1.1.1 This Waste Management Plan is prepared
for Contract HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between Scenic Hill and Hong Kong Boundary Facilities (¡§the Contract¡¨)
for the Highways Department of HKSAR. The Contract is part of the
Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Link Road (HKLR) Project and Hong
Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF),
these projects are considered to be ¡§Designated Projects¡¨, under Schedule 2 of
the Environmental Impact Assessment (EIA) Ordinance (Cap 499) and Environmental
Impact Assessment (EIA) Reports (Register No. AEIAR-144/2009 and
AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/A for HKLR and EP-353/2009/D for HKBCF were issued on 31 October
2011 and 7 March 2012, respectively. These documents are available
through the EIA Ordinance Register.
1.1.2 Condition 2.12 of EP-352/2009/A and
Condition 2.10 of EP-353/2009/D state: ¡§The Permit Holder shall deposit with
the Director, at least one month before the commencement of the construction of
the project, three hard copies and one electronic copy of a waste management
plan (WMP) for the construction stage of the Project. The WMP shall describe the arrangements
for avoidance, reuse, recovery and recycling, storage, collection, treatment
and disposal of different categories of waste to be generated from the
construction activities and shall include the recommended mitigation measures
on waste management in the EIA Report.
The WMP shall indicate the disposal location(s) of all surplus excavated
spoil and other waste. A trip
ticket system (TTS) shall be included in the WMP. Surplus excavated spoil and
other wastes shall only be disposed of at designated disposal locations unless
otherwise approved by the Director.
All measures recommended in the WMP shall be fully and properly
implemented by the Permit Holder and any person working on the Project
throughout the construction period.
1.2.1 This WMP applies to the works
undertaken by China State Construction Engineering Hong Kong Ltd. (CSHK) for
the Contract. A Site Location Plan
is provided as Appendix A. The works include:
l New reclamation along the east coast of the Hong Kong International
Airport (HKIA), approximately 23 hectares.
l Tunnel SHT from Scenic Hill to the new reclamation, of approximately
1km in length with three (3) lanes for the east bound carriageway heading to
the HKBCF and four (4) lanes for the westbound carriageway heading to the Hong
Kong Zhuhai Macao Bridge (HZMB) Main Bridge.
l An abutment of the viaduct portion of the HKLR at the west portal of
Tunnel SHT and associated road works at the west portal of Tunnel SHT.
l An at grade road on the new reclamation along the east coast of the
HKIA to connect with the Hong Kong Boundary Crossing Facilities (HKBCF), of
approximately 1.6 km along dual 3-lane carriageway with hard shoulder for each
bound.
l Road links between the HKBCF and the HKIA including new roads and
the modification of existing roads at the HKIA, involving viaducts, at grade
roads and a Tunnel HAT.
l A highway operation and maintenance area (HMA) located on the new
reclamation, south of the Dragonair Headquarters Building, including the
construction of buildings, connection roads and other associated facilities.
l Associated civil, structural, building, geotechnical, marine,
environmental protection, landscaping, drainage and sewerage, tunnel and
highway electrical and mechanical works, together with the installation of
street lightings, traffic aids and sign gantries, water mains and fire
hydrants, provision of facilities for installation of traffic control and
surveillance system (TCSS), reprovisioning works of affected existing
facilities, implementation of transplanting, compensatory planting and
protection of existing trees, and implementation of an environmental monitoring
and audit (EM&A) program.
1.3.1 This WMP will describe the
arrangements for avoidance, minimization, handling, reuse, recovery and
recycling, storage, transportation, collection, treatment and disposal of the
different categories of waste that are expected to be generated during the
construction activities of the Contract.
This WMP includes the recommended mitigation measures on waste management
that are contained in the EIA report and EM&A manual.
1.3.2 The main objectives of this WMP are
to:
l Provide reference to the applicable environmental legislation and
guidelines pertaining to waste management.
l Clarify each party¡¦s responsibilities regarding waste management,
and identify the personnel from each party that are assigned these
responsibilities and their respective role on the Contract.
l Establish waste management practices and treatment procedures, for
the avoidance, minimization, material reuse/recovery/recycling, collection,
transportation, storage and disposal of wastes that are generated during the
course of the Contract that are specified by the EP and the implementation of
the mitigation measures that are outlined in the EIA report.
1.4.1 An Environmental
Policy has been established by CSHK to outline guidance, technical information,
and instructions to designated personnel who will be responsible for the
management of site environmental issues, and to ensure that all statutory and contractual environmental requirements and the
Company Environmental Policy are followed. In addition, CSHK will create an
Environmental Management Team (EMT) for establishing and implementing effective
and efficient environmental protection procedures for the Contractor.
1.4.2 The Environmental
Policy Statement, together with the Environmental Objectives and Targets, are listed below in the CSHK Environmental
Policy:
1.5.1 CSHK aims to
recover, avoid and minimize the construction waste generated on site by
utilizing the hierarchy illustrated below.
This attempts to evaluate waste management practices and selects the best practical option since
conceptually it makes sense to avoid producing a
waste rather than developing extensive treatment schemes. Through good planning, and effective
site management practices, CSHK will minimise the amount of construction waste
that is generated. The objective of CSHK is to reduce and
minimize the amount of wastes generated and hence minimise the costs associated with
subsequent waste handling and disposal.
1.6.1 During the
course of the Contract, it is anticipated that various types of waste will be
generated. Each
distinct waste type will require a different approach for the effective
management and disposal as stipulated
in the applicable legislation and guidelines.
1.6.2 The following legislation relates to
the handling, treatment and disposal of waste in Hong Kong:
l The Waste Disposal (Amendment) Ordinance (WDO) (Cap 354).
l The Waste Disposal (Chemical Waste) (General) Regulation (Cap
354).
l The Waste Disposal (Charges for Disposal of Construction Waste) Regulation.
l The Land (Miscellaneous Provisions) Ordinance (Cap 28).
l The Dumping at Sea Ordinance (Cap 466).
l The Public Health and Municipal Services Ordinance (Cap 132) -
Public Cleansing and Prevention of Nuisances (Urban Council) and (Regional
Council) By-Laws.
l Summary Offences Ordinance (Cap 228).
l Other relevant regulations.
1.6.3 The WDO
prohibits the unauthorized disposal of waste. Construction waste is not directly
defined in the WDO, but is considered
to fall within the category of ¡§trade waste¡¨. Under the WDO, wastes can only be disposed of at sites licensed by
the Environmental Protection Department (EPD).
1.6.4 Under the WDO and the Charging
Regulation, wastes can only be disposed of at designated waste disposal
facilities that are licensed by the EPD.
For construction work with a value of more than
HK$1M, the main contractor is required to establish a billing account at the EPD before transporting the
construction waste to the designated waste disposal
facilities (e.g. landfill, public fill etc.). The vessels for delivering
construction waste to a public fill reception facility would need prior
approval from EPD. Breach of these
regulations can lead to a fine and/or
imprisonment.
1.6.5 Under the Waste Disposal (Chemical Waste) (General)
Regulation all producers of chemical wastes
(including asbestos) must register with the EPD and treat their wastes either utilizing on-site plant licensed by the EPD,
or arranging for a licensed collector transport
the wastes to an appropriately licensed facility. The regulation also
prescribes the storage facilities to be provided on site, including labelling and
warning signs, and requires the preparation of written procedures and training
to deal with emergencies such as spillages, leakages, or accidents arising from the storage of chemical wastes.
1.6.6 The current policy
related to the dumping of construction and demolition (C&D) material is
documented in the Works Branch Technical Circular
No. 2/93, ¡¥Public Dumps¡¦. C&D materials that are wholly inert, namely public
fill, should not be disposed of at landfill, but should be taken to public
filling areas, which usually form part of reclamation schemes.
1.6.7 The Land
(Miscellaneous Provisions) Ordinance requires
that dumping licenses be obtained by individuals or companies who deliver public fill to public filling areas. The Civil Engineering & Development Department
(CEDD) issues the licenses under delegated powers from the Director of Lands.
1.6.8 Under the Dumping
at Sea Ordinance, a permit from the EPD is required if any waste generator intends
to dump materials at sea. Cross
boundary disposal of waste is also possible for this contract under permit
issued by the State Oceanic Administration PRC (SAO).
1.6.9 The Public
Cleansing and Prevention of Nuisances By-Laws provide further controls on the illegal tipping of wastes on unauthorized (unlicensed)
sites.
1.6.10 The Contractor is
required to obtain all necessary permits and licenses under these ordinances
including, but not limited to:
l Chemical waste permits/licenses under the Waste Disposal Ordinance (Cap
354).
l Public Dumping License under the Land (Miscellaneous Provisions)
Ordinance (Cap 28).
l The Dumping at Sea Ordinance (Cap 466).
1.6.11 The following guidelines related to
waste management and disposal would be adhered
to during construction:
l Waste Disposal Plan for Hong Kong (1989), Planning, Environmental
and Lands Branch Government Secretariat.
l Environmental Guidelines for Planning in Hong Kong. Hong Kong planning Standards and
Guidelines (1990).
l New disposal Arrangements for Construction Waste, EPD and CEDD
(1992).
l Code of Practice on the Packaging, Labelling and storage of Chemical
Wastes EPD (1992).
l Code of Practice on the Handling, Transportation and Disposal of
Asbestos Waste, EPD.
l Works Branch Technical Circular No. 12/2000, Fill Management, Works
Bureau, HKSAR Government.
l Works Branch Technical Circular No. 19/2005, Environmental
Management on Construction Site, Works Bureau, HKSAR Government.
l Environment, Transport and Works Bureau Technical Circular (Works)
No. 34/2002, Management of Dredged/Excavated Sediment, Environment, Transport
and Works Bureau, HKSAR Government.
l Works Branch Technical Circular, 32/92, the Use of Tropical Hard
Wood on Construction Site, Works Branch, HKSAR Government.
l Works Branch Technical Circular No. 2/93, Public Dumps, Works
Branch, Hong Kong Government.
l Works Branch Technical Circular No. 16/96, Wet Soil in Public Dumps,
Works Branch, Hong Kong Government.
l Works Bureau Technical Circular No. 4/98 and No.4/98A, Use of Public
Fill in Reclamation and Earth Filling Projects, Works Bureau, HKSAR Government.
l Works Bureau Technical Circular No. 5/98, On-site sorting of
Construction Waste on Demolition Site, Works Bureau, HKSAR Government.
l Environment, Transport and Works Bureau Technical Circular (Works)
No. 33/2002, Management of
Construction and Demolition
Material including Rock, Environment, Transport and Works Bureau, HKSAR
Government.
l Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment
and Lands Bureau, Government Secretariat, 5 November 1998.
l Works Bureau Technical Circular No. 6/2002 and 6/2002A, Enhanced
Specification for Site Cleanliness and Tidiness, Works Bureau, HKSAR
Government.
l Works Bureau Technical Circular No. 25/99, 25/99A and
25/99C.Incorporation of Information on Construction and Demolition Material
Management in Public Works Sub-committee Papers, Works Bureau, HKSAR
Government.
l A Guide to the Registration of Chemical Waste Producers and Guide to
the Chemical Waste Control Scheme.
2
Site Organization and Staff Duties
2.1.1
The
organization structure for waste management onsite is outlined in Figure
1. This structure outlines the overall
site management in relation to waste management and the associated
environmental issues. Details on the roles and
responsibilities of staff members responsible for the implementation of the WMP are outlined in the CSHK
organizational chart for waste management below:
2.2.1
The
Project Director (PD) is responsible for coordinating all environmental matters
on site and reporting on these matters to the CSHK EMT. Approve (internally) the WMP and ensure
adequate resources for the implementation of the WMP.
2.2.2 The Project Manager
(PM) is responsible for ensuring commitment to the WMP and assigning the
necessary resources
for its effective implementation.
2.2.3 The Deputy Project
Manager (DPM) is also responsible for ensuring commitment to the WMP and
assisting the PM in assigning the necessary resources for its effective
implementation.
2.2.4
The Safety and Environmental Manager (S&EM) is
also responsible for ensuring commitment to environmental performance with the WMP, and
assists the PM and DPM in assigning adequate resources for the implementation
and operation of the WMP.
2.2.5
The Construction Manager (CM) reports to the PD, and
has the responsibility
to coordinate all environmental matters related to the WMP. The CM is also responsible for all site operations,
management of environmental issues, staff supervision,
control, coordination & planning, external liaison as well as implementing
and monitoring corrective actions related to the WMP.
2.2.6
The
CM, when necessary, will also carry out immediate corrective action to rectify
any non-compliance
of environmental requirements of the WMP, as well as handle any complaints that
are received from the public regarding the
WMP.
2.2.7
The
CM will also assist the EO in overseeing the implementation
and performance of the WMP. The CM
would also assist with environmental duties onsite and ensure that works are executed in accordance with the
WMP. The CM will arrange regular
site inspections with the EO.
2.2.8
The
EO will be appointed on site for the overall coordination, monitoring,
oversight and implementation of the WMP for the duration of the contract. The EO directly reports to the
S&EM. The responsibilities of the EO include, but are not limited to:
l Review of the Site Management Plan for Implementation of the TTS and
ensure works are executed in accordance with the plan.
l Monitor onsite work to ensure compliance with the environmental
requirements for the site.
l Assist the CM in handling any complaints that are received.
l Ensure that the required environmental monitoring is carried out,
and that all environmental monitoring results are recorded.
l Carrying out waste management training.
2.2.9 The Engineers shall:
l Coordinate with the EO regarding the implementation of all
appropriate environmental mitigation measures.
l Coordinate with the EO to make sure that all the applicable
environmental licenses and permits are identified and allowed for in the
program of work.
2.2.10
The
Environmental Supervisor (ES) is responsible for the implementation of the WMP
with the assistance of the Foremen. The ES is also responsible for:
l Assisting the EO to rectify any non-conformances with the
environmental requirements of this WMP that are identified onsite.
l Attend environmental meetings related to waste management when
necessary.
l Carry out environmental site inspections with the EO when
deficiencies in waste management are identified.
l Assist the EO with any environmental accidents, such as the release
of chemicals.
2.2.11
The
foremen are responsible for onsite supervision, the coordination
of the works as well as the implementation of any corrective actions as directed by the CM/EO. The
Foremen are also responsible for:
l Assisting in the daily implementation of the WMP including the
sorting and segregation of construction waste in to separate stockpiles/staging
areas and where possible the recycling (via recycling containers) or reusing
materials.
l Ensuring that the trip-ticket system is followed and that all
paperwork (e.g. CHIT / Disposal Delivery Form (DDF)) is signed, completed and
collected.
l Ensuring that, where possible, the generation of waste is avoided or
minimized.
2.2.12
The
onsite workers are expected to follow the practices that are outlined in the
WMP. They are obligated to
complete certain specific tasks, such as:
l The sorting of different types of wastes that are generated during
construction.
l The collection of sorted wastes from work areas to the temporary
storage area/designated fill banks/landfills.
l General site cleaning and upkeep.
l Attending waste management training that is organized by the EO.
3
Site Specific Waste Management
3.1.1
The
key to successful waste management is undertaking proactive measures to reduce
the amount of waste generated.
Waste management options will be exercised in accordance with the hierarchy outlined in Table 2 below:
Table 2: Hierarchy of
Waste Management
Waste Management Option
|
Required Actions
|
|
|
Avoidance /
Reduction / Minimization
|
Avoid the
generation of excessive waste by planning and scheduling material deliveries.
Minimize the amount
of waste generated through careful planning and design, before commencing the
contract.
|
|
Re-use
|
Where appropriate and
practicable, construction materials such as timber formwork, metal, etc, and
any spoil generated during excavation work should be re-used onsite.
|
|
Recovery and
Recycling
|
Recyclable
construction materials such as plastics and metal will be recovered, sorted
and stored onsite in containers.
The containers will be transported off site for recycling at an
approved facility.
Regularly serviced,
covered recycling containers will be provided for the use of the onsite
workforce.
|
|
Treatment and
Disposal
|
All waste removed
from the site requiring treatment and/or disposal will be transported to an
approved facility.
|
|
3.1.2
To
achieve waste reduction, environmentally responsible purchasing would involve the introduction
of practices that discourage unnecessary purchases and encourage the
purchase of products or materials that can be found locally, that have reduced
packaging or recyclable packaging, increased durability and materials with
recycled content, such as, recycled paper, steel, concrete and other raw construction
materials.
3.1.3 Waste minimization
is best achieved through the use of careful planning, design and close supervision. It is expected that, following good
waste management practices on site will result in a reduction of the amount waste being
generated. To minimize the wastage
of raw materials that are delivered to the site, good management, estimation
and planning techniques will be required.
3.2.1 In order to determine whether the
waste management procedures used by CSHK are effective, the following specific
targets will be implemented onsite in an effort to reduce the generation of
waste materials, and thus minimize the amount of waste requiring disposal at
landfill:
l All excavated material will be sorted on site to recover the inert
portion of construction and demolition debris materials, such as hard rock,
soil and broken concrete, for subsequent re-use on site or disposal to
designated outlets.
l Recover and store all metallic waste (e.g. scrap metal) for
subsequent collection by a recycling contractor and recycling at an approved
facility.
l Recover all cardboard and/or paper packaging (for plant, equipment
and materials) will be stored in covered stockpiles (to keep dry and prevent
contamination) for subsequent collection and recycling at an approved facility.
l All chemical waste that is generated on site (e.g. servicing of
plant) will be stored for collection and disposal at an approved disposal
facility.
l All demolition debris will be sorted on site to recover broken
concrete, reinforcement bars, mechanical and electrical fittings, hardware as
well as other recyclable fittings for subsequent recycling at an approved
facility.
l To minimize the use of timber during construction, recyclable metal
formwork and hoarding will be used where practicable.
3.3.1 CSHK designate suitable areas onsite
for the storage, sorting and segregation of construction waste. The areas that are designated by CSHK
will be clearly defined with appropriate signage and barriers (or similar) and
allow for easy access by workers and vehicles. As the project progresses it is
anticipated that the designated areas will be reviewed depending upon construction
program requirements. The areas designated
by CSHK will be sufficient for the amounts of construction waste that are
anticipated to be generated during the course of the contract.
Table 3 below shows the actions that will be taken for each type of
construction waste generated onsite.
Table 3: Sorting of
C&D Waste
Type of C&D Material
|
Required Action
|
Responsible Party
|
Rock
|
Re-use
on site where possible or recycle off site
|
CSHK
|
Excavated
material
|
Re-use
on site where possible or dispose of at approved landfill facility
|
CSHK
|
Excavated
Marine Deposits
|
Dispose
of offsite at approved location
|
CSHK
|
Concrete
|
Sorted
and segregated onsite, re-use on site where possible or recycle offsite
|
CCHK
/ Subcontractors
|
Metal
|
Segregate
and recycle offsite
|
CSHK
/ Subcontractors
|
Paper/Cardboard
Materials
|
Segregate
and recycle offsite
|
CSHK
/ Subcontractors
|
Plastics
|
Use
recycling containers and recycle offsite
|
CSHK
/ Subcontractors
|
Aluminium
Cans
|
Use
recycling containers and recycle offsite
|
CSHK
/ Subcontractors
|
Timber
|
Re-use
on site if possible, other segregate and recycle off site
|
CSHK
/ Subcontractors
|
Chemical
Waste
|
Store
in approved containers and transport offsite for disposal at an approved
facility
|
CSHK
/ Subcontractors
|
3.4.1
For imported fill materials, CSHK will seek the SO¡¦s
approval prior to
acceptance of such materials from other site(s). To ensure that the fill materials are imported from
approved site(s) and to avoid the potential for illegal disposal of such
materials, a tracking system for imported material will be
developed by CSHK. The tracking
system will be submitted to the SO for approval before commencing importation
of material to the site.
3.4.2
In
order to confirm that the material that is imported to the site complies with
the requirements for General Filling material, as stipulated in the General
Specification for Civil Engineering Works, representative material samples will
be collected for analysis by an approved laboratory. The sampling and testing will be
conducted at the material source, to confirm its
compliance with the requirements.
The test results will be provided for verification and/or
approval by the Supervising Office (SO) and the IEC before the material is allowed to be imported to the site.
3.4.3
The
target fine content of sand fill in the WMP shall not exceed 5% when placed onsite. The target maximum level of the fine
content of the public fill material will be below 25%.
Design, Construction and Operation of Sorting Facilities and Barge
Points
3.4.5 The delivery of imported materials
as part of the reclamation to a formation level of +5.0mPD is estimated to
commence in July 2013. In order to
achieve this formation level the required daily handling rate of imported
material is outlined in Table 4 below. The proposed sorting facilities together
with barge points have been designed to meet this production.
Table 4: The Overall
Quantity of Fill Required for Reclamation
Material
|
Duration
|
Maximum
Daily Fill Rate (m3/day)
|
Sand Fill
|
July 2013 - March 2014
|
4,000
|
Public Fill
|
September 2013 ¡V May 2014
|
5,000
|
Surcharge
|
December 2013 ¡V September 2014
|
8,000
|
Use of Public Fill from Fill Banks and Projects of MTRCL as Source
Material
3.4.6 CSHK will utilize our barges to collect
the fill material from designated barge points.
3.4.7 Owing to the available sorting
facilities, the supply quantities of public fill will be constant and sorted to
the most suitable for reclamation purposes. CSHK will closely coordinate with the
contractors of barging points regarding the schedule of barge for collection of
public fill and the site conditions of the loading facilities to ensure smooth
progress of loading and transporting of public fill to the site.
3.4.8 In order to achieve the daily fill
rates outlined in Table 4, CSHK will
deploy a total of twelve (12) barges.
Details of the barges are outlined in the table below:
Table 5: The Daily
Delivery Capacity of our Planned Fleet
Site
|
Barge Type
|
Barge (No¡¦s)
|
Avg. Capacity per Barge
|
Seawall Reclamation
|
Hopper Barge
|
10
|
350 ¡V 2,000m3
|
Flat Top Barge
|
2
|
4,500T
|
3.4.9 In the above table, the overall logistic
arrangements for barges has sufficient flexibility and takes into account
unforeseen delays due to inclement weather and general holidays. Details of the estimated monthly filling
rates of Public Fill, Sand Fill and Suitable Fill are outlined in Tables 6, 7 and 8 below.
Table 6: Estimated
Monthly Filling Rate for Public Fill Surcharge
Units
|
Dec 13
|
Jan 14
|
Feb 14
|
Mar 14
|
Apr 14
|
May 14
|
Jun 14
|
Jul 14
|
Aug 14
|
Sep 14
|
Ton
|
18,000
|
70,000
|
160,000
|
190,000
|
70,000
|
25,000
|
34,000
|
130,000
|
130,000
|
8,600
|
Table 7: Estimated
Monthly Filling Rate for Sand Fill
Units
|
Jul 13
|
Aug 13
|
Sep 13
|
Oct 13
|
Nov 13
|
Dec 13
|
Jan 14
|
Feb 14
|
Mar 14
|
Apr 14
|
Ton
|
10,000
|
50,000
|
69,000
|
98,000
|
96,000
|
84,000
|
58,000
|
41,000
|
15,000
|
1,200
|
Table 8: Estimated
Monthly Filling Rate for Suitable Fill
Units
|
Sep 13
|
Oct 13
|
Nov 13
|
Dec 13
|
Jan 14
|
Feb 14
|
Mar 14
|
Apr 14
|
May 14
|
Ton
|
10,000
|
53,000
|
83,000
|
128,000
|
140,000
|
100,000
|
80,000
|
54,000
|
18,000
|
3.5.1 The construction of the tunnels will
require excavation of marine sediments.
The excavated sediments will then be disposed of once a Loading /
Dumping permit has been acquired.
In order to apply for the permit a Sediment Quality Report (which will
be duly updated to extend its reliability period) will be required, however, as
the program of works calls for reclamation before excavation, the permit will
be acquired after the reclamation has been stabilised. The estimated volume of marine sediment
requiring excavation is outlined in Table
9 below (subject to permanent design by Atkins China Ltd):
Table 9: Estimated Volume
of Marine Sediment to be Excavated
Works
|
Volume of Marine Sediment (m3)
|
HAT
C&C Tunnel
|
36,000
|
SHT
C&C Tunnel
|
167,000
|
Outfall
|
6,000
|
Foundation
of Administration Building
|
550
|
Total
|
209,550
|
3.5.2 In accordance to the Sediment
Quality Report (¡§SQR¡¨), the marine sediments will be classified into different categories
based upon test results, and the categories will determine whether the
sediments can be disposed of locally or by cross-boundary disposal to the
Mainland. Marine sediments that
fall into categories Mf and H will need to be disposed of at the designated
disposal site in Hong Kong. Marine
sediments that fall into categories L and Mp will need to be disposed of at the
designated disposal facilities in Hong Kong or at a cross-boundary facility.
According to Marine Fill Committee¡¦s (MFC) memo Ref (0RD1Z-01) in FM 4/1C/65
Pt.20, MFC has agreed to allocate marine disposal spaces to HyD for the
Category L/Mp/Mf/Hp sediments arising from the HKLR project. However, as the current SQR expired in
July 2012, the SQR will need to be updated. Details of the disposal requirements for
marine sediment will be subject to the updated SQR. Given that reclamation work is scheduled
to take place before the excavation/ work it is proposed to carry out the
reclamation work prior to the updating of the SQR.
4.1.1 The waste that is generated during
the construction process will be disposed of at designated disposal
facilities. Monthly summaries of
the amount of waste material disposed of offsite will be provided to the SO in the
form of a Waste Flow Table (WFT).
The summaries will indicate the estimated
quantities of waste removed the types of materials removed and the
corresponding disposal ground in the WFT.
4.1.2
The
quantities of C&D material disposed of will be recorded under the barcode
TTS by
using the CHIT / DDF (for disposal of C&D Materials at
Disposal Grounds (Other than Prescribed Facilities) as designated in the
Contract or as Directed by the SO, or Alternative Disposal Grounds Proposed by
the Contractor and Approved by the SO). In addition, a completed ¡§CHIT¡¨
will also be presented to the receiving facility as part of the system for the
disposal charging scheme which became
officially effective in January 2006.
Waste transaction records could be obtained either from the
waste disposal facilities directly, or retrieved
from the EPD bill statement each month.
4.2.1
According
to the Highways Department¡¦s Memo ref. (2NQ9) in Highways Department 7/10/1
dated 15 July 2010. The new waste
acceptance criteria (WAC) (as tabulated below) became effective from 29 December 2010.
Table 10: Waste
Acceptance Criteria
Vehicle Type
|
Waste Depth
|
Weight Ratio
|
Designated
Facility
|
Non-demountable Vehicle
|
Over 1.5m
|
No restriction
|
Landfill
|
1.5m or below
|
0.20 or
below
|
Over 0.20
|
Sorting Facility
|
Demountable
Vehicle
|
Over 1m
|
No
restriction
|
Landfill
|
1m or below
|
0.25 or
below
|
Over 0.25
|
Sorting Facility
|
4.2.2
CSHK
will comply with the acceptance criteria laid down by the operators of the corresponding
fill bank(s) and landfill(s), as outlined below:
4.2.3
The
truck drivers should bear a duly signed CHIT / a duly
completed, signed and stamped DDF (for approved alternative disposal grounds). The dump truck should also have a valid Dumping
Licence issued by CEDD. Dump trucks without valid Dumping Licences will be
rejected.
4.2.4
The
inert C&D materials to be delivered to the fill bank(s) should be in
accordance with the conditions stipulated
in the Dumping Licence. Any
over-sized inert C&D materials will be broken down to less than 250mm in size so as to facilitate its reuse by other
reclamation or earth-filling projects.
The C&D materials to be disposed should consist entirely of inert
construction waste (i.e. 100% inert
construction waste).
4.2.5
Recyclable
materials such as metal, paper, plastics and milled bituminous materials etc.,
which have been sorted on the site for the purposes of recycling, shall not be
considered as C&D materials and should be delivered to a proper recycling
outlet for processing.
4.2.6
The
truck drivers should bear a duly signed CHIT. The dump truck should also have a valid Dumping
License issued by CEDD. Dump trucks without valid Dumping Licenses will be
rejected.
4.2.7
The
non-inert C&D waste to be delivered to the landfills should be in
accordance with the conditions stipulated in the Dumping
License.
4.2.8
Construction
waste containing not more than 50% by weight of inert C&D waste (Gazette
Notice G.N. 4274 published on 16 June 2008).
4.2.9
For
a load of C&D waste not consisting entirely of bamboo, plywood or timber delivered by a vehicle,
the weight of the waste divided by the permitted gross vehicle weight of
the vehicle must not greater than 0.25 for goods vehicle with demountable skip
and 0.2 for other types of vehicle (Gazette Notice G.N. 4274 published on
16 June 2008).
4.2.10
Mixed C&D materials should be sorted at source to
reduce the inert content as far as practicable to meet the above criteria
before they are delivered to landfills.
4.2.11
C&D
waste delivered for landfill disposal should contain no free water and the liquid content
will not exceed 70% by weight.
4.2.12
At
least one (1) week¡¦s notice, including contractors name and contact details
etc, will be submitted to the EPD before starting to deliver the
C&D waste to the landfills. EPD will be informed of any subsequent change to
the disposal programme.
4.3.1 CSHK will
implement a TTS to
track the disposal of C&D materials.
Under the TTS, each truck carrying C&D materials leaving the Site for a
disposal facility will be accompanied by a duly completed and stamped CHIT
/ DDF. The C&D materials must be disposed of at the disposal
grounds as stipulated in the DDF. The
TTS will be executed according to the following procedures:
4.3.2 The Foremen will
arrange the C&D waste to be segregated on site and also check the total
actual amount of cumulated C&D waste after the completion of the particular
works in the working area.
4.3.3 If the sorted
C&D waste is less than 1/3 of truckload, then the C&D waste will be
transferred to the temporary holding area in CSHK¡¦s Works Area for temporary
stockpiling. The C&D waste will
be sorted and stored separately into different storage areas.
4.3.4 Non-inert C&D
waste will be stored in storage containers covered with tarpaulin sheeting in
the temporary holding area. Inert
C&D materials will be stored on the ground properly covered with tarpaulin
sheeting in the temporary holding area.
Larvicidal oil or larvicide will be applied to the stored C&D waste,
if necessary, to control pests.
4.3.5 Upon every seven
(7) days or one (1) truckload transported from the site, the stored non-inert
C&D waste in the temporary holding area will be transferred to the
designated landfills a duly completed, signed and stamped CHIT.
4.3.6 The stored inert
C&D waste will be stored in the temporary holding area for reuse as first
priority and where such case is not allowed, the inert C&D waste will be
transferred to the designated fill banks along with a duly completed, signed
and stamped CHIT.
4.3.7 If the sorted
C&D waste is more than 1/3 of truckload, then the Foreman will arrange
disposal of the C&D waste to designated fill banks / landfills after the
DDF has been received from the SO.
4.3.8 For each truckload
of C&D material leaving the working area / temporary holding area to the
designated fill banks / landfills, the truck driver must bear a duly completed,
signed and stamped CHIT.
4.3.9 The truck will
proceed to the designated disposal facility as stipulated in the CHIT /
DDF. The truck driver will present
the CHIT / DDF to the reception facility operator. If the C&D waste accords with the
acceptance criteria, disposal of the C&D waste will be permitted and the
facility operator will give the truck driver a transaction receipt and stamp
the CHIT / DDF.
4.3.10 The truck driver
will present the CHIT at the weighbridge.
If the vehicle load is accepted, the CHIT is deemed to be used and the
weight would be recorded on the ¡§Transaction Record Slip¡¨.
4.3.11 If the truck driver
is instructed by the reception facility operator to go to the sorting facility,
the driver will need return back to the site and report to the Foremen. No driver is allowed to go to sorting
facility without Foremen permission or instruction.
4.3.12 The truck driver
will then return the transaction receipt and the stamped CHIT / DDF to CSHK as
soon as possible. All CHIT / DDFs
are to be return to the EO.
4.3.13 CSHK will maintain
a daily record summary (DRS) of disposal of C&D material from the Site
including details of the C&D waste, the truck number, departure time,
etc. This record will be checked
against the SO records as soon as possible and the SO will be notified
immediately in case any discrepancy is noted.
4.3.14 Part 1 of the DRS
will be completed in duplicate and a copy should be kept by the SO.
4.3.15 For disposal at
government disposal facilities, CSHK will check the information recorded in the
DRS against the disposal records on CEDD¡¦s or the EPD¡¦s website (see below).
l http:www.cedd.gov.hk/eng/services/tripticket/index.html.
l http://www.epd.gov.hk/epd/misc/cdm/trip.html
4.3.16 Part 2 of the DRS
will be completed and submit to the SO within 1 working day after the records
are posted at the EPD web-site.
4.3.17 Where an
irregularity is observed or where requested by the SO under special
circumstances (e.g. a CHIT / DDF has been issued but there is no disposal
record at the disposal ground), CSHK will submit to the SO within 5 working
days after the recorded date of disposal the supporting evidence such as duly
stamped CHIT / DDF and/or the Transaction Record Slip (where relevant) to
confirm proper completion of the delivery trips in question, or within 2
working days after the SO has requested for such evidence, whichever is later.
A fax copy of the CHIT / DDF or Transaction Record Slip is acceptable, unless
otherwise directed by the Supervising
4.4.1
Import
public fill and sand will be primarily by barges onto the site for
filling although land route will also be used in some cases for filling
works. The control of
barges and trucks coming
to the site for
filling works will be
controlled by the implementation of a TTS.
4.4.2
The
public fill would be from the source sites of Fill Bank 137 at Tseung Kwan O managed by CEDD and
the MTRC projects currently under construction. A TTS will be agreed with the SO, CEDD
and MTRC for the filling record such as the date and time
of the barge leaving the site and the quantities of fill checked and agreed by ER and CEDD/MTRC
for endorsing the tickets. The
copies of tickets would be issued to the SO daily for their record and a summary
of the record would be issued to the SO
monthly for checking and verification.
4.4.3
The
public fill at source site must be tested to confirm compliance with the
Contract Specifications
such as the fine contents of the public fill etc. Before barges are allowed to leave
the source site to start filling work.
Test samples of public fill and sand at the source site must be submitted to the SO for record.
4.5.1
All
trucks to transport waste from the site will be in good working condition and
will be equipped with mechanical covers (or similar) to prevent leakage of
waste onto public areas. In addition to the
cover, to further minimize the leaking of waste from the trucks, trucks should
not be filled higher than the trail board.
4.5.2 Wastes
collected on all the wheels and bodies of trucks will be washed off by
wheel washing facilities before leaving the construction site. CSHK will provide wheel washing
facilities on site at the site entrance.
4.6.1
Where
CSHK has identified a project that can serve as an alternative disposal
facility, CSHK will provide a detailed description of the alternative disposal
ground, including location, lot number (where appropriate)
and location plan(s) to the SO to request for his written approval to dispose of waste at the proposed
location.
4.6.2
Where
the alternative disposal facility is a private construction project, CSHK will submit a letter
from the Authorized Person of the development (as defined under the Building
Ordinance) to confirm that:
l The use of C&D materials in the development is acceptable.
l The use of land formed by C&D materials is in conformity with
the statutory town plan / lease conditions.
l The SO is allowed to enter the alternative facility to conduct an
inspection when necessary.
l The estimated quantity and type of C&D materials to be used in
the construction works and the approximate delivery program, together with the
name, post and specimen signature of the competent person to sign the DDF /
internal trip ticket.
4.6.3
Where the alternative disposal facility is a private
facility but not a construction site, CSHK will submit a letter from the
relevant authorities, such as the Lands Department and Planning Department, to confirm the
suitability of the alternative disposal facility to receive the proposed amount
of C&D materials for use, and a written consent from the landowner.
4.6.4
Where the alternative disposal facility is a
government project, CSHK will submit written consent from the project office
of the alternative disposal facility to use the C&D materials
generated from the Site, and to confirm the estimated quantity and type of
C&D materials required and the approximate delivery programme.
4.6.5
A
system for transmitting disposal records from the alternative disposal ground
will be submitted to the SO for approval before disposal to
the alternative ground starts.
4.7.1
CSHK has been registered as Chemical Waste
Producer. Chemical waste that is generated, as
defined by Schedule 1 of the Waste Disposal (Chemical Waste) (General)
Regulation, will be handled in accordance with the Code of Practice on the Packaging, Labelling and Storage
of Chemical Wastes as follows:
4.7.2
Chemical
waste will be packed and held in containers of suitable design and construction
so
as to prevent leakage, spillage or escape of the contents under normal
conditions of handling,
storage and transport.
4.7.3 Containers used for the storage of
chemical wastes will:
l Be suitable for the substance they are holding, resistant to
corrosion, maintained in a good condition, and securely closed.
l Have a capacity of less than 450 litres unless the specifications
have been approved by the EPD.
l Display a label in English and Chinese in accordance with
instructions prescribed in Schedule 2 of the Regulations.
4.7.4
Every
container of chemical waste will bear an appropriate label which with details
of the chemical waste. The waste
producer will ensure that the information contained on the label
is accurate and sufficient so as to enable proper and safe handling, storage
and transport of the chemical
waste.
4.7.5
The
storage area will be specially constructed and bunded, and located close to the
source of waste generation. The storage area for chemical wastes
will:
l Be clearly labelled and used solely for the storage of chemical
waste.
l Be enclosed on at least three (3) sides.
l Have an impermeable floor and bunding of sufficient capacity to
accommodate 110% of the volume of the largest container or 20% of the total
volume of waste stored in that area, whichever is the greatest.
l Have adequate ventilation.
l Be covered to prevent rainfall entering (water collected with the
bund must be tested and disposed of as chemical waste).
l Be arranged so that incompatible materials are adequately separated.
l Before reaching 80% capacity of the storage container, licensed
waste collectors will be contracted to remove the chemical waste.
4.7.6
After
the chemical wastes have been packed, labelled, and stored, the chemical wastes
will
be transported by licensed waste collectors and disposed of at Chemical Waste Treatment
Facility in Tsing Yi or other approved facilities.
4.8.1 Measures to be implemented to
encourage general waste avoidance / minimization include:
l Reducing the number of photocopies to a minimum and copying on both
sides of paper for internal documents and external documents where appropriate.
l Preventing over-ordering of office equipment and consumables.
l Procuring energy efficient office equipment and consumables.
l Deploying and servicing recycling containers on site to facilitate
collection of recyclables (e.g. aluminum cans, plastic bottles).
l Deploying containers with covers onsite to facilitate the collection
of non-recyclables for disposal at landfills.
l General refuse generated from working vessels and barges will be
collected into temporary waste collection points.
l Working vessels for import fill or delivery should be handled by
themselves.
l There will be waste containers on the working vessels for the collection
of waste. In the event that refuse
is found on the water, CSHK will collect the refuse on an as needed basis.
4.9.1 Sewage waste will be generated from
amenity facilities used by the construction workforce and site office¡¦s
sanitary facilities. Night soil
from chemical toilets will also be generated. The sludge needs to be properly managed
to minimise odour and potential health risks to the workforce by attracting
pests and other disease vectors.
4.9.2
The
peak number of construction workers anticipated to on site by CSHK is to be
about 500 staff. As the workers
will be scattered within the construction site, the most cost-effective
solution will be to provide adequate number of portable toilets within the site
to ensure that sewage from site staff is properly collected. CSHK will ensure adequate numbers of
portable toilets for the workforce and ensure no adverse water impacts by
contracting with licensed contractors to maintain the facilities.
4.10.1 Before starting the transportation
of recyclable materials off site to recycling facilities, CSHK will meet with
recycling contractors to establish a suitable system for collecting recyclable
materials with care.
4.11
Estimate Quantities of C&D Material/Waste
4.11.1
The
following types of waste will be generated during the construction of the HKLR.
l Excavated sediments.
l C&D materials / waste.
l Chemical waste.
l General refuse.
l Recyclable waste.
l Fill material for reclamation.
4.11.2
The
estimated amount of waste to be generated from the Contract is listed in Table 11 below:
Table 11: Estimated
Amount of Waste to be Generated During the Contract
Material
|
Imported
¡V Total Volume (Mm3)
|
Generated
¡V Total Volume (Mm3)
|
Generated
from HKLR (Mm3)
|
Generated
from BCF roadlink works (Mm3)
|
Re-used
onsite or on other Projects (Mm3)
|
Disposal
(Mm3)
|
Proposed
Disposal Outlet
|
Imported Sand
|
0.84
|
0
|
0
|
0
|
N/A
|
N/A
|
N/A
|
Imported Public Fill
|
0.52
|
0
|
0
|
0
|
N/A
|
N/A
|
N/A
|
Imported Rock
|
0.67
|
0
|
0
|
0
|
N/A
|
N/A
|
N/A
|
General Waste
|
N/A
|
0.85
|
0.6375
|
0.2125
|
N/A
|
0.85
|
WENT Landfill or Outlying
Islands Transfer Facilities
|
Chemical Waste (kg)
|
N/A
|
15,000
|
11250
|
3750
|
N/A
|
15,000
|
To be handled by Registered
Contractor on the approved list
|
Inert C&D Soft
Material (MT)
|
N/A
|
1.1
|
0.825
|
0.275
|
1.1
|
0
|
Tuen Mun Area 38 Fill Bank
|
Surplus Surcharge (MT)
|
N/A
|
0.9
|
0.7
|
0.2
|
0.9
|
0
|
Tuen Mun Area 38 Fill Bank
|
Low Quality Rock (MT)
|
N/A
|
0.1
|
0.1
|
0
|
0.1
|
0
|
Tuen Mun Area 38 Fill Bank
|
Good Quality Rock (MT)
|
N/A
|
0.38
|
0.38
|
0
|
0.38
|
0
|
Tuen Mun Area 38 Fill Bank
|
C&D Waste (MT)
|
N/A
|
0.03
|
0.0225
|
0.0075
|
0
|
0.03
|
Tuen Mun Area 38 Fill Bank
|
Category L Sediment
(m3)
|
0
|
207,700*
|
207,700*
|
0
|
0
|
207,700*
|
Designated disposal
facilities in Hong Kong / Cross
boundary disposal
|
Category Mp Sediment (m3)
|
0
|
0*
|
0*
|
0
|
0
|
0*
|
Designated disposal
facilities in Hong Kong / Cross boundary
disposal
|
Category Mf Sediment (m3)
|
0
|
1,850*
|
1,850*
|
0
|
0
|
1,850*
|
Designated disposal sites
for confined marine disposal in Hong Kong
|
These
numbers are the estimations from the EIA report and to be updated.
* The amount will be
updated upon completion of the SQR
4.11.3
It
is estimated that this Contract will employ approximately 500 site personnel at
peak level and the total general waste generated would be about 4,500m3.
4.11.4 The estimated amount
of chemical waste is based upon the amounts of chemical waste generated during
previous construction projects.
4.11.5 CSHK will either
dispose of the excavated sediment generated during the course of the contract
onsite under permit from the EPD or use a cross-boundary Mainland
facility. The amount of marine
sediment will be updated once the Sediment Quality Report has been updated.
4.11.6
Control
measures would
be devised to ensure that the recyclable materials are delivered to a proper recycling outlet
for processing, and to avoid such materials being considered as C&D materials for
the purposes of the Contract.
4.11.7
All recyclable material that is generated during the
course of the Contract will be collected by registered contractors and
transported to an approved facility.
4.11.8 Details of these
contractors were listed in the website of EPD as waste collectors and recyclers, the
information can be search via the hyperlinks at:
l http://www.epd.gov.hk/epd/english/environmentinhk/waste/guide_ref/guide_ref_dwc.html
4.12.1 CSHK¡¦s aim is to minimize the use of
timber during construction, where practicable, by using suitable alternatives,
such as, recyclable metal formwork.
Where the use of timber is unavoidable for temporary works construction
processes or activities with an estimated quantity of greater than 5m3,
CHSK will submit a method statement to the SO for agreement prior to starting
the relevant temporary works. The
method statement will include the justification for the use and the measures
taken to minimize the use of timber.
4.12.2 The summary table of timber usage
will be submitted to the SO together with the monthly summary WFT for
monitoring and review by not later than the fifteenth (15) day of each month
or, if it is a general holiday, the day following the general holiday, or a day
agreed upon with the SO.
5.1.1
The
applicable waste disposal requirements are listed in Section 1 of this WMP.
5.1.2
It
is anticipated that there will be inert C&D materials (comprising soil,
broken rock and concrete, etc), non-inert C&D materials and excavated
sediments generated under Contract No. HY/2011/03. With reference to the clause
25.25 of PS, the designated disposal grounds for inert and non-inert C&D materials are listed as follows:-
Inert C&D Materials
l Tuen Mun Area 38 Fill Bank or other disposal outlets as directed by
the SO.
Non-inert C&D Materials
l West New Territories Landfill (WENT) or Outlying Island Transfer
Facilities.
5.1.3
Monthly
summaries of the amount of C&D material disposed of off site will be
provided to the SO. The summaries
will indicate the estimated quantities of
C&D material removed, the types of C&D materials removed and the
corresponding disposal ground in the WFT.
5.1.4
Inert C&D materials will be disposed of at Tuen
Mun Area 38. Non-inert C&D materials will be
disposed of at WENT landfill or Outlying Island Transfer
Facilities.
Marine Sediments
5.1.5 Marine sediments
will be disposed of at designated disposal site in Hong Kong or at a
cross-boundary facility.
6.1.1
CSHK
will contact all transportation companies who are contracted by CSHK, or its
subcontractors, for the removal
of C&D materials
from the Site and highlight the following parts of the WMP:
l Each truck transporting C&D
materials from the Site to a disposal facility
must carry a duly completed, signed and stamped DDF, irrespective of the
location and nature of the disposal facility.
l The C&D materials must be disposed of at the
disposal ground as stipulated in the CHIT / DDF.
l The improper disposal of C&D materials, as outlined
by the Public Fill Committee, may
result in the revoking of the transportation company Dumping License.
l Truck drivers must bear a valid Dumping License that
has been issued by the CEDD.
6.1.2
The
Flow Chart
of the TTS is attached in Appendix
B.
7.1.1
The
CHIT will be used for each and every vehicle that
transports C&D material
off site to a disposal facility.
7.1.2
Prior
to the vehicle leaving the site, the SO will input the serial number, date, time of
departure, vehicle licence plate number, designated public filling facility /
landfill, and
any other information as required onto the DDF, then stamp the DDF. The SO will retain the
first strip of the form and pass the rest of the DDF to CSHK¡¦s
representative. The DDF will be
carried on board the vehicle by the driver at all times, for the duration of
the trip.
7.1.3
A
register of the DDF¡¦s issued will be maintained by CSHK in the project
environmental filing system, and will be made available for inspection by the
SO upon request. The following
records will be kept to enable monitoring of the DDF¡¦s that have
been issued:-
l DRS and the WFT will be completed and submitted to the SO for their
records. A sample of the DRS and
the WFT is provided in Appendices C and D of this WMP.
7.2.1
CSHK
will maintain a record of the quantities of C&D materials that are
generated each month using the monthly summary WFT.
The CSHK EO will complete and submit the monthly summary WFT to the SO
by no later than the fifteenth (15th) day of the following month, or
if this day is a general holiday, the day following the General Holiday, or a later date as agreed to by the SO.
7.3.1
The estimated quantities of C&D materials that are
generated each year from the site will be summarised using the yearly summary WFT. The yearly summary WFT will be updated
on a half-yearly basis and will be submitted to the SO by not later than 1st
of June and 1st of December of each calendar year, or if these
days are general holidays, the day following the general holiday, or a later
date as agreed to by the SO.
7.3.2 These summaries shall also be made
available to the ETL and the IEC/ENPO.
7.3.3
Specific
trip tickets and records for the internal transfer of C&D materials and
imported fill materials will also be kept for monitoring and shall
be made available to the SO upon request.
7.3.4
For
recyclable materials, CSHK¡¦s Representative will record the quantities of recyclable materials before removal
off the Site via recycling contractors, and also include the details in the WFT for submission to the SO.
7.4.1 In order to ensure
the proper disposal of C&D materials that are generated during the course
of the contract, the following enhancement measure to improve the TTS
recording system will be utilised:
l A video recording system will be installed onsite by CSHK and
disposal records shall be checked against the survey record. The video recording system shall also be
used to monitor the vehicular exit / entrance of the site.
8.1.1 The aims and objectives of the waste
management audit program are:
l To ensure that waste generated by the works is handled, stored,
collected, transported and disposed of in accordance with the applicable
environmental guidelines and regulations.
l To ensure that the handling, storage, collection and disposal of
waste arising from the demolition works complies with the relevant requirements
under the WDO and its regulations, and this WMP.
l To encourage the reuse and recycling of materials.
8.1.2
The
Environmental Team (i.e. BMT Asia Pacific), with assistance from the PM or DPM,
will conduct audits of the waste management practices during
the weekly environmental site inspection to evaluate the overall
implementation of the WMP, and to ensure that the appropriate control measures
are properly implemented. The
results of the waste management audits will be reported in
the monthly EM&A reports.
8.1.3
In
the event of any non-compliance observations or complaints against the
provisions of this WMP, appropriate actions will be taken according
to the particular event. An Action
Plan for non-compliance and
complaints is shown in the following tables:
Table 12: Event Action
Plan for Non-compliance
Step
|
Day
|
Action
|
CSHK/ET
|
SO
|
IEC/ENPO
|
1
|
1
|
A
non-compliance record will be created within
one (1) working day of making the observation during a site audit. The ET will send a Notice of
Non-Compliance (NC) to CSHK, SO
and IEC/ENPO. The NC would include details of the observation/s, the time and
location of the observation/s and the
reason/s for the non-compliance.
|
X
|
-
|
-
|
2
|
2
|
CSHK
will propose suitable corrective action/s to mitigate the non-compliance
observed within one (1) working day
of receipt of the NC from the ET.
|
X
|
-
|
-
|
3
|
3
|
The
SO and IEC/ENPO will review CSHK¡¦s proposed corrective
action/s and make additional recommendations as necessary.
|
-
|
X
|
X
|
4
|
-
|
CSHK
will implement the proposed corrective action/s once they have been agreed to by all parties.
|
X
|
-
|
-
|
5
|
-
|
The
implementation of the corrective action/s
will be checked at the next site audit.
Close the NC if the implementation of the corrective action/s is satisfactory.
|
X
|
X
|
X
|
6
|
-
|
CSHK
will propose preventive action/s within three (3) working
days of the closure of the NC.
|
X
|
-
|
-
|
Note: ¡§x¡¨ denotes action party comments on
the NC where applicable.
Table 13: Event Action
Plan for Complaint
Step
|
Day
|
Action
|
CSHK/ET
|
SO
|
IEC/ENPO
|
1
|
1
|
The ET will investigate validity of
complaint, and assess whether the complaint
is due to an onsite activity. If the complaint is valid and
due to site activity, the ET will log details of the complaint into a Complaint Record Form
(CR).
|
X
|
-
|
-
|
2
|
2
|
CSHK will assess the CR and propose
suitable mitigation measures.
|
X
|
-
|
-
|
3
|
3
|
The ER and IEC/ENPO will review the
mitigation measures and agree or propose further mitigation measures if
required.
|
-
|
X
|
X
|
4
|
-
|
CSHK will implement the proposed
mitigation measures once they have been agreed to by all parties.
|
X
|
-
|
-
|
5
|
-
|
The ETL will check the implementation of
the mitigation measures during the next site audit. The ET will close out the CR, if the
implementation of the mitigation measures is satisfactory.
|
X
|
X
|
X
|
6
|
-
|
CSHK will propose suitable prevention
measures within three (3) working days after closure of the CR.
|
X
|
-
|
-
|
Note: ¡§x¡¨ denotes action party comments on