Contract No.
HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road
Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities
Monthly EM&A Report No.135 (Dec 2023)
9
January 2024
Revision
0
Main
Contractor Designer
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Month
2....... Air Quality Monitoring
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4....... Water
Quality Monitoring
4.3 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring
Schedule for the Reporting Month
6.1 Sedimentation
Rate Monitoring
6.3 Mudflat
Ecology Monitoring Methodology
6.4 Event
and Action Plan for Mudflat Monitoring
6.5 Mudflat
Ecology Monitoring Results and Conclusion
7....... Environmental Site
Inspection and Audit
7.2 Advice
on the Solid and Liquid Waste Management Status
7.3 Environmental
Licenses and Permits
7.4 Implementation
Status of Environmental Mitigation Measures
7.5 Summary
of Exceedances of the Environmental Quality Performance Limit
7.6 Summary
of Complaints, Notification of Summons and Successful Prosecution
8.1 Construction
Programme for the Coming Months
8.2 Environmental
Monitoring Schedule for the Coming Month
Figures
Figure 1.1 Location
of the Site
Figure 2.1 Environmental
Monitoring Stations
Figure 2.2 Transect
Line Layout in Northwest and Northeast Lantau Survey Areas
Figure 6.1 Mudflat
Survey Areas
Appendices
Appendix A Environmental
Management Structure
Appendix
B Construction Programme
Appendix C Calibration
Certificates
Appendix D Monitoring Schedule
Appendix E Monitoring Data and
Graphical Plots
Appendix F Event and Action Plan
Appendix G Wind Data
Appendix H Dolphin Monitoring
Results
Appendix I Mudflat
Monitoring Results
Appendix J Waste Flow Table
Appendix K Cumulative Statistics
on Complaints
Appendix L Environmental Licenses
and Permits
Appendix M Implementation Schedule of
Environmental Mitigation Measures
Appendix N Record of ¡§Notification
of Summons and Prosecutions¡¨
Appendix O Location of Works Areas
Executive Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern waters of the Hong Kong International Airport
(HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The
main works of the Contract include land tunnel at Scenic Hill, tunnel
underneath Airport Road and Airport Express Line, reclamation and tunnel to the
east coast of the Airport Island, at-grade road connecting to the HKBCF and
highway works of the HKBCF within the Airport Island and in the vicinity of the
HKLR reclamation. The Contract is
part of the HKLR Project and HKBCF Project, these projects are considered to be
¡§Designated Projects¡¨, under Schedule 2 of the Environmental Impact Assessment
(EIA) Ordinance (Cap 499) and Environmental Impact Assessment (EIA) Reports
(Register No. AEIAR-144/2009 and AEIAR-145/2009) were prepared for the
Project. The current Environmental
Permit (EP) EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on
22 December 2014 and 11 April 2016, respectively. These documents are available
through the EIA Ordinance Register. The construction phase of Contract was commenced on 17 October 2012.
BMT Hong Kong Limited was
appointed by the Contractor to implement the Environmental Monitoring &
Audit (EM&A) programme for the Contract in accordance with the Updated
EM&A Manual for HKLR (Version 1.0) and provided environmental team services
to the Contract until 31 July 2020.
ANewR Consulting Limited has been employed by HyD
as the Independent Environmental Checker (IEC) and Environmental Project Offer
(ENPO) for the Project with effective from 1 October 2022.
This is the 135th
Monthly EM&A report for the Contract which summarizes the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 30 December 2023.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of the monitoring activities during this
reporting month is listed below:
1-hr TSP Monitoring at
AMS5 |
5, 11, 15, 21 and
27 December 2023 |
24-hr TSP Monitoring at
AMS5 |
4, 8, 14, 20
and 26 December 2023 |
Noise Monitoring |
5, 11, 21 and 27 December 2023 |
Water Quality Monitoring |
1, 4, 6, 8, 11, 13, 15, 18,
20, 22, 25, 27 and 29 December 2023 |
Chinese White Dolphin
Monitoring |
4, 6, 8 and 11 December
2023 |
Site Inspection |
5, 15, 21 and 29 December
2023 |
Mudflat Monitoring
(Ecology) |
2, 3, 4 and 5 December 2023 |
Mudflat Monitoring (Sedimentation
Rate) |
4 December 2023 |
The existing air quality
monitoring location AMS6 - Dragonair / CNAC (Group)
Building (HKIA) was handed over to Airport Authority Hong Kong on 31 March
2021. 1-hr and 24-hr TSP monitoring at AMS6 was temporarily suspended
starting from 1 April 2021. A new alternative air quality monitoring location
is still under processing. |
Breaches of Action and Limit Levels
A summary of environmental exceedances
for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
0 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
0 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
0 |
0 |
Complaint Log
There was no complaint received
in relation to the environmental impacts during this reporting month.
Notifications
of Summons and Prosecutions
There were no
notifications of summons or prosecutions received during this reporting month.
Reporting
Changes
This report has been developed
in compliance with the reporting requirements for the subsequent EM&A
reports as required by the Updated EM&A Manual for HKLR (Version 1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May
2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was
observed inside the perimeter silt curtain of Contract HY/2010/02 on 1 July
2013, as such the original impact water quality monitoring location at IS(Mf)9 was temporarily shifted outside the silt curtain. As advised by the Contractor of HY/2010/02 in August 2013, the perimeter
silt curtain was shifted to facilitate safe anchorage zone of construction
barges/vessels until end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N
since 1 July 2013. According to the
water quality monitoring team¡¦s observation on 24 March 2014, the original
monitoring location of IS(Mf)9 was no longer enclosed
by the perimeter silt curtain of Contract HY/2010/02. Thus, the impact water
quality monitoring works at the original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
The water quality
monitoring stations at IS10 (Coordinate: 812577E, 820670N) and SR5 (811489E,
820455N) are located inside Hong Kong International Airport (HKIA) Approach
Restricted Areas. The previously granted Vessel's Entry Permit for accessing
stations IS10 and SR5 were expired on 31 December 2016. During the permit renewing
process, the water quality monitoring location was shifted to IS10(N)
(Coordinate: 813060E, 820540N) and SR5(N) (Coordinate: 811430E, 820978N) on 2,
4 and 6 January 2017 temporarily. The permit has been granted by Marine
Department on 6 January 2017. Thus, the impact water quality monitoring works
at original monitoring location of IS10 and SR5 has been resumed since 9
January 2017.
Transect lines 2, 3, 4, 5,
6 and 7 for dolphin monitoring have been revised and transect line 24 has been
added due to the presence of a work zone to the north of the airport platform
with intense construction activities in association with the construction of
the third runway expansion for the Hong Kong International Airport. The EPD
issued a memo and confirmed that they had no objection on the revised transect
lines on 28 July 2017. The alternative dolphin transect lines are adopted
starting from August¡¦s dolphin monitoring.
The role and responsibilities as the ET Leader of the Contract was
temporarily taken up by Mr Willie Wong instead of Ms Claudine Lee from 25 September 2017 to 31 December 2017.
The topographical condition of the water monitoring
stations SR3 (Coordinate: 810525E, 816456N), SR4 (Coordinate: 814760E,
817867N), SR10A (Coordinate: 823741E, 823495N) and SR10B (Coordinate: 823686E,
823213N) cannot be accessed safely for undertaking water quality monitoring.
The water quality monitoring has been temporarily conducted at alternative
stations, namely SR3(N) (Coordinate 810689E, 816591N), SR4(N) (Coordinate:
814705E, 817859N) and SR10A(N) (Coordinate: 823644E, 823484N) since 1 September
2017. The water quality monitoring at station SR10B was temporarily conducted
at Coordinate: 823683E, 823187N on 1, 4, 6, 8 September 2017 and has been
temporarily fine-tuned to alternative station SR10B(N2) (Coordinate: 823689E,
823159N) since 11 September 2017. Proposal for permanently relocating the
aforementioned stations was approved by EPD on 8 January 2018.
The works area WA5
was handed over to other party on 22 June 2013.
According to
latest information received in July 2018, the works area WA7 was handed over to
other party on 28 February 2018 instead of 31 January 2018.
Original WQM stations IS8 and SR4(N) are located
within the active work area of TCNTE project and the access to the WQM stations
IS8 (Coordinate: E814251, N818412) and SR4(N) (Coordinate: E814705, N817859)
are blocked by the silt curtains of the Tung Chung New Town Extension (TCNTE)
project. Alternative monitoring stations IS8(N) (Coordinate: E814413, N818570)
and SR4(N2) (Coordinate: E814688, N817996) are proposed to replace the original
monitoring stations IS8 and SR4(N). Proposal for permanently relocating the
aforementioned stations was approved by EPD on 20 August 2019. The
water quality monitoring has been conducted at stations IS8(N) and SR4(N2) on
21 August 2019.
There were no marine works conducted by
Contract No. HY/2011/03 since July 2019. A proposal for temporary suspension of
marine related environmental monitoring (water quality monitoring and dolphin
monitoring for the Contract No. HY/2011/03) was justified by the ET leader and verified
by IEC in mid of September 2019 and it was approved by EPD on 24 September
2019. Water quality monitoring and dolphin monitoring for the Contract will not
be conducted starting from 1 October 2019 until marine works (i.e. toe loading
removal works) be resumed. As discussed with Contract No. HY/2012/08, they will
take up the responsibility from Contract No. HY/2011/03 for the dolphin
monitoring works starting from 1 October 2019.
