Contract
No. HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road
Section between Scenic Hill and Hong Kong Boundary Crossing Facilities
Monthly EM&A Report No.57 (June 2017)
9 August 2017
Revision 2
Main
Contractor Designer
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Month
2....... Air
Quality Monitoring
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4....... Water Quality Monitoring
4.3 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring
Schedule for the Reporting Month
6.1 Sedimentation
Rate Monitoring
6.3 Mudflat
Ecology Monitoring Methodology
6.4 Event
and Action Plan for Mudflat Monitoring
6.5 Mudflat
Ecology Monitoring Results and Conclusion
7....... Environmental
Site Inspection and Audit
7.2 Advice
on the Solid and Liquid Waste Management Status
7.3 Environmental
Licenses and Permits
7.4 Implementation
Status of Environmental Mitigation Measures
7.5 Summary
of Exceedances of the Environmental Quality Performance Limit
7.6 Summary
of Complaints, Notification of Summons and Successful Prosecution
8.1 Construction
Programme for the Coming Months
8.2 Environmental
Monitoring Schedule for the Coming Month
Figures
Figure
1.1 Location
of the Site
Figure
2.1 Environmental
Monitoring Stations
Figure
6.1 Mudflat
Survey Area
Appendices
Appendix A Environmental
Management Structure
Appendix B Construction Programme
Appendix C Calibration
Certificates
Appendix D Monitoring Schedule
Appendix
E Monitoring
Data and Graphical Plots
Appendix F Event and Action
Plan
Appendix G Wind
Data
Appendix H Dolphin Monitoring
Results
Appendix I Mudflat
Monitoring Results
Appendix J Waste Flow Table
Appendix
K Cumulative
Statistics on Complaints
Appendix L Environmental
Licenses and Permits
Appendix
M Implementation
Schedule of Environmental Mitigation Measures
Appendix N Record of ¡§Notification
of Summons and Prosecutions¡¨
Appendix O Location
of Works Areas
Executive
Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The main works of the Contract include
land tunnel at Scenic Hill, tunnel underneath Airport Road and Airport Express
Line, reclamation and tunnel to the east coast of the Airport Island, at-grade
road connecting to the HKBCF and highway works of the HKBCF within the Airport
Island and in the vicinity of the HKLR reclamation. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ¡§Designated Projects¡¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was
commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the fifty-seventh Monthly EM&A report for the Contract which
summarizes the monitoring results and audit findings of the EM&A programme
during the reporting period from 1 to 30 June 2017.
Environmental
Monitoring and Audit Progress
The monthly EM&A programme
was undertaken in accordance with the Updated EM&A Manual for HKLR (Version
1.0). A summary of the monitoring
activities during this reporting month is listed below:
1-hr TSP
Monitoring |
1, 7, 13, 19, 23 and 29 June 2017 |
24-hr TSP
Monitoring |
6, 12, 17, 22, 28 and 29 June 2017 |
Noise
Monitoring |
1, 7, 15, 19 and 29 June 2017 |
Mudflat Monitoring (Mudflat) |
2, 3, 9, 10 and 11 June 2017 |
Mudflat Monitoring (Sedimentation Rate) |
8 June 2017 |
Chinese White
Dolphin Monitoring |
14, 15, 20 and
26 June 2017 |
Site
Inspection |
1, 7, 14, 21
and 30 June 2017 |
Due
to power supply failure, the 24-hour TSP monitoring at AMS5 was rescheduled
from 28 June 2017 to 29 June 2017.
Due
to weather condition, the noise monitoring schedule was rescheduled from 13
June 2017 to 15 June 2017.
The
monitoirng schedule of water quality monitoring for all stations except station
CS2 were adopted from the published Monthly Environmental Monitoring and Audit
(EM&A) Report for June 2017 prepared for Contract No. HY/2010/02 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Reclamation
Works. The monitoirng schedule of water quality monitoring for station CS2 was
adopted from the published Monthly EM&A Report for June 2017 prepared by
Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between HKSAR Boundary and Scenic Hill.
Due
to suitable weather and ambient temperature, the mudflat monitoring was
rescheduled from 12 June 2017 to 2 and 3 June 2017.
