Contract
No. HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road
Section between Scenic Hill and Hong Kong Boundary Crossing Facilities
Monthly EM&A Report No.23 (August 2014)
15 September 2014
Revision 1
Main Contractor Designer
Contents
Executive Summary
1.4 Construction Works Undertaken During the Reporting Month
2....... Air Quality Monitoring
2.4 Monitoring Parameters, Frequency and Duration
2.6 Monitoring Schedule for the Reporting Month
3.4 Monitoring Parameters, Frequency and Duration
3.6 Monitoring Schedule for the Reporting Month
4....... Water Quality Monitoring
4.3 Monitoring Parameters, Frequency and Duration
4.6 Monitoring Schedule for the Reporting Month
6....... ENVIRONMENTAL SITE INSPECTION AND AUDIT
6.2 Advice on the Solid and Liquid Waste Management Status
6.3 Environmental Licenses and Permits
6.4 Implementation Status of Environmental Mitigation Measures
6.5 Summary of Exceedances of the Environmental Quality Performance
Limit
6.6 Summary of Complaints, Notification of Summons and Successful
Prosecution
7.1 Construction Programme for the Coming Months
7.2 Environmental Monitoring Scheme for the Coming Month
Figures
Figure 1.1 Location
of the Site
Figure 2.1 Environmental
Monitoring Stations
Appendices
Appendix
A Environmental
Management Structure
Appendix
B Construction
Programme
Appendix C Calibration
Certificates
Appendix D Monitoring
Schedule
Appendix E Monitoring
Data and Graphical Plots
Appendix F Event and
Action Plan
Appendix
H Dolphin
Monitoring Results
Appendix J Cumulative
Statistics on Complaints
Appendix
K Environmental
Licenses and Permits
Appendix
L Implementation
Schedule of Environmental Mitigation Measures
Appendix
N Location
of Works Areas
Executive Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The main works of the Contract include
land tunnel at Scenic Hill, tunnel underneath Airport Road and Airport Express
Line, reclamation and tunnel to the east coast of the Airport Island, at-grade
road connecting to the HKBCF and highway works of the HKBCF within the Airport
Island and in the vicinity of the HKLR reclamation. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ¡§Designated Projects¡¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap 499)
and Environmental Impact Assessment (EIA) Reports (Register No. AEIAR-144/2009
and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/C for HKLR and EP-353/2009/G for HKBCF were issued on 5 September
2013 and 6 August 2013, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was
commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the twenty-third
Monthly EM&A report for the Contract which summaries the monitoring results
and audit findings of the EM&A programme during the reporting period from 1
to 31 August 2014.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities in this reporting month is listed below:
1-hr TSP
Monitoring |
1, 7, 13, 19, 25 and 29 August 2014 |
24-hr TSP
Monitoring |
5, 11, 15, 21 and 27 August 2014 |
Noise
Monitoring |
7, 15, 22 and 25 August 2014 |
Water Quality
Monitoring |
1, 4, 6, 8, 11, 13, 15, 18, 20, 22, 25, 27 and 29 August 2014 |
Chinese White
Dolphin Monitoring |
5, 6, 15 and 19 August 2014 |
Site
Inspection |
6, 13, 20 and 29 August 2014 |
Due
to boat availability issue, the dolphins monitoring schedule was rescheduled
from 7 August 2014 to 6 August 2014.
Water quality monitoring for mid-ebb tide on 13 August 2014 was
cancelled for safety reason as a thunderstorm warning was hoisted by Hong Kong Observatory. Due to the inclement weather on 13 August 2014 (red
rainstorm signal was hoisted by Hong Kong Observatory), dolphin monitoring
was rescheduled to 15 August 2014.
|
Due to the inclement weather, the noise monitoring at NMS5 was
rescheduled from 13 August 2014 to 15 August 2014 and from 19 August 2014 to
22 August 2014. |
Breaches
of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
0 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
2 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
8 |
0 |
|
Dolphin Monitoring |
Quarterly Analysis (Jun to Aug
2014) |
2 |
0 |
An Action Level exceedance of suspended solid level was recorded on 11 and 13 August 2014 respectively. Eight Action Level exceedances of dissolved oxygen level were recorded on 15
August 2014. According to the
information provided by the Contractor, marine construction activities were
carried out within silt curtain as recommended in the EIA Report. There were no
specific activities recorded during the monitoring period that would cause any
significant impacts on monitoring results. Therefore, the exceedances were considered non-contract related.