According to
information received in January 2020, the works area WA3 and WA4 were handed
over to Highways Department on 23 December 2019 and 14 March 2019 respectively.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Manson Yeung instead of Mr Ray Yan since 18 May 2020.
Mr. Leslie Leung
was Environmental Team Leader of the Contract for July 2020. The role and
responsibilities as the Environmental Team Leader of the Contract has been
taken up by Ms. Claudine Lee with effective from 1 August 2020.
The existing air quality monitoring location AMS6 - Dragonair
/ CNAC (Group) Building (HKIA) was handed over to Airport Authority Hong Kong
on 31 March 2021. 1-hr and 24-hr TSP monitoring at AMS6 was temporarily
suspended starting from 1 April 2021. A new alternative air quality monitoring
location is still under processing.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Brian Tam instead of Mr Manson Yeung since 12
April 2021.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Adi Lee instead of Mr Brian Tam since 3 May
2022.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Brian Tam
instead of Mr Adi Lee since 25 July 2022.
The role and
responsibilities as the ENPO Leader of the Contract has been taken up by Mr
Louis Kwan from ANewR Consulting Limited instead of Mr H.Y. Hui from Ramboll Hong Kong
Limited since 1 October 2022.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr James Choi
from ANewR Consulting Limited instead of Mr Brian Tam from Ramboll Hong Kong
Limited since 1
October 2022.
Future Key
Issues
The future key
issues include potential noise, air quality, water quality and ecological
impacts and waste management arising from the following construction activities
to be undertaken in the upcoming month:
¡P
Landscape maintenance
works at SHT East Portal.
¡P
Removal of Temporary
Toe Loading Platform at Portion X.
¡P
New reclamation along
the east coast of the approximately 23 hectares.
¡P
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in length
with three (3) lanes for the east bound carriageway heading to the HKBCF and
four (4) lanes for the westbound carriageway heading to the HZMB Main Bridge.
¡P
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
¡P
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
¡P
Road links between the
HKBCF and the HKIA including new roads and the modification of existing roads
at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
¡P
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the Dragonair Headquarters Building, including the construction
of buildings, connection roads and other associated facilities.
¡P
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Supervising Officer¡¦s Representative |
(Senior Resident
Engineer, SRE) |
Eddie Tsang |
3968 4802 |
2109 1882 |
Environmental Project Office / Independent Environmental Checker |
Environmental Project Office Leader |
Louis Kwan |
9275 0975 |
3007 8448 |
Independent Environmental Checker |
James Choi |
6122 5213 |
3007 8448 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968 7002 |
2109 2588 |
Environmental Officer |
Federick Wong |
3968 7117 |
2109 2588 |
|
Environmental Team (Meinhardt Infrastructure and Environment Limited) |
Environmental Team Leader |
Claudine Lee |
2859 5409 |
2559 0738 |
724 hours complaint
hotline |
--- |
--- |
5699 5730 |
--- |
|
Table 1.2 Construction Activities During Reporting Month
Description of Activities |
Site Area |
Landscape
maintenance works |
SHT East Portal |
Removal
of Temporary Toe Loading Platform |
Portion X |
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ¡V Dragonair / CNAC (Group) Building
(HKIA) |
360 |
Table 2.2 Action
and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ¡V Dragonair / CNAC (Group) Building
(HKIA) |
173 |
260 |
Table 2.3 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable direct reading dust meter (1-hour
TSP) |
Sibata Digital Dust Indicator (Model No. LD-5R) |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total
Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170) |
Table 2.4 Locations
of Impact Air Quality Monitoring
Stations
Monitoring
Station |
Location |
AMS5 |
Ma Wan Chung Village (Tung Chung) |
AMS6 |
Dragonair / CNAC (Group) Building (HKIA) |
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour TSP |
Three times every 6 days while the highest dust impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was
at least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the
monitoring stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ¡Ó2.5% deviation over 24-hour
sampling period.
