Contract No. HY/2012/07
Tuen Mun ¡V Chek
Lap Kok
Link ¡V Southern Connection Viaduct Section
Contract Specific Environmental Monitoring and Audit Manual
Contents
1.1
Background Information
1.2
Policy
1.3
EM&A Programme Objectives
1.4
Scope of the EM&A Programme
1.5
Project Organisation
1.6
Terminology
2.1
Scope of the Project
2.2 Northern
Section in Tuen Mun (not applicable)
2.3
Submarine Tunnel
(not applicable)
2.4
Southern Section at HKBCF
/ North Lantau (not applicable)
2.5
Works Areas
2.6
Sewage and Drainage
2.7
Project Programme
2.8
Concurrent Projects
2.9
Traffic Data and Assumptions
3.1
Air Quality
Parameters
3.2
Monitoring Equipment
3.3
Laboratory Measurement/Analysis
3.4
Monitoring Locations
3.5
Baseline Monitoring
3.6
Impact Monitoring
3.7
Event and Action Plan for Air Quality
3.8
Dust Mitigation Measures
4
NOISE
4.1
Introduction
4.2
Noise Parameters
4.3
Monitoring Equipment
4.4
Monitoring Locations
4.5
Baseline Monitoring
4.6
Construction Phase Impact Monitoring
4.7
Event and Action Plan for
Construction Noise
4.8
Noise Mitigation Measures
5.1
Introduction
5.2
Mitigation Measures
5.3
Water Quality
Parameters
5.4
Monitoring Equipment
5.5
Laboratory Measurement / Analysis
5.6
Monitoring Locations
5.7
Baseline Monitoring for Water Quality
5.8
Efficiency of Silt Curtains (not applicable)
5.9
Impact Monitoring for Water Quality
5.10 Post-construction Monitoring
5.11 Operational Phase Monitoring
5.12 Event and Action Plan
6
ECOLOGY
6.1
Introduction
6.2
Ecology EM&A Procedures
6.3
Design Phase Audit
6.4
Baseline Monitoring
6.5
Construction and Operational Phase EM&A
6.6
Mitigation and Enhancement Measures
7. LANDSCAPE AND VISUAL ASSESSMENT
7.1 Introduction
7.2 Relevant
Legislation
7.3 Methodology and Criteria
7.4 Baseline Monitoring
7.5 Event and Action Plan
7.6 Mitigation Measures
8
WASTE MANAGEMENT AND CONTAMINATED LAND
8.1
Waste Issues
8.2
Contaminated Land
8.3
Waste EM&A Requirements
9.1
Introduction
10
Landfill
Gas
Hazard Assessment
10.1 Introduction
11.1 Site Inspections
11.2 Compliance with Legal and Contractual Requirements
11.3 Environmental Complaints
11.4 Choice of Construction
Metho
12
REPORTING
12.1 General
12.2 Documentation
12.3 Design Audit Report
12.4 Baseline Monitoring Report
12.5 EM&A Reports
12.6 First EM&A Report
12.7 Subsequent EM&A Reports
12.8 Quarterly EM&A Summary Reports
12.9 Annual/Final
EM&A Review Reports
12.10 Data Keeping
12.11 Interim Notifications of Environmental Quality Limit
Exceedances
Appendices
Appendix A Environmental Mitigation Implementation Schedules
Appendix B Environmental Proformas
Annexes
Annex A Silt Curtain Arrangement & Temporary Staging Preliminary Layout
Annex B Figures
Figure 1.1 Design Phase EM&A Procedure and Organisation
Figure 1.2 Construction and Operational Phase Procedure and Organisation
Figure 2.1 General Layout of TM-CLKL
Figure 2.2a Not
applicable
Figure 2.2b Layout Plan of Southern Landfall
Figure 2.3a Not applicable
Figure 2.3b Not
applicable
Figure 2.3c Not
applicable
Figure 2.4a Not
applicable
Figure 2.4b Not
applicable
Figure 2.4c General Layout for Southern Viaduct (1)
Figure 2.4d General Layout for Southern Viaduct (2)
Figure 2.4e General Layout for Southern Viaduct (3)
Figure 2.4f General Layout for Southern Viaduct (4)
Figure 2.4g General Layout for Southern Viaduct (5)
Figure 2.4h General Layout for Southern Viaduct (6)
Figure 2.4i General Layout for Southern Viaduct (7)
Figure 2.4j General Layout for Southern Viaduct (8)
Figure 2.5a Geological Section (Sheet 1 of 3)
Figure 2.5b Not
applicable
Figure 2.5c Not
applicable
Figure 2.6a Not
applicable
Figure 2.6b Not applicable
Figure 2.6c Not applicable
Figure 2.7 Southern Viaduct Connection and Slip Roads
Figure 2.8a Not
applicable
Figure 2.8b Proposed Works Areas for TM-CLKL (Lantau Side)
Figure 2.9a Not applicable
Figure 2.9b Indicative Construction Programme in North Lantau
Figure 2.9c Not applicable
Figure 2.9d Portions of Works in North Lantau
Figure 3.1 Data Sheet for TSP Monitoring (at
the end of Section 3)
Figure 3.2 Environmental Monitoring Stations
Figure 4.1 Noise Monitoring Field Record Sheet
(at the end of Section 4)
Figure 4.2 Not applicable
Figure 5.1 Not applicable
Figure 5.2 Not applicable
Figure 5.3 Not applicable
Figure 5.4 Not applicable
Figure 5.5a Not applicable
Figure 5.5b Not applicable
Figure 5.5c Not applicable
Figure 5.6a Not applicable
Figure 5.6b Not applicable
Figure 5.6c Not applicable
Figure 5.7 Water Quality Monitoring Data Record Sheet
Figure 5.8 Not applicable
Figure 5.9 Not applicable
Figure 5.10 Not applicable
Figure 6.1 Construction Phase Ecological EM&A Procedure
Figure 6.4 Location of Stream NL1
Figure 7.1.1.1 Not applicable
Figure 7.1.1.2 Not applicable
Figure 7.1.1.3 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 3
of 5)
Figure 7.1.1.4 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 4
of 5)
Figure 7.1.1.5 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 5
of 5)
Figure 7.2.1.1 Not applicable
Figure 7.2.1.2 Not applicable
Figure 7.2.1.3 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 3 of 5)
Figure 7.2.1.4 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 4 of 5)
Figure 7.2.1.5 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 5 of 5)
Figure 7.3.1.1 Not applicable
Figure 7.3.1.2 Baseline Key VSRs and Viewpoint at Local Level
with Development Proposal Overlaid During Construction (Sheet 2 of 2)
Figure 7.3.1.3 Not applicable
Figure 7.3.1.4 Baseline Key VSRs and Viewpoint at Local Level
with Development Proposal Overlaid During Operation (Sheet 2 of 2)
Figure 7.3.2.1 Baseline Key VSRs Viewpoints at Strategic and
District Level with Development Proposal Overlaid
Figure 9.1 Not applicable
Figure 12.1 Sample Template for Interim Notifications of Environmental Quality Limits Exceedances
Annex C Summary of Change
Tables
Table 1.1 |
|
Table 2.1 |
Not applicable |
Table 2.2 |
|
Table 2.3 |
Not applicable |
Table 3.1a |
Method of Derivation of Action and
Limit Levels for Air Quality |
Table 3.1b |
|
Table 3.2 |
|
Table 4.1 |
|
Table 4.2 |
|
Table 5.1 |
|
Table 5.2a |
Proposed Water Quality Monitoring
Stations (Construction and Post-construction Phases) |
Table 5.2b |
Proposed Water Quality Monitoring
Stations (Operation Phase) |
Table 5.3 |
|
Table 5.4 |
|
Table 6.1 |
|
Table 6.2 |
|
Table 6.3 |
|
Table 6.4 |
Not applicable |
Table 6.5 |
|
Table 6.6 |
|
Table 6.7 |
Not applicable |
Table 6.8 |
Not applicable |
Table 6.9a |
|
Table 6.9b |
Event / Action Plan for During and
Post Construction Dolphin Monitoring |
Table 7.1 |
|
Table 7.2 |
|
Table 8.1 |
|
Table 8.2 |
|
Table 9.1 |
Not applicable |
Table 9.2 |
Not applicable |
Table 10.1 |
Not applicable |
Note:
All information regarding the Mf
Related Monitoring are no longer applicable as
recommended in Supporting Document of Variation of EP for TM-CLKL (EP354/2009).
1.1.1.1 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by
the Transport Department, Tuen Mun Road, Ting
Kau Bridge,
Lantau Link
and
North Lantau
Highway (NLH)
will
be operating beyond capacity after 2016 due to the increase in cross boundary traffic,
developments in the NWNT, and possible
developments in North Lantau,
including the Airport developments,
the
Lantau Logistics Park (LLP)
and
the
Hong Kong
¡V
Zhuhai
¡V
Macao
Bridge (HZMB).
In
order to cope with the anticipated
traffic demand, two new connections between
NWNT and
North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
1.1.1.2 The proposed TM-CLKL
if combined with the TMWB will
provide a direct route
linking NWNT and North Lantau, from north to south, the Kong Sham Western
Highway
(KSWH), port
back-up areas in NWNT, Tuen Mun
River Trade
Terminal, the existing EcoPark in Tuen Mun
Area 38, the Airport, the proposed
LLP,
HZMB
and
North Lantau developments. The new connection
will significantly reduce the travelling time between the KSWH and the NWNT region
at its northern side, and
1.1.1.3 In 2005, Highways
Department (HyD)
commissioned
an engineering feasibility
study (FS), namely Tuen Mun Chek Lap Kok Link and
Tuen Mun Western Bypass ¡V Feasibility Study (Agreement
No. CE 28/2005 (HY)), to evaluate the technical
feasibility and
impacts of the Project.
The FS recommended that the TM-CLKL should be a dual 2-lane road with a total length of about 9 km with
about 4 km long submarine
tunnel and 5 km long elevated structure.
1.1.1.4 In order to progress this project, Maunsell
Consultants Asia Ltd. were appointed by HyD to carry out the Assignment on Tuen Mun ¡V Chek Lap Kok
Link - Investigation under Agreement
No. CE 52/2007 (HY). The
Assignment
commenced on 19 May 2008 and shall be completed within 24 months, i.e. by mid-May 2010.
1.1.1.5 The
Feasibility Study
initially
proposed an
alignment of
the
TM-CLKL comprising a toll plaza island at Tai Mo To and this alignment formed the basis of the EIA Study Brief (ESB 175/2007). However, subsequent to these documents
being prepared and based upon the proposed schemes for the
1.1.1.6 The project is a designated project under Section A.1 of Schedule 2 of the Environmental
Impact Assessment Ordinance (EIAO).
As such, the statutory procedures under the EIAO need to be followed and an environmental permit (EP) will be required prior to the commencement of construction. Thus, as part of this assignment, an Environmental Impact Assessment (EIA) has been undertaken.
1.1.1.7 The
EIA for the project
has recommended comprehensive Environmental
Monitoring
and
Audit requirements
to be undertaken during the design,
construction and operational stages of
the project.
This Report constitutes
the
Environmental
Monitoring
and
Audit (EM&A) Manual for the
proposed Tuen Mun - Chek Lap Kok Link (TM-CLKL) Project, providing details of the EM&A
recommendations.
1.1.1.8 The
Hong
Kong SAR Government¡¦s
applicable environmental regulations
for noise, air
quality, ecology,
water quality,
landscape and visual resources
and waste
management
and heritage protection, the Hong Kong Planning Standards
and Guidelines and recommendations
in the TM-CLKL EIA Report have served as guidance documents in the preparation of this Manual. This EM&A Manual
fulfills the requirements of the Study Agreement and follows the approach
recommended in EPD¡¦s
Generic EM&A Manual, Annex 21 of the Technical
Memorandum on
the EIA
Process
and
EM&A Guidelines
for
Development
Projects in
1.2.1.1 The Supervising
Officer¡¦s Representative (SOR) and the Contractor
shall adopt
Environmental
Policy Statements in accordance with the requirements of this Manual in order to
foster
a sound EM&A programme to protect
the environment.
The following policy statements shall be adopted:
- establish a commitment
to environmental excellence
in all activities arising from the development project;
- encourage
the
adoption of
environmental management
principles
to prevent potential impacts and minimise adverse impacts; and
- commit to the recommendations
in the EIA study report and related EIA
process requirements.
1.3.1.1 The broad objective of this EM&A Manual is to define the procedures of the EM&A programme for monitoring the environmental
performance
of the TM-
CLKL project during design, construction and implementation.
1.3.1.2 The manual provides details of the environmental monitoring requirements arising
from the EIA including air, noise and water quality, as well
as audit recommendations for the noise, air, water quality, ecology, landscape and visual, waste and cultural heritage. The purposes of the defined EM&A programme
are as follows:
- to ensure the specified
mitigation recommendations of
the EIA
are
included in the design of
the project;
- to clarify and identify sources of pollution,
impact and nuisance
arising from the works;
- to confirm compliance with legal, contract specifications
and EIA study recommendations;
- to provide an early warning system for impact prevention;
- to
provide
a database of environmental parameters against
which to determine any short term or long term environmental impacts;
- to propose timely, cost-effective and viable solutions to actual or potential environmental issues;
- to
monitor performance
of the
mitigation measures and to
assess
their
effectiveness and, whenever necessary, identify any further need for additional measures;
- to verify the EIA predicted impacts;
- to collate information and evidence for use in public, District Council and
Government consultation; and
- to audit environmental performance.
1.3.1.3 EM&A procedures are required during the design, construction
and
operational
phases of the project implementation and a summary of the requirements for each of
the environmental parameters is detailed in Table 1.1 below.
Table 1.1 Summary of EM&A Requirements
Parameter |
EM&A
Phase |
||
Design |
Construction Phase |
Operational
Phase |
|
Air Quality |
|
Y |
|
Noise |
|
Y |
|
Ecology |
Y |
Y |
Y |
Water Quality |
|
Y |
Y |
Landscape
and Visual |
Y |
Y |
Y |
Waste/Contaminated Land |
|
Y |
|
Cultural
Heritage |
Not applicable
as cultural heritage resource is not identified for the works area of the
Contract. |
1.4.1.1 The scope of the EM&A programme
is to undertake the following, which follows the
demarcation of monitoring responsibilities set out in Environmental
Project Office¡¦s letter dated 29.10.2013:
a)
Implement
monitoring
and audit activities for each
environmental
parameter as follows:
Dust: |
i)
Establish baseline dust levels at specified locations and review these
levels on a regular basis. |
|
ii)
Implement construction dust impact monitoring programme. |
Noise: |
i)
Establish baseline noise, levels at specified locations and review
these levels on a regular basis. |
|
ii)
Implement
construction noise impact monitoring |
Ecology: |
i)
Implement design phase audit for ecological dolphin protection
specifications, ecological translocation specifications and design integrated
ecological mitigation measures. |
|
ii)
Implement baseline survey to establish existing ecological conditions. |
|
iii)
Implement construction phase monitoring and audit requirements for
ecology resources. |
|
iv)
Implement operational phase monitoring. |
Water Quality: |
i)
Establish baseline water quality levels at specified locations and
review these levels on a regular basis. |
|
ii)
Implement construction water quality impact monitoring programme. |
|
iii)
Implement operational phase water quality impact monitoring programme. |
|
|
Landscape
and |
i)
Design detailed landscape specifications. |
Visual: |
ii)
Implement baseline survey to establish/confirm existing landscape and
visual conditions. |
|
iii)
Implement construction phase audit requirements for landscape and visual
resources. |
|
iv)
Implement operational phase audit
requirements for landscape and visual aspects. |
Waste: |
i)
Implement construction phase audit requirements for waste aspects. |
Heritage:
|
i)
Not applicable |
|
|
b)
Liaison and provision of advice to construction site staff on the purposes and implementation of the EM&A programme.
c)
Identify and resolve environmental issues that may arise from the project.
d)
Check
and quantify the Contractor¡¦s
overall performance, implement Event/Action Plans and recommend and implement remedial actions to
mitigate adverse environmental
effects as identified by
the EM&A programme
and EIA.
e)
Conduct monthly reviews of
monitored impact
data during the construction phase and bi-monthly reviews during the operational phase as
the basis for assessing compliance with defined criteria and ensuring that necessary mitigation
measures
are identified,
designed
and implemented
and
to undertake additional ad hoc monitoring and audit as required by
particular circumstances.
f)
Evaluate and interpret all environmental
monitoring data
to provide
an early indication should any of the environmental
control measures or
practices fail to achieve the acceptable standards and to verify the environmental impacts predicted in the EIA.
g)
Manage
and liaise with other individuals or
parties
concerning any relevant environmental issues.
h)
Audit the effectiveness of the
Environmental Management System (EMS) practices and procedures and implement
any changes as appropriate.
i)
Conduct regular site audits of formal or informal nature to assess:
- the level of the Contractor¡¦s general environmental awareness;
- the Contractor¡¦s implementation of the recommendations in the EIA;
- the Contractor¡¦s performance as measured
by the EM&A;
- the need for specific mitigation measures to be implemented or the continued usage of
those previously agreed;
and
- to
advise the site staff of any
identified potential environmental issues.
j)
Submit EM&A
reports which summarise
project monitoring and auditing data, with full interpretation, illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of
the
implementation status of agreed mitigation measures.
1.4.1.2 Thus, this EM&A
Manual provides the following information:
a)
Description of the project.
b)
Identification and recommendations for
monitoring requirements for all phases of
development, including:
- identification of sensitive receivers;
- monitoring locations;
- monitoring parameters and frequencies;
- monitoring equipment to be used;
- programmes for baseline monitoring and impact monitoring; and
- data management of monitoring results.
c) The organisation management structure, and procedures for auditing of the Project and implementation of mitigation measures that are recommended
for the Project.
d) The environmental quality performance limits for compliance auditing for each of the recommended monitoring
parameters to ensure compliance with relevant environmental quality objectives, statutory or planning
standards.
e) Organisation
and management
structure, and procedures for reviewing the design
submissions, monitoring results and auditing the compliance of
the
monitoring data with the environmental
quality performance limits,
contractual and regulatory requirements, and environmental
policies and
standards.
f) Event and Action plans for impact and compliance procedures.
g) Complaints handling, liaison and consultation procedures.
h) Interim notification of exceedances, reporting procedures, report
formats and
reporting
frequency
including periodical quarterly summary reports and annual reviews to cover all construction, post-Project and operational phases of the development.
i)
Implementation schedules,
summarising
all
recommended mitigation measures.
1.4.1.3 This
Manual is considered to be a working document and should be reviewed periodically and revised once substantial changes have been made.
1.5.1.1 For the purpose of this EM&A Manual, the Highways Department of the Hong
Kong SAR Government is
referred
to as the ¡§Employer¡¨
and the Project ¡§Supervising Officer¡¨ defined
as the Supervising Officer¡¦s Representative (SOR),
who
will
be responsible for the supervision of
the construction of the Project.
1.5.1.2 The mitigation/enhancement measures recommended by the TM-CLKL EIA that will require
a design audit or preparation
of
specifications
during the detailed
design phase of
the project will include:
- bored
piling monitoring programme;
- pre,
during and post construction dolphin monitoring;
- 250m
dolphin exclusion zone for use during dredging, reclamation, sheet, bored
piling works and temporary staging construction;
- acoustic decoupling methods for
use during reclamation and
dredging works;
- marine
vessel control specifications;
- deployment
of an artificial reef (Not applicable);
- installation of
hoarding for the
protection of the
pitcher plants and surrounding habitat (Not
applicable);
- coral
translocation;
- design
of toll plaza for grave G1 set back and protection (Not applicable); and
- landscape
design drawings.
1.5.1.3 In respect of the design phase EM&A, the Consultant commissioned to undertake the Detailed
Design
contract will be
required
to
designate
an
auditor(s)
to undertake the preparation
of
the
design specifications
as detailed
above, in
addition to an environmental
audit of
the
design
of
the specified
landscape measures in order to ensure that the recommendations of the EIA have been fully
and properly specified. The Consultant
shall use suitably qualified staff
to undertake the audit requirements to the satisfaction of the EPD and the AFCD as
appropriate. A flow chart of the design phase EM&A
procedures is shown in Figure 1.1.
1.5.1.4 During the construction and operational phases of the project, an Environmental
Team (ET) is to be employed by the Contractor. The ET will be headed by an
Environmental Team
Leader (ETL). He shall
ensure
the Contractor¡¦s compliance with the project¡¦s
environmental performance requirements during construction and undertake the post construction EM&A works and his responsibilities will
include field measurements,
sampling, analysis
of monitoring results,
reporting
and
auditing.
The ETL shall be approved by the SOR
and
the Director of Environmental
Protection (DEP) and shall be competent and shall have at least 7
years relevant
environmental monitoring and audit experience
on projects of a similar scale and nature.
1.5.1.5 The ET will comprise suitably qualified support staff to carrying out the EM&A
programme. The ET shall be independent and shall not be in any way connected
to
the Contractor¡¦s company.
Due to the specialist nature of some of the EM&A works required for this project,
the ET should comprise professionals proficient to undertake the tasks involved. Thus, the ET should include personnel experienced
in
noise, dust and water quality monitoring and mitigation, supervision of waste
management,
compensatory tree planting, coral relocation and dolphin monitoring
and
supervision.
1.5.1.6 Accordingly, a qualified dolphin specialist(s), together with a suitably experienced team of dolphin spotters, and a coral specialist, to the satisfaction of AFCD, will be required as part of
the ET to undertake the dolphin abundance monitoring, implement the dolphin exclusion zones and undertake the coral relocation process.
In addition,
a Registered Landscape Architect, as defined by the Landscape Architect¡¦s Registration Board, will be required on the ET to monitor and audit
the landscaping installation works and assist in the audit of the ecological transplantation and restoration works.
1.5.1.7 The overall duties of ETL and the team are as follows:
- Sampling, analysis
and
statistical evaluation of
monitoring parameters with
reference
to
the
EIA
study recommendations and requirements
in respect of noise, dust and water quality.
- Environmental site surveillance
- Audit of
compliance with environmental protection and pollution
prevention and control regulations.
- Monitor the implementation of environmental mitigation measures.
- Monitor compliance with the
environmental
protection
clauses/specifications in the Contract.
- Review construction programme
and comment as necessary.
- Review construction methodology and comment as necessary.
- Complaint
investigation, evaluation and
identification of
corrective measures.
- Audit of
the EMS and recommend and implement any
changes as
appropriate.
- Liaison
with the Independent
Environmental
Checker
(IEC) on
all environmental performance matters.
-
Advice to the
Contractor on environmental improvement, awareness, enhancement matter, etc.,
on site.
- Timely submission of the designated EM&A reports to the SOR, the IEC, the DEP, the AFCD and the AMO as appropriate.
1.5.1.8 In addition to the ETL and ET, an Independent Environmental
Checker (IEC) shall be employed to advise the SOR on environmental
issues related to the project.
The role of the IEC shall be independent
from
the management
of
construction
works, but the IEC shall be empowered to audit the environmental performance of
the construction activities and operational mitigation. The IEC shall have project management experience in addition to the requirements of the ET specified above and the appointment of the IEC will be subject to the approval
of the SOR and the
DEP. The IEC may require specialist support staff in order to properly carry out
his
duties, which shall include the following:
-
Review and audit all
aspects of the EM&A programme.
-
Validate and confirm
the accuracy of monitoring results, monitoring equipment, monitoring locations,
monitoring procedures and locations of sensitive receivers.
-
Carry out
random sample check and
audit on monitoring data and sampling procedures, etc.
-
Conduct random site
inspection.
-
Audit the EIA
recommendations and requirements against the status of implementation of
environmental protection measures on site.
-
Review the
effectiveness of environmental mitigation measures and project environmental
performance.
-
Audit the
Contractor¡¦s construction methodology and agree the least impact alternative in
consultation with the ET and the Contractor.
-
Check complaint cases
and the effectiveness of corrective measures.
-
Review EM&A
report submitted by the ET.
-
Feedback audit
results to ET by signing off relevant EM&A proformas.
1.5.1.9 An
organisation
chart
showing
the
lines
of
communication
between
the
key
parties with respect to the EM&A works is provided on Figure 1.2.
Both the ET
and IEC shall be retained for the duration of the EM&A works which will span both the construction phase and one year into the operational phase of the project.
The operational EM&A works will be the responsibility of the Contractor and will be undertaken in parallel to the maintenance period after the completion of
construction.
1.5.1.10 Notwithstanding the above, given that the TM-CLKL, HKBCF and HKLR will be
constructed concurrently, an
Environmental Protection Office (ENPO)
or equivalent to oversee the cumulative construction projects in North Lantau area
will be established
by the Project
Proponent.
The responsibility of the ENPO would be similar to that of
the IEC but should also include:
-
coordination of the monitoring and auditing works for all the on-going projects in
the area in order to identify possible sources/causes of exceedances
and recommend suitable remedial actions where appropriate;
-
identify and assess
cumulative impacts including possible sources/causes of exceedance
and recommending suitable remedial actions;
-
undertake liaison
with the mainland project teams counterparts to identify and assess any
cross-boundary cumulative impacts; and
-
coordinate the
assessment and response to complaints/enquires from locals, green groups,
district councils or the public at large.
1.5.1.11 The exact responsibilities and organisation of
the ENPO will be defined during the detailed design stage.
1.6.1.1 To clarify the terminology for impact monitoring and audit, key definitions are
specified below and are used throughout this Manual.
1.6.1.2 Monitoring refers to the systematic collection of data through a series of repetitive
measurements. The stages of monitoring are defined in this document as follows:
a) Baseline
Monitoring refers
to the measurement
of parameters, such as
noise and air quality impact parameters, during a representative
pre-project period for the purpose of
determining the nature and ranges of natural
variation and to establish, where appropriate, the nature of change.
b) Impact Monitoring involves the measurement of environmental impact parameters, such as noise and air quality, during Project construction
and implementation so as
to detect changes in these parameters which
can
be attributed to the Project.
1.6.1.3 Audit is a term that infers the verification of a practice and certification of data.
The types of audit are defined below:
a) Compliance audit is defined as follows:
-
the process of verification that all or selected parameters measured by
a noise or air quality impact monitoring programme or levels of
an operation
are
in compliance with
regulatory requirements and internal policies and standards; and
-
the determination of
the degree and scope of
any
necessary remediation in
the event of
exceedance
of compliance.
b) Post Project
Audit is carried
out
after
the
implementation and commissioning of a Project.
1.6.1.4 For the purpose of noise, air and water quality impact monitoring and audit, the
Action and Limit Levels are defined as follows:
a)
The Action Level is
the level defined in which there is an indication of a deteriorating ambient level for
which a typical response could be
an increase in the monitoring frequency.
b)
The Limit Level is the level beyond the appropriate remedial pollution control ordinances, noise and
air quality impact objectives or Hong Kong Planning Standards and Guidelines
established by the EPD for a particular project, such that the
works should not
proceed without appropriate remedial action, including a
critical review of plant and work methods.
2.1.1.1 Further to the
recommendations of
the Option Assessment and
subsequent alignment developments detailed in Section 2 of
the EIA report, the preferred TM-
CLKL scheme
comprises Northern
Connection Option N1b, Main
Connection Option
M3
and Southern Connection Option S1. This preferred alignment is shown in Figure 2.1 and will comprise:
a)
construction of approximately 5.0
km
long dual 2-lane road tunnel between Tuen Mun Area 40 and the HZMB HKBCF at north-east of HKIA;
b)
construction of approximately 4.2km seawalls and approximately
35.6
ha of
reclamation to the Government foreshore and
sea-bed
at
Tuen Mun Area 40 and Lantau for the tunnel portals
and the associated
roads, as shown in Figures 2.2a and 2.2b;
c)
construction
of approximately 1.6km
long dual 2-lane
viaduct
between HZMB HKBCF and NLH and the associated roads at Tai Ho;
d)
construction of a toll plaza at Tuen Mun Area 46 and the associated
roads at Tuen Mun;
e)
construction of footpaths areas;
f)
construction
of administration
building, ventilation
buildings and other
ancillary buildings to facilitate ventilation and tunnel control
operation serving the proposed road tunnel in (a) above and toll plaza in (d) above;
g)
modification and realignment of sections of Lung Fu Road and Lung Mun Road at Tuen Mun;
h)
modification and realignment of sections of North Lantau
Highway and Cheung Tung Road at Tai Ho;
i)
permanent closure
and demolition
of sections of existing
at-grade carriageways, footpaths and central median/refuge islands;
j)
temporary closure and reconstruction/modifications of sections of existing at-grade carriageways, footpaths and central median/refuge islands;
(k) ancillary works
including site formation,
slope, drainage,
utilities, footbridge, noise barriers, retaining walls, berths and temporary pontoon;
(l) temporary staging
construction for the viaduct construction between HKBCF and
2.1.1.2 Details of the various elements of the selected TM-CLKL alignment are detailed
in
the sections below.
Marine Viaduct
2.4.2.1
The marine viaduct comprises a dual 2-lane carriageway with a straight alignment
connecting the TM-CLKL southern landfall to
2.4.2.2 Span lengths will typically be 60m using a constant
structural deck depth of 3.2m.
At the navigation
channel off the south-east
corner
of the southern landfall,
a 160m span with a haunched deck will be used to achieve the minimum navigation
clearance of
100m
horizontally and a minimum of +26.25mPD vertically. The haunched segment at pier will be about 11m
deep. The spans adjacent to the navigation span will be 100m long to provide a transition to the typical 60m spans. In
total about
50 piers will be constructed
in
the marine environment,
with a
predicted loss of seabed of about 0.2ha. The piers supporting the viaduct will sit on bored piles founded on rock at some 40m below seabed level.
Pile caps will be
positioned above the high water level for marine safety.
Land Connections and Slip Roads
2.4.2.3
There
are
four
slip
roads connecting
the
marine
viaduct to
the
North Lantau Highway (NLH) for eastbound and westbound traffic on the highway connecting to and from the marine crossing.
The slip roads comprise four viaducts curving out from
the marine viaduct and crossing over the MTR Airport Express Railway
before
ramping
down to
connect with the North
Lantau
Highway. The two
viaducts on the west provide for a 1-lane carriageway and the two viaducts
on the east provide for 2-lane carriageways.
2.4.2.4
The
viaducts are all prestressed concrete box girders supported on reinforced
concrete piers.
The viaducts for a 1-lane carriageway will each be around 11.3m
wide, and the viaducts for the 2-lane carriageways,
around 14.6m wide. Span lengths will typically be 60m using a constant structural deck depth of 3.2m, while for crossings
over the MTR Airport
Express Railway
and the North
Lantau
Highway, larger spans of 90m are required, together with a haunched
deck of a depth of
around 6m at piers.
2.4.2.5
The piers supporting the viaducts will all be constructed within the disturbed area
of the NLH transport corridor, and sit on bored piles founded on rock at some 20m
below ground level, or deeper if
underground cavities are encountered (as the site falls
within
the Designated Area of Northshore
Lantau with
regards
to
foundation
works). In order to
accommodate the viaduct connections to the North
Lantau Highway, diversion of Cheung Tung Road including some of the existing utilities below this road will be required, with associated slope cutting works at the west.
2.4.3.1 Diversion of the existing Cheung Tung Road will require cutting back the road
side slope features 9SE-B/C8 and 9SE-B/C9.
The features comprise soil and rock
cut slopes, and a similar cut slope profile to the existing would be proposed.
If necessary, soil nails will be installed to ensure adequate current safety standard.
Some streams pass through
the existing slopes works in the form of U shaped channels, and these existing channels
will need to be extended up hill
to accommodate the new slope extent and profile.
2.4.4A
Temporary
Staging Construction
2.4.4.1A Temporary staging is required to provide
a stable working platform and transfer of materials for the piling work in
connection of the viaduct construction between HKBCF and
The proposed temporary staging
scheme comprises a combination of temporary
access bridges (TABs) and isolated working
platforms. Such design scheme can
facilitate the transfer of material and hence save time for the construction
work. Moreover, the use of a combination
of TABs and isolated working platforms can minimise obstructions to the navigation channel/marine
traffic around the works area and minimise propeller
wash in shallow waters offshore.
The temporary staging works also require construction of three landing
platforms along the seawall as the landing points of the TABs
and for the temporary storage and transfer of material from land to the staging
platforms.
The
preliminary layout plan of the proposed temporary staging is shown in Figure 2.1A
in Annex A, which corresponds to the
permanent bridge pile layout. The
temporary staging consists of 12 isolated working platforms (spaced from
approximately 73m to approximately 195m apart, centre to centre) and two TABs with three landing points near the North Lantau Highway.
The typical pile configurations and details of the temporary staging are
provided in Figures 2.2A and 2.3A in Annex A. The landing point of the TABs comprises three landing platforms to be formed along
the seawall near the NLH as shown in Figure 2.4A in
Annex A. Design drawings of these landing platforms
are shown in Figure
2.5A to
2.8A in Annex A. These platforms will be removed and the
seawall will be reinstated upon completion of the TM-CLKL construction works.
2.5.1.1 Six works areas have been identified for use during the construction period of
TM-CLKL, and will be used for locating site offices and for storage of materials
and viaduct segments, etc.
The locations of the works areas are shown in Figure 2.8b and described in Table
2.2 below.
Table 2.2 Details of TM-CLKL Proposed
Works Areas
Works Area |
Location |
Proposed Use |
Lantau |
||
WA4 |
At the existing reclaimed land near Tai Ho Offtake and Pigging Station at Cheung
Tung Road
in
Lantau |
Works area for storage of materials and viaduct segment and site office |
WA5 |
At the existing site offices for Yam O Road Watermains
near Yam O Wan at Cheung Tung Road in Lantau |
Works area for storage of materials and viaduct segment and site office |
WA6 |
At the existing site offices and storage yard for Penny¡¦s bay Reclamation near Yam O Wan
at Cheung Tung Road in Lantau |
Works area for storage of materials and viaduct segment and site office |
WA23 |
At the existing reclaimed land at Wok Tai
Wan in Tsing Yi |
Casting yard for fabrication of precast units, storage of work boats, materials and site office |
Tuen Mun* |
*
Note: Not applicable
2.5.1.2 All the works areas are currently formed on developed
land, with some already being used as works areas for on-going construction
projects.
2.6.1.1 Stormwater drainage systems will be provided to collect stormwater
from the
carriageway surfaces. The stormwater will enter into gullies along the kerb
lines. The gullies will
be fitted with sumps to trap silt and grit prior to discharging the
stormwater
into the stormwater drainage systems. The drainage systems
will eventually discharge
the stormwater into the sea at discrete locations.
Similar
systems will be provided along the marine viaduct. Sump traps will be built into the deck
structure, and
the
collected stormwater
will
discharge into
the
sea at the column locations.
2.6.1.2 Not applicable
2.6.1.3 Not applicable
2.6.1.4 Not applicable
2.7.1.1 The
Design and Construction Contract of the Southern Connection Viaduct Section of
TM-CLKL commenced in June 2013. An indicative construction programme
showing the key activities in different major construction
areas is shown in Figure 2.9b. Locations of
the construction areas are shown in Figure 2.9d.
This
is based upon working 12 hours per day for all land works and 16 hours per day for the marine works, although piling works for the marine sheet piled wall
will, also, be restricted to 12 hours per day.
2.7.1.2 Not
applicable
2.7.1.3 Not
applicable
2.7.1.4
Not
applicable
2.7.1.5
Not
applicable
2.8.1.1 The southern landfall reclamation of the TM-CLKL forms an integrated part of
the
HKBCF
reclamation
and
interfaces with
the
latter at
a temporary
seawall along its eastern edge.
Reclamation
works
sequencing and programme
have been planned to
match those of
the
HKBCF in
order to
achieve its Phase
1 commissioning date target in 2014.
HKLR is also scheduled to open in 2014 in matching the Phase 1 commissioning date of HKBCF.
Detailed coordination of
the
interfacing construction
activities
will
be required, including
construction access, layout of
mitigation
measures to control water quality during
the
construction stage, joint water quality monitoring system, and engineering and construction details at the interface. The layout of the TM-CLKL, HKBCF and
HKLR in relation to each other is shown in Figure 2.1.
2.8.1.2 As the projects are proposed to be constructed
concurrently and will
be
operational at
the
same time,
cumulative impacts
are
possible
and
have
been assessed.
2.8.3.1 In addition to the interface with the major concurrent projects described above, details of other concurrent projects during either the construction and/or the
operational phases, together with details of how these are assessed
in the EIA, are described in the summary table of concurrent projects included as Appendix A2 of the EIA report.
2.9.1.1 A Local Area Model was developed to provide traffic
forecasts for EIA purposes.
The
EIA requires cumulative traffic forecasts and,
hence,
EIA flows
were
produced assuming the HZMB, HKLR, HKBCF, TMWB and TM-CLKL were all in
place.
In order to
achieve consistency, a consistent set of model
input
assumptions have been adopted for the interfacing studies of TM-CLKL, HKBCF,
HKLR and TMWB.
2.9.1.2 The TMWB was assumed to be ¡§non tolled¡¨ for the purposes of the TM-CLKL EIA
forecasts. This would
make a marginal
difference
to the predicted TM-
CLKL traffic forecasts, increasing the traffic flows slightly
and, therefore, would represent a potentially worst case for assessing the environmental impacts. The traffic flows have been divided into the 16 vehicle classes required to determine the emissions of the traffic.
2.9.1.3 The
opening
year for the whole TM-CLKL, i.e.
both
northern
and southern
sections, is 2016.
Design year peak hour
traffic forecasts have, therefore, been prepared for the years 2016, 2021 and 2031 which reflect the full
operation of
the
TM-CLKL. In addition, to assess the environmental impacts at the interim year of
2014, when the southern section will be opened
to form part of the new road
network
servicing
the
HKBCF
Phase 1 commissioning,
the
relevant traffic
forecasts for this year have also been prepared. A
summary of the traffic data for
the prevailing year of 2007 and the future years of 2014, 2016, 2021 and 2031 and
the road links are included in the EIA Report.
3.1.1.1 Monitoring of the Total Suspended Particulates (TSP) levels shall be carried out
by the Environmental Specialist (ET) (see Section 1)
to ensure that construction
works
are not generating dust which exceeds the acceptable level. Timely action
should be taken to rectify the situation if an exceedance is detected.
3.1.1.2 1-hour
and 24-hour TSP levels
shall
be measured to indicate the impacts
of construction dust on air quality. The TSP levels shall be measured
by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter
1 (Part 50),
Appendix B. Upon approval by the
Supervising Officer¡¦s Representative (SOR) and the Environmental Protection Department
(DEP), 1-hour TSP levels may be measured by direct reading methods for ad hoc measurements.
3.1.1.3 All relevant data including
temperature,
pressure, weather conditions, elapsed-
time meter reading for the start and stop of the sampler, identification and weight
of the filter
paper, any other
special
phenomena and work
progress of
the
concerned site shall be recorded in detail by the ET. A
sample data sheet is shown
in
Figure 3.1
(at the end of Section 3).
3.2.1.1 A high volume sampler in compliance with the following specifications shall be
used for carrying out the 1-hr and 24-hr TSP monitoring:
i)
0.6-1.7 m3/min
(20-60 SCFM) adjustable flow range;
ii)
equipped with a timing/control device with +/- 5 minutes
accuracy for 24
hours operation;
iii)
installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
iv)
capable of providing a minimum exposed area of 406
cm2 (63 in2);
v)
flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;
vi) equipped with a shelter to protect the filter and sampler;
vii) incorporated
with an
electronic mass flow
rate
controller
or other equivalent devices;
viii) equipped with a flow recorder for continuous monitoring;
ix) provided with a peaked roof inlet;
x)
equipped with a manometer;
xi) able to hold and seal the filter paper to the sampler housing in a horizontal
position;
xii) easy to change the filter; and
xiii) capable of operating continuously for 24-hr period.
3.2.1.2 The Contractor is responsible for provision of
the monitoring equipment and shall ensure
that sufficient number of high
volume samplers with an
appropriate calibration kit are available for carrying out the
baseline monitoring, impact monitoring and ad hoc monitoring. The high volume samplers shall be equipped with
an
electronic
mass flow
controller and
be calibrated against
a
traceable standard at regular intervals. All the equipment, calibration kit, filter papers,
etc. shall be clearly labeled by the ET.
3.2.1.3 Calibration of
dust monitoring equipment
shall be conducted by the ET upon
installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognised primary
standard and be calibrated annually. The calibration data shall be properly documented for future reference by concerned parties, such as
the
IEC.
All
the data shall be converted into
standard temperature and pressure condition.
3.2.1.4 The flow-rate of the sampler before and after the sampling exercise with the filter in
position shall be verified to be constant and
recorded
in the
data sheet
as
described in Section 3.1.
3.2.1.5 If the ET proposes
to use a direct reading dust meter to measure 1-hr TSP levels on an ad hoc
basis, he shall submit sufficient information to the IEC to prove that the instrument is
capable of achieving
a
comparable
result as that
the
High Volume Sampler (HVS) and may be used for the 1-hr sampling. The instrument
should also be calibrated regularly and the 1-hr sampling shall be checked
periodically
by the HVS
to check
the validity
and
accuracy
of the results measured by the direct reading method.
3.2.1.6
Wind data monitoring
equipment
shall also be provided and set up at suitable
locations for logging wind speed and wind direction
near to the dust monitoring locations.
The equipment installation location shall be proposed by the ET and
agreed with the SOR, in consultation with the IEC.
3.2.1.7
For installation and operation of wind data monitoring equipment, the following
points shall be observed:
i)
the wind sensors should be installed on masts at an elevated level 10 m above ground so that they are clear of obstructions or turbulence caused by the buildings;
ii)
the wind data should be captured by a data logger to be down-loaded for processing at least once a month;
iii)
the wind data monitoring equipment should be re-calibrated at least once
every six months; and
iv)
wind direction should be divided into 16 sectors of
22.5 degrees each.
3.2.1.8 In exceptional situations, the ET may propose alternative methods to obtain representative wind data upon approval from the SOR and agreement from the IEC.
3.3.1.1
A clean laboratory with constant temperature and humidity control and equipped with necessary measuring and conditioning instruments shall be used for sample analysis and equipment calibration and maintenance. The laboratory shall be HOKLAS accredited.
3.3.1.2 If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved
by the SOR, in
consultation with the IEC.
Measurement performed
by the laboratory shall be demonstrated to the satisfaction of the SOR and the IEC. The IEC shall conduct regular audits of the measurements performed by the laboratory
to
ensure the accuracy of the results. The ES shall provide the SOR and the IEC
with one copy
each of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B
for reference.
3.3.1.3
Filter paper of size 8"x10"
shall be labeled before sampling. It shall be a clean filter paper with
no
pin holes
and
shall be conditioned in
a humidity controlled
chamber for over 24-hr and be pre-weighed before use for the sampling.
3.3.1.4 After sampling, the filter paper
loaded with dust shall be kept in a clean and tightly sealed plastic bag.
The filter paper shall then be returned to the laboratory for reconditioning in the
humidity
controlled
chamber followed
by accurate weighing by an electronic balance with a readout down to 0.1 mg. The balance
shall be regularly calibrated against a
traceable standard.
3.3.1.5
All the collected samples shall be kept in a good condition for 6 months before disposal.
3.4.1.1 The air quality sensitive receivers, as determined by the EIA, are shown in Figure 3.2
and these will also form the recommended
dust monitoring locations. The status
and locations of dust
sensitive receivers
may change after issue of this manual.
If this happens, the ET shall propose updated monitoring locations and
seek approval from the SOR and agreement from IEC.
3.4.1.2 When
alternative monitoring
locations
are proposed,
the following preferred locations and factors shall be considered:
i)
the site boundary or locations close to the major dust emission source;
ii)
close to the sensitive receptors; and
iii) the prevailing meteorological conditions.
3.4.1.3 The ET shall agree with the SOR, in consultation with the IEC, the position of the
high volume samplers.
When positioning the samplers, the following points shall
be
noted:
i)
a horizontal
platform with
appropriate
support to
secure the samplers
against gusty wind shall be provided;
ii)
the distance between the sampler and an obstacle, such as buildings, shall be at least twice the height that the obstacle protrudes above the sampler;
iii) a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
iv) a minimum of
2 metres
separation from any
supporting
structure,
measured horizontally is required;
v) no furnace or incinerator flue is nearby;
vi) airflow around the sampler is unrestricted;
vii) the sampler is more than 20 metres
from the dripline;
viii) any wire
fence
and
gate, to
protect the sampler, shall not
cause any obstruction during monitoring;
ix) permission must be obtained to set up the samplers and to obtain access to
the monitoring stations;
x) a secured supply of electricity is needed to operate the samplers; and
xi) no two samplers should be placed less than 2 metres apart.
3.4.1.4
Prior to construction, the dust monitoring schedule shall be developed by the ET
based upon the construction schedule supplied by the Contractor. The
ET shall inform the IEC of the impact monitoring programme such that he can conduct on-
site audits to ensure accuracy of the impact monitoring results. The environmental
monitoring schedule shall be approved by the SOR.
3.5.1.1 The ET shall carry out baseline
monitoring
at two representative
dust monitoring locations (ASR9A
and ASR9C). The monitoring
at these locations shall be
undertaken for at least 14 consecutive
days prior to the start of the construction
works to obtain
daily 24-hr TSP samples. 1-hr sampling shall also be carried out at least 3 times per day during the same period. Monitoring
shall take place within a 3 week period prior to
the commencement of
construction works.
3.5.1.2
During the baseline
monitoring,
there
should not be any construction or
dust generation activities in the vicinity of
the monitoring stations.
3.5.1.3 In case the baseline monitoring cannot be carried out at the designated monitoring locations
during the baseline monitoring
period, the ET shall carry
out the monitoring at alternative locations which can effectively represent the baseline conditions
at
the impact monitoring locations. The alternative baseline monitoring
locations shall be approved by the SOR, IEC and agreed with DEP.
3.5.1.4
In the event that insufficient baseline monitoring data or questionable results are
obtained, the ET shall liaise with the DEP to agree on an appropriate set of data to be
used
as a baseline reference
and
submit
this
data to
the
SOR and IEC
for
approval.
3.5.1.5 Ambient conditions may vary seasonally and shall be reviewed at three monthly intervals.
If
the ET considers that the ambient conditions
have changed and a repeat of
the baseline monitoring is
required to
be carried out
for
obtaining updated baseline levels, the monitoring should be at times when
the Contractor's activities
are
not generating dust, at least in
the
proximity
of the
monitoring
stations. Should
a change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, shall be revised. The revised baseline levels and air quality criteria shall be agreed with the DEP and supplied to the IEC.
3.5.1.7 The Baseline Air Quality Monitoring
at ASR9A and ASR9C was conducted during October 2011. Monitoring results are presented in the Baseline Environmental Monitoring for Hong
Kong-Zhuhai-Macao Bridge Hong Kong Projects ¡V
Investigation ([1]). The baseline
data will be adopted in the current EM&A Programme.
3.6.1.1 The ET shall carry out impact monitoring during the course of the works.
For
regular impact monitoring, the sampling frequency of at least once in every six days shall be strictly observed
at two of the designated monitoring stations for 24-hr TSP monitoring (ASR9A and ASR9C). For 1-hr TSP monitoring, the sampling frequency of at least
three times in every six days should be undertaken at two
locations (ASR9A and ASR9C) when the highest dust impact occurs. The stations to be monitored should be selected based
on
the prevailing wind direction and their proximity to the active construction
works.
3.6.1.2
The specific time
to
start and stop the 24-hr TSP monitoring shall
be clearly
defined for each location and be strictly followed by the operator.
3.6.1.3 In case of non-compliance with the air quality criteria, more frequent monitoring, as specified in the Action
Plan in Section 3.7,
shall be conducted within 24 hours
after
the
non-compliance is
detected.
This
additional
monitoring
shall be
continued until the excessive dust emission or the deterioration in air quality is rectified.
3.7.1.1
The baseline monitoring results formed the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour
TSP and 1-hour TSP.
Table 3.1a and Table 3.1b show the method of derivation and the Action and Limit levels to be used,
respectively. Should non-compliance with the air quality criteria occur, the ET, the IEC and the SOR and
the
Contractor
shall undertake
their
specified actions in
accordance with
the
Action Plan shown in Table 3.2.
Table 3.1a Method of
Derivation of Action and Limit Levels for Air Quality
Parameter |
Action Level |
Limit Level |
24-hour
TSP Level in mg/m3 |
For
baseline level ≤ 200 mg/m³ Action
level = (Baseline*1.3+ Limit level )/2 |
260 |
|
For
baseline level >200 mg/m³ Action
level = Limit level |
|
1-hour
TSP Level in mg/m3 |
For
baseline level ≤ 384 mg/m³ Action
level = (Baseline*1.3+ Limit level )/2 |
500 |
|
For baseline level >
384 mg/m³ Action level = Limit level |
Table 3.1b Action and Limit Levels for
Air Quality
Parameters |
Action |
Limit |
24 Hour TSP Level in µg/m³ |
ASR9A = 178 ASR9C = 178 |
260 |
1 Hour TSP Level
in µg /m³ |
ASR9A = 394 ASR9C = 393 |
500 |
3.7.1.2 In case of non-compliance with the air quality criteria, more frequent monitoring exercise,
shall be conducted within 24 hours after the result is obtained. This additional monitoring shall be continued until the excessive dust emission or the
deterioration in air quality is rectified.
The Event/Action
Plan for air quality is
given in the attached Table
3.2.
3.7.1.3 The Independent Environmental Checker (IEC) shall be empowered to audit the environmental performance of construction, all aspects of the EM&A programme, validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations and procedures. If any exceedances
occur, the IEC shall
follow the actions stated in the Event and Action Plan in Table 3.2.
3.8.1.1 The EIA report
has
recommended dust control and
mitigation measures. The Contractor shall be responsible for the design and implementation of
the following
measures.
The
recommended
construction
dust mitigation
measures
are summarised
in the Air
Quality
Environmental
Mitigation Implementation
Schedule provided in Appendix A.
i)
All unpaved roads/exposed area shall be watered which results in dust suppression by forming moist cohesive films among the discrete grains of
road surface material. An effective watering programme of
twice daily
watering with complete coverage, is estimated to reduce
by 50%. This is
recommended for all areas in order to reduce dust levels to a minimum;
ii)
Watering of the construction
area 8 times per
day is
recommended to
reduce dust emissions by 87.5% and shall be undertaken;
iii)
The Contractor shall, to the satisfaction of the Supervising Officer, install effective
dust suppression measures
and
take such
other measures as may
be
necessary to ensure that at the Site boundary
and any nearby sensitive receiver, dust levels are kept to acceptable levels;
iv) The Contractor shall not burn debris or other materials on the works areas;
v)
In hot, dry or windy weather, the watering programme shall maintain all exposed road surfaces and dust sources wet;
vi)
Where breaking of
oversize rock/concrete is required, watering shall be implemented to control dust. Water spray shall be used during the handling of fill material
at
the site and at active cuts, excavation and fill sites where
dust is likely to be created;
vii)
Open dropping heights for
excavated materials
shall
be controlled to a maximum
height of
2m to minimise
the
fugitive
dust arising from unloading;
viii)
During transportation
by truck,
materials
shall not be loaded to a level
higher than the side and tail boards, and shall be dampened
or
covered before transport. Materials having the
potential
to
create dust shall not be
loaded to a level higher than the side and tail boards, and shall be covered by a clean tarpaulin. The tarpaulin shall
be properly secured and shall
extend at least 300mm over the edges of the side and tail boards;
ix) No earth, mud, debris, dust and the like shall be deposited on public roads.
x)
Wheel washing facility shall be usable prior to any earthworks excavation
activity on the site;
xi)
Areas of exposed
soil shall be minimised
to
areas in which works have
been completed shall be restored as soon as is practicable; and
xii)
All stockpiles of aggregate or spoil shall be enclosed or covered and water
applied in dry or windy condition.
3.8.1.2 If the above measures
are not sufficient
to restore the air quality to acceptable
levels upon the advice of the ET, the Contractor shall liaise with the ET regarding other mitigation measures and consult the IEC
for
their effectiveness, and then propose these measures to the SOR for approval prior to the implementation of
the
measures.
Table 3.2 Event / Action Plan for Air Quality
EVENT |
ACTION |
|||
ET (1) |
IEC (1) |
SOR(1) |
Contractor |
|
Action Level |
|
|
|
|
1. Exceedance for one
sample |
1. Identify the source. 2. Inform the IEC and the SOR. 3. Repeat measurement to confirm finding. 4. Increase
monitoring frequency
to
daily. |
1. Check monitoring data submitted by the ET. 2. Check Contractor¡¦s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable
practice 2. Amend working methods if appropriate |
2. Exceedance for two
or more consecutive
samples |
1. Identify the source. 2. Inform the IEC and the SOR. 3. Repeat measurements to
confirm findings. 4. Increase
monitoring frequency to daily. 5. Discuss with the IEC and the Contractor on remedial actions
required. 6. If
exceedance continues, arrange meeting with the IEC
and the SOR. 7. If
exceedance stops, cease additional monitoring. |
1. Check monitoring data submitted by the ET. 2. Check the Contractor¡¦s working method. 3. Discuss with the ET and the Contractor on
possible
remedial measures. 4. Advise the SOR on
the
effectiveness of the proposed
remedial measures. 5. Supervisor implementation of remedial measures. |
1. Confirm receipt of notification
of failure in writing. 2. Notify the Contractor. 3. Ensure remedial measures
properly implemented. |
1. Submit proposals for remedial
actions to IEC within 3 working days of notification 2. Implement the agreed
proposals 3. Amend proposal if appropriate |
EVENT |
ACTION |
|||
Limit Level |
ET (1) |
IEC (1) |
SOR(1) |
Contractor |
1. Exceedance for one sample |
1. Identify the source. 2. Inform the SOR and the
DEP. 3. Repeat measurement to confirm
finding. 4. Increase monitoring frequency to daily. 5. Assess effectiveness of
Contractor¡¦s remedial actions and
keep the IEC, the DEP and the SOR informed of the results. |
1. Check monitoring data submitted by the ET. 2. Check Contractor¡¦s working method. 3. Discuss with the ET and the Contractor on
possible
remedial measures. 4. Advise the SOR on
the
effectiveness of the proposed
remedial measures. 5. Supervisor implementation of remedial measures. |
1. Confirm receipt of notification
of failure in writing. 2. Notify the Contractor. 3. Ensure remedial measures are properly mplemented. |
1. Take immediate action to
avoid further exceedance 2. Submit proposals for remedial
actions to IEC within 3 working days of notification 3. Implement the agreed proposals 4.
Amend proposal if appropriate |
2. Exceedance for two or more
consecutive samples |
1. Notify the IEC, the SOR, the DEP And the Contractor. 2. Identify the source. 3. Repeat measurements to confirm findings. 4. Increase monitoring frequency to daily. 5. Carry out analysis of the Contractor¡¦s
working procedures to determine possible mitigation to be implemented. 6. Arrange meeting with the IEC and the SOR to discuss the remedial actions to be taken. 7. Assess effectiveness of he Contractor¡¦s remedial actions and
keep the IEC, the DEP and the SOR informed of the results. 8. If exceedance stops, cease
additional monitoring. |
1. Discuss amongst the SOR, ET and the Contractor on the potential remedial actions. 2. Review the Contractor¡¦s remedial actions whenever necessary to assure their effectiveness and advise the
SOR accordingly. 3. Supervise the implementation of
remedial measures. |
1. Confirm receipt of notification
of failure in writing. 2. Notify the Contractor. 3. In consultation with the IEC,
agree with the Contractor on
the remedial measures to be
implemented. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider
what activity of the
work is responsible and instruct the Contractor to stop that activity of work until the
exceedance is abated. |
1. Take immediate action to
avoid further exceedance. 2. Submit proposals for remedial
actions to IEC within 3 working days of notification. 3. Implement the agreed proposals. 4. Resubmit proposals if problem still
not under control. 5. Stop the relevant
activity of works as determined by the SOR until the exceedance is abated. |
Note: ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SOR ¡V Supervising Officer¡¦s Representative
4.1.1.1
Based upon the EIA Report, while impacts are not predicted, as the results are marginally within the criteria, EM&A is recommended at existing Noise Sensitive Receivers (NSRs) in North Lantau during the construction
phase to ensure the
noise levels are reduced to acceptable levels.
4.2.1.1
The construction noise level shall be monitored by the ET and shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 min)
shall be used
as the monitoring parameter for the time
period
between 0700-1900 hours on normal weekdays. In respect of all other time periods, Leq(5 min) shall be employed for comparison with the Noise Control Ordinance criteria.
4.2.1.2
As supplementary information for data auditing, statistical results such as L10 and
L90 shall also be obtained
for
reference
and
shall be recorded by the ES. A sample data record sheet is shown in
Figure 4.1
(at the end of Section 4) for reference.
4.3.1.1
As
referred to in the
Technical Memorandum
(TM) issued
under the Noise
Control
Ordinance (NCO),
sound level
meters
in compliance with
the International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications
shall
be used for carrying out
the noise
monitoring.
4.3.1.2
Immediately prior to and following each noise measurement the accuracy of the
sound
level
meter
shall be
checked using an acoustic calibrator
generating a
known
sound
pressure level at a known
frequency. Measurements may be
accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0dB.
4.3.1.3
Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in
m/s.
4.3.1.4 The Contractor shall ensure that sufficient noise measuring equipment
and
associated instrumentation
are
available for carrying out the baseline monitoring,
construction phase impact monitoring and ad hoc monitoring. All the equipment
and associated instrumentation shall be clearly labeled.
4.4.1.1
The representative
noise
monitoring
stations/sensitive
receiver at Pak Mong
Village (NSR1) is
shown in
Figure
3.2. If the status or locations of noise sensitive receiver changes after issuing this manual, the ET shall propose the updated
monitoring location and seek approval from the Supervising Officer¡¦s Representative (SOR) and agreement from the
Independent
Environmental
Checker (IEC) and Environmental Protection Department (DEP) of
the proposal to amend the monitoring location.
4.4.1.2
When alternative monitoring locations are proposed,
the
monitoring
locations shall be chosen based on the following criteria:
a) monitoring at sensitive receivers close to the major site activities which
are
likely to have noise impacts;
b) monitoring at the noise
sensitive
receivers
as
defined
in the
Technical
Memorandom; and
c) assurance of minimal disturbance to the occupants during monitoring.
4.4.1.3 The monitoring station shall normally be at a point 1m from the exterior of the sensitive receivers building facade and, in
the case the measurement is not being carried
out at a building, be at a position 1.2m above the ground.
If there is
problem with access to the normal monitoring position, an alternative
position
may be chosen and a correction to the measurements shall be made.
4.4.1.4
For reference, a correction of
+3dB(A)
shall be
made to
the free field measurements.
Noise levels shall be corrected in accordance with Section 2.10,
2.11 and 2.13 of the ¡§Technical
Memorandum on Noise From
Construction
Works Other Than Percussive Piling¡¨. The ET shall agree with the IEC on the
monitoring position and the corrections adopted prior to the commencement
of the works.
4.4.1.5
Once the positions for the monitoring stations are chosen, the baseline monitoring
and the construction phase impact monitoring shall be carried out at the same positions.
4.4.1.6 The Contractor
shall establish the construction equipment list and construction schedule which shall be checked and approved
by the SOR and agreed by the IEC. The
timing of the noise impact monitoring
work
shall be developed by the ES based upon the construction schedule prepared
by the Contractor.
The monitoring
programme shall be approved
by the SOR, the IEC and the DEP
and shall
be reviewed
on a regular
basis in light
of
any changes to the Contractor¡¦s construction schedule.
4.5.1.1
The Baseline Noise Monitoring was
conducted at NSR1 during the period of 18 October and 1 November 2011.
Monitoring results are presented in the Baseline
Environmental Monitoring for Hong Kong-Zhuhai-Macao
Bridge Hong Kong Projects - Investigation([2]). The baseline
data will be adopted for analysis in the current EM&A Programme.
4.5.1.2 Not
applicable
4.5.1.3 Not
applicable
4.6.1.1
Noise
monitoring
shall be
carried out
at the designated monitoring station (NSR1)
directly affected by the construction works once every 6 days after the commencement of construction. During construction works between 0700-1900
hours, one set of
Leq (30 mins)
measurements on normal weekdays shall be taken. If construction works are extended to include works during the hours of
1900-0700, additional weekly impact
monitoring comprising 3 consecutive Leq(5 mins) shall be
carried out during evening
and nighttime works and applicable permits shall be obtained by the Contractor in accordance with the NCO.
4.6.1.2 In case of non-compliance with the construction noise criteria, more frequent
monitoring as specified in the Event/Action Plan in Table 4.2 shall be carried out. This additional monitoring shall
be continued
until
the recorded
noise
levels are
rectified or proved to be unrelated to the construction activities.
4.7.1.1 The
Action
and Limit levels for
construction noise
are
defined in Table 4.1. Should non-compliance of
the criteria occur, the ET, the IEC, the SOR
and the
Contractor shall undertake their specified actions in accordance with the Action
Plan shown in Table
4.2.
Table 4.1 Action
and Limit Levels for
Construction Noise
Time
Period |
Action |
Limit |
0700-1900 hrs on normal
weekdays |
When one documented complaint is received |
75* dB(A) |
Note:
If works are to be
carried during restricted hours, the conditions stipulated in the construction
noise permit issued by the Noise Control Authority have to be followed.
* reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.
4.8.1.1 As no impacts are predicted during the construction
stage at the existing NSRs in north Lantau, no specific
mitigation measures
have been
recommended.
However, the
Contractor will
be
responsible for ensuring
noise levels
are
minimized
as
far as possible through
the
application
of
good site
practices,
including maintenance of equipment. During the operational phase, no mitigation is required.
Table 4.2 Event /
Action Plan for Construction Noise
EVENT |
ACTION |
|||
ET |
IEC |
SOR |
Contractor |
|
Action Level |
1. Notify the IEC and the Contractor. 2. Carry out
investigation. 3. Report the results of investigation to the IEC and the Contractor. 4. Discuss with the Contractor and formulate remedial measures. 5. Increase monitoring frequency to check mitigation effectiveness. |
1. Review the analysed results submitted by the ET. 2. Review the proposed remedial measures by the Contractor and advise the SOR
accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of
failure in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure remedial measures are
properly implemented. |
1. Submit noise mitigation proposals to IEC 2. Implement noise mitigation
proposals |
Limit
Level |
1. Notify the IEC, the SOR, the DEP and the Contractor. 2. Identify the source. 3. Repeat measurement to confirm
findings. 4. Increase monitoring frequency. 5. Carry out analysis of Contractor¡¦s working procedures to determine possible mitigation to be
implemented. 6. Inform the IEC, the SOR and the DEP the causes &
actions taken for the exceedances. 7. Assess effectiveness of the Contractor¡¦s remedial actions and keep the IEC, the DEP and the SOR informed of the results. 8. If exceedance stops, cease
additional monitoring. |
1. Discuss amongst the SOR, the ET and the Contractor on
the
potential remedial actions. 2. Review the Contractor¡¦s
remedial actions whenever
necessary to assure their effectiveness and advise the SOR accordingly. 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of
failure in writing. 2. Notify the Contractor. 3. Require the Contractor to propose remedial measures for the analysed noise problem. 4. Ensure remedial measures are properly implemented. 5. If exceedance continues, consider
what activity of the
work is responsible and instruct
the Contractor to stop that activity of work until the
exceedance is abated. |
1. Take immediate action to avoid
further exceedance 2. Submit proposals for
remedial actions to IEC within 3
working days of notification 3. Implement the agreed proposals 4. Resubmit proposals if problem still
not under control 5. Stop the relevant activity of works as determined by the SOR
until the exceedance is abated. |
Note: ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SOR ¡V Supervising Officer¡¦s Representative
Figure 4.1 Noise Monitoring Field Record Sheet
Monitoring Location: |
|
Description of Location: |
|
Date of Monitoring: |
|
Measurement Start Time (hh:mm): |
|
Measurement Time Length (min.): |
|
Noise Meter Model/Identification: |
|
Calibrator Model/Identification: |
|
Measurement Results |
L90 (dB(A)): |
L10 (dB(A)): |
|
Leq (dB(A)): |
|
Major Construction Noise Source(s) During Monitoring: |
|
Other Noise Source(s) During Monitoring: |
|
Remarks: |
5.1.1.1
Since the marine works of TM-CLKL will be concurrent with HKBCF and HKLR
and
the southern landfall of TM-CLKL is indeed an integrated part of the HKBCF
The potential water quality impacts of TM-CLKL has been assessed
jointly with HKBCF and HKLR. The EIA has, therefore, recommended that the water quality monitoring works of the three concurrent projects, also by the same project
proponent, be conducted
as a whole to enhance the efficiency and cost-
effectiveness of the monitoring programme. Based on this, the water quality monitoring scheme designed assuming the monitoring will be implemented jointly
and
be coordinated with a project ENPO office.
5.2.1.1 The EIA Report has assessed the water quality impacts caused by the construction and operation stages.
Mitigation measures have been recommended in the EIA to ensure compliance with the relevant legislative requirements.
These mitigation measures are summarised below.
For
construction of the marine viaduct:
• Bored piling shall be undertaken
within a metal casing for the construction of marine viaducts;
and
• The minimum distance between two
pile cap construction sites shall be 50m and maximum pier sites simultaneously
under construction shall be limited to 15 piers. The pier locations shall be
enclosed by cofferdams.
Additional mitigation measures regarding
the temporary staging works are listed as follow:
• Regular inspection for the
accumulation of floating refuse and collection of floating refuse if required;
• Provision of temporary drainage system on the temporary
staging for collection of construction site runoff to allow appropriate
treatment before discharge into the sea;
• Wastewater generated from construction works such as bored /
drilling water will be collected, treated, neutralized and de-silted through
silt trap or sedimentation tank before disposal; and
• One additional water quality
monitoring station for EM&A is proposed at the coral communities in the
proximity of the temporary staging (station SR4a as shown in Figure 3.2), as some coral colonies are not feasible to
be translocated.
In
case elevated SS or turbidity is identified during the water quality
monitoring, the source of pollution will be tracked down and be removed as soon
as possible. In case depletion of
dissolved oxygen is identified, artificial aeration will be arranged at the
monitoring station SR4a where corals are identified.
5.2.1.2
Prior
to the commencement
of the construction
work, a detailed
site drainage management plan should be
submitted to EPD. The plan should cover measures to minimize all potential water quality impact arising from the surface runoffs of all the
related constructions.
5.2.1.3 The guidelines outlined in the Practice Note for Professional Persons (ProPECC),
Construction Site Drainage (PN 1/94) should
be adopted to control construction
site runoff. Mitigation measures
to minimise
water
quality impacts from construction site
runoff and wastewater and sewage generated from construction activities are:
• Provision of site drainage systems over the entire construction site with sediment control facilities. Regular inspection and maintenance of the site drainage systems are required to ensure proper and efficient operation at all
times.
• Sedimentation tanks or package treatment systems are required to treat the
large amount of sediment-laden wastewater generated from foundation construction work, wheel washing, site runoff. Any construction activities that generate wastewater with high concentrations of SS should also be
collected to these facilities for proper treatment prior to disposal. Treated wastewater can
be reused for
vehicle
washing, dust suppression and
general cleaning. Bentonite slurry used in bore-pile
construction should be
reconditioned and reused to minimise the disposal volume of
the used slurry.
• The
construction programme should be properly planned to avoid soil excavation in rainy seasons.
Exposed stockpiles of excavated soils or
construction materials should
be covered with tarpaulin or impervious sheets to avoid release of pollutants into the drainage channels.
• Sewage generated from site toilets and canteen should be collected using a temporary storage system. Chemical toilets should be
provided at different
locations for use by the workers on site. Licensed waste collectors should be employed for
collection and disposal
of the sewage.
The drainage system for collection
of wastewater generated from canteen, if any, should be
equipped with grease trap capable of providing at least 20 minutes retention during peak flow.
• Wheel washing facilities should be installed at all site entrances/exits.
• An emergency plan should
be developed by the contractors to deal with accidental spillage of chemicals.
5.2.1.4
Upon completion of the TM-CLKL / HKLR / HKBCF development, stormwater drainage systems would be completed to collect stormwater
generated from the
whole area including
new roads. Sewage generated from the TM-CLKL southern landfall and HKBCF development would be treated on site to fulfill effluent limit for discharge. Additional mitigation measures would not be required.
5.2.1.5
Not
applicable
5.2.1.6
The EIA Report has recommended construction and operational phase mitigation
measures. All the prepared mitigation measures are summarised in the Environmental Mitigation Implementation Schedules in Appendix A.
5.3.1.1
As
identified in the EIA Report,
key water
quality issues during construction
phase will be dredging and filling works for the reclamation. Marine water quality monitoring shall be
carried out during the construction phase to ensure that any unacceptable increase in suspended solids / turbidity and decrease in dissolved oxygen due to dredging and filling activities could be readily detected and timely
action be taken to rectify the situation.
5.3.1.2
Dissolved oxygen (DO), turbidity
(NTU), suspended solids (SS) levels and other general
in-situ parameters
shall be monitored at
all designated marine
water quality
monitoring stations during the whole construction phase. DO and turbidity
should be measured in-situ whereas SS should be determined by an accredited laboratory.
5.3.1.3 Other relevant data shall also be recorded in a Water Quality Monitoring Logs, including monitoring location / position, time, water depth, pH value, salinity,
temperature, tidal stages, weather conditions and any special phenomena or work underway at the construction site.
A
sample monitoring record sheet is shown in
Figure 5.7.
5.3.1.4 According to the EIA report, there is low concentration
for PAH, PCB, TBT, and chlorinated pesticides. Monitoring of these chemicals would
not be required during the construction stage.
5.3.1.5 The proposed water quality monitoring schedule shall be submitted to EPD at least 2 weeks before the first day of the monitoring month. EPD shall also be notified
immediately for any changes in schedule by fax.
5.3.1.6
For TM-CLKL southern viaducts, surveys of the watercourse NL1 in
5.4.1.1
The instrument should be a portable
and weatherproof dissolved oxygen (DO)
measuring instrument complete
with cable and
sensor,
and use a DC
power source.
The equipment should be capable of measuring:
• DO
level in the range of 0 - 20 mg/ L and 0 - 200% saturation; and
• Temperature of 0 - 45 degree Celsius.
5.4.1.2 It should have a membrane electrode with automatic temperature
compensation complete with a cable.
5.4.1.3
Should salinity
compensation not be built-in to the DO equipment, in-situ salinity
should be measured to calibrate the DO equipment prior to each DO measurement.
5.4.2.1 The
instrument
should
be
a portable
and
weatherproof turbidity measuring instrument using a DC
power source. It should have a photoelectric sensor
capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument).
5.4.3.1 A water sampler is required.
It should comprise a transparent PVC cylinder, with
a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open
and
prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico
Water Sampler or an approved similar instrument).
5.4.4.1
A portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station.
This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
5.4.5.1 A portable salinometer capable of measuring salinity
in the range of 0 - 40 parts per thousand (ppt) should be provided for measuring salinity
of the water at each monitoring location.
5.4.6.1
A
portable pH meter capable of measuring a range between 0.0 and 14.0 shall be
provided to measure pH under the specified conditions (e.g., Orion Model 250A
or an approved similar instrument).
5.4.7.1
Water samples for SS should be stored in high density polythene bottles, packed in
ice
(cooled to 4¢XC without being frozen) and keep in dark during both on-site temporary storage and shipment to the testing laboratory. The
samples shall be
delivered to the laboratory within 24 hours of collection and be analysed as soon as possible after collection.
5.4.8.1 A
hand-held or boat-fixed
type digital Differential
Global Positioning
System (DGPS) with way point bearing indication and Radio Technical Commission
for maritime (RTCM) Type 16 error message ¡¥screen pop-up¡¦ facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong
Hydrographic Office), or other equipment instrument of similar accuracy, should
be provided and used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.
5.4.9.1
The pH meter, DO meter and turbidimeter
shall be checked and calibrated before
use. DO meter and turbidimeter shall be certified by
a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-
calibrated at 3 monthly
intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with certified
standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.
5.4.10.1 Sufficient
stocks of spare parts
shall be maintained for
replacements when necessary.
Backup monitoring equipment shall also be made available so that
monitoring can proceed uninterrupted even when some equipment is
under maintenance, calibration, etc.
For the on site calibration of field equipment, the BS127:1993,
"Guide to Field and on-site test methods for the analysis of waters"
shall be observed.
5.4.10.2
The Water Quality Monitoring will involve a large number of monitoring stations and
measurements should be conducted within the prescribed
tidal conditions
(within ¡Ó 1.75 hour of the predicted mid-ebb or mid-flood tides) in order to ensure the measurement/samples are representative. A multi-probe monitoring equipment
set
integrated with water sampler(s) is highly recommended to improve the monitoring efficiency. It is, also, likely that more than one field survey vessels will
be required simultaneously to ensure the monitoring are conducted within
the acceptable monitoring windows. The ET shall also consider the use of unattended automatic sampling/monitoring devices at
fixed stations where monitoring are required throughout the construction period. The use of such unattended automatic
devices, however, shall be subject to the approval of the SOR, IEC and EPD.
5.5.1.1
Duplicate samples from each independent sampling event are required for all the suspended solids measurement, which shall be carried in a
HOKLAS or other international accredited laboratory.
Sufficient water samples shall be collected at the monitoring stations for carrying out the laboratory measurement and analysis.
The laboratory determination work shall start within 24 hours after collection
of the water samples. The analysis for SS is summarized in Table 5.1.
Table 5.1 Laboratory
Analysis for SS
Parameters |
Instrumentation |
Reference Method |
Reporting Limit |
Detection Limit |
Suspended Solid (SS) |
Weighting |
APHA 2540-D |
0.5 mg/L |
0.5 mg/L |
5.5.1.2
If a site laboratory is set up or a non-HOKLAS and non-international accredited laboratory
is
hired for
carrying out the laboratory analysis,
the
laboratory
equipment, analytical procedures,
and quality control shall be approved by EPD. All the analysis shall be witnessed
by the SOR. The ET Leader shall provide the SOR with one copy
of the relevant chapters of the ¡§APHA Standard
Methods for the Examination
of Water and Wastewater¡¨
19th edition
and any other relevant document for his reference.
5.6.1.1
Locations
of the seven (7) water quality monitoring stations are shown in
Figure 3.2. The demarcation
of the monitoring stations for different projects will
be further determined by the ENPO before the commencement of the construction. The selection of these stations is based on the following
criteria:
ii)
Impact stations (IS/GG) within 250m ¡V
500m envelope of the construction
works and within the Mf
sediment
backfilling
sites (i.e., 3 impact locations).
iii)
Sensitive receiver (SR) stations near
to
key
sensitive receivers
(i.e.
2 SR stations).
iv)
Control stations at
representative
locations with less influence by the projects (i.e. 2
Control stations). Control stations
should be located, as far as practicable, both upstream and downstream of the
works area.
v)
Not applicable
vi)
Not applicable
vii)
Mf receiving pit are not required based on
the supporting documents for application for variation of
environmental permit (EP
354/2009). Therefore, monitoring of nutrients and heavy metals of Mf
Stations are no longer required.
5.6.1.2
The co-ordinates
of the proposed monitoring stations
during construction,
post-construction and operation phases are listed in Tables 5.2a
and 5.2b and their
distribution shown in Figure 3.2. As shown in Figure 3.2, the proposed locations
for the sensitive receiver monitoring stations represent
the typical sensitive receivers around the project works.
Table
5.2a Proposed
Water
Quality Monitoring Stations (Construction
and Post-construction Phases)
Station |
Description |
Easting |
Northing |
Parameters to be measured |
IS(Mf)9 |
Impact Station (Close to
HKBCF construction site) |
813273 |
818850 |
DO, Turbidity, SS |
IS(Mf)16 |
Impact Station (Close to
HKBCF construction site) |
814328 |
819497 |
DO, Turbidity, SS |
IS8 |
Impact Station (Close to
HKBCF construction site) |
814251 |
818412 |
DO, Turbidity, SS |
SR4 |
Sensitive receiver |
814760 |
817867 |
DO, Turbidity, SS |
SR4a |
Sensitive receiver |
815247 |
818067 |
DO, Turbidity, SS |
CS(Mf)3 |
Control Station |
809989 |
821117 |
DO, Turbidity, SS |
CS(Mf)5 |
Control Station |
817990 |
821129 |
DO, Turbidity, SS |
Notes:
DO =
Dissolved Oxygen;
SS =
Suspended Solid;
Table
5.2b Proposed
Water
Quality Monitoring Stations (Operation Phase)
Station |
Description |
Easting |
Northing |
Parameters to be measured |
SR3 |
Sensitive
receivers (San Tau Beach SSSI) |
810525 |
816456 |
DO, Turbidity, SS, pH,
Salinity, Temperature |
SR4 |
Sensitive
receivers (Tai Ho Wan) |
814760 |
817867 |
DO, Turbidity, SS, pH,
Salinity, Temperature |
CS2 |
Control
Station |
805849 |
818780 |
DO, Turbidity, SS, pH, Salinity,
Temperature |
CS(Mf)5 |
Control
Station |
817990 |
821129 |
DO, Turbidity, SS, pH,
Salinity, Temperature |
Notes:
DO =
Dissolved Oxygen;
SS =
Suspended Solid;
5.6.1.3
Control stations (CS(Mf)3 and CS(Mf)5) are necessary to
compare the water quality from potentially impacted sites with the ambient water quality. Control stations shall be located within the same body of water as the impact
monitoring stations but should be outside the area
of influence
of the works and, as far as practicable, not affected by any other works. The Control stations shown in
Figure 3.2 are indicative subject to further review before
construction phase. During the review, the location of the Impact stations for
boundary of mixing zones will also be re-visited. If there are any changes to the monitoring locations,
these shall be submitted 4 weeks before commencement of baseline monitoring for EPD approval.
5.6.1.4
In-situ monitoring (DO, temperature, turbidity, pH, salinity) and water sample for
SS
shall be taken at 3 water depths, namely, 1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6 m, in which
case the mid-depth station may be omitted. Should the water depth be less than 3
m, only the mid-depth
station will be monitored.
No marine construction activities should be conducted in the vicinity of the stations during the Baseline Monitoring period. The status and locations of water sensitive receivers and the
marine activities may change after issuing this Manual.
If such cases exist, the ET Leader
shall propose with justification for changes to monitoring
locations or other requirements of
the EM&A programme,
and seek approval from the IEC and EPD.
5.6.1.5 The ENPO
may,
depending
on site conditions and monitoring results,
decides
whether additional monitoring locations shall be included or any monitoring locations could be removed/relocated during any stage of the construction phase, after getting approval from EPD.
5.7.1.1
Baseline conditions for marine water quality shall be established and agreed with EPD
prior to the commencement of works.
The purpose of the baseline
monitoring is to establish ambient conditions prior to the commencement of the works and to demonstrate the suitability
of the proposed impact and control monitoring stations. The baseline conditions
shall normally be
established by measuring the DO, temperature, turbidity, pH, salinity and SS at
all
designated locations specified in Section 5.6 above. The measurements shall be taken at all
designated monitoring stations including
control stations, 3
days per week, at mid- flood (within ¡Ó 1.75 hour of the predicted time) and mid-ebb (within
¡Ó 1.75 hour of the predicted time) tides, for at least 4 weeks prior to the commencement
of
marine works. Replicate in-situ measurements and
samples collected from each independent sampling event shall be collected to ensure a robust statistically interpretable database.
5.7.1.2 Baseline monitoring programme may overlap with
other reclamation
activities. The monitoring exercise should be scheduled as far as possible
to avoid concurrent
dredging / backfilling
activities
around the monitoring
stations
such that representative ambient data could be sampled.
5.7.1.3
Other relevant data shall also be recorded, such as monitoring location / position,
time, water depth, tidal stages, weather conditions and any
special phenomena
underway near the monitoring station.
There shall not be any marine construction
activities in the vicinity of the stations during the baseline monitoring.
5.7.1.4
As this project will last for a few years, the ET Leader should seek approval from
the IEC and EPD on an appropriate set of data to be used with the baseline data
collected by this study to establish
two set of AL levels respectively for the wet and dry season.
5.7.1.5
Baseline monitoring schedule shall be faxed to EPD 2 weeks prior
to
the
commencement of baseline monitoring. The
interval between two sets of monitoring shall not be less than 36 hours.
5.7.1.6 A Baseline
Water Quality Monitoring was conducted at sensitive receiver SR4a from 29 August
to 24 September 2013.
5.7.1.7 A For
the other six water quality monitoring stations, baseline monitoring was
conducted during the period of 6 October and 31 October 2011. Monitoring results are presented in the Baseline Environmental Monitoring for Hong
Kong-Zhuhai-Macao Bridge Hong Kong Projects ¡V
Investigation ([3]). The baseline
data will be adopted for analysis in the current EM&A Programme.
5.9.2.1 The preliminary ground investigation conducted for TM-CLKL did not detect Mf material (ie. Category M Sediment which fails the biological test as per ETWB
TC 34/2002) in the
project
site
and no handling of Mf has
been predicted.
Therefore, this sub-section
is only relevant to HKBCF and HKLR projects.
5.9.2.2 Not
applicable
5.9.2.3 Not
applicable
5.9.4A Water
Quality Monitoring for TM-CLKL Southern Connection
5.9.4.1 During
the course of construction works, impact monitoring should be undertaken at
seven
(7) monitoring stations in Table 5.2a
three days per week, at mid-ebb and mid-flood tides, with sampling/
measurement. Replicate in-situ measurements and samples
collected from each independent sampling
event shall be collected to ensure a
robust statistically interpretable database.
The measurement parameters for Post-
construction monitoring shall include DO, temperature, turbidity, pH, salinity
and SS. The measurement shall
be taken
at all
designated monitoring stations including control stations,
3 days per week, at mid-flood (within ¡Ó 1.75 hour of
the predicted time) and mid-ebb (within
¡Ó 1.75 hour of the predicted time) tides.
5.10.1.1
Upon completion of
all marine-based
construction activities,
a post-project monitoring exercise on water quality shall be carried out for 4 weeks in the same manner as the Baseline Monitoring. Replicate in-situ
measurements and samples collected
from each independent
sampling event shall be collected to ensure a
robust statistically interpretable database.
The measurement parameters for Post-
construction monitoring shall include DO, temperature, turbidity, pH, salinity
and SS. The measurement shall
be taken
at all
designated monitoring stations including control stations,
3 days per week, at mid-flood (within ¡Ó 1.75 hour of
the predicted time) and mid-ebb (within
¡Ó 1.75 hour of the predicted time) tides, for at least 4 weeks.
5.10.1.2 Not
applicable
5.11.1.1 The marine
water quality monitoring shall be performed monthly during the first year of
Project operation at all designated monitoring stations including control
stations. Each monthly monitoring
event shall consist of one monitoring and sampling event during both mid-ebb
(within ¡Ó 1.75 hour of the predicted time) and mid-flood (within ¡Ó 1.75 hour of
the predicted time) tides of the same monitoring day. The operation phase monitoring shall be
ceased after the first year of operation of the Project subject to the first
year review. No marine construction
activities should be conducted in the vicinity of the stations during the
Operational Phase monitoring period.
5.11.1.2 Sampling shall be
taken at three water depths, namely, 1m below water surface, mid-depth and 1m
above sea bed, except where the water depth is less than 6m, in which case the
mid-depth station may be omitted.
If the water depth be less than 3m, only the mid-depth station will be
monitored. In-situ measurements at
DO, turbidity, SS, pH, salinity and temperature shall be taken at all the
monitoring stations SR2, SR3, CS2 and CS(Mf)5 (refer to Table 5.2b). A full set of in duplicated situ
measurement and water samples shall be collected during each of the mid-ebb
(within ¡Ó 1.75 hour of the predicted time) and mid-flood (within ¡Ó 1.75 hour of
the predicted time) tides.
5.12.1.1
The Action and Limit levels for water quality are defined in Table
5.3. Should
non-compliance of the criteria occur, action in accordance with the Action Plan in
Table 5.4 shall be carried out.
5.12.1.2 Not
applicable
Table
5.3 Action and Limit Levels for Water Quality
Parameters |
Action# |
Limit# |
DO in mg L-1 (Surface, Middle & Bottom) |
Surface and Middle 5.0 mg/L Bottom 4.7 mg/L |
Surface and Middle 4.2 mg/L
Bottom 3.6mg/L |
SS in mg L-1 (depth-
averaged) at all monitoring stations
and control stations |
120% of upstream control station
at the same tide of the same day and 95%-ile of baseline data, i.e., 23.5 mg/L |
130% of upstream control station
at the same tide of the same day and and 99%-ile of
baseline data, i.e., 34.4 mg/L |
Turbidity in NTU (depth-averaged) |
120% of upstream control station at
the same tide of the same day and 95%-ile of baseline data, i.e., 27.5 NTU |
130% of upstream control station
at the same tide of the same day and 99%-ile of baseline data, i.e., 47.0 NTU |
Notes: |
|
|
# Baseline data: data from HKZMB
Baseline Water Quality Monitoring between 6 and 31 October 2011. |
||
(a) For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits. |
||
(b) ¡§Depth-averaged¡¨
is calculated by taking the arithmetic means of reading of all three depths |
||
(c) For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits. |
||
(d) All figures
given in the table are used for reference only, and EPD may amend the figures
whenever it is considered as necessary |
||
(e) The
1%-ile of baseline data for surface and middle DO is 4.2 mg/L, whilst for
bottom DO is 3.6 mg/L. |
Table
5.4 Event and Action Plan for Water Quality
Event |
ET Leader |
IEC |
SOR |
Contractor |
|||||
Action level being exceeded by
one sampling day |
1.
Repeat in situ measurement on
next day of exceedance to confirm findings; 2.
Identify source(s) of impact; 3.
Inform IEC, contractor and SOR; 4.
Check monitoring data, all plant, equipment and Contractor's working methods. |
1.
Check monitoring data submitted by ET and
Contractor¡¦s working methods. |
1.
Confirm receipt of notification of
non-compliance in writing; 2.
Notify Contractor. |
1.
Inform the SOR and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3.
Amend working methods if
appropriate. |
|||||
Action level being exceeded by
two or more consecutive
sampling days |
1.
Repeat measurement on next day of exceedance to confirm findings; 2.
Identify source(s) of impact; 3.
Inform IEC, contractor, SOR and EPD; 4.
Check monitoring data, all plant, equipment and Contractor's working methods; 5.
Discuss mitigation measures with
IEC, SOR and Contractor; 6.
Ensure mitigation measures are implemented; 7.
Increase the monitoring frequency to daily until
no exceedance of Action level; |
1.
Check monitoring data submitted by ET and
Contractor¡¦s working method; 2.
Discuss with ET and Contractor on possible remedial actions; 3.
Review the proposed mitigation measures submitted by
Contractor and advise the SOR accordingly; 4.
Supervise the implementation
of
mitigation measures. |
1.
Discuss with IEC on the proposed
mitigation measures; 2.
Ensure mitigation measures are properly implemented; 3.
Assess the effectiveness of the implemented mitigation measures. |
1.
Inform the Supervising Officer and confirm
notification of the non-compliance
in writing; 2.
Rectify unacceptable practice;
3.
Check all plant and equipment and consider changes
of working methods; 4.
Submit proposal of additional mitigation measures to SOR within 3 working days of notification and discuss with ET, IEC and SOR; 5.
Implement the agreed mitigation
measures. |
|||||
Limit level being exceeded by
one sampling day |
1.
Repeat measurement on next day of exceedance to confirm findings; 2.
Identify source(s) of impact; 3.
Inform IEC, contractor, SOR and EPD; 4.
Check monitoring data, all plant, equipment and Contractor's working methods; 5.
Discuss mitigation measures with 6.
IEC, SOR and Contractor; |
1.
Check monitoring data submitted by ET and
Contractor¡¦s working method; 2.
Discuss with ET and Contractor on possible remedial actions; 3.
Review the proposed mitigation measures submitted by
Contractor and advise the SOR accordingly. |
1.
Confirm receipt of notification of failure in writing; 2.
Discuss with IEC, ET and
Contractor on the proposed
mitigation measures; 3.
Request Contractor to review the
working methods. |
1.
Inform the SOR and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice;
3.
Check all plant and equipment and consider changes
of working methods; 4.
Submit proposal of mitigation measures
to SOR within 3 working days
of
notification and discuss with ET,
IEC and SOR. |
|
||||
Limit level being exceeded by
two or more consecutive
sampling days |
1.
Repeat measurement on next day of exceedance to confirm findings; 2.
Identify source(s) of impact; 3.
Inform IEC, contractor, SOR and EPD; 4.
Check monitoring data, all plant,
equipment and Contractor's
working methods; 5.
Discuss mitigation measures with
IEC, SOR and Contractor; 6.
Ensure mitigation measures are implemented; 7.
Increase the monitoring frequency to daily until
no exceedance of Limit level for
two consecutive days; |
1.
Check monitoring data submitted by ET and
Contractor¡¦s working method; 2.
Discuss with ET and Contractor on possible remedial actions; 3.
Review the Contractor¡¦s mitigation measures whenever necessary to assure their
effectiveness and advise the SOR accordingly; 4.
Supervise the implementation
of mitigation measures. |
1.
Discuss with IEC, ET and
Contractor on the proposed
mitigation measures; 2.
Request Contractor to critically review the working methods; 3.
Make agreement on the mitigation measures to be implemented; 4.
Ensure mitigation measures are properly implemented; 5.
Consider and instruct, if necessary,
the Contractor to slow down or to
stop all or part of the construction activities until no exceedance of Limit level. |
1.
Take immediate
action to avoid
further exceedance; 2.
Submit proposal of mitigation measures
to SOR within 3 working days
of
notification and discuss with ET,
IEC and SOR; 3.
Implement the agreed mitigation measures; 4.
Resubmit proposals of mitigation measures if problem
still not under
control; 5.
As directed by the Supervising
Officer, to slow down or to stop all or part of the construction activities until no
exceedance of Limit level. |
|
||||
6.1.1.1 The EIA has recommended that an EM&A for ecology is undertaken during the design, construction and operational phases of the project. The objectives of the
design phase EM&A are to prepare detailed specifications for translocation works
to be undertaken prior to construction.
The construction and operational EM&A objectives are to ensure that the ecological
contract works and construction mitigation procedures recommended in the EIA are carried out as specified and
are
effective.
The
construction and operational phase EM&A will be carried out
as part of the site monitoring and audit programme.
6.2.1.1 The design phase audit procedures
are detailed in Section 1.5.3 and Figure 1.1.
Ecological specifications for species translocation will be designed as part of
the
project detailed design phase. The specifications and designs will be reviewed as
and
when they are produced. The final ecological specifications and designs shall be
signed off by the design auditor(s) using the appropriate
proforma
(see Appendix B).
6.2.1.2 The construction phase ecological
audit is
concerned
with checking the effectiveness of the implementation of the ecology contract works, together with
auditing
the effectiveness of site mitigation. Operational phase EM&A will
comprise the audit of the reestablishment of
habitat areas and the on-going
effectiveness of
mitigation measures as
appropriate.
The
operational phase EM&A
shall be undertaken
during the Contractor¡¦s one year maintenance period.
The overall procedures
for
the ecological EM&A during construction and operation are shown in Figures 1.2 and 6.1.
6.3.1.1 Ecological measures proposed by the EIA to mitigate the ecology impacts of the scheme will be incorporated into the detailed design of the project.
In particular,
ecology specifications will be produced for the elements detailed in Table
6.1
below.
Table 6.1
Ecological Design Specifications
Number |
Specification |
1 |
Hoarding along the works boundary for protecting
the pitcher plants and its surrounding habitat (Not applicable to the current EM&A
Programme) |
2 |
Translocation specifications for corals |
3 |
Pre, during and post construction dolphin monitoring. |
4 |
Vessel speed limits and restrictions specification |
5 |
Bored piling monitoring programme specification |
6 |
Design of dredging and reclamation works acoustic decoupling
methods (Not applicable) |
7 |
Specification for dolphin
exclusion zone during
dredging, reclamation, sheet,
bored piling and
temporary staging const |
8 |
Artificial reef deployment (Not applicable) |
6.3.1.2 The specifications
should be issued to the EPD and
AFCD
and other
relevant
Authorities for approval
before being implemented prior to construction.
6.3.1.3 Designs and specifications
will
be prepared during the detailed design stage
by suitably qualified staff on the design
team. The
designs will be checked by a design auditor(s)
to
ensure
that
the
measures are
fully
incorporated and
that
potential conflicts
with the engineering are resolved prior to construction.
In the event of a non conformity, the Event/Action
plan
detailed in Table 6.2 below shall be followed by the relevant parties.
Table 6.2 Event / Action Plan for Design Phase
Action Level |
Ecology Auditor |
Project
Engineer (PE) |
Project
Ecologist (PEC) |
Non Conformity
(with Design Standards and
Specification) |
- Identify
Source - Inform PE and PEC - Discuss remedial
actions with PE,
and PEC - Verify remedial
actions when complete |
- Notify PEC - Discuss remedial
actions with PEC - Ensure remedial designs are fully incorporated |
- Amend designs - Discuss remedial actions with PE |
6.4.1.1 Ecological baseline EM&A will consist of undertaking the following:
¡P Walk-over survey, prior to construction works, of the land and streams
where works will be undertaken. It may be necessary
to rope off and protect specific habitats or species of
special interest identified during the ecological surveys;
¡P Audit of species translocation works (corals);
¡P Pre-construction dolphin monitoring; and
¡P Bored piling monitoring.
6.4.2.1
The purpose of the walk over survey will be to confirm the existing ecological
conditions, with
reference to the habitat maps included in the EIA Report and the established baseline conditions,
in
relation to the extent
and
condition
of the habitats
and
species noted
during
the walkover
survey. No detailed ecological surveys
of flora and fauna will be required at this stage.
6.4.3.1
In respect of translocation works, the ET will be required to audit the effectiveness
of
the implementation of the ecology translocation contract works, item 2 detailed
in
Table 6.1 above.
Prior to the translocation works, pre-construction
surveys of corals were conducted at Tai Ho Wan and the potential receptor site
of Tai Mo To (Figure 6.2). An alternative receptor site at Yam Tsui Wan is proposed for the translocated
coral from Tai Ho Wan. Finding of
the pre-construction survey are included in the Detailed Coral Translocation
Methodology which was submitted to the EPD in accordance with Condition 2.6 of the EP-354/2009A. The implementation of
the specification for translocation of
the corals should be undertaken prior to any major relevant
construction
works
and
thus, the
EM&A for these will
be
undertaken early in the Contract. The audit will continue into the construction
phase after the translocations have been completed.
6.4.3.2
A qualified ecologist(s), as part of the ET, will carry out the audit. The ecological
contract works, detailed in
Table
6.1, shall be audited with reference to the audit
schedule detailed in Table
6.3 below.
Table 6.3 Audit Schedule for Ecological Contract Works
Specification Number (Table 6.1) |
Baseline Phase |
Construction Phase |
2 |
Audit compliance at least once per
week during implementation which
will be prior to the start of the main construction activities. After translocation is complete,
carry out audit survey to determine if all corals have been moved. |
Audit success of translocation once
every 3 months after
completion by assessing survival of transplanted species. Continue for a
period of 12
months. |
6.4.4.1 Perhaps the most important
ecological measure of all is to conduct
surveys to monitor the density and behavior
of
the animals before,
during, and after the period of
the potential disturbance.
This objective is to determine if the other
mitigation
measures have been effective
in protecting the animals
from
disturbance and maintaining their habitat quality. In addition, it is necessary to monitor the effects of the construction works
on the use of dolphin travelling
corridors.
While there is not expected to be a complete physical blockage of the travelling corridors, the
works may have
some impacts in
terms
of reducing
dolphin use of these corridors.
As
data on this is scarce, dolphin monitoring is, also, required to monitor the use of the travel corridors and if the dolphins stop
using the corridors, then it will be necessary to provide some remediation to deal with this, in the form of adaptive management.
6.4.4.2 In order for
such monitoring
to
be effective, it needs to be divided
into
three phases: pre-disturbance
(i.e., baseline phase), disturbance (i.e, construction phase),
and
post-disturbance (i.e., operational
phase). Survey techniques must be held
constant from phase to phase and survey
equipment and personnel should ideally
be
the same as well.
6.4.4.3
Project-specific dolphin monitoring using line
transect
surveys
combined with photo-identification studies, also, have the advantage of
being able to provide evaluation of dolphin fine-scale
habitat use patterns.
This
includes 1 km2 per grid densities and grid-based patterns of feeding, socializing and calving, as well
as individual ranging patterns, allowing the detection of any smaller-scale impacts and changes in core area use (see Hung 2008).
6.4.4.4
Considering
that
AFCD
monitoring
provides useful
data, the monitoring
programme should comprise undertaking surveys, 2 days per month for a period
of 12 months during each phase.
Notwithstanding,
as
9
months of baseline
surveys have been undertaken for the purposes of this EIA, a further 3 months
only would be required for the pre-construction phase. In summary, the following
monitoring would be required:
¡P
Six, one-day survey
events to be undertaken at a frequency of 2 per month over a period of 3 months
before commencement of construction;
¡P
One-day survey events
to be undertaken at a frequency of 2 per month for the duration of the marine
works construction period; and
¡P
Forty-eight, one-day
survey events to be undertaken at a frequency of 2 per month over a period of
24 months following cessation of the construction.
6.4.4.5 The period required for the monitoring is considered to be adequate to derive a
reasonably large
amount of data, thereby
allowing
any significant trends in
dolphin distribution to be detected (Jefferson pers. comm.).
6.4.4.6
The
monitoring
should also be undertaken
by a suitably
qualified person (in biology)
and
should
be independent of the construction
contractor and should form part of the independent Environmental Team (ET).
The IEC may audit the work of the ET if deemed necessary.
Monitoring should be conducted following the methodology detailed below:
Vessel-based Observations
6.4.4.7 Line transect surveying
techniques have now been standardized in Hong Kong Special Administrative Region Waters so that data from all surveys are directly comparable. The study area with line
transects is presented in Figure 6.3 which
covers the Northeast Lantau (NEL) and Northwest Lantau (NWL). In order to provide a suitable
long-term dataset for comparison,
pre-, during and post-construction phase dolphin monitoring will employ an identical methodology and follow the same line transects as those in the EIA
Report.
Additional
transect lines that are used in the AFCD long-term dolphin monitoring are also included,
such that the monitoring data collected in this project is comparable to the
long-term databases maintained by AFCD.
6.4.4.8 On each survey day, the survey vessel will depart from Tung Chung New Pier. Observation for incidental sighting will begin immediately on departure from
the
assigned pier and continue until the vessel reaches the survey area. The survey
vessel shall have an open upper deck, allowing for observer eye heights of 4 to 5m above water level and relatively unobstructed forward visibility between 270º and
90º. When on-effort, the vessel shall travel along the survey lines at a speed of
approximately 7 to 8 knots (13 to 15 km/hr). The direction of the survey shall be
alternated on different days to avoid possible biases related to the timing of the
survey coverage.
6.4.4.9 Vessel-based transect observations by a three-person team shall be conducted by
searching the 180q swath in front of the survey vessel (270º to 90º). The area
behind the vessel need not be searched, although dolphins observed in this area should be recorded as off-effort
sightings. The primary observer will scan the entire search path (270º to 90º) continuously with Fujinon
7x50 marine binoculars or equivalent as the second member of the team, designated the data ¡§recorder¡¨, scans the same area with the naked eye and occasional binocular check. The third observer on the boat is required to rotate into the observation team after half an hour, thus relieving one of the initial
team. Observers should rotate every
half an hour.
While on-effort, observers shall ignore potential sighting cues that could
bias the sighting distance calibration (eg pair-trawl fishing vessels).
6.4.4.10 A critical consideration in the survey will be to ensure a strict timed quantification of
¡§sighting effort¡¨ in order to maximise the comparative value of the field survey
results. The time and position for the start and end of a period of intensive,
uninterrupted
effort, and
the
sighting
conditions such
as visibility
range and
Beaufort scale associated with it shall be recorded.
The collection of effort data
allows comparisons within a single
study as well
as between
studies.
Strict recording of time and speed travelling along the assigned transect (¡§on-effort¡¨)
shall, therefore, be recorded. Time spent during any deviation from the transect will be recorded as ¡§off-effort¡¨.
6.4.4.11 During periods of poor weather, when visibility is hindered (e.g., below 1km) or when a Beaufort force 5 is reached, the survey should normally be postponed.
6.4.4.12 Sightings distant to 500m perpendicular distance and sightings of single dolphins that were hard to track should not be pursued (although those distant to 500m
ahead of the vessel should be pursued). The initial sighting distance between the dolphin and the survey vessel and sighting angle shall be recorded in
order
to estimate the positions of the dolphins. These and other details of the sighting,
including the exact location of the sighting and number of individuals should be
agreed among
the observation
team and recorded immediately. Distances
and
angles shall be as accurate as possible.
6.4.4.13 A global positioning system shall be used during the surveys. A sighting record shall be filled out at
the
initial
sighting
with time, position, distance and angle data
filled in immediately and verified between primary observer and recorder. All other
information on sea state, weather conditions (Beaufort
Scale),
as
well as notes on dolphin appearance, behaviour, and any other information shall also be completed.
6.4.4.14 A summary of equipment requirement is summarized in Table
6.5 below.
Table 6.5 Summary of Dolphin Monitoring Equipment Requirements
Equipment |
Type |
Vessel for Monitoring |
A monitoring boat which should have a flying bridge
or upper deck with a relatively unobstructed forward visibility (270o ¡V 90o) allowing for observer eye height of 4-5m above water |
Observation |
Fujinon 7x50 marine binoculars (or similar) with
compass/reticule |
Calibration |
Leica Geovid laser range finder binnacles or equivalent |
Navigation and Positioning |
Global Positioning System Device (Magellen NAV 5000D or similar approved) (+ spare batteries) |
6.4.4.15
A The
three-month vessel-based Baseline Dolphin Monitoring was conducted between 5
September and 7 November 2011. The
monitoring results are presented in the Baseline
Environmental Monitoring for Hong Kong-Zhuhai-Macao
Bridge Hong Kong Projects ¡V Investigation ([4]). The baseline data will be adopted for
analysis in the current EM&A Programme.
6.4.5.1
Based upon the specification prepared during the detailed design phase (Item 5 in Table
6.1 above), a comprehensive monitoring plan
should be implemented before, during and after the bored piling works is proposed.
The monitoring plan would
include both underwater acoustic monitoring, the study
the acoustic behaviour
of dolphins near the bored piling works site and theodolite
tracking of
dolphin movement from land in order to determine the actual magnitude of impacts.
Acoustic Monitoring
6.4.5.2
In
order
to
ensure
that bored
piling
noise will
not
affect
the
Chinese
White
Dolphins,
noise levels
from
bored
piling
activities should be
measured,
with
details of frequency/intensity spectra to be evaluated.
The acoustic results of the monitoring should be analysed in terms of both the Broadband range (100 Hz to
25.6 kHz) and,
also, the dolphin
sensitive range (400
Hz to
12.6 kHz). The monitoring will study the acoustic
behaviour of dolphins near
the bored piling
works site and at a control
site for comparison, to determine whether foraging
behaviour is
affected by the bored
piling
activities and whether dolphin echolocation clicks are masked by bored piling activity noise.
6.4.5.3
The
specification and detailed
methodology for the bored piling acoustic monitoring should be prepared
as part of the detailed design and submitted to the EPD
and AFCD for approval.
6.4.5.4
The acoustic monitoring will be undertaken
during the construction phase and
commence at the start of the bored piling works. The exact monitoring period will
be
determined and detailed in the specification to
be
prepared during the detailed
design stage but is likely to comprise as a minimum:
¡P
underwater noise levels measurements from bored piling activities for 10 days from the start of bored piling activities; and
¡P
study the acoustic behaviour of dolphins from a small boat during periods
with and without bored piling for 30 days from the start of bored piling activities.
6.4.5.5
The monitoring works will consist of
data
acquisition and analysis of
sound to be gathered
by an
experienced bio-acoustician
with specialised experience
in processing of appropriate low frequency
(to infrasound, down to 20 Hz) and high
frequency (into ultrasound, to at least 100 kHz) hydrophone and digital recording equipment, as well as the appropriate analysis devices and programmes. The bio-
acoustician should have at least ten years of dolphin sound data gathering and analysis experience, at least three technical publications related to dolphin sounds.
6.4.5.6
As bored piling will also be undertaken for the HKLR project, it is possible that a combined monitoring could be undertaken.
The monitoring should be conducted at a location at which significant impacts on dolphins are unlikely.
Land-based Theodolite
Tracking
6.4.5.7
The objective of the land-based theodolite
tracking of
dolphins is to monitor their
movements
and behaviour
near the bored piling works site before,
during
and after the works and record and note any changes in response to the bored piling noise.
The details of the land-based dolphin tracking methodology and frequency
will be defined
in a specification prepared during detailed design phase.
However, as
a minimum the monitoring is likely to comprise 30 days before, 30 days during and 30 days after bored piling works
6.4.5.8
This monitoring would consist of data acquisition and analyses of movement and behavioural information of
CWD, as gained from a 5-sec. resolution conventional theodolite and a 5-sec. resolution
¡§total
station¡¨
theodolite
with laser
range- finding capability, appropriate hand-held range finders, binoculars with distance- measuring reticles and built-in compass, recording gear of digital voice recorder, data sheets, and computer slaved to theodolites.
6.4.5.9
Two experienced
theodolite/behavioural
data
gathering operators should undertake the monitoring. The primary and secondary theodolite operators should
have at least ten years of theodolite and behavioural data gathering and analysis
experience, at
least three
technical publications
to cover the subject, and appropriate long-term familiarity with the latest version of the tracking program
¡§Pythagoras¡¨.
These
experienced
operators need to
have further experience
in detailed power analyses for efficient evaluation of number of samples and
time/energy needed for statistical evaluations.
6.5.1.1 During the construction
and operational
phases the ET will be
required
to
undertake the following:
- continued audit of the translocation
works
as
per
the
requirements in Table 6.3 above;
-
audit of habitat protection measures as follows:
¡±
ensure that work site boundaries are not breached and that damage does not occur to surrounding
areas;
¡±
provided and scheduled environmental briefing/training sessions for site staff to raise their awareness
on environmental protection;
¡±
ensure placement
of equipment is within
designated areas within the existing disturbed land;
¡±
ensure construction activities are
restricted to within the
proposed works boundary;
¡±
ensure spoil heaps are be covered at all times;
¡±
ensure that disturbed areas are reinstated immediately
after completion of the works; and
¡±
ensure
temporary disturbance and gabion wall works of steam NL1 in
¡±
ensure
enhancement planting works undertaken.
-
audit
of acoustic decoupling for dredging
and reclamation work and the vessel restrictions requirements, as specified by
the specifications prepared during the design stage (items 4 and 6 in Table
6.1 above);
-
implement
any further recommendations, if any, of the bored piling monitoring;
-
implementation of the dolphin exclusion zone during dredging, reclamation , sheet, piling
works and temporary staging construction;
-
audit
the avoidance of peak CWD
calving season in May and June for driving of metal caissons during
bored piling works; and
-
audit
the pre-construction, construction and
operational phase dolphin monitoring.
6.5.2.1
A dolphin exclusion zone within a radius
of 250m around
the
dredging, reclamation, sheet, bored piling works as well as temporary staging
construction should be implemented and the area
visually inspected
for dolphins prior to commencement
of the marine works. The principles
of the exclusion
zone are that, during daylight hours, the area should be
visually inspected for dolphins prior to commencement
of
dredging, reclamation
or sheet piling works.
The sheet piling works will be restricted to 12 hours a day and
visual inspection will
be possible. However,
it is possible
that
the other marine works for the TM-CLKL would continue for 16 hours per day. As such, as the visual exclusion zone relies on the visual detection of
dolphins, it would not
suitable during evening or nighttime
periods. Based upon this, an alternative
method using Passive Acoustic Monitoring (PAM) would be required for
any dredging and reclamation
works
undertaken outside daylight hours.
PAM involves the use of hydrophones or cetacean detectors.
The specification prepared during the detailed design should further specify the use of
PAM.
6.5.2.2
The
dolphin
exclusion zone should be monitored
by independent dolphin
observers with an unobstructed, elevated view of
the area. Piling should not begin
until the observer certifies that the area is continuously clear of dolphins for a
period of 30 minutes
(thereby adequately
spanning the approximate
maximum
dive time of the dolphins of 4 minutes). The
observers must be suitably trained in
biology and should be independent of the construction contractor and should form
part of the
independent
Environmental
Team (ET)
to
be
employed
by
the
Contractor. An Independent
Environmental Checker
(IEC) would be required to audit the work of the ET.
6.5.2.3 For the overall audit of habitat protection, acoustic decoupling, dolphin exclusion zone and the vessel restrictions requirements, in the event of non-compliance, the Event /Action plan detailed in Table 6.6 below should be implemented.
Table 6.6 Event / Action Plan for General Ecology
Action Level |
ET |
IEC |
SOR |
Contractor |
Non-conformity
on one occasion |
1.
Identify Source
2.
Inform the IEC
and the SOR 3.
Discuss remedial
actions with the IEC, the SOR and
the Contractor 4.
Monitor remedial
actions until
rectification has been completed |
1.
Check report 2.
Check the Contractor's working method 3.
Discuss with the ET and the Contractor on
possible remedial
measures 4.
Advise the SOR on
effectiveness of proposed remedial measures. 5.
Check implementation
of remedial measures. |
1.
Notify Contractor Ensure remedial
measures are properly implemented 2.
Consider and instruct, if necessary, the
Contractor to slow down or
to
stop all or part of the works in the case of a serious non-
conformity until situation rectified. |
1.
Amend working methods 2.
Rectify damage and undertake any necessary
replacement |
Repeated Non conformity |
1.
Identify Source
Inform the IC(E) and the SOR
2.
Increase monitoring frequency Discuss remedial actions with the
IC(E), the SOR and the Contractor 3.
Monitor remedial
actions until
rectification has been completed 4.
If
exceedance stops, cease
additional monitoring |
1.
Check monitoring
report 2.
Check the Contractor's
working method 3.
Discuss with the ES and the Contractor on
possible remedial
measures 4.
Advise the SOR on
effectiveness of proposed remedial measures 5.
Supervise implementation of remedial measures |
1.
Notify the Contractor
2.
Ensure remedial
measures are properly implemented 3.
Consider and instruct, if necessary, the
Contractor to slow down or
to
stop all or part of the works in the case of a serious non-
conformity until situation rectified. |
1.
Amend working methods 2.
Rectify damage and undertake any necessary
replacement |
Note: ET ¡V
Environmental Specialist, IC(E) ¡V Independent Checker (Environmental),
SOR ¡V
Supervising Officer¡¦s Representative
6.5.3.1
The dolphin monitoring methodology is described in Section 6.4
above and this should be continued both
during construction
and
post construction
(operational) phase based using the same transect, method and survey techniques, based upon the following frequency:
-
one-day surveys to be undertaken at a frequency of 2 per month for the
duration of
the marine works construction; and
-
forty-eight, one-day survey events to be undertaken at a frequency of 2 per
month over a period of 24 months following cessation of the construction.
6.5.3.2
The data after each
phase should
be compared
the
pre-construction baseline
findings. Any apparent differences in density
among survey phases should be analysed
for trends and the statistical power of the analysis to detect effects of the desired size should be tested. Comparison
of the during and post construction dolphin monitoring with that of over the pre-construction dolphin monitoring will
allow the assessment of
the overall efficacy of the project-specific mitigation measures through the implementation of an Event
and Action Plan detailed in the Table 6.9b below.
Statistical procedures shall be used for data
comparison. A range of
applicable statistical procedures exist (e.g., t-test, ANOVA and ANCOVA, etc.) and the ET shall propose the procedure to be applied as part of the during and
post-construction phase dolphin monitoring programme design to be agreed with AFCD prior to the monitoring being undertaken.
6.5.3.3 Should dolphin sighting numbers in the construction or post-construction phases
be
significantly different (taking into account naturally
occurring alterations to
distribution patterns such
as
due
to
seasonal change) to
the
pre-construction
activity, recommendations
for a further post-construction monitoring survey will
be
made. Data
should then
be re-assessed and the
need for any
further monitoring
established.
Comparison of the pre-construction dolphin monitoring with that of the during and post- construction dolphin monitoring will allow the assessment of the overall efficacy of the project-specific mitigation measures and an
Event and Action Plan
for the dolphin is provided in Table
6.9b below.
6.5.3.4
An
action plan
should be defined to indicate that should dolphin numbers
be
significantly different (taking into account naturally occurring alterations to distribution
patterns
such
as
due
to
seasonal change) to
the
pre-construction
activity following the during and post-construction monitoring, recommendations
for further
monitoring
and mitigation will be required. The Action
and Limit level which will trigger the Event and Action Plan is
proposed for the EM&A programme of the HKBCF. The Action and Limit Level and the Event
and Action Plan of the HKBCF EM&A Programme will
both be adopted for the current EM&A Programme
given the same area of dolphin monitoring of the two programmes
(ie Northeast Lantau (NEL)
and Northwest Lantau (NWL)).
Table 6.9a Action
and Limit Level for Dolphin Monitoring
|
NEL |
NWL |
Action Level |
(STG < 4.2) & (ANI < 15.5) |
(STG < 6.9) & (ANI < 31.3) |
Limit Level |
(STG < 2.4) & (ANI <8.9) |
(STG < 3.9) & (ANI < 17.9) |
Note:
(1) AL
will be trigger if either NEL or NWL fall below the criteria; LL will be
triggered if both NEL and NWL fall below the criteria
Table 6.9b Event / Action Plan for During and Post Construction Dolphin
Monitoring
Event |
ET Leader |
IEC |
SOR |
Contractor |
Action
Level |
1.
Repeat statistical data analysis to confirm findings;
2.
Review all available and relevant data, including raw
data and statistical analysis results of other parameters covered in the
EM&A, to ascertain if differences are as a result of natural variation or
previously observed seasonal differences; 3.
Identify source(s) of impact; 4.
Inform the IEC, SOR and Contractor; 5.
Check monitoring data. 6.
Review to ensure all the dolphin protective measures
are fully and properly implemented and advise on additional measures if
necessary. |
1.
Check monitoring data submitted by ET and Contractor;
2.
Discuss monitoring results and findings with the ET
and the Contractor. |
1.
Discuss monitoring with the IEC and any other
measures proposed by the ET; 2.
If SOR is satisfied with the proposal of any other
measures, SOR to signify the agreement in writing on the measures to be
implemented. |
1.
Inform the SOR and confirm
notification of the non-compliance in writing; 2.
Discuss with the ET and the IEC and propose measures
to the IEC and the SOR; 3. Implement the
agreed measures. |
Limit
Level |
1.
Repeat statistical data analysis to confirm findings;
2.
Review all available and relevant data, including raw
data and statistical analysis results of other parameters covered in the
EM&A, to ascertain if differences are as a result of natural variation or
previously observed seasonal differences; 3.
Identify source(s) of impact; 4.
Inform the IEC, ER/SOR and Contractor of findings; 5.
Check monitoring data; 6.
Repeat review to ensure all the dolphin protective
measures are fully and properly implemented and advise on additional measures
if necessary; 7.
If ET proves that the source of impact is caused by
any of the construction activity by the works contract, ET to arrange a
meeting to discuss with IEC, ER/SOR and Contractor the necessity of
additional dolphin monitoring and/or any other potential mitigation measures
(e.g., consider to modify the perimeter silt curtain or consider to
control/temporarily stop relevant construction activity etc.) and submit to
IEC a proposal of additional dolphin monitoring and/or mitigation measures
where necessary. |
1.
Check monitoring data submitted by ET and Contractor;
2.
Discuss monitoring results and findings with the ET
and the Contractor; 3.
Attend the meeting to discuss with ET, ER/SOR and
Contractor the necessity of additional dolphin monitoring and any other
potential mitigation measures; 4.
Review proposals for additional monitoring and any other
mitigation measures submitted by ET and Contractor and advise ER/SOR of the
results and findings accordingly; 5.
Supervise / Audit the implementation of additional monitoring and/or
any other mitigation measures and advise ER/SOR the results and findings
accordingly. |
1.
Attend the meeting to discuss with ET, IEC and
Contractor the necessity of additional dolphin monitoring and any other
potential mitigation measures; 2.
If ER/SOR is satisfied with the proposals for
additional dolphin monitoring and/or any other mitigation measures submitted
by ET and Contractor and verified by IEC, ER/SOR to
signify the agreement in writing on such proposals and any other mitigation
measures; 3.
Supervise the implementation of additional monitoring
and/or any other mitigation measures. |
1.
Inform the ER/SOR and confirm
notification of the non- compliance in writing; 2.
Attend the meeting to discuss with ET, IEC and ER/SOR
the necessity of additional dolphin monitoring and any other potential
mitigation measures; 3.
Jointly submit with ET to IEC a proposal of
additional dolphin monitoring and/or any other mitigation measures when
necessary; 4.
Implement the agreed additional dolphin monitoring
and/or any other mitigation measures. |
6.5.3.5A It
should be noted that the current Southern Connection Viaduct Section EM&A programme is exempted from carrying out the vessel-based
line transect dolphin monitoring until the completion of the dolphin monitoring
carried out under the HKBCF Reclamation Contract and the Northern Connection
Sub-sea Tunnel Section Contract.
Vessel-based line transect dolphin monitoring data from the impact
monitoring of Contract No. HY/2011/03 -
HZMB HKLR - Section between Scenic Hill and HKBCF will be adopted for the
current Southern Connection Viaduct Section EM&A programme.
6.6.1.1 Ecological mitigation and enhancement measures recommended by the EIA are
largely
related
to the
protection of
key floral
and fauna species and are summarized below.
In addition, measures recommended to minimise impacts on water quality will, also, reduce impacts on marine ecological resources. The
ecological
mitigation and enhancement measures
to
be implemented during the construction phase are as follows:
l
use acoustic
decoupling methods to minimise noise being transmitted through the dredging and reclamation barges;
Vessel speed limit and restrictions
required for other parts of the works under the TM-CLKL will be implemented;
250m
dolphin
exclusion
zone
during
dredging, reclamation, sheet, bored
piling works and temporary staging work;
l
avoidance of the peak calving season of May
and June for installation of metal
caisson during bored piling works;
l
survey and translocation of corals before
the temporary staging construction as an enhancement measure;
l
regularly check the
work site boundaries to
ensure that they are
not breached and that damage does not occur to surrounding areas;
l
provided environmental briefing/training
sessions for site staff;
l
planting of approximately 33ha as an
enhancement measure for vegetation loss; and
l
gabion wall works in steam NL1 in Lantau to be undertaken in the dry season.
6.6.1.2 The mitigation measures shall be audited at least once every week as part of the site audit programme. In the event of a non-compliance, the Event /Action plan
detailed above shall be followed by the relevant
parties.
6.6.1.3 In addition, in order to address the cumulative impacts from all the projects and
compensate for the cumulative Chinese
White Dolphin and fisheries habitat loss,
the Government has made a firm commitment to seek to designate the Brothers
Islands as a marine park for enhancing the CWD habitat in accordance with the
statutory process stipulated in the Marine Parks Ordinance.
The designation of
the proposed marine park would proceed after the
completion of
these projects. A study will be conducted to confirm the details of the proposed marine park before
the commencement of the statutory
procedures as stipulated in the Marine Parks
Ordinance. The Government¡¦s commitment to the marine park and its control
and
management in accordance
with
the
Marine Parks
Ordinance,
as
well as
the
Marine
Parks and Marine
Reserves Regulations, would significantly help
conserve the CWD,
and hence serves as an effective
mitigation measure for the loss of
CWD habitat arising from
these projects. With this committed measures, the residual cumulative impacts to the CWD in terms of permanent habitat loss would
be
acceptable.
7.1.1.1
The EIA
has
recommended landscape and visual
mitigation
measures to be undertaken during both the construction and operational phases of the project. This section outlines
the monitoring and audit of these measures.
7.1.1.2 The sensitive receivers are shown in Figures 7.1.1.3 to 7.1.1.5, 7.2.1.3 to 7.2.1.5, 7.3.1.2, 7.3.1.4 and 7.3.2.1.
7.2.1.1
The following legislation, standards and guidelines are applicable to landscape and
visual impact assessment associated with the construction and operation of the project:
¡P Environmental Impact Assessment Ordinance
(Cap.499.S.16) and the Technical
¡P Memorandum on EIA Process (EIAO TM),
particularly Annexes 10 and 18
¡P Environmental Impact Assessment Ordinance
Guidance Note 8/2002
¡P ETWB No. 36/ 2004 - Advisory Committee on
the Appearance of Bridges and Associated Structures (ACABAS)
¡P ETWB TCW No. 10/2005 - Planting on
Footbridges and Flyovers
¡P ETWB
TCW No. 2/2004 -
Maintenance of Vegetation and Hard Landscape Features
¡P ETWB
TCW No. 29/2004 -
Registration of Old
and Valuable Trees, and Guidelines for their Preservation
¡P ETWB TCW No. 3/2006 - Tree Preservation
¡P ETWB TCW No. 5/2005 on Protection of
natural streams/rivers from adverse impacts arising from construction works
¡P Hong Kong International Airport Approved
Plant Species List (Revision 3: June 2007)
¡P Hong Kong Planning Standards and
Guidelines, particular Chapter 4, Chapter 8, Chapter 10 and Chapter 11
¡P HQ/GN/13 - Interim Guidelines for Tree
Transplanting Works under Highways Department¡¦s Vegetation Maintenance Ambit
¡P HyDTC No. 3/2008 - Independent Vetting of Tree
Works under the Maintenance of Highways Department
¡P HyDTC No. 5/2000 on Control in the Use of Shotcrete (Sprayed Concrete) in Slope Works
¡P Protection of Endangered Species of Animals
And Plants Ordinance (Cap 586)
¡P Study on Landscape Value Mapping of Hong
Kong
¡P Town Planning Ordinance (Cap 131)
¡P WBTC No. 17/2000 on Improvement to the
Appearance of Slopes
¡P WBTC No. 25/92 - Allocation of Space for
Urban Street Trees
¡P WBTC No. 25/93 on Control of Visual Impact
of Slopes
¡P WBTC No. 7/2002 - Tree Planting in Public
Works
7.3.1.1 The
design, implementation
and maintenance of landscape and visual mitigation
measures should be checked to ensure that they are fully realised and that potential
conflicts between the proposed landscape measures and any other project works and
operational
requirements are resolved at the earliest possible date and without compromise to the intention of the mitigation measures.
7.3.1.2 Site inspection and audit is necessary in the operation stage.
Table 7.1 Monitoring Programme
Stage |
Monitoring
Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring
of design works against
the recommendations
of the
landscape and visual
impact assessments within the
EIA should be undertaken
during detailed design and tender stages,
to ensure that they fulfil the intentions of the
mitigation measures. Any
changes
to the design,
including design changes on site should also be checked. |
Report by SOR
confirming that the design conforms to
requirements
of
EP |
Approved by Client |
At Completion
of Design Stage |
Construction |
Monitoring of the contractor¡¦s
operations during the construction period. |
Report on
Contractor's compliance,
by
ET |
Counter-signature of report by IEC |
Weekly |
Establishment Works |
Monitoring of
the
planting
works during the
24-month establishment period
after completion
of the construction works. |
Report on
Contractor's compliance,
by
ET |
Counter-signature of report by IEC |
3 months |
Design
Phase
7.3.1.3
The
mitigation measures proposed within the EIA to mitigate the landscape and visual impacts of the scheme should be embodied into the detailed engineering design and landscape design drawings and contract documents. Detailed landscaping
drawings and specification
should be checked during detailed design
stage and before tender stage by a Registered Landscape Architect to ensure that the measures are fully incorporated and that potential conflicts with civil engineering, geo-technical,
structural, lighting, signage, drainage, underground utility and operational
requirements are resolved prior to construction. Monitoring of design works against
the recommendations of the landscape and visual impact assessments within the EIA
should be undertaken
when the designs are produced to ensure that
they fulfill the intentions of mitigation measures.
Construction & Establishment Period
7.3.1.4
The implementation of landscape construction works and subsequent maintenance
operations during the 12-month
establishment period must be supervised by fully qualified Landscape Resident Site Staff (Registered Landscape Architect or
Professional Member of the Hong Kong Institute of landscape Architects).
7.3.1.5
Measures to mitigate landscape
and visual impacts during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance
with the intended aims of the mitigation measures.
7.3.1.6
The progress of the engineering works shall be regularly reviewed on site to identify
the
earliest practical opportunities for the landscape works
to be undertaken.
7.4.1.1
A one off survey shall be conducted prior to commencement of any construction
works. A photographic record of the site at the time of the contractor¡¦s possession of
the site shall be prepared by the Contractor and approved by the SOR.
The approved photographic Record shall be submitted to the Project proponent, ET, IEC and EPD
for record.
7.5.1.1
Should non-compliance of
the
landscape
and
visual
impacts
occur, actions
in
accordance with the
action plan
stated in Table 7.2 should be carried out.
Table 7.2 Event and Action Plan for Landscape and Visual Impact
EVENT ACTION LEVEL ¡@ |
Action |
|||
ET |
IEC |
SOR |
Contractor |
|
Design Check |
¡P Check final design conforms to the requirements
of EP and prepare report. |
¡P Check report. |
¡P Undertake remedial design if necessary |
¡@ |
¡@ |
¡@ |
¡P
Recommend remedial design if necessary |
¡@ |
¡@ |
Non-conformity on one occasion |
¡P Identify Source |
¡P Check report |
¡P Notify Contractor |
¡P Amend working methods |
¡@ |
¡P Inform IEC and |
¡P Check Contractor's working method |
¡P Ensure remedial measures are properly
implemented |
¡P Rectify damage and undertake any
necessary replacement |
¡@ |
¡P Discuss remedial actions with IEC, SOR and
Contractor |
¡P Discuss with ET and Contractor on
possible remedial measures |
¡@ |
¡@ |
¡@ |
¡P Monitor remedial actions until
rectification has been completed |
¡P Advise SOR on effectiveness of proposed
remedial measures. |
¡@ |
¡@ |
¡@ |
|
¡P Check implementation of remedial
measures. |
¡@ |
¡@ |
Repeated Non-conformity |
¡P Identify Source |
¡P Check monitoring report |
¡P Notify Contractor |
¡P Amend working methods |
¡@ |
¡P Inform IEC and SOR |
¡P Check Contractor's working method |
¡P Ensure remedial measures are properly
implemented |
¡P Rectify damage and undertake any
necessary replacement |
¡@ |
¡P Increase monitoring frequency |
¡P Discuss with ET and Contractor on
possible remedial measures |
|
¡@ |
¡@ |
¡P Discuss remedial actions with IEC, SOR
and Contractor |
¡P Advise SOR on effectiveness of proposed
remedial measures |
¡@ |
¡@ |
¡@ |
¡P Monitor remedial actions until
rectification has been completed |
¡P Supervise implementation of remedial
measures. |
¡@ |
¡@ |
¡@ |
¡P If non-conformity stops, cease additional
monitoring |
¡@ |
¡@ |
¡@ |
7.6.1.1 The landscape and visual impact assessment of the EIA recommends a series on
mitigation measures, as noted below:
Design Landscape and Visual Mitigation Measures
|
|
„h |
|
„h |
¡P
Round angle, patterned finishes, and oval shaped pier were considered in
the viaduct design, and further details will be developed under ACABAS
submission (DM3); |
„h |
¡P
Details of the street furniture will be developed in the detailed design stage (DM4); and |
„h |
¡P
Aesthetic design of the viaduct, retaining wall and other structures will be developed under ACABAS submission
(DM5). |
Landscape and Visual Mitigation Measures during Construction Phase
„h |
¡P
Existing trees on boundary of the Project Area shall be carefully
protected during construction. Detailed Tree Protection Specification shall
be provided in the Contract Specification. Under this specification, the
Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor¡¦s works areas.
(Tree protection measures will be detailed at Tree Removal Application stage)
(CM1), |
„h |
¡P
Trees unavoidably affected by the works shall be transplanted where
practical. Trees will be
transplanted straight to their final receptor site and in the Contract
Specification. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme
(CM2),not held in a temporary nursery. A detailed Tree Transplanting
Specification shall be provided |
„h |
¡P
Hillside and roadside screen planting to proposed roads, associated
structures and slope works (CM3), |
„h |
¡P
Hydroseeding or sheeting of soil stockpiles with
visually unobtrusive material (in earth tone) (CM4), |
„h |
¡P
Screening of construction works by hoardings around works area in visually unobtrusive colours, to screen works (CM5), |
„h |
¡P
Control night-time lighting and glare by hooding all lights (CM6), |
|
¡P
Ensure no run-off into water body adjacent to the Project Area (CM7), |
„h |
¡P
Avoidance of excessive height and bulk of buildings and structures
(CM8), |
„h |
¡P
Recycle/Reuse all felled trees and vegetation, e.g. mulching (CM9), |
„h |
¡P
Compensatory tree planting
shall be provided to the satisfaction of relevant Government departments.
Required numbers and locations of compensatory trees shall be determined and
agreed separately with Government during the Tree Felling Application process
under ETWBTC 3/2006 (CM10). |
Landscape and Visual Mitigation Measures during Operation Phase
„h |
¡P
Re-vegetation of affected woodland/shrubland
with native species (OM1), |
„h |
¡P
Tall buffer screen tree / shrub / climber planting should be
incorporated to soften hard engineering structures and facilities (OM2), |
„h |
¡P
Streetscape elements (e.g. paving, signage, street furniture, lighting
etc.) shall be sensitively designed in a manner that responds to the local
context, and minimises potential negative landscape
and visual impacts. Lighting units should be directional and minimise unnecessary light spill (OM3), |
„h |
¡P
Structure, ornamental tree / shrub / climber planting should be provided
along roadside amenity strips, central dividers and newly formed slopes to
enhance the townscape quality and further greenery enhancement (OM4), |
„h |
¡P
Aesthetically pleasing design (visually unobtrusive and non-reflective)
as regard to the form, material and finishes shall be incorporated to all buildings, engineering structures and associated
infrastructure facilities (OM5), |
„h |
¡P
Avoidance of excessive height and bulk of buildings and structures
(OM6). |
8.1.1.1 The
Contractor
is responsible
for
waste control within the construction site, removal of waste material produced from the site and to implement any mitigation
measures to minimise
waste or redress problems arising from the waste from the
site.
Activities during the construction phase will result in the generation of a variety
of wastes which can broadly be classified into distinct categories based on
their nature and the options for their disposal. These include:
¡P
Marine
dredged sediment;
¡P
Excavated construction and
demolition (C&D)
materials suitable for public fill,
including the alluvium from the tunnel construction;
¡P
Construction
and demolition waste, including cleared vegetation, which is not suitable for
public fill;
¡P
Chemical
waste;
¡P
Sewage;
and
¡P
General
refuse.
|
|
8.1.1.2 Not applicable
8.1.1.3 Not applicable
8.1.1.4
A
total
of 0.028Mm3 of dredged material
is predicted
to
be generated, comprising
approximately 0.02Mm3 of Category L, 0.005 Mm3 of Category Mp and
0.003 Mm3 of Category
Mf materials.
8.1.1.5 The Construction and Demolition (C&D) materials generated from the TM-CLKL
project will comprise the following:
¡P
Alluvium
and CDG from the submarine tunnel and deep sections of the marine viaduct
bridge piers and building foundations;
¡P
Excavation materials from the land viaduct construction, slope cutting, utility diversions, site formation of
the toll plaza and
administration buildings formation; and
¡P
Road
and pavement demolition waste from the modification of the existing roads for
new roads connections.
8.1.1.6
In accordance with the waste hierarchy, the amounts of materials to be generated has been minimised by optimizing the slope profiles. However, a total of
141,994 m3 of
soft C&D material will
be generated and
will require off site disposal or to be reused. All
the material will be suitable for public fill, although alluvium and small amounts of CDG generated by the deeper sections of the marine
viaduct piles will require to be treated at a
slurry treatment plant and suitably dried before transfer to a fill bank.
The by-
product of the treatment comprises both a coarser, dry material and a wet spoil, and, where required, the spoil material shall be scarified to ensure it is "suitably" dried before it can be disposed
of to the fill bank.
This principle of disposal has
been agreed by the Public Fill Committee.
8.1.1.7 An
estimated total of 129,006 m3 of C&D materials
will be reused on site.
In addition, 1,249
m3 of various new material will, also,
required importing.
The onsite transfer and off site removal of the material has the potential for impacting any local residents associated with the possible dust generation from
the
exported
fill,
deposition of
material on
public
roads and emissions
and noise from the construction
vehicles.
However,
the additional
traffic is not expected to cause any additional impacts to sensitive receivers along this route. It should be noted that the forecast of
the volume of generated C&D materials would be updated upon completion of
the Design works for the Project
8.1.1.8 The volumes C&D
waste, are expected to be limited but the material, not being suitable for public fill, will require disposal to landfill.
It
is, also, unlikely that
any large quantities of chemical wastes will be generated during the construction of this project but
any
materials
should be
handled,
stored,
transported and disposed
of in an appropriate manner.
Other wastes including sewage and general
refuse will be generated
and these will also need to be collected and disposed offsite appropriately.
8.1.2.1
Based on the mitigation measures recommended in the EIA Report, the following measures,
as summarized in
the Environmental Mitigation
Implementation Schedule
in
Appendix A, shall
be undertaken
when
handling waste material
during construction phase:
i)
The requirements as stipulated
in the ETWB TC(W) No.19/2005 Environmental Management on Construction Sites and the other relevant
guidelines should be included in the
Particular Specification for the Contractor as appropriate.
ii)
The TM-CLKL Contractor should be
requested
to submit
an outline Waste Management Plan
(WMP) prior to the commencement of
construction work, in accordance with the ETWB TC(W) No.19/2005 so
as to provide an overall framework of
waste management and reduction.
The WMP should include:
¡P
Waste management policy;
¡P
Record of
generated waste;
¡P
Waste reduction target;
¡P
Waste reduction programme;
¡P
Role and responsibility of waste management team;
¡P
Benefit of waste management;
¡P
Analysis of waste materials;
¡P
Reuse, recycling and disposal plans;
¡P
Transportation process of waste products; and
¡P
Monitoring and action plan.
iii) The waste
management
hierarchy below should be
strictly followed.
This hierarchy should be adopted
to evaluate the waste management
options in order to maximise
the extent of waste reduction and cost
reduction. The records of quantities of
waste generated, recycled and disposed
(locations) should be properly documented.
iv) A trip-ticket system should be established in accordance with ETWB(W) 31/2004
and Waste
Disposal
(Charges for Disposal of
Construction
Waste) Regulation to monitor the disposal of public
fill and solid wastes
at public filling facilities and landfills, and to control fly-tipping.
A
trip-
ticket system would be included as one of the contractual requirements
for
the Contractor to
strictly
implement. The Supervising
Officer would
also
regularly audit the effectiveness of the system.
v)
A recording system for
the amount
of waste
generated, recycled and disposed
(locations)
should
be established.
The
future Contractor should also provide proper training to workers
regarding the appropriate
concepts
of
site cleanliness and
waste management
procedures, e.g.
waste reduction, reuse and recycling all the time.
vi)
The CEDD should be timely notified of the estimated spoil volumes to be generated and the Public Fill Committee should be notified and agreement sort on the disposal of surplus inert C&D materials e.g. good
quality rock during detailed design of the TM-CLKL project. Wherever practicable,
C&D materials should be segregated from other wastes to
avoid contamination
and
to ensure acceptability at public filling areas or reclamation sites.
vii) The
extent of cutting
operation should be
optimised where possible. Earth retaining structures and bored pile walls should
be proposed to minimise the extent of cutting.
viii)
Inert C&D materials from slopes and road pavement will be reused for construction of the raised platform for the toll plaza.
ix) C&D materials
generated by construction of cut slopes along NLH at
x)
The surplus surcharge
should be transferred
to a fill bank.
xi)
TMB generated alluvium and CDG material should be treated at a slurry treatment plant prior to transfer to a fill bank
(Not applicable).
xii)
Rock
armour from the existing
seawall
should be reused
on the new
sloping seawall as far as possible.
xiii) The site and surroundings shall be kept tidy and litter free.
xiv) No waste shall be burnt on site.
xv)
Make provisions in contract documents to allow and promote the use of recycled aggregates where appropriate.
xvi)
Prohibit the Contractor to dispose
of C&D materials at any sensitive
locations e.g. natural habitat,, etc. The Contractor should propose the final disposal sites in the EMP and WMP for approval before
implementation.
xvii)
Stockpiled material shall be covered
by tarpaulin and /or watered as
appropriate to prevent windblown dust and surface run off.
xviii)Excavated material in trucks shall be covered by tarpaulins to reduce the potential for spillage and dust generation.
xix)
Wheel washing facilities shall be used by all trucks leaving the site to
prevent transfer of mud onto public roads.
xx)
Dredged marine mud shall be disposed of in a gazetted marine disposal ground under the requirements of the Dumping at Seas Ordinance.
xxi)
Standard formwork
or pre-fabrication should be
used as far as practicable so as to minimise the C&D materials
arising. The use of
more durable formwork or plastic facing for construction works should also be considered.
The use of wooden hoardings should be avoided and
metal hoarding should be used to facilitate recycling.
Purchasing of
construction materials should
be carefully planned
in
order to avoid over-ordering and wastage.
xxii)
The Contractor should recycle as many C&D materials (this is a waste section) as possible on-site. The public fill and C&D waste should be segregated
and stored
in separate
containers or skips to facilitate the reuse or recycling of materials and proper disposal.
Where practicable,
the concrete and masonry should be crushed and used as fill materials.
Steel reinforcement bar should be collected for use by
scrap steel mills. Different
areas of the sites
should
be considered for segregation and storage activities.
xxiii)All falsework
will be steel instead of wood.
xxiv)
Chemical waste
producers
should
register with
the
EPD. Chemical waste should be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes as follows:
¡P
Suitable for the substance to
be held,
resistant
to corrosion,
maintained in good conditions and securely closed;
¡P
Having a capacity
of <450L unless the specifications have been approved by the EPD; and
¡P
Displaying
a label in English and Chinese according to the instructions prescribed in Schedule 2 of the Regulations.
¡P Clearly labelled and used solely for the storage of chemical wastes;
¡P Enclosed with at least 3 sides;
¡P
Impermeable floor and bund with capacity to accommodate 110% of
the
volume
of the largest
container or
20%
by
volume
of the chemical waste stored in the area, whichever is greatest;
¡P
Adequate ventilation;
¡P
Sufficiently covered to
prevent rainfall entering
(water collected
within the bund must be tested and disposed of
as
chemical waste, if
necessary); and
¡P
Incompatible materials are adequately separated.
xxv) Waste oils, chemicals or solvents shall not be disposed
of to drain;
xxvi) Adequate
numbers of portable toilets should be
provided for on-site workers. Portable toilets should be
maintained in reasonable states, which will not deter the workers
from utilising them. Night soil should be regularly collected
by licensed collectors.
xxvii) General
refuse arising on-site should be
stored in enclosed bins or compaction units separately from
C&D and chemical wastes.
Sufficient dustbins shall be
provided for storage of waste as required under the Public Cleansing and Prevention of
Nuisances By-laws. In addition, general
refuse shall be
cleared daily and shall be
disposed of to the nearest licensed landfill or refuse
transfer station. Burning of refuse on construction sites is prohibited.
xxviii) All waste containers shall be in a secure area on hardstanding;
xxix) Aluminum
cans are usually collected and
recovered from the
waste stream by individual collectors if they are
segregated and easily accessible. Separately labelled bins for
their deposition should be provided as far as practicable.
xxx) Office wastes can be reduced by recycling of paper if
such volume is sufficiently large to warrant collection. Participation in a local collection
scheme by the
Contractor should be
advocated. Waste separation facilities for paper, aluminum cans, plastic bottles, etc
should be provided on-site.
xxxi) Training
shall be provided to
workers about the
concepts of site cleanliness and
appropriate waste management procedure, including waste reduction, reuse and
recycling.
8.1.3.1 The recommended disposal sites for the different types of waste are detailed in Table 8.1 below:
Table 8.1 Recommended
Waste Disposal Sites
Type of
Waste |
Disposal Site |
Marine Dredged Mud
(1) |
Category L and Mp ¡V South Dangan
Liedao, South Cheung Chau
Open Sea Sediment Disposal Area and ESC/SB Contaminated Mud Pits. Category Mf ¡V ESC/SB Contaminated Mud Pits. |
C&D materials |
Tuen Mun Areas 38 public fill bank |
C&D waste (plastics, glass, wood, including cleared vegetation etc.) |
North Lantau Refuse Transfer Station; or NWNT Refuse Transfer Station |
Chemical waste (as defined under Schedule
1 of the Waste Disposal (Chemical
Waste) Regulation) |
Chemical Treatment Facility at Tsing Yi: or Other approved facility |
General refuse |
North Lantau Refuse Transfer Station; or NWNT Refuse Transfer Station |
Note: (1) Subject to DASO application
8.2.1.1
The results of the contaminated land assessment did not reveal any contamination hotspots that might be affected by the proposed TM-CLKL works and as such no mitigation measures in the form
of contaminated land remediation is required. Therefore, no EM&A activities for the construction nor operational phases have
been recommended as no significant impacts are predicted.
8.3.1.1 EM&A requirements are required for waste management during the construction
phase only and the effective management of
waste arisings during the construction
phase will be monitored through the site audit programme.
The aims of the waste
audit are:
¡P
to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and
¡P
to encourage the reuse and recycling of material.
8.3.1.2
The Contractor shall be required to pay attention to the environmental standard
and guidelines
and
carry out appropriate
waste management
and
obtain the relevant licence/permits for waste disposal. The Environmental Team (ET) shall
ensure that
the Contractor has obtained
from the
appropriate authorities the necessary waste disposal permits or licences including:
¡P
Chemical Waste Permits/licenses under the
Waste Disposal Ordinance (Cap 354);
¡P
Public
Dumping Licence under the
Land (Miscellaneous
Provisions) Ordinance (Cap 28);
¡P
Marine Dumping Permit under the Dumping at
Sea Ordinance (Cap 466); and
¡P
Effluent Discharge Licence
under the Water Pollution Control Ordinance.
8.3.1.3
The
Contractor shall
refer
to
the
relevant booklets issued
by
the
DEP
when applying for the licence/permit and the Environmental Team (ET) (see Section 1) shall refer to these booklets for auditing purposes.
8.3.1.4 During the site inspections and the document review procedures as mentioned in Chapter 10 of this Manual, the ET shall pay special attention to the issues relating to waste management and check whether the Contractor has followed the relevant contract specifications and the procedures specified under the laws of Hong Kong.
In addition to
the
site inspections, the ET
shall review the documentation procedures
prepared by the Waste Coordinator once a
week to ensure
proper records are being maintained and procedures
undertaken in accordance with the Waste Management Plan.
8.3.1.5
The Contractor¡¦s waste management practices should be audited with reference to
the checklist detailed in
Table 8.2 below:
Table 8.2 Waste Management Checklist
Activities |
Timing |
Monitoring Frequency |
If non-compliance,
Action Required |
All necessary waste disposal
permits or
licences have been
obtained |
Before the commencement of demolition
works |
Once |
Apply for the necessary permits/
licences prior to
disposal of the waste. The ET shall ensure that corrective action has been taken. |
Only licensed waste haulier are used for
waste collection. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to use a
licensed
waste haulier. The Contractor shall temporarily
suspend waste collection of
that particular waste until a licensed
waste haulier is used. Corrective action shall
be undertaken within 48 hours. |
Records of quantities of wastes generated,
recycled and disposed
are properly kept. For demolition material/waste, the number of loads for
each day shall be recorded (quantity of waste can then be
estimated based on
average truck load.
Should landfill
charging be implemented, the receipts of
the charge
could be used for estimating the quantity). |
Throughout the works |
Weekly |
The Contractor shall
estimate the missing data based on
previous
records and the
activities carried
out. The ET shall audit the results and forward to the SOR and IEC for approval. |
Wastes are removed from site in
a timely
manner. General refuse
is collected on
a daily basis. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to remove waste accordingly. |
Waste storage areas are properly cleaned and do not cause windblown litter and dust nuisance. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to clean
the storage area and/or cover the waste. |
Different types of waste are segregated
in different containers
or skip to enhance recycling of material
and proper disposal of
waste. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to provide
separate skips/
containers. The Contractor
shall ensure the workers place the waste in the appropriate containers. |
Chemical wastes are stored, handled
and disposed of in accordance with the Code of Practice on
the Packaging,
Handling and Storage
of Chemical Wastes, published by the EPD. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to rectify the problems immediately. Warning shall be
given to the Contractor if
corrective actions are not taken within 24 hrs and the Waste Control Group of the EPD shall be identified. |
Demolition material/waste in dump trucks
are properly covered
before leaving the site. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall instruct the Contractor to comply. The Contractor shall
prevent trucks
shall leaving the site until the waste are properly covered. |
Wastes are disposal of at licensed sites. |
Throughout the works |
Weekly |
The ET shall inform the SOR and IEC of the non- compliance. The SOR shall warn the Contractor and instruct the Contractor to ensure the wastes are disposed of at the licensed sites. Should
it
involve chemical waste, the Waste Control Group of EPD shall be notified. |
Note: ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, SOR ¡V Supervising
Officer¡¦s Representative
9.1.1.1
Cultural
heritage resources are not identified within the works area of TM-CLKL Southern
Connection Viaduct Section. As
such, EM&A requirements for cultural heritage are Not applicable to the
Southern Connection Viaduct Section.
10.1.1.1 The
landfill gas hazard assessment undertaken in the EIA identified the hazards
that are likely to be generated from the Pillar Point Valley (PPV) Landfill,
during the construction and operation phases of this Project and evaluate the
associated risk. The EIA Report
recommended that some precautionary measures are required to protect the
proposed TM-CLKL toll plaza from the landfill gas risk due to the PPV Landfill. As such, the EM&A requirements for
landfill gas hazard are Not applicable for the current Southern Connection
Viaduct Section EM&A Programme.
11.1.1.1 Site inspections
provide
a direct means to assess and ensure
the
Contractor¡¦s environmental protection and pollution control measures are in compliance with the contract specifications. Site inspections shall be undertaken routinely by the Environmental
Team (ET) (see Section 1) to inspect the construction activities in order to ensure that appropriate environmental protection and pollution control
mitigation measures are properly implemented in accordance with the EIA.
11.1.1.2 The ET is responsible for the formulation of an environmental
site inspection, deficiency and remedial action reporting system and for carrying out the site
inspection works. In consultation with the Independent
Environmental Checker (IEC), the ET shall prepare a procedure for the site inspection, deficiency and
remedial action reporting requirements and submit this to the Contractor for agreement and to the Supervising
Officer¡¦s Representative (SOR) for approval
within 21 days
of commencement to the construction contract.
11.1.1.3
Regular site inspections shall be carried out at least once per week. The areas of inspection shall not be limited to the site area and should also include the
environmental conditions outside the site which are likely to be affected, directly or indirectly, by the site activities.
11.1.1.4
The ET shall make reference to the following information while conducting the
inspections:
i)
the EIA recommendations
on environmental protection and
pollution control mitigation measures as stated in the EIA report;
ii)
work progress and programme;
iii)
individual works methodology proposals;
iv) the contract specifications on environmental protection;
v)
the relevant environmental protection and pollution control laws;
vi) previous site inspection results; and
vii) environmental monitoring data.
11.1.1.5 The
Contractor shall
update the ET
with all relevant
information on
the
construction works prior to carrying out the site inspections. The site inspection
results
and associated recommendations
on
improvements
to
the environmental
protection and pollution control
works
shall be submitted, in a site inspection
proforma
(see Appendix B), by the ET to the IEC, the SOR and the Contractor within 24 hours
for reference
and for taking immediate
action. The Contractor
shall follow the procedures and time-frame, as stipulated in
the environmental site
inspection,
deficiency and remedial
action reporting
system to
report on
any
remedial measures subsequent to site inspections.
11.1.1.6 Ad hoc site inspections shall also be carried out by the ET and IEC if significant
environmental
problems
are identified. Inspections may also be
required subsequent to receipt of an environmental complaint (an example of the complaint
log is provided in Appendix B) or as
part of the investigation work as specified in
the Action Plan for environmental monitoring and audit.
11.2.1.1 There are contractual environmental protection and pollution control requirements as well as environmental protection and pollution control laws in Hong Kong with which the construction activities shall comply.
11.2.1.2 In order that the works are in compliance with the contractual requirements, all the
works
method statements submitted by the Contractor to the SOR for approval
shall be sent to the ET for vetting to see whether sufficient environmental protection
and
pollution control measures
have been included.
11.2.1.3 The ET shall also review the progress and programme
of the works to check that relevant environmental laws
have
not
been violated and
that
any
foreseeable potential for violating the laws can be prevented.
11.2.1.4 The Contractor
shall regularly copy relevant documents to
the ET so that the checking work can be carried out. The documents shall include at minimum the
updated Work Progress Reports, the updated Works Programme, the application letters for different licence/permits
under the environmental protection laws and all valid
licence/permit. The site
diaries shall
also be available
for
the
ET¡¦s inspection upon request.
11.2.1.5 After
reviewing
the document,
the
ET shall advise the IEC, the SOR
and
the
Contractor
of any non-compliance with
the
contractual and legislative
requirements on environmental
protection and pollution control for them
to take follow-up actions.
The ET shall also advise the IEC, the Contractor and the SOR
on the
current status on licence/permit applications
and
any environmental protection and pollution control preparation works that may not be suitable for the
works
programme or may result in potential violation of environmental protection and pollution control requirements.
11.2.1.6 Upon receipt of the advice, the Contractor
shall undertake immediate
action to
remedy the situation.
The ET, IEC and the SOR shall follow up to ensure that
appropriate
action has been
taken by the Contractor
in order
that the environmental protection and pollution control requirements are fulfilled.
11.3.1.1
Complaints shall be referred to the
ET for
carrying out complaint investigation
procedures. The ET shall
prepare a flow
chart of the complaint
response
procedures that addresses, complaint
receiving
channels, responsible parties/contacts for information, the investigation
process, procedures for the
implementation of mitigation/remedial
action, guidelines for communication and
public relation with the complainant etc.
The flow chart should be agreed by all
parties and issued to the Contractor, SOR and IEC for reference.
11.3.1.2 The ET shall undertake the following procedures upon receipt of
a complaint:
i)
log complaint and date of receipt into the complaint database and inform
the IEC immediately;
ii)
investigate
the complaint and discuss with the Contractor to determine its
validity and to assess whether the source of the problem is due to works
activities;
iii)
if a complaint is considered
valid by the SOR or EPD and due to the works,
the ET shall identify mitigation measures in consultation with the IEC;
iv)
if mitigation measures are required, the ET shall
advise the Contractor accordingly;
v)
review the Contractor's response on the identified mitigation measures and
the updated situation;
vi)
if the
complaint is
transferred from
EPD, an
interim report shall
be submitted to EPD on the status
of the complaint investigation and follow-
up action within the time frame assigned by EPD;
vii)
(vii)
undertake additional
monitoring and audit
to verify the situation
if necessary and ensure that any valid reason for complaint does not recur;
viii)
report the investigation results and the subsequent actions on the source of the complaint for responding to complainant. If
the source of complaint is
EPD, the results
should
be reported within the time
frame assigned by
EPD; and
ix)
record the complaint, investigation, the subsequent actions and the results
in
the monthly EM&A reports.
11.3.1.3 During the complaint investigation work, the Contractor
and SOR shall cooperate with
the
ET in
providing all the necessary
information
and
assistance for completion of the investigation.
If mitigation measures are identified in the investigation by the
ET, in consultation
with the IEC,
the Contractor
shall promptly carry out the mitigation measures. The ET and SOR shall approve the
proposed mitigation measures and check that the measures have been carried out by
the Contractor.
11.4.1.1 At times during the construction phase the Contractor may submit method
statements for various aspects of construction. This state of affairs would only apply to
those construction
methods
that
the EIA has
not
imposed
conditions
while for construction methods that have been assessed
in the EIA, the Contractor is bound to follow the requirements and recommendations in the EIA study. The Contractor¡¦s options for alternative construction methods may introduce adverse environmental impacts into the project.
It
is the responsibility of the ET, in accordance
with
established standards, guidelines and EIA study
recommendations and requirements, to review and determine the adequacy of
the
environmental protection
and pollution
control measures
in
the
Contractor¡¦s
proposal in order to ensure no unacceptable impacts would result. To achieve this
end, the
ET
shall
provide a copy
of the Proactive Environmental Protection Proforma as
shown in Appendix B to
the IEC for approval. The IEC
should audit the review of the construction method and endorse the proposal on
the basis of no adverse environmental impacts.
12.1.1.1 The following
reporting requirements are
based upon a paper documented approach. However, the same information can be provided in an electronic medium upon agreeing the format with the Supervising Officer¡¦s Representative (SOR). The
reports are required to be prepared by the Environmental Team (ET).
12.2.1.1 All documentation is required to be filed in a traceable
and systematically manner.
Site documentation, including
monitoring
field
records,
laboratory
analysis
records, meeting minutes, correspondences etc.(some
examples are provided in
Appendix B) shall be cross-referenced by the ET and be ready for inspection upon
request. All EM&A
results and findings shall be
documented in the
respective construction and operational phase EM&A reports prepared by the ET
and endorsed by the Independent Environmental Checker (IEC) prior to dissemination to the Contractor, the SOR and EPD.
All reports including details of
water quality monitoring, ecology, landscape
and visual and archaeological
EM&A shall also be issued to the AFCD and the AMO as appropriate.
12.2.1.2
All documentation shall be in paper form and/or electronic (in an agreed format) upon
request. All documents and data shall be kept for at least one year after the completion of the operational phase EM&A works. All submissions
(reports, data and correspondences etc.) shall
be liable to free use for the purposes
of communicating environmental data and the owner of information shall claim no
copyright. Any request to treat all or part of a submission in confidence will be
respected, but if no such request
is made it will be assumed that the submission is
not intended to be confidential.
12.3.1.1 The Design
Audit Report shall provide the means for the Consultant undertaking
the detailed design of the project to certify that environmental design
elements and specifications have been completed in accordance with the EIA requirements.
The Consultant shall include in the report a signed off proforma
(see Appendix B)
to confirm that there are no outstanding environmental
measures, identified as requiring
design phase audit, that require further
action.
The Design Audit Report and specifications shall be prepared by the Consultants and issued to EPD, the AFCD and the PlanD,
as appropriate, prior to the commencement of the tendering period.
12.4.1.1 In respect
of the
construction
phase
EM&A works,
the
ET shall prepare and submit a Baseline Environmental Monitoring Report within 10 working days of completion
of baseline monitoring. Copies of the Baseline Environmental
Monitoring Report
shall be submitted to the following: the Contractor, the IEC,
the SOR, EPD, the AFCD and the AMO as appropriate.
The ET shall liaise with the relevant parties on the exact number of
copies required.
12.4.1.2 The baseline
monitoring reports for both the construction and operational phases
12.4.1.2 The
baseline monitoring reports for both the construction and operational phases
shall include at least the following:
i)
Up to half a page executive summary.
ii)
Background information.
iii)
Drawings showing locations of the baseline monitoring stations.
iv)
An updated construction programme with milestones of environmental protection/mitigation activities annotated.
v)
Monitoring results (in both hard and
diskette copies)
together with the following information:
¡P
monitoring
methodology;
¡P
name
of laboratory and equipment used and calibration details;
¡P
parameters
monitored;
¡P
monitoring
locations (and depth);
¡P
monitoring
date, time, frequency and duration; and
¡P
QA/QC
results and detection limits.
vi)
Details on
influencing factors, including:
¡P
major activities, if any, being carried out on the site during the period;
¡P
weather
conditions during the period; and
¡P
other
factors which might affect the results.
vii) Determination of
the Action and
Limit Levels for
each monitoring parameter
and statistical analysis of the baseline data.
viii) Revisions for inclusion in the EM&A Manual. (ix) Comments
and conclusions.
12.5.1.1 The results and findings of all construction phase EM&A work required in this
Manual shall be recorded in the EM&A
Reports prepared by the ET on
a monthly basis and endorsed
by the
IEC. The EM&A Reports shall be prepared and submitted within 10 working days of the end of each reporting month, with the first report due one month and 10 days after construction commences.
12.5.1.2 A maximum of 4 copies of each EM&A Report shall be submitted to each of the following parties: the Contractor, the IEC, the SOR, EPD, the AFCD, the AMO and the PlanD, as appropriate. Before submission of the first EM&A Report, the ET
shall liaise with
the
parties on the exact
number
of copies
and
format of the reports in both hard copy and electronic medium.
12.5.1.3 Not applicable
12.5.1.4 The
ET shall review
the
monitoring
programme every 6 months
or on an as needed basis in order to cater for any changes in the surrounding environment and
nature of
works
in progress and shall document all observations in
the
monthly/bi-
monthly reports.
12.6.1.1 The first EM&A report for both th