There were two Action Level
exceedances of dolphin monitoring for the quarterly monitoring data (June -
August 2014). The exceedances will be reported in the quarterly report for June
to August 2014.
Complaint
Log
There were no complaints
received in relation to the environmental impact during the reporting period.
Notifications
of Summons and Prosecutions
There were no notifications
of summons or prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin Monitoring was approved by EPD on 6 May 2013.
The original monitoring
station at IS(Mf)9 (Coordinate- East:813273, North 818850) was observed inside
the perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As advised by the Contractor of HY/2010/02 in
August 2013, the perimeter silt curtain was shifted to facilitate safe
anchorage zone of construction barges/vessels until end of 2013 subject to
construction progress. Therefore,
water quality monitoring station IS(Mf)9 was shifted to 813226E and 818708N
since 1 July 2013. According to the
water quality monitoring team¡¦s observation on 24 March 2014, the original
monitoring location of IS(Mf)9 was no longer enclosed by the perimeter silt
curtain of Contract HY/2010/02. Thus, the impact water quality monitoring works
at the original monitoring location of IS(Mf)9 has been resumed since 24 March
2014.
Future
Key Issues
The future key issues
include potential noise, air quality, water quality and ecological impacts and
waste management arising from the following construction activities to be
undertaken in the upcoming month:
¡P
Dismantling/trimming of Temporary 40mm Stone Platform for Construction of
Seawall at
Portion X;
¡P
Stone Column Installation at Portion X;
¡P
Filling Works behind Stone Platform at Portion X;
¡P
Band Drains Installation at Portion X;
¡P
Construction of Seawall at Portion X;
¡P
Loading and Unloading Filling Material at Portion X;
¡P
Temporary Stone Platform Construction at Portion X;
¡P
Temporary Diversion of Existing Box Culvert at Portion X;
¡P
Sheet Piling & Jet Grouting at Portion X;
¡P
Works for Diversion of Airport Road and Kwo Lo Wan Road at Kwo Lo Wan /
Airport Road;
¡P
Pre-grouting and Pipe Piling Works for AEL Access Shafts at Airport
Express Line;
¡P
Utilities Detection at Kwo Lo Wan / Airport Road / Airport Express Line/
East Coast Road;
¡P
Establishment of Site Access at Airport Road / Airport Express Line/East
Coast Road;
¡P
Excavation and Lateral Support Works at shaft 3 extension north shaft at
Kwo Lo Wan Road;
¡P
Pipe Piling Cofferdam Works at Airport Road;
¡P
Access Shaft Construction for HAT Tunnel at Portion Y;
¡P
Utility Culvert Excavation at Portion Y;
¡P
Pipe roofing installation for
HAT tunnel at Portion Y
¡P
Excavation for Tunnel SHT at West Portal;
¡P
Abutment Construction at West Portal; and
¡P
Transformer Room Construction at West Portal, East Coast Road and Kwo Lo Wan Road.
¡P
New reclamation
along the east coast of the approximately 23 hectares.
¡P
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
¡P
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
¡P
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
¡P
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
¡P
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the
Dragonair Headquarters Building, including the construction of buildings,
connection roads and other associated facilities.