Due
to weather condition, the dolphin monitoring schedule was rescheduled from 19
June 2017 to 20 June 2017.
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
0 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
0 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
0 |
0 |
Complaint
Log
For Environmental Complaint
No. COM-2017-095(3) mentioned in previously Monthly EM&A Report for May
2017, it was considered that the complaint was likely related to Contract No. HY/2011/03.
The Contractor has implemented the following measures to minimize the potential
noise impact:
- Additional
noise barriers have been erected in the active working area to further mitigate
the associated noise emissions as far as practicable;
-
Cover
the breaker tip with acoustic material;
-
Noise
barriers have been located as close as possible to the noise source. Also, gaps
and openings at joints in the barriers material have been minimized;
-
Speed
up of construction works in order to shorten the duration noise impact/nuisance
to the surrounding;
-
Minimize
the quantities of noisy plant as far as practicable; and
-
Regular
review of working duration and switch off all unnecessary machinery and plant.
There was no complaint
received in relation to the environmental impacts during the reporting period.
Notifications
of Summons and Prosecutions
There were no notifications
of summons or prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May 2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As advised by the Contractor of HY/2010/02 in
August 2013, the perimeter silt curtain was shifted to facilitate safe
anchorage zone of construction barges/vessels until end of 2013 subject to
construction progress. Therefore,
water quality monitoring station IS(Mf)9 was shifted to 813226E and 818708N
since 1 July 2013. According to the
water quality monitoring team¡¦s observation on 24 March 2014, the original
monitoring location of IS(Mf)9 was no longer enclosed by the perimeter silt
curtain of Contract HY/2010/02. Thus, the impact water quality monitoring works
at the original monitoring location of IS(Mf)9 has been resumed since 24 March
2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
Future
Key Issues
The future key issues include
potential noise, air quality, water quality and ecological impacts and waste
management arising from the following construction activities to be undertaken
in the upcoming month:
¡P
Stockpiling at WA7;
¡P
Removal of toe loading at Portion X;
¡P
Works for Diversion of Airport Road;
¡P
Construction
of Tunnel Box Structure at Shaft 3 Extension North Shaft;
¡P
Superstructure Works for Scenic Hill
Tunnel West Portal Ventilation building at West Portal.
¡P
New reclamation along the east coast
of the approximately 23 hectares.
¡P
Tunnel of Scenic Hill (Tunnel SHT)
from Scenic Hill to the new reclamation, of approximately 1km in length with
three (3) lanes for the east bound carriageway heading to the HKBCF and four
(4) lanes for the westbound carriageway heading to the HZMB Main Bridge.
¡P
An abutment of the viaduct portion of
the HKLR at the west portal of Tunnel SHT and associated road works at the west
portal of Tunnel SHT.
¡P
An at grade road on the new
reclamation along the east coast of the HKIA to connect with the HKBCF, of
approximately 1.6 km along dual 3-lane carriageway with hard shoulder for each
bound.
¡P
Road links between the HKBCF and the
HKIA including new roads and the modification of existing roads at the HKIA,
involving viaducts, at grade roads and a Tunnel HAT.
¡P
A highway operation and maintenance
area (HMA) located on the new reclamation, south of the Dragonair Headquarters
Building, including the construction of buildings, connection roads and other
associated facilities.
¡P
Associated civil, structural,
building, geotechnical, marine, environmental protection, landscaping, drainage
and sewerage, tunnel and highway electrical and mechanical works, together with
the installation of street lightings, traffic aids and sign gantries, water
mains and fire hydrants, provision of facilities for installation of traffic
control and surveillance system (TCSS), reprovisioning works of affected
existing facilities, implementation of transplanting, compensatory planting and
protection of existing trees, and implementation of an environmental monitoring
and audit (EM&A) program.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Supervising Officer¡¦s Representative |
(Chief
Resident Engineer, CRE) |
Robert Antony
Evans |
3968 0801 |
2109 1882 |
Environmental Project Office /
Independent Environmental Checker |
Environmental Project Office Leader |
Y. H. Hui |
3465
2888 |
3465
2899 |
Independent Environmental Checker |
Antony Wong |
3465
2888 |
3465
2899 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968
7002 |
2109
2588 |
Environmental Officer |
Federick Wong |
3968
7117 |
2109
2588 |
|
Environmental Team |
Environmental Team Leader |
Claudine Lee |
2241
9847 |
2815
3377 |
24
hours complaint hotline |
--- |
--- |
5699
5730 |
--- |
Table 1.2 Construction
Activities During Reporting Month
Description of Activities |
Site Area |
Stockpiling |
WA7 |
Dismantling/trimming of temporary 40mm stone platform for construction
of seawall |
Portion X |
Construction of seawall |
Portion X |
Loading and unloading of filling materials |
Portion X |
Backfilling at Scenic Hill Tunnel (Cut & Cover Tunnel) |
Portion X |
Excavation for HKBCF to Airport Tunnel &
construction of tunnel box structure |
Portion X |
Excavation for diversion of culvert PR14 |
Portion X |
Works for diversion |
Airport Road |
Utilities detection |
Airport Road/
Airport Express Line/ East Coast Road |
Establishment of site access |
Airport Road/
Airport Express Line/ East Coast Road |
Mined tunnel excavation/ box jacking underneath
Airport Road and Airport Express Line |
Airport
Road and Airport
Express Line |
Construction of Tunnel box structure at Package T1.12.1 |
Near Kwo Lo
Wan Road |
Construction of Tunnel box structure |
Shaft 3
Extension South & North Shaft |
Excavation and lateral support works & Construction of Tunnel Box
Structure for HKBCF to Airport Tunnel West (Cut & Cover Tunnel) |
Airport Road |
Excavation and lateral support works & construction of tunnel box
structure for HKBCF to Airport Tunnel East (Cut & Cover Tunnel) |
Portion X |
Sub-structure & superstructure works for Highway Operation and
Maintenance Area Building |
Portion X |
Superstructure works for Scenic Hill Tunnel West Portal Ventilation
building |
West Portal |
Table
2.1 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
360 |
Table
2.2 Action
and Limit Levels for 24-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
173 |
260 |
Table
2.3 Air
Quality Monitoring Equipment
Equipment |
Brand and
Model |
Portable direct reading
dust meter (1-hour TSP) |
Sibata Digital Dust
Monitor (Model No. LD-3B) |
High Volume Sampler |
Tisch Environmental
Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Air
Sampler (Model No. TE-5170) |
Table
2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
AMS5 |
Ma Wan Chung Village
(Tung Chung) |
AMS6 |
Dragonair / CNAC
(Group) Building (HKIA) |
Table
2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
1-hour TSP |
Three times every 6 days while the highest dust
impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air
sensitive receivers. The following criteria were considered in the installation
of the HVS.
(i) A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
(ii) The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
(iii) A minimum of 2 meters separation from walls,
parapets and penthouse for rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and
access to the monitoring stations.
(vii) A secured supply of electricity was obtained to
operate the samplers.
(viii) The sampler was located more than 20 meters from any
dripline.
(ix) Any wire fence and gate, required to protect the
sampler, did not obstruct the monitoring process.
(x) Flow control accuracy was kept within ¡Ó2.5%
deviation over 24-hour sampling period.
(b) Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and
sufficient filters that were clean and without pinholes were selected.
(ii) All filters were equilibrated in the conditioning environment
for 24 hours before weighing. The conditioning environment temperature was
around
(iii) All filter papers were prepared and analysed by ALS
Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has
comprehensive quality assurance and quality control programmes.
(c) Field Monitoring
(i) The power supply was checked to ensure the HVS works
properly.
(ii) The filter holder and the area surrounding the
filter were cleaned.
(iii) The filter holder was removed by loosening the four
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully.
(iv) The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter.
(v) The swing bolts were fastened to hold the filter
holder down to the frame. The
pressure applied was sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured
with the aluminium strip.
(vii) The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
(viii) A new flow rate record sheet was set into the flow
recorder.
