Contract No. HY/2012/07
Tuen Mun ¡V Chek
Lap Kok
Link ¡V Southern Connection Viaduct Section
Contract Specific Environmental Monitoring and Audit Manual
Contents
1.1
Background Information
1.2
Policy
1.3
EM&A Programme Objectives
1.4
Scope of the EM&A Programme
1.5
Project Organisation
1.6
Terminology
2.1
Scope of the Project
2.2 Northern
Section in Tuen Mun (not applicable)
2.3
Submarine Tunnel
(not applicable)
2.4
Southern Section at HKBCF
/ North Lantau (not applicable)
2.5
Works Areas
2.6
Sewage and Drainage
2.7
Project Programme
2.8
Concurrent Projects
2.9
Traffic Data and Assumptions
3.1
Air Quality
Parameters
3.2
Monitoring Equipment
3.3
Laboratory Measurement/Analysis
3.4
Monitoring Locations
3.5
Baseline Monitoring
3.6
Impact Monitoring
3.7
Event and Action Plan for Air Quality
3.8
Dust Mitigation Measures
4
NOISE
4.1
Introduction
4.2
Noise Parameters
4.3
Monitoring Equipment
4.4
Monitoring Locations
4.5
Baseline Monitoring
4.6
Construction Phase Impact Monitoring
4.7
Event and Action Plan for
Construction Noise
4.8
Noise Mitigation Measures
5.1
Introduction
5.2
Mitigation Measures
5.3
Water Quality
Parameters
5.4
Monitoring Equipment
5.5
Laboratory Measurement / Analysis
5.6
Monitoring Locations
5.7
Baseline Monitoring for Water Quality
5.8
Efficiency of Silt Curtains (not applicable)
5.9
Impact Monitoring for Water Quality
5.10 Post-construction Monitoring
5.11 Operational Phase Monitoring
5.12 Event and Action Plan
6
ECOLOGY
6.1
Introduction
6.2
Ecology EM&A Procedures
6.3
Design Phase Audit
6.4
Baseline Monitoring
6.5
Construction and Operational Phase EM&A
6.6
Mitigation and Enhancement Measures
7. LANDSCAPE AND VISUAL ASSESSMENT
7.1 Introduction
7.2 Relevant
Legislation
7.3 Methodology and Criteria
7.4 Baseline Monitoring
7.5 Event and Action Plan
7.6 Mitigation Measures
8
WASTE MANAGEMENT AND CONTAMINATED LAND
8.1
Waste Issues
8.2
Contaminated Land
8.3
Waste EM&A Requirements
9.1
Introduction
10
Landfill
Gas
Hazard Assessment
10.1 Introduction
11.1 Site Inspections
11.2 Compliance with Legal and Contractual Requirements
11.3 Environmental Complaints
11.4 Choice of Construction
Metho
12
REPORTING
12.1 General
12.2 Documentation
12.3 Design Audit Report
12.4 Baseline Monitoring Report
12.5 EM&A Reports
12.6 First EM&A Report
12.7 Subsequent EM&A Reports
12.8 Quarterly EM&A Summary Reports
12.9 Annual/Final
EM&A Review Reports
12.10 Data Keeping
12.11 Interim Notifications of Environmental Quality Limit
Exceedances
Appendices
Appendix A Environmental Mitigation Implementation Schedules
Appendix B Environmental Proformas
Annexes
Annex A Silt Curtain Arrangement & Temporary Staging Preliminary Layout
Annex B Figures
Figure 1.1 Design Phase EM&A Procedure and Organisation
Figure 1.2 Construction and Operational Phase Procedure and Organisation
Figure 2.1 General Layout of TM-CLKL
Figure 2.2a Not
applicable
Figure 2.2b Layout Plan of Southern Landfall
Figure 2.3a Not applicable
Figure 2.3b Not
applicable
Figure 2.3c Not
applicable
Figure 2.4a Not
applicable
Figure 2.4b Not
applicable
Figure 2.4c General Layout for Southern Viaduct (1)
Figure 2.4d General Layout for Southern Viaduct (2)
Figure 2.4e General Layout for Southern Viaduct (3)
Figure 2.4f General Layout for Southern Viaduct (4)
Figure 2.4g General Layout for Southern Viaduct (5)
Figure 2.4h General Layout for Southern Viaduct (6)
Figure 2.4i General Layout for Southern Viaduct (7)
Figure 2.4j General Layout for Southern Viaduct (8)
Figure 2.5a Geological Section (Sheet 1 of 3)
Figure 2.5b Not
applicable
Figure 2.5c Not
applicable
Figure 2.6a Not
applicable
Figure 2.6b Not applicable
Figure 2.6c Not applicable
Figure 2.7 Southern Viaduct Connection and Slip Roads
Figure 2.8a Not
applicable
Figure 2.8b Proposed Works Areas for TM-CLKL (Lantau Side)
Figure 2.9a Not applicable
Figure 2.9b Indicative Construction Programme in North Lantau
Figure 2.9c Not applicable
Figure 2.9d Portions of Works in North Lantau
Figure 3.1 Data Sheet for TSP Monitoring (at
the end of Section 3)
Figure 3.2 Environmental Monitoring Stations
Figure 4.1 Noise Monitoring Field Record Sheet
(at the end of Section 4)
Figure 4.2 Not applicable
Figure 5.1 Not applicable
Figure 5.2 Not applicable
Figure 5.3 Not applicable
Figure 5.4 Not applicable
Figure 5.5a Not applicable
Figure 5.5b Not applicable
Figure 5.5c Not applicable
Figure 5.6a Not applicable
Figure 5.6b Not applicable
Figure 5.6c Not applicable
Figure 5.7 Water Quality Monitoring Data Record Sheet
Figure 5.8 Not applicable
Figure 5.9 Not applicable
Figure 5.10 Not applicable
Figure 6.1 Construction Phase Ecological EM&A Procedure
Figure 6.4 Location of Stream NL1
Figure 7.1.1.1 Not applicable
Figure 7.1.1.2 Not applicable
Figure 7.1.1.3 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 3
of 5)
Figure 7.1.1.4 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 4
of 5)
Figure 7.1.1.5 Baseline Landscape Resources with Development Proposal Overlaid (Sheet 5
of 5)
Figure 7.2.1.1 Not applicable
Figure 7.2.1.2 Not applicable
Figure 7.2.1.3 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 3 of 5)
Figure 7.2.1.4 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 4 of 5)
Figure 7.2.1.5 Baseline Landscape Character Areas with Development Proposal Overlaid
(Sheet 5 of 5)
Figure 7.3.1.1 Not applicable
Figure 7.3.1.2 Baseline Key VSRs and Viewpoint at Local Level
with Development Proposal Overlaid During Construction (Sheet 2 of 2)
Figure 7.3.1.3 Not applicable
Figure 7.3.1.4 Baseline Key VSRs and Viewpoint at Local Level
with Development Proposal Overlaid During Operation (Sheet 2 of 2)
Figure 7.3.2.1 Baseline Key VSRs Viewpoints at Strategic and
District Level with Development Proposal Overlaid
Figure 9.1 Not applicable
Figure 12.1 Sample Template for Interim Notifications of Environmental Quality Limits Exceedances
Annex C Summary of Change
Tables
Table 1.1 |
|
Table 2.1 |
Not applicable |
Table 2.2 |
|
Table 2.3 |
Not applicable |
Table 3.1a |
Method of Derivation of Action and
Limit Levels for Air Quality |
Table 3.1b |
|
Table 3.2 |
|
Table 4.1 |
|
Table 4.2 |
|
Table 5.1 |
|
Table 5.2a |
Proposed Water Quality Monitoring
Stations (Construction and Post-construction Phases) |
Table 5.2b |
Proposed Water Quality Monitoring
Stations (Operation Phase) |
Table 5.3 |
|
Table 5.4 |
|
Table 6.1 |
|
Table 6.2 |
|
Table 6.3 |
|
Table 6.4 |
Not applicable |
Table 6.5 |
|
Table 6.6 |
|
Table 6.7 |
Not applicable |
Table 6.8 |
Not applicable |
Table 6.9a |
|
Table 6.9b |
Event / Action Plan for During and
Post Construction Dolphin Monitoring |
Table 7.1 |
|
Table 7.2 |
|
Table 8.1 |
|
Table 8.2 |
|
Table 9.1 |
Not applicable |
Table 9.2 |
Not applicable |
Table 10.1 |
Not applicable |
Note:
All information regarding the Mf
Related Monitoring are no longer applicable as
recommended in Supporting Document of Variation of EP for TM-CLKL (EP354/2009).
1.1.1.1 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by
the Transport Department, Tuen Mun Road, Ting
Kau Bridge,
Lantau Link
and
North Lantau
Highway (NLH)
will
be operating beyond capacity after 2016 due to the increase in cross boundary traffic,
developments in the NWNT, and possible
developments in North Lantau,
including the Airport developments,
the
Lantau Logistics Park (LLP)
and
the
Hong Kong
¡V
Zhuhai
¡V
Macao
Bridge (HZMB).
In
order to cope with the anticipated
traffic demand, two new connections between
NWNT and
North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
1.1.1.2 The proposed TM-CLKL
if combined with the TMWB will
provide a direct route
linking NWNT and North Lantau, from north to south, the Kong Sham Western
Highway
(KSWH), port
back-up areas in NWNT, Tuen Mun
River Trade
Terminal, the existing EcoPark in Tuen Mun
Area 38, the Airport, the proposed
LLP,
HZMB
and
North Lantau developments. The new connection
will significantly reduce the travelling time between the KSWH and the NWNT region
at its northern side, and
1.1.1.3 In 2005, Highways
Department (HyD)
commissioned
an engineering feasibility
study (FS), namely Tuen Mun Chek Lap Kok Link and
Tuen Mun Western Bypass ¡V Feasibility Study (Agreement
No. CE 28/2005 (HY)), to evaluate the technical
feasibility and
impacts of the Project.
The FS recommended that the TM-CLKL should be a dual 2-lane road with a total length of about 9 km with
about 4 km long submarine
tunnel and 5 km long elevated structure.
1.1.1.4 In order to progress this project, Maunsell
Consultants Asia Ltd. were appointed by HyD to carry out the Assignment on Tuen Mun ¡V Chek Lap Kok
Link - Investigation under Agreement
No. CE 52/2007 (HY). The
Assignment
commenced on 19 May 2008 and shall be completed within 24 months, i.e. by mid-May 2010.
1.1.1.5 The
Feasibility Study
initially
proposed an
alignment of
the
TM-CLKL comprising a toll plaza island at Tai Mo To and this alignment formed the basis of the EIA Study Brief (ESB 175/2007). However, subsequent to these documents
being prepared and based upon the proposed schemes for the
1.1.1.6 The project is a designated project under Section A.1 of Schedule 2 of the Environmental
Impact Assessment Ordinance (EIAO).
As such, the statutory procedures under the EIAO need to be followed and an environmental permit (EP) will be required prior to the commencement of construction. Thus, as part of this assignment, an Environmental Impact Assessment (EIA) has been undertaken.
1.1.1.7 The
EIA for the project
has recommended comprehensive Environmental
Monitoring
and
Audit requirements
to be undertaken during the design,
construction and operational stages of
the project.
This Report constitutes
the
Environmental
Monitoring
and
Audit (EM&A) Manual for the
proposed Tuen Mun - Chek Lap Kok Link (TM-CLKL) Project, providing details of the EM&A
recommendations.
1.1.1.8 The
Hong
Kong SAR Government¡¦s
applicable environmental regulations
for noise, air
quality, ecology,
water quality,
landscape and visual resources
and waste
management
and heritage protection, the Hong Kong Planning Standards
and Guidelines and recommendations
in the TM-CLKL EIA Report have served as guidance documents in the preparation of this Manual. This EM&A Manual
fulfills the requirements of the Study Agreement and follows the approach
recommended in EPD¡¦s
Generic EM&A Manual, Annex 21 of the Technical
Memorandum on
the EIA
Process
and
EM&A Guidelines
for
Development
Projects in
1.2.1.1 The Supervising
Officer¡¦s Representative (SOR) and the Contractor
shall adopt
Environmental
Policy Statements in accordance with the requirements of this Manual in order to
foster
a sound EM&A programme to protect
the environment.
The following policy statements shall be adopted:
- establish a commitment
to environmental excellence
in all activities arising from the development project;
- encourage
the
adoption of
environmental management
principles
to prevent potential impacts and minimise adverse impacts; and
- commit to the recommendations
in the EIA study report and related EIA
process requirements.
1.3.1.1 The broad objective of this EM&A Manual is to define the procedures of the EM&A programme for monitoring the environmental
performance
of the TM-
CLKL project during design, construction and implementation.
1.3.1.2 The manual provides details of the environmental monitoring requirements arising
from the EIA including air, noise and water quality, as well
as audit recommendations for the noise, air, water quality, ecology, landscape and visual, waste and cultural heritage. The purposes of the defined EM&A programme
are as follows:
- to ensure the specified
mitigation recommendations of
the EIA
are
included in the design of
the project;
- to clarify and identify sources of pollution,
impact and nuisance
arising from the works;
- to confirm compliance with legal, contract specifications
and EIA study recommendations;
- to provide an early warning system for impact prevention;
- to
provide
a database of environmental parameters against
which to determine any short term or long term environmental impacts;
- to propose timely, cost-effective and viable solutions to actual or potential environmental issues;
- to
monitor performance
of the
mitigation measures and to
assess
their
effectiveness and, whenever necessary, identify any further need for additional measures;
- to verify the EIA predicted impacts;
- to collate information and evidence for use in public, District Council and
Government consultation; and
- to audit environmental performance.
1.3.1.3 EM&A procedures are required during the design, construction
and
operational
phases of the project implementation and a summary of the requirements for each of
the environmental parameters is detailed in Table 1.1 below.
Table 1.1 Summary of EM&A Requirements
Parameter |
EM&A
Phase |
||
Design |
Construction Phase |
Operational
Phase |
|
Air Quality |
|
Y |
|
Noise |
|
Y |
|
Ecology |
Y |
Y |
Y |
Water Quality |
|
Y |
Y |
Landscape
and Visual |
Y |
Y |
Y |
Waste/Contaminated Land |
|
Y |
|
Cultural
Heritage |
Not applicable
as cultural heritage resource is not identified for the works area of the
Contract. |
1.4.1.1 The scope of the EM&A programme
is to undertake the following, which follows the
demarcation of monitoring responsibilities set out in Environmental
Project Office¡¦s letter dated 29.10.2013:
a)
Implement
monitoring
and audit activities for each
environmental
parameter as follows:
Dust: |
i)
Establish baseline dust levels at specified locations and review these
levels on a regular basis. |
|
ii)
Implement construction dust impact monitoring programme. |
Noise: |
i)
Establish baseline noise, levels at specified locations and review
these levels on a regular basis. |
|
ii)
Implement
construction noise impact monitoring |
Ecology: |
i)
Implement design phase audit for ecological dolphin protection
specifications, ecological translocation specifications and design integrated
ecological mitigation measures. |
|
ii)
Implement baseline survey to establish existing ecological conditions. |
|
iii)
Implement construction phase monitoring and audit requirements for
ecology resources. |
|
iv)
Implement operational phase monitoring. |
Water Quality: |
i)
Establish baseline water quality levels at specified locations and
review these levels on a regular basis. |
|
ii)
Implement construction water quality impact monitoring programme. |
|
iii)
Implement operational phase water quality impact monitoring programme. |
|
|
Landscape
and |
i)
Design detailed landscape specifications. |
Visual: |
ii)
Implement baseline survey to establish/confirm existing landscape and
visual conditions. |
|
iii)
Implement construction phase audit requirements for landscape and visual
resources. |
|
iv)
Implement operational phase audit
requirements for landscape and visual aspects. |
Waste: |
i)
Implement construction phase audit requirements for waste aspects. |
Heritage:
|
i)
Not applicable |
|
|
b)
Liaison and provision of advice to construction site staff on the purposes and implementation of the EM&A programme.
c)
Identify and resolve environmental issues that may arise from the project.
d)
Check
and quantify the Contractor¡¦s
overall performance, implement Event/Action Plans and recommend and implement remedial actions to
mitigate adverse environmental
effects as identified by
the EM&A programme
and EIA.
e)
Conduct monthly reviews of
monitored impact
data during the construction phase and bi-monthly reviews during the operational phase as
the basis for assessing compliance with defined criteria and ensuring that necessary mitigation
measures
are identified,
designed
and implemented
and
to undertake additional ad hoc monitoring and audit as required by
particular circumstances.
f)
Evaluate and interpret all environmental
monitoring data
to provide
an early indication should any of the environmental
control measures or
practices fail to achieve the acceptable standards and to verify the environmental impacts predicted in the EIA.
g)
Manage
and liaise with other individuals or
parties
concerning any relevant environmental issues.
h)
Audit the effectiveness of the
Environmental Management System (EMS) practices and procedures and implement
any changes as appropriate.
i)
Conduct regular site audits of formal or informal nature to assess:
- the level of the Contractor¡¦s general environmental awareness;
- the Contractor¡¦s implementation of the recommendations in the EIA;
- the Contractor¡¦s performance as measured
by the EM&A;
- the need for specific mitigation measures to be implemented or the continued usage of
those previously agreed;
and
- to
advise the site staff of any
identified potential environmental issues.
j)
Submit EM&A
reports which summarise
project monitoring and auditing data, with full interpretation, illustrating the acceptability or otherwise of any environmental impacts and identification or assessment of
the
implementation status of agreed mitigation measures.
1.4.1.2 Thus, this EM&A
Manual provides the following information:
a)
Description of the project.
b)
Identification and recommendations for
monitoring requirements for all phases of
development, including:
- identification of sensitive receivers;
- monitoring locations;
- monitoring parameters and frequencies;
- monitoring equipment to be used;
- programmes for baseline monitoring and impact monitoring; and
- data management of monitoring results.
c) The organisation management structure, and procedures for auditing of the Project and implementation of mitigation measures that are recommended
for the Project.
d) The environmental quality performance limits for compliance auditing for each of the recommended monitoring
parameters to ensure compliance with relevant environmental quality objectives, statutory or planning
standards.
e) Organisation
and management
structure, and procedures for reviewing the design
submissions, monitoring results and auditing the compliance of
the
monitoring data with the environmental
quality performance limits,
contractual and regulatory requirements, and environmental
policies and
standards.
f) Event and Action plans for impact and compliance procedures.
g) Complaints handling, liaison and consultation procedures.
h) Interim notification of exceedances, reporting procedures, report
formats and
reporting
frequency
including periodical quarterly summary reports and annual reviews to cover all construction, post-Project and operational phases of the development.
i)
Implementation schedules,
summarising
all
recommended mitigation measures.
1.4.1.3 This
Manual is considered to be a working document and should be reviewed periodically and revised once substantial changes have been made.
1.5.1.1 For the purpose of this EM&A Manual, the Highways Department of the Hong
Kong SAR Government is
referred
to as the ¡§Employer¡¨
and the Project ¡§Supervising Officer¡¨ defined
as the Supervising Officer¡¦s Representative (SOR),
who
will
be responsible for the supervision of
the construction of the Project.
1.5.1.2 The mitigation/enhancement measures recommended by the TM-CLKL EIA that will require
a design audit or preparation
of
specifications
during the detailed
design phase of
the project will include:
- bored
piling monitoring programme;
- pre,
during and post construction dolphin monitoring;
- 250m
dolphin exclusion zone for use during dredging, reclamation, sheet, bored
piling works and temporary staging construction;
- acoustic decoupling methods for
use during reclamation and
dredging works;
- marine
vessel control specifications;
- deployment
of an artificial reef (Not applicable);
- installation of
hoarding for the
protection of the
pitcher plants and surrounding habitat (Not
applicable);
- coral
translocation;
- design
of toll plaza for grave G1 set back and protection (Not applicable); and
- landscape
design drawings.
1.5.1.3 In respect of the design phase EM&A, the Consultant commissioned to undertake the Detailed
Design
contract will be
required
to
designate
an
auditor(s)
to undertake the preparation
of
the
design specifications
as detailed
above, in
addition to an environmental
audit of
the
design
of
the specified
landscape measures in order to ensure that the recommendations of the EIA have been fully
and properly specified. The Consultant
shall use suitably qualified staff
to undertake the audit requirements to the satisfaction of the EPD and the AFCD as
appropriate. A flow chart of the design phase EM&A
procedures is shown in Figure 1.1.
1.5.1.4 During the construction and operational phases of the project, an Environmental
Team (ET) is to be employed by the Contractor. The ET will be headed by an
Environmental Team
Leader (ETL). He shall
ensure
the Contractor¡¦s compliance with the project¡¦s
environmental performance requirements during construction and undertake the post construction EM&A works and his responsibilities will
include field measurements,
sampling, analysis
of monitoring results,
reporting
and
auditing.
The ETL shall be approved by the SOR
and
the Director of Environmental
Protection (DEP) and shall be competent and shall have at least 7
years relevant
environmental monitoring and audit experience
on projects of a similar scale and nature.
1.5.1.5 The ET will comprise suitably qualified support staff to carrying out the EM&A
programme. The ET shall be independent and shall not be in any way connected
to
the Contractor¡¦s company.
Due to the specialist nature of some of the EM&A works required for this project,
the ET should comprise professionals proficient to undertake the tasks involved. Thus, the ET should include personnel experienced
in
noise, dust and water quality monitoring and mitigation, supervision of waste
management,
compensatory tree planting, coral relocation and dolphin monitoring
and
supervision.
1.5.1.6 Accordingly, a qualified dolphin specialist(s), together with a suitably experienced team of dolphin spotters, and a coral specialist, to the satisfaction of AFCD, will be required as part of
the ET to undertake the dolphin abundance monitoring, implement the dolphin exclusion zones and undertake the coral relocation process.
In addition,
a Registered Landscape Architect, as defined by the Landscape Architect¡¦s Registration Board, will be required on the ET to monitor and audit
the landscaping installation works and assist in the audit of the ecological transplantation and restoration works.
1.5.1.7 The overall duties of ETL and the team are as follows:
- Sampling, analysis
and
statistical evaluation of
monitoring parameters with
reference
to
the
EIA
study recommendations and requirements
in respect of noise, dust and water quality.
- Environmental site surveillance
- Audit of
compliance with environmental protection and pollution
prevention and control regulations.
- Monitor the implementation of environmental mitigation measures.
- Monitor compliance with the
environmental
protection
clauses/specifications in the Contract.
- Review construction programme
and comment as necessary.
- Review construction methodology and comment as necessary.
- Complaint
investigation, evaluation and
identification of
corrective measures.
- Audit of
the EMS and recommend and implement any
changes as
appropriate.
- Liaison
with the Independent
Environmental
Checker
(IEC) on
all environmental performance matters.
-
Advice to the
Contractor on environmental improvement, awareness, enhancement matter, etc.,
on site.
- Timely submission of the designated EM&A reports to the SOR, the IEC, the DEP, the AFCD and the AMO as appropriate.
1.5.1.8 In addition to the ETL and ET, an Independent Environmental
Checker (IEC) shall be employed to advise the SOR on environmental
issues related to the project.
The role of the IEC shall be independent
from
the management
of
construction
works, but the IEC shall be empowered to audit the environmental performance of
the construction activities and operational mitigation. The IEC shall have project management experience in addition to the requirements of the ET specified above and the appointment of the IEC will be subject to the approval
of the SOR and the
DEP. The IEC may require specialist support staff in order to properly carry out
his
duties, which shall include the following:
-
Review and audit all
aspects of the EM&A programme.
-
Validate and confirm
the accuracy of monitoring results, monitoring equipment, monitoring locations,
monitoring procedures and locations of sensitive receivers.
-
Carry out
random sample check and
audit on monitoring data and sampling procedures, etc.
-
Conduct random site
inspection.
-
Audit the EIA
recommendations and requirements against the status of implementation of
environmental protection measures on site.
-
Review the
effectiveness of environmental mitigation measures and project environmental
performance.
-
Audit the
Contractor¡¦s construction methodology and agree the least impact alternative in
consultation with the ET and the Contractor.
-
Check complaint cases
and the effectiveness of corrective measures.
-
Review EM&A
report submitted by the ET.
-
Feedback audit
results to ET by signing off relevant EM&A proformas.
1.5.1.9 An
organisation
chart
showing
the
lines
of
communication
between
the
key
parties with respect to the EM&A works is provided on Figure 1.2.
Both the ET
and IEC shall be retained for the duration of the EM&A works which will span both the construction phase and one year into the operational phase of the project.
The operational EM&A works will be the responsibility of the Contractor and will be undertaken in parallel to the maintenance period after the completion of
construction.
1.5.1.10 Notwithstanding the above, given that the TM-CLKL, HKBCF and HKLR will be
constructed concurrently, an
Environmental Protection Office (ENPO)
or equivalent to oversee the cumulative construction projects in North Lantau area
will be established
by the Project
Proponent.
The responsibility of the ENPO would be similar to that of
the IEC but should also include:
-
coordination of the monitoring and auditing works for all the on-going projects in
the area in order to identify possible sources/causes of exceedances
and recommend suitable remedial actions where appropriate;
-
identify and assess
cumulative impacts including possible sources/causes of exceedance
and recommending suitable remedial actions;
-
undertake liaison
with the mainland project teams counterparts to identify and assess any
cross-boundary cumulative impacts; and
-
coordinate the
assessment and response to complaints/enquires from locals, green groups,
district councils or the public at large.
1.5.1.11 The exact responsibilities and organisation of
the ENPO will be defined during the detailed design stage.
1.6.1.1 To clarify the terminology for impact monitoring and audit, key definitions are
specified below and are used throughout this Manual.
1.6.1.2 Monitoring refers to the systematic collection of data through a series of repetitive
measurements. The stages of monitoring are defined in this document as follows:
a) Baseline
Monitoring refers
to the measurement
of parameters, such as
noise and air quality impact parameters, during a representative
pre-project period for the purpose of
determining the nature and ranges of natural
variation and to establish, where appropriate, the nature of change.
b) Impact Monitoring involves the measurement of environmental impact parameters, such as noise and air quality, during Project construction
and implementation so as
to detect changes in these parameters which
can
be attributed to the Project.
1.6.1.3 Audit is a term that infers the verification of a practice and certification of data.
The types of audit are defined below:
a) Compliance audit is defined as follows:
-
the process of verification that all or selected parameters measured by
a noise or air quality impact monitoring programme or levels of
an operation
are
in compliance with
regulatory requirements and internal policies and standards; and
-
the determination of
the degree and scope of
any
necessary remediation in
the event of
exceedance
of compliance.
b) Post Project
Audit is carried
out
after
the
implementation and commissioning of a Project.
1.6.1.4 For the purpose of noise, air and water quality impact monitoring and audit, the
Action and Limit Levels are defined as follows:
a)
The Action Level is
the level defined in which there is an indication of a deteriorating ambient level for
which a typical response could be
an increase in the monitoring frequency.
b)
The Limit Level is the level beyond the appropriate remedial pollution control ordinances, noise and
air quality impact objectives or Hong Kong Planning Standards and Guidelines
established by the EPD for a particular project, such that the
works should not
proceed without appropriate remedial action, including a
critical review of plant and work methods.
2.1.1.1 Further to the recommendations of the Option Assessment and subsequent alignment developm