¡P
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
Table
1.1 Contact
Information of Key Personnel
Party |
Position
|
Name |
Telephone
|
Fax |
Supervising Officer¡¦s Representative |
(Chief
Resident Engineer, CRE) |
Robert Antony
Evans |
3968 0801 |
2109 1882 |
Environmental Project Office /
Independent Environmental Checker |
Environmental Project Office Leader |
Y. H. Hui |
3465
2888 |
3465
2899 |
Independent Environmental Checker |
Antony Wong |
3465
2888 |
3465
2899 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968
7002 |
2109
2588 |
Environmental Officer |
Federick Wong |
3968
7117 |
2109
2588 |
|
Environmental Team |
Environmental Team Leader |
Claudine Lee |
2241
9847 |
2815
3377 |
24
hours complaint hotline |
--- |
--- |
5699
5730 |
--- |
Table 1.2 Construction Activities During Reporting Month
Description
of Activities |
Site
Area |
Dismantling/trimming
of temporary 40mm stone platform for construction of seawall |
Portion X |
Stone column
installation |
Portion X |
Filling works behind
stone platform |
Portion X |
Temporary stone
platform construction |
Portion X |
Band drains
Installation |
Portion X |
Piling works |
Portion X |
Pipe roofing
installation and excavation for tunnel SHT |
West Portal |
Works for diversion
of Airport Road and Kwo Lo Wan Road |
Kwo Lo Wan / Airport Road |
Pre-grouting and
pipe piling works for AEL access shafts |
Airport Express Line |
Utilities detection |
Kwo Lo Wan/ Airport Road/ Airport Express
Line |
Excavation and
lateral support works at shaft 3 extension north shaft |
Kwo Lo Wan Road |
Access shaft
construction for SHT & HAT |
Portion Y |
Pipe roofing
installation for Tunnel HAT |
Portion Y |
Utility culvert
excavation |
Portion Y |
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
360 |
Table 2.2 Action
and Limit Levels for 24-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
173 |
260 |
Table 2.3
Air Quality Monitoring Equipment
Equipment |
Brand and
Model |
Portable direct reading
dust meter (1-hour TSP) |
Sibata Digital Dust
Monitor (Model No. LD-3B) |
High Volume Sampler |
Tisch Environmental
Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Air
Sampler (Model No. TE-5170) |
Table
2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
AMS5 |
Ma Wan Chung Village
(Tung Chung) |
AMS6 |
Dragonair / CNAC
(Group) Building (HKIA) |
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
1-hour TSP |
Three times every 6
days while the highest dust impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air
sensitive receivers. The following criteria were considered in the installation
of the HVS.
(i) A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
(ii) The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
(iii) A minimum of 2 meters separation from walls,
parapets and penthouse for rooftop sampler.
(iv) No furnace or incinerator flues nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and
access to the monitoring stations.
(vii) A secured supply of electricity was obtained to operate
the samplers.
(viii) The sampler was located more than 20 meters from any
dripline.
(ix) Any wire fence and gate, required to protect the
sampler, did not obstruct the monitoring process.
(x) Flow control accuracy was kept within ¡Ó2.5%
deviation over 24-hour sampling period.
(b) Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and
sufficient filters that were clean and without pinholes were selected.
(ii) All filters were equilibrated in the conditioning
environment for 24 hours before weighing. The conditioning environment
temperature was around
(iii) All filter papers were prepared and analysed by ALS
Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has
comprehensive quality assurance and quality control programmes.
(c) Field Monitoring
(i) The power supply was checked to ensure the HVS
works properly.
(ii) The filter holder and the area surrounding the
filter were cleaned.
(iii) The filter holder was removed by loosening the four
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully.
(iv) The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter.
(v) The swing bolts were fastened to hold the filter
holder down to the frame. The
pressure applied was sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured
with the aluminium strip.
(vii) The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
(viii) A new flow rate record sheet was set into the flow
recorder.
(ix) On site temperature and atmospheric pressure
readings were taken and the flow rate of the HVS was checked and adjusted at
around 1.1 m3/min, and complied with the range specified in the
Updated EM&A Manual for HKLR (Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a
sampling period of 24 hours, and the starting time, weather condition and the
filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and
atmospheric pressure readings were taken and the final flow rate of the HVS was
checked and recorded.
(xiii) The final elapsed time was recorded.
(xiv) The sampled filter was removed carefully and folded
in half length so that only surfaces with collected particulate matter were in
contact.
(xv) It was then placed in a clean plastic envelope and
sealed.
(xvi) All monitoring information was recorded on a
standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty
Ltd. For analysis.
(d) Maintenance and Calibration
(i) The HVS and its accessories were maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using
TE
(iii) Calibration certificate of the HVSs are provided in
Appendix C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction
Manual as follows:-
(i)
Turn
the power on.
(ii) Close the air collecting opening cover.
(iii) Push the ¡§TIME SETTING¡¨ switch to [BG].
(iv) Push ¡§START/STOP¡¨ switch to perform background
measurement for 6 seconds.
(v) Turn the knob at SENSI ADJ position to insert the
light scattering plate.
(vi) Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨
is indicated in the display.
(vii) Push ¡§START/STOP¡¨ switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii) Pull out the knob and return it to MEASURE
position.
(ix) Push the ¡§TIME SETTING¡¨ switch the time set in the
display to 3 hours.
(x) Lower down the air collection opening cover.
(xi) Push ¡§START/STOP¡¨ switch to start measurement.
(b) Maintenance and Calibration
(i) The
1-hour TSP meter was calibrated at 1-year intervals against a Tisch
Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High
Volume Air Sampler. Calibration certificates of the Laser Dust Monitors are
provided in Appendix C.
Table
2.6
Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
16 |
3 - 47 |
352 |
500 |
AMS6 |
17 |
8 - 40 |
360 |
500 |
Table 2.7 Summary
of 24-hour TSP Monitoring Results During the Reporting Month
Monitoring
Station |
Average (mg/m3) |
Range (mg/m3) |
Action
Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
22 |
12 - 30 |
164 |
260 |
AMS6 |
41 |
17 - 83 |
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ¡V Ma Wan
Chung Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900
hours on normal weekdays |
When one
documented complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
B&K 2238 |
Acoustic
Calibrator |
B&K 4231 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10 and L90
would be recorded. |
At least once
per week |
(a) The sound level
meter was set on a tripod at a height of
(b) The battery
condition was checked to ensure the correct functioning of the meter.
(c)
Parameters such
as frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency
weighting: A
(ii) time weighting:
Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
¡V 1900 on normal weekdays
(e) Prior to and
after each noise measurement, the meter was calibrated using the acoustic
calibrator for 94.0 dB(A) at 1000 Hz.
If the difference in the calibration level before and after measurement
was more than 1.0 dB(A), the measurement would be considered invalid and repeat
of noise measurement would be required after re-calibration or repair of the
equipment.
(f) During the
monitoring period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(g) Noise
measurement was paused during periods of high intrusive noise (e.g. dog
barking, helicopter noise) if possible. Observations were recorded when
intrusive noise was unavoidable.
(h) Noise monitoring
was cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The microphone
head of the sound level meter was cleaned with soft cloth at regular intervals.
(b) The meter and
calibrator were sent to the supplier or HOKLAS laboratory to check and
calibrate at yearly intervals.
(c) Calibration
certificates of the sound level meters and acoustic calibrators are provided in
Appendix C.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station |
Average Leq (30 mins), dB(A) |
Range of Leq (30 mins), dB(A) |
Limit Level Leq (30 mins), dB(A) |
NMS5 |
57 |
55 ¡V 59 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved
Oxygen (mg/L) (surface, middle and bottom) |
Surface and
Middle |
5.0 |
4.2 except 5
for Fish Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity
(NTU) |
Depth average |
27.5 or 120%
of upstream control station¡¦s turbidity at the same tide of the same day; The action
level has been amended to ¡§27.5 and 120% of upstream control
station¡¦s turbidity at the same tide of the same day¡¨ since 25 March 2013. |
47.0 or 130%
of turbidity at the upstream control station at the same tide of same day; The limit
level has been amended to ¡§47.0 and 130% of turbidity at the
upstream control station at the same tide of same day¡¨ since 25 March 2013. |
Suspended
Solid (SS) (mg/L) |
Depth average |
23.5 or 120%
of upstream control station¡¦s SS at the same tide of the same day; The action
level has been amended to ¡§23.5 and 120% of upstream control
station¡¦s SS at the same tide of the same day¡¨ since 25 March 2013. |
34.4 or 130%
of SS at the upstream control station at the same tide of same day and 10mg/L
for Water Services Department Seawater Intakes; The limit
level has been amended to ¡§34.4 and 130% of SS at the upstream
control station at the same tide of same day and 10mg/L for Water Services
Department Seawater Intakes¡¨ since 25 March 2013 |
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO, non-compliance
of the water quality limit occurs when monitoring result is lower that the
limit.
(3) For SS
& turbidity non-compliance of the water quality limits occur when
monitoring result is higher than the limits.
(4) The change
to the Action and limit Levels for Water Quality Monitoring for the EM&A
works was approved by EPD on 25 March 2013.
Table 4.2 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO and
Temperature Meter, Salinity Meter, Turbidimeter and pH Meter |
YSI Model 6820
V2-M, 650 |
Positioning
Equipment |
DGPS ¡V KODEN :
KGP913MkII, KBG3 |
Water Depth
Detector |
Layin
Associates: SM-5 & SM5A |
Water Sampler |
Wildlife
Supply Company : 5487-10 |
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field
Stations: Sensitive Receiver Stations: |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen
(DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P Suspended Solids (SS), mg/L |
Three times per week during
mid-ebb and mid-flood tides (within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water
depth be less than 3 m, only the mid-depth station will be monitored). |
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |
|
Easting |
Northing |
||
IS5 |
Impact Station
(Close to HKLR construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station
(Close to HKLR construction site) |
812101 |
817873 |
IS7 |
Impact Station
(Close to HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station
(Close to HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact Station
(Close to HKBCF construction site) |
813273 |
818850 |
IS10 |
Impact Station
(Close to HKBCF construction site) |
812577 |
820670 |
SR3 |
Sensitive
receivers (San Tau SSSI) |
810525 |
816456 |
SR4 |
Sensitive
receivers (Tai Ho Inlet) |
814760 |
817867 |
SR5 |
Sensitive
receivers (Artificial Reef In NE Airport) |
811489 |
820455 |
SR10A |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823741 |
823495 |
SR10B |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823686 |
823213 |
CS2 |
Control
Station (Mid-Ebb) |
805849 |
818780 |
CS(Mf)5 |
Control
Station (Mid-Flood) |
817990 |
821129 |
(a) The
in-situ water quality parameters including dissolved oxygen, temperature, salinity
and turbidity, pH were measured by multi-parameter meters.
(a) Digital Differential Global Positioning
Systems (DGPS) were used to ensure that the correct location was selected prior
to sample collection.
(b) Portable, battery-operated echo sounders
were used for the determination of water depth at each designated monitoring
station.
(c) All in-situ measurements were taken at 3
water depths, 1 m below water surface, mid-depth and 1 m above sea bed, except
where the water depth was less than 6 m, in which case the mid-depth station
was omitted. Should the water depth be less than 3 m, only the mid-depth
station was monitored.
(d) At each measurement/sampling depth, two
consecutive in-situ monitoring (DO concentration and saturation, temperature,
turbidity, pH, salinity) and water sample for SS. The probes were retrieved out
of the water after the first measurement and then re-deployed for the second
measurement. Where the difference in the value between the first and second
readings of DO or turbidity parameters was more than 25% of the value of the
first reading, the reading was discarded and further readings were taken.
(e) Duplicate samples from each independent
sampling event were collected for SS measurement. Water samples were collected
using the water samplers and the samples were stored in high-density polythene
bottles. Water samples collected were well-mixed in the water sampler prior to
pre-rinsing and transferring to sample bottles. Sample bottles were pre-rinsed
with the same water samples. The sample bottles were then be packed in
cool-boxes (cooled at 4oC without being frozen), and delivered to
ALS Technichem (HK) Pty Ltd. for the analysis of suspended solids
concentrations. The laboratory determination work would be started within 24
hours after collection of the water samples. ALS Technichem (HK) Pty Ltd. is a
HOKLAS accredited laboratory and has comprehensive quality assurance and
quality control programmes.
(f) The analysis method and detection limit for
SS is shown in Table 4.5.
Table 4.5 Laboratory Analysis for Suspended Solids
Parameters |
Instrumentation |
Analytical Method |
Detection Limit |
Suspended
Solid (SS) |
Weighting |
APHA 2540-D |
0.5mg/L |
(g) Other relevant data were recorded, including
monitoring location / position, time, water depth, tidal stages, weather
conditions and any special phenomena or work underway at the construction site
in the field log sheet for information.
Table 4.6 Summary
of Water Quality Exceedances
Station |
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Total number of exceedances |
|||||
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
||
IS5 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS(Mf)6 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
11
Aug 2014 |
-- |
1 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS7 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS8 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS(Mf)9 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS10 |
Action Level |
15
Aug 2014 |
15
Aug 2014 |
15
Aug 2014 |
15
Aug 2014 |
-- |
-- |
-- |
-- |
2 |
2 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR3 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR4 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR5 |
Action Level |
15
Aug 2014 |
15
Aug 2014 |
15
Aug 2014 |
15
Aug 2014 |
-- |
-- |
-- |
13
Aug 2014 |
2 |
3 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR10A |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR10B |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |