductory section, the report is structured as follows:

Section 2          Roles and Responsibilities

Section 3          Spill Prevention Measures

Section 4          Spill Response Procedures

Section 5          Spill Response Plan Implementation

Section 6          Relevant Parties Contact List

 

 

2             Roles and Responsibilities

 

 

 

2.1            General

Prevention and actions in relation to spillage incidents are the responsibility of the designated Emergency Team. The organisation of the Emergency Team and the responsibilities of the key personnel during an emergency spill response are described under this section.

2.2            Responsibilities of Key Personnel

2.2.1        Emergency Team Leader

The Emergency Team Leader’s main responsibility is to ensure the SRP is issued and followed by all construction workers of the project. The Emergency Team Leader shall ensure that all construction workers perform their tasks and duties safely and correctly with sufficient resources. During spill response, the Emergency Team Leader shall provide high level direction to the Emergency Team members during any spill event, and maintain communication with China State Construction Engineering (Hong Kong) Limited and other relevant external parties in the event of spillage as mentioned in this SRP.

2.2.2        Emergency Team Coordinator

The Emergency Team Coordinator is mainly responsible for reporting to the Emergency Team Leader and coordinating all health, safety and environmental matters related to the SRP onsite. The Emergency Team Coordinator shall oversee the implementation and performance of the SRP and shall assist the Emergency Team Leader when any spillages occur. All management of environmental issues, staff supervision, control, planning as well as implementing and monitoring necessary remedial actions as related to the SRP shall be the responsibility of the Emergency Team Coordinator with assistance from the Environmental Officer (EO) / Environmental Supervisor (ES).

2.2.3        Safety Manager (SM) / Safety Officer (SO)

The SM / SO is responsible for assisting the Emergency Team Coordinator in all health and safety matters related to this SRP. The SM / SO is also responsible for assisting the EO / ES as part of spill incident / accident investigation.

2.2.4        Environmental Officer (EO) / Environmental Supervisor (ES)

The EO / ES is responsible for assisting the Emergency Team Coordinator to coordinate, monitor and oversee the performance and implementation of the SRP onsite. The EO / ES shall ensure that all construction workers follow the requirements of this SRP and shall provide related spill prevention and response training to all construction workers. The EO / ES shall conduct a spill incident / accident investigation when required, and shall review and update the SRP on a regular basis.

2.2.5        Foremen

The Foremen are responsible for assisting in daily implementation of the SRP, site supervision and coordination of individual construction works as well as implementation of any remedial actions or environmental protection measures as directed by the EO / ES and/or Emergency Team Coordinator in relation to spill response and cleanup in accordance with the SRP. The Foremen are also responsible for reporting all spillage incidences immediately to the EO / ES and Emergency Team Coordinator, and ensuring that all workers comply with this SRP onsite.

2.2.6        Onsite Workers

All onsite construction workers are responsible for complying with the SRP and following the instructions of the Foremen as related to this SRP. All workers are required to attend training provided by the EO / ES to ensure construction materials, chemicals and wastes are handled and stored properly onsite as required by the EIA and the SRP. Workers are required to properly use the spill kits to collect and store the spillage wastes generated during cleanup of any spills as directed in this SRP where applicable. Workers are also responsible for reporting immediately to the Foremen any incidences that occurred during the site works. 

2.3            Emergency Team Organization

The typical Emergency Team organization chart for spillage incidences is presented in Figure 2.1.

Figure 2.1:     Emergency Team Organization Chart for Spillage Incidents

 

3             Spill Prevention Measures

 

 

 

3.1            General Precautions

The following general precautionary measures shall be applied to all construction works areas to minimise the risk of accidental spillage:

¡  Maintain good site housekeeping practices and ensure all materials, chemicals and wastes are properly stored and placed in appropriate disposal areas onsite at the end of each day.

¡  Avoid disorder and storage of unnecessary materials in working areas.

¡  Open flames and smoking is prohibited within the construction site; smoking is permitted only at designated smoking areas.

¡  Stacked containers should be secured from falling.

¡  Large / heavy containers should be stored on the floor as far as possible to prevent falling.

3.2            Chemicals, Oils and Fuels

For chemicals, oils and fuels required and used onsite, the following measures shall be applied.

For procurement:

¡  Label all chemical storage containers and tanks in accordance with the Environmental Protection Department (EPD) ‘Code of Practice on the Package, Labelling and Storage of Chemical Wastes’.

¡  An up to date list of chemicals, chemical waste and fuel oil should be maintained.

For storage:

¡  Suitable container should be used which are resistant to the stored oil fuel, chemical / chemical waste to avoid leakage.

¡  Containers should be checked before use and container lids should be closed tightly to avoid leakage of chemicals and chemical waste.

¡  Chemical waste storage areas should be located in a designated area that is sheltered on at least 3 sides and the top, and is locked and kept clean and free from obstruction.

¡  Incompatible chemicals should be separated.

¡  Chemical, oil and fuel containers should be kept under eyelevel as far as possible.

¡  Drip trays or bunds should be used for storage containers of chemicals and oil / fuel tanks and should have a capacity equal to 110 % of the storage capacity of the largest tank.

¡  Chemical storage area and drip trays should be inspected daily to ensure the containers are in good condition.

¡  Where chemicals are temporarily taken outside the sheltered chemical storage area, the chemicals including the drip trays / bund should be covered by waterproof tarpaulins and kept free of rainwater.

¡  The chemical storage area should be locked.

¡  Suitable fire-fighting, spill response materials should be provided in the storage areas or the vicinity of the storage areas.

For transfer / transport:

¡  Pumps should be used to transfer large quantities of oil, fuel, chemical / chemical wastes instead of pouring.

¡  Oil, fuel, chemical / chemical wastes should be transferred slowly to prevent spillage or overfilling.

¡  Suitable trolley should be used to transport chemicals / chemical wastes to other location.

¡  Storage containers should be checked to ensure they are tightly sealed with no leakage before transport to other location.

 

 

4             Spill Response Procedures

 

 

 

4.1            General

In the event of a spillage incident, the spill response needs to be carried out promptly and efficiently according to the spillage location, type of spill and quantity of spill. An effective spill response can prevent adverse impacts to the environment and may also minimize the quantity of release into the environment. The spill responses for different spillage types and scenarios are discussed in the following sections.

4.2            Construction Phase Spill Response

When a spill occurs, the worker shall inform the Emergency Team to proceed with the appropriate spill response immediately. The worker shall report the following to the Emergency Team:

¡  The location of the spill;

¡  Nature of the affected location (e.g. concrete, dirt, marine environment);

¡  When the spill occurred;

¡  The type of spill (e.g. oil, chemical, hazardous materials, suspended solid); and

¡  The approximate quantity and size of the spill.

After receiving the description of the spill from the worker, the Emergency Team shall proceed with the appropriate spill response according to the relevant scenario described below.

4.2.1        Oil or Hazardous Chemicals Spill on Land or on Deck of Marine Vessel

For spillage area less than 100m2

1.     Worker shall take immediate measures (in line with spill response training) to stop the source of the spill if the source is obvious and it is safe to do so, and inform the Emergency Team of the spill incident;

2.     Emergency Team Leader shall inform all relevant parties such as Engineer’s Representative (ER), Environmental Team (ET) and Independent Environmental Checker (IEC) immediately and keep such parties informed throughout the spill response;

3.     Emergency Team Leader / Coordinator shall organize the manpower to identify / check the source of the spill and provide instructions for stopping / containing the spill;

4.     Worker shall stop, reduce, isolate or contain the spillage if possible measures can be taken (e.g. turn off the valve);

5.     Worker shall install forced ventilation to ensure a safe spillage condition is provided, where applicable;

6.     Emergency Team member shall appoint well-trained cleanup crew to cleanup the spillage area;

7.     Emergency Team member shall review relevant Material Safety Data Sheet (MSDS) for the chemical spill. The MSDS would have specific instruction on how to deal with chemical spill;

8.     Emergency Team member shall ensure all the workers involved in the cleanup works are equipped with suitable personal protective equipment (PPE);

9.     The spilt material shall be put back into the containers of origin, if possible and practical. Otherwise dry sand, sawdust or other suitable materials shall be used to absorb the spill;

10.  Any contaminated materials shall be collected and put in a bag and clearly marked as “Chemical Waste”;

11.  All collected chemical waste shall be stored in designated chemical waste area;

12.  EO / ES shall carry out spill investigation and submit the spill incident report to the ENPO, ER, ET and IEC within 2 days.

For spillage area greater than 100m2

1.     Worker shall immediately inform the Emergency Team of the spill incident;

2.     Emergency Team Leader shall inform all relevant parties such as EPD, Highways Department (HyD), ER, ET and IEC immediately and keep such parties informed throughout the spill response;

3.     Follow item nos. 3 to 11 of the spill response for spillage area less than 100m2; and

4.     The SM / SO and EO / ES shall carry out joint spill investigation and submit  the spill incident report to the ENPO, ER, ET and IEC within 2 days with provisions for improvement measures / practices to prevent re-occurrence and update this SRP if necessary.

4.2.2        Oil or Hazardous Chemicals Spill into Marine Environment

When oil or other hazardous materials are spilt into the marine environment, the spill could be spread out quickly due to the water current and wind speed, therefore, a timely and effectively spill response shall be implemented in order to minimize the impacts to the marine environment.

For spillage area less than 100m2

1.     Worker shall take immediate measures (in line with spill response training) to stop the source of the spill if the source is obvious and it is safe to do so, and inform the Emergency Team of the spill incident;

2.     Emergency Team Leader shall inform all relevant parties such as ER, ET and IEC immediately and keep such parties informed throughout the spill response;

3.     Emergency Team Leader / Coordinator shall organize the manpower to identify / check the source of the spill and provide instructions for stopping / containing the spill;

4.     Worker shall stop, reduce, isolate or contain the spillage if possible measures can be taken (e.g. deploy containment booms);

5.     Worker shall isolate nearby sensitive receivers from the spillage area as an additional precaution if required (e.g. deploy perimeter booms around seawater intakes);

6.     Emergency Team member shall appoint well-trained cleanup crew to cleanup the spillage area;

7.     Emergency Team member shall ensure all the workers involved in the cleanup works are equipped with suitable PPE;

8.     Absorption materials such as pads or pillow shall be used to absorb the spillage;

9.     Any contaminated materials shall be collected and put in a spill containment and clearly marked as “ Chemical Waste”;

10.  All collected chemical waste shall be stored in designated chemical waste area;

11.  The ET shall review whether additional water quality monitoring is necessary to ascertain whether the spill has resulted in any exceedances at nearby sensitive receivers;

12.  EO / ES shall carry out spill investigation and submit the spill incident report to the ENPO, ER, ET and IEC within 2 days.

For spillage area greater than 100m2

1.     Worker shall immediately inform the Emergency Team of the spill incident;

2.     Emergency Team Leader shall inform all relevant parties such as EPD, HyD, Marine Department (MD), Agriculture Fisheries and Conservation Department (AFCD), Fire Services Department (FSD), ER, ET and IEC immediately and keep such parties informed throughout the spill response;

3.     Follow item nos. 3 to 11 of the above spill responses for spillage area less than 100m2;

4.     Implement the specific dolphin contingency as per Section 4.3 and the procedures for protection of sensitive receivers as per Section 4.4; 

5.     The SM / SO and EO / ES shall carry out joint spill investigation and submitted the spill incident report to the ENPO, ER, ET and IEC within 2 days with provisions for improvement measures / practices to prevent re-occurrence and update this SRP if necessary.

The overall process for oil and hazardous chemical spill procedures is presented in Figure 4.1.

Figure 4.1:     Overall Oil / Hazardous Chemicals Spill Response Procedure

 

4.3            Dolphin Contingency Plan

Chinese White Dolphin (CWD) is commonly found within the western waters in Hong Kong. If a spill of oil / hazardous chemicals occurs in the marine environment and spreads over a large area, the health and wellbeing of CWD might be endangered. As such, a Dolphin Contingency Plan shall be implemented for large scale oil / hazardous chemicals spills released into marine environment.

When a large scale spill occurs, the worker shall inform the Emergency Team to proceed with the Dolphin Contingency Plan immediately as follows:

1.     The EO / ES shall determine the location and approximate extent of the spill from a high platform;

2.     The dolphin watchers shall check whether any CWD is present in the vicinity of the spill, if possible;

3.     The Emergency Team Leader shall ensure the appropriate spill response measures are implemented. These may include:

a.     Containment booms to minimise the spread of spill. This helps to prevent the CWD from coming into contact with the spill and can act as a visual barrier to prevent the CWD from entering the contaminated area;

b.    Underwater barrier nets to isolate the CWD from the spill area, if necessary; and

c.     Absorption materials such as pads or pillow to clean up the spillage as soon as possible.

4.     The dolphin watchers shall maintain watch of the spillage area until the spill is completely cleaned up. If dolphins are found to be entering into the contained spillage areas, the Emergency Team Leader / Emergency Team Coordinator shall contact the ET and seek their advice for appropriate actions.

4.4            Sensitive Receivers

When a large scale spill occurs, the following procedures will be taken in order to protect sensitive receivers within the vicinity of the project site:

1.     Affected sensitive receivers such as seawater intakes, ecological sensitive receivers, fisheries and fish culture zones, corals and bathing beaches shall be identified.

2.     Absorbent booms or other similar booms shall be used in order to surround and protect the sensitive receivers.

3.     The Emergency Team Leader shall immediately inform the relevant parties as mentioned in Section 4.2.

4.     The Emergency Team shall implement all possible mitigation measures in order to isolate the spill and minimize any potential adverse impacts to the sensitive receivers.

5.     The ET shall implement additional monitoring if necessary to determine any potential adverse impacts to the sensitive receivers.

 

5             Spill Response Plan Implementation

 

 

 

5.1            Training

All construction site workers shall be introduced to the SRP during the environmental induction training and Tool Box talks which should be carried out by the EO / ES for each construction site. During the induction training and Tool Box talks, a demonstration of the containment methods and equipment shall be carried out by the EO / ES. The EO / ES shall conduct Tool Box talks with the site workers regarding the SRP periodically. Examples of spill related training topics are shown in Table 5.1. The Emergency Team Leader shall ensure that all relevant workers receive the appropriate spill related training prior to undertaking activities that may lead to spillage or involve spill response. A training record shall be maintained by the EO / ES to register the training provided and each individual’s signoff to acknowledge that the training has been attended and the content is understood.

Table 5.1:      Spill Related Training Topics

Training Topic

Applicable Personnel

Introduction to the SRP and its requirements on spill response

All construction site workers

Work safety around the spill

All construction site workers

Containment of spill

All construction site workers

Recovery and cleanup of spill

Spill cleanup crew

Handling and disposal of waste generated from spill

Spill cleanup crew

5.2            Spill Control Equipment

At least one set of spill kit should be provided and stored onsite near to each storage area for chemicals or chemical waste. At least three sets of spill kits should be available aboard each vessel if involved in marine works. Additional one set of spill kit should be located near to the EO / ES office. Additional spill kits should also be provided onsite at locations or activities with a higher risk of spills. The EO / ES shall ensure that sufficient spill kits are available onsite at all times. The EO / ES shall also notify the Foremen and onsite workers of the locations of spill kits. The spill kit shall include, but are not limited to the following items:

¡  Oil absorbent pads;

¡  Oil absorbent socks;

¡  Sorbent booms;

¡  Sweeps;

¡  Goggles;

¡  Protective masks;

¡  Nitrile gloves;

¡  Disposal bags; and

¡  Instruction sheets.

The standard spill kit details are shown in Appendix B.

5.3            Drills

Regular drills would be carried out to ensure all site workers, especially the Emergency Team members, are proficient in his/her assigned duties. Where applicable, spill incidents will be simulated, drilled and practiced at least annually. Relevant authorities such as FSD, MD, AFCD and Hong Kong Police Force would be invited to participate and/or witness the drill exercises.

5.4            Spillage Incident Report

The EO / ES shall prepare a spillage incident report for submission to ENPO, ER, ET and IEC within 2 days after the incident occurred. The report will investigate the reasons for the spillage and evaluate the effectiveness of the procedures and precautionary measures taken and specified in this SRP. Where applicable, additional mitigation measures will be proposed and implemented to prevent similar occurrence of spillage. The incident report should include but are not limited to the following:

¡  Details of the spillage incident;

¡  Clean up actions taken;

¡  Any residues of the spill remaining in the environment;

¡  Follow up or monitoring actions taken if required; and

¡  Photo records.

5.5            Review and Update

The spill response procedures in this SRP should be reviewed after every spill incident and/or spill response drill, and at least annually, and relevant procedures and measures shall be updated as required.

 

 

6             Relevant Parties Contact List

 

 

 

6.1            Emergency Contacts

The following tables (Table 6.1 to Table 6.4) provide the names and telephone contacts of various parties who should be contacted in case of a spill incident or emergency.

Table 6.1:      Project / Environmental Team Contact List

Role

Name

Contact No.

Employer’s Representative (ER)

Ir Lee Ping Kuen, JP

6329 8443

 

Miranda Wong

9212 3668

Independent Environmental Checker (IEC)

Raymond Dai

5181 8401

Environmental Team Leader (ETL)

Terence Kong

2828 5919

Table 6.2:      Emergency Team Contact List

Role

Name

Contact No.

Emergency Team Leader

P Z Zhou

6746 4151

Emergency Team Coordinator

Eddie Tang

9863 7686

Safety Manager

K K Chiu

9048 7948

Environmental Officer / Environmental Supervisor

Gary Ng

9475 6832

Foreman

T K Tam

6101 1113

Table 6.3:      Government Department Contract List

Government Department

Contact No.

General Emergency Services

999

Highways Department

2926 4111

Labour Department

2717 1717

Fire Services Department

2302 5373

Agriculture, Fisheries and Conservation Department

2708 8885

Environmental Protection Department

2838 3111

Marine Department

2542 3711

Vessel Traffic Centre

2233 7801

Maritime Rescue Coordination Centre

2233 7999

Fire Station

Tung Chung Fire Station: 2988 1898

Chek Lap Kok Fire Station: 2949 9081

Ambulance

Tung Chung Ambulance Depot: 2988 8282

Hospital

North Lantau Hospital: 3467 7000

Table 6.4:      Utility Company Contract List

Utility Company

Contact No.

CLP Power Hong Kong Limited

2728 8333

The Hong Kong and China Gas Company Limited

2880 6999


 

The emergency contact list shall be reviewed annually. Any changes should be amended and notified to all onsite staff immediately.


 

 

 

Appendices

 

 

 

 

Appendix A. Site Layout Plan________________________________________________________________ 19

Appendix B. Standard Spill Kit Details__________________________________________________________ 20

 

 

 

 

 

Appendix A.           Site Layout Plan

 

 

 

 

 

 

 

Appendix B.           Standard Spill Kit Details