(ix) On site temperature and atmospheric pressure
readings were taken and the flow rate of the HVS was checked and adjusted at
around 1.1 m3/min, and complied with the range specified in the
Updated EM&A Manual for HKLR (Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a
sampling period of 24 hours, and the starting time, weather condition and the
filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and
atmospheric pressure readings were taken and the final flow rate of the HVS was
checked and recorded.
(xiii) The final elapsed time was recorded.
(xiv) The sampled filter was removed carefully and folded
in half length so that only surfaces with collected particulate matter were in
contact.
(xv) It was then placed in a clean plastic envelope and
sealed.
(xvi) All monitoring information was recorded on a
standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty
Ltd. for analysis.
(d) Maintenance and Calibration
(i) The HVS and its accessories were maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using
TE
(iii) Calibration certificate of the HVSs are provided in
Appendix C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction Manual
as follows:-
(i)
Turn
the power on.
(ii) Close the air collecting opening cover.
(iii) Push the ¡§TIME SETTING¡¨ switch to [BG].
(iv) Push ¡§START/STOP¡¨ switch to perform background
measurement for 6 seconds.
(v) Turn the knob at SENSI ADJ position to insert the
light scattering plate.
(vi) Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨
is indicated in the display.
(vii) Push ¡§START/STOP¡¨ switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii) Pull out the knob and return it to MEASURE
position.
(ix) Push the ¡§TIME SETTING¡¨ switch the time set in the
display to 3 hours.
(x) Lower down the air collection opening cover.
(xi) Push ¡§START/STOP¡¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The
1-hour TSP meter was calibrated at 1-year intervals against a Tisch
Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High
Volume Air Sampler. Calibration certificates of the Laser Dust Monitors are
provided in Appendix C.
Table 2.6 Summary of 1-hour TSP
Monitoring Results During the Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
16 |
8 ¡V 36 |
352 |
500 |
AMS6 |
13 |
4 ¡V 28 |
360 |
500 |
Table
2.7 Summary
of 24-hour
TSP Monitoring Results During the Reporting Month
Monitoring
Station |
Average (mg/m3) |
Range (mg/m3) |
Action
Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
34 |
30 ¡V 39 |
164 |
260 |
AMS6 |
48 |
23 ¡V 95 |
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ¡V Ma Wan
Chung Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900
hours on normal weekdays |
When one
documented complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
B&K 2238 |
Acoustic
Calibrator |
B&K 4231 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10 and L90
would be recorded. |
At least once
per week |
(a) The sound level
meter was set on a tripod at a height of
(b) The battery
condition was checked to ensure the correct functioning of the meter.
(c)
Parameters such
as frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency
weighting: A
(ii) time
weighting: Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
¡V 1900 on normal weekdays
(d) Prior to and
after each noise measurement, the meter was calibrated using the acoustic
calibrator for 94.0 dB(A) at 1000 Hz.
If the difference in the calibration level before and after measurement
was more than 1.0 dB(A), the measurement would be considered invalid and repeat
of noise measurement would be required after re-calibration or repair of the
equipment.
(e) During the
monitoring period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(f) Noise
measurement was paused during periods of high intrusive noise (e.g. dog
barking, helicopter noise) if possible. Observations were recorded when
intrusive noise was unavoidable.
(g) Noise monitoring
was cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The
microphone head of the sound level meter was cleaned with soft cloth at regular
intervals.
(b) The
meter and calibrator were sent to the supplier or HOKLAS laboratory to check
and calibrate at yearly intervals.
(c) Calibration
certificates of the sound level meters and acoustic calibrators are provided in
Appendix C.
Table
3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring
Station |
Average Leq
(30 mins), dB(A) |
Range of Leq (30 mins), dB(A) |
Limit Level Leq (30 mins), dB(A) |
NMS5 |
66 |
60 ¡V 70 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved
Oxygen (mg/L) (surface, middle and bottom) |
Surface and
Middle |
5.0 |
4.2 except 5
for Fish Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity
(NTU) |
Depth average |
27.5 or 120%
of upstream control station¡¦s turbidity at the same tide of the same day; The action
level has been amended to ¡§27.5 and 120% of upstream control
station¡¦s turbidity at the same tide of the same day¡¨ since 25 March 2013. |
47.0 or 130%
of turbidity at the upstream control station at the same tide of same day; The limit
level has been amended to ¡§47.0 and 130% of turbidity at the
upstream control station at the same tide of same day¡¨ since 25 March 2013. |
Suspended
Solid (SS) (mg/L) |
Depth average |
23.5 or 120%
of upstream control station¡¦s SS at the same tide of the same day; The action
level has been amended to ¡§23.5 and 120% of upstream control
station¡¦s SS at the same tide of the same day¡¨ since 25 March 2013. |
34.4 or 130%
of SS at the upstream control station at the same tide of same day and 10mg/L
for Water Services Department Seawater Intakes; The limit
level has been amended to ¡§34.4 and 130% of SS at the upstream
control station at the same tide of same day and 10mg/L for Water Services
Department Seawater Intakes¡¨ since 25 March 2013 |
Notes:
(1)
Depth-averaged is calculated by taking the
arithmetic means of reading of all three depths.
(2)
For DO, non-compliance of the water quality limit
occurs when monitoring result is lower that the limit.
(3)
For SS & turbidity non-compliance of the water
quality limits occur when monitoring result is higher than the limits.
(4)
The change to the Action and limit Levels for Water
Quality Monitoring for the EM&A works was approved by EPD on 25 March 2013.
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field Stations: Sensitive Receiver
Stations: |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen (DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P
Suspended Solids (SS), mg/L |
Three times per week
during mid-ebb and mid-flood tides (within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored). |
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |
|
Easting |
Northing |
||
IS5 |
Impact Station
(Close to HKLR construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station
(Close to HKLR construction site) |
812101 |
817873 |
IS7 |
Impact Station
(Close to HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station
(Close to HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact Station
(Close to HKBCF construction site) |
813273 |
818850 |
IS10 |
Impact Station
(Close to HKBCF construction site) |
812577 |
820670 |
IS10(N) |
Impact Station
(Close to HKBCF construction site) |
812942 |
820881 |
SR3 |
Sensitive
receivers (San Tau SSSI) |
810525 |
816456 |
SR4 |
Sensitive
receivers (Tai Ho Inlet) |
814760 |
817867 |
SR4(N) |
Sensitive
receivers (Tai Ho Inlet) |
814705 |
817859 |
SR5 |
Sensitive
receivers (Artificial Reef In NE Airport) |
811489 |
820455 |
SR5(N) |
Sensitive
receivers (Artificial Reef In NE Airport) |
812569 |
821475 |
SR10A |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823741 |
823495 |
SR10B |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823686 |
823213 |
SR10B(N) |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823683 |
823187 |
CS2 |
Control
Station (Mid-Ebb) |
805849 |
818780 |
CS(Mf)5 |
Control
Station (Mid-Flood) |
817990 |
821129 |
Remarks: 1) Technical issues have been
observed from impact monitoirng of the Contract and thus published informatin
from Monthly EM&A Report
for June 2017 prepared for Contract No.
HY/2010/02 and Contract No. HY/2011/09 were adopted for the Contract.
2)
Due to safety concern and topographical condition of the original
locations of SR4 and SR10B, alternative impact water quality monitoring
stations, naming as SR4(N) and SR10B(N), were adopted, which are situated in
vicinity of the original impact water quality monitoring stations (SR4 and
SR10B) and could be reachable.
3)
Due to marine work of the Expansion of Hong Kong International Airport
into a Three-Runway System (3RS Project), original locations of water quality
monitoring stations SR5 and IS10 are enclosed by works boundary of 3RS
Project. Alternative impact water quality monitoring stations, naming as
SR5(N) and IS10(N) was approved in 12 May 2017 and were adopted starting from
15 May 2017 to replace the original locations of water quality monitoring for
Contract No. HY/2010/02.
|
Table 5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster |
|
NEL |
NWL |
|
Action Level |
STG < 4.2 & ANI < 15.5 |
STG < 6.9
& ANI < 31.3 |
Limit Level |
(STG < 2.4
& ANI < 8.9) and (STG < 3.9 & ANI < 17.9) |
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.