(b)
Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around
(iii)
All filter papers were prepared and analysed by ALS Technichem
(HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive
quality assurance and quality control programmes.
(c) Field
Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied was
sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium
strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24
hours, and the starting time, weather condition and the filter number were
recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so that only surfaces with collected
particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK)
Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE
(iii) Calibration certificate of the HVSs are provided in Appendix C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ¡§TIME SETTING¡¨ switch to [BG].
(iv)
Push ¡§START/STOP¡¨ switch to perform background measurement for 6
seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi)
Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨ is indicated in the
display.
(vii)
Push ¡§START/STOP¡¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ¡§TIME SETTING¡¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ¡§START/STOP¡¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The
1-hour TSP meter was calibrated at 1-year intervals against a Tisch
Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High
Volume Air Sampler. Calibration certificates of the Laser Dust Monitors are
provided in Appendix C.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
60 |
31-84 |
352 |
500 |
AMS6 |
|
|
360 |
500 |
Table 2.7 Summary of 24-hour TSP Monitoring Results During the
Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
90 |
54-121 |
164 |
260 |
AMS6 |
|
|
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ¡V Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900 hours on normal
weekdays |
When one documented
complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level
Meter |
B&K 2238 |
RION NL-52 |
|
Acoustic Calibrator |
B&K 4231 |
RION NC-74 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung Village (Ma Wan
Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins measurement at
each monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90
would be recorded. |
At least once per week |
(a) The sound level meter was
set on a tripod at a height of
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency
weighting: A
(ii) time weighting: Fast
(iii) time
measurement: Leq(30-minutes)
during non-restricted hours i.e. 07:00 ¡V 1900 on normal weekdays
(d)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
1.0 dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
(e)
During the monitoring
period, the Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(f)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(g)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station |
Average Leq
(30 mins), dB(A) |
Range of Leq
(30 mins), dB(A) |
Limit Level Leq
(30 mins), dB(A) |
NMS5 |
61 |
59-64 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved Oxygen (mg/L)
(surface, middle and bottom) |
Surface and Middle |
5.0 |
4.2 except 5 for Fish
Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity (NTU) |
Depth average |
27.5 or 120% of upstream
control station¡¦s turbidity at the same tide of the same day; The action level has been
amended to ¡§27.5 and 120% of upstream control station¡¦s turbidity at the same
tide of the same day¡¨ since 25 March 2013. |
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day; The limit level has been
amended to ¡§47.0 and 130% of turbidity at the upstream control station at the
same tide of same day¡¨ since 25 March 2013. |
Suspended Solid (SS)
(mg/L) |
Depth average |
23.5 or 120% of upstream
control station¡¦s SS at the same tide of the same day; The action level has been
amended to ¡§23.5 and 120% of upstream control station¡¦s SS at the same tide of
the same day¡¨ since 25 March 2013. |
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes; The limit level has been
amended to ¡§34.4 and 130% of SS at the upstream control station at the same
tide of same day and 10mg/L for Water Services Department Seawater Intakes¡¨
since 25 March 2013 |
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3) For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4) The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
Table 4.2 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO and Temperature Meter,
Salinity Meter, Turbidimeter and pH Meter |
YSI Model 6820 (V2) YSI Pro Quatro |
Positioning Equipment |
Garmin GPS72H |
Water Depth Detector |
Lowrance x-4 |
Water Sampler |
Kahlsio Water Sampler (Vertical)
2.2 L with messenger |
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field
Stations: Sensitive Receiver
Stations: |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen
(DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P Suspended Solids (SS), mg/L |
Three times per week
during mid-ebb and mid-flood tides (within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored). |
Remark:
1) Original WQM stations IS8 and SR4(N) are located within the active work area
of TCNTE project and the access to the WQM stations IS8 (Coordinate: E814251,
N818412) and SR4(N) (Coordinate: E814705, N817859) are blocked by the silt
curtains of the Tung Chung New Town Extension (TCNTE) project. Alternative
monitoring stations IS8(N) (Coordinate: E814413, N818570) and SR4(N2)
(Coordinate: E814688, N817996) were proposed to replace the original monitoring
stations IS8 and SR4(N). Proposal for permanently relocating the aforementioned
stations was approved by EPD on 20 August 2019. The water quality monitoring
has been conducted at stations IS8(N) and SR4(N2) since 21 August 2019.
2) The water quality monitoring programme was temporarily suspended
during the reporting month since no marine works were scheduled or conducted,
therefore no water quality monitoring was conducted.
Table 4.4 Impact Water
Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |