TABLE OF CONTENTS                                              

Page

EXECUTIVE SUMMARY  1

1       introduction  5

1.1     Background  5

1.2     Scope of Report 5

1.3     Project Organization  6

1.4     Summary of Construction Works  7

2       Summary of EM&A Programme Requirements  8

2.1     Monitoring Parameters  8

2.2     Environmental Quality Performance (Action/Limit Levels) 9

2.3     Environmental Mitigation Measures  9

3       MONITORING Results  10

3.1     Air Quality Monitoring  10

3.2     Noise Monitoring  26

3.3     Water Quality Monitoring  27

3.4     Dolphin Monitoring  45

3.5     Environmental Site Inspection and Audit 46

4       Advice on the Solid and Liquid Waste Management Status  49

4.1     Summary of Solid and Liquid Waste Management 49

5       Implementation Status of Environmental Mitigation Measures  50

5.1     Implementation Status of Environmental Mitigation Measures  50

6       Summary of Exceedances of the Environmental Quality Performance Limit  51

6.1     Summary of Exceedances of the Environmental Quality Performance Limit 51

7       Summary of Complaints, Notification of Summons and Successful Prosecutions  52

7.1     Summary of Environmental Compliants, Notification of Summons and Successful Prosecutions  52

8       Comments, recommendations and Conclusions  56

8.1     Comments on mitigation measures  56

8.2     Recommendations on EM&A Programme  57

8.3     Conclusions  58

 

 

 

 

                                                                                                                     


 

List of Tables

 

Table 1.1         Contact Information of Key Personnel

Table 3.1         Summary of Number of Monitoring Events for 1-hr & 24-hr TSP Concentration

Table 3.2         Summary of Number of Exceedances for 1-hr & 24-hr TSP Monitoring

Table 3.3        Summary of Number of Monitoring Events for Impact Noise

Table 3.4        Summary of Number of Monitoring Exceedances for Impact Noise

Table 3.5        Summary of Water Quality Exceedances in Dec 13- Feb 14

Table 3.6        Summary of Key Dolphin Survey Findings in Dec 13- Feb 14

Table 3.7        Summary of STG and ANI encounter rates  in Dec 13- Feb 14

 

Figures

 

Figure 1         General Project Layout Plan

Figure 2         Impact Air Quality and Noise Monitoring Stations and Wind Station

Figure 3         Impact Water Quality Monitoring Stations

Figure 4         Impact Dolphin Monitoring Line Transect Layout Map

Figure 5         Environmental Complaint Handling Procedures


List of Appendices

 

Appendix A       Project Organization for Environmental Works

Appendix B       Three Month Rolling Construction Programmes

Appendix C       Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D      Summary of Action and Limit Levels

Appendix E       Graphical Presentation of Impact Air Quality Monitoring Results

Appendix F       Graphical Presentation of Impact Daytime Construction Noise Monitoring Results

Appendix G      Graphical Presentation of Impact Water Quality Monitoring Results

Appendix H       Impact Dolphin Monitoring Survey Findings and Analysis

Appendix I        Quarterly Summary of Waste Flow Table

Appendix J      Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

Appendix K       Event Action Plan

Appendix L        Incident Report on Action Level or Limit Level Non-compliance for Impact Dolphin Monitoring

 


EXECUTIVE SUMMARY

Contract No. HY/2010/02 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Reclamation Work (here below, known as “the Project”) mainly comprises reclamation at the northeast  of  the  Hong  Kong  International  Airport  of  an  area  of  about  130-hectare  for  the construction of an artificial island for the development of the Hong Kong Boundary Crossing Facilities (HKBCF), and about 19-hectare for the southern landfall of the Tuen Mun - Chek Lap Kok Link (TMCLKL). It is a designated project and is governed by the current permits for the Project, i.e. the amended Environmental Permits (EPs) issued on 06 August 2013 (EP-353/2009/G) and 28 January 2014 (EP-354/2009/B) (for TMCLKL Southern Landfall Reclamation only).

Ove Arup & Partners Hong Kong Limited (Arup) was appointed by Highways Department (HyD) as the consultants for the design and construction assignment for the Project’s reclamation works (i.e. the Engineer for the Project).

China Harbour Engineering Company Limited (CHEC) was awarded by HyD as the Contractor to undertake the construction work of the Project.

ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

AECOM Asia Co. Ltd. (AECOM) was appointed by CHEC to undertake the role of Environmental Team for the Project for carrying out the environmental monitoring and audit (EM&A) works.

The construction phase of the Project under the EPs was commenced on 12 March 2012 and will be tentatively completed by early Year 2016. The EM&A programme, including air quality, noise, water quality and dolphin monitoring and environmental site inspections, was commenced on 12 March 2012.

This report documents the findings of EM&A works conducted in the period between 1 December 2013 and 28 February 2014. As informed by the Contractor, major activities in the reporting quarter were:-

Marine-based Works

-              Cellular structure installation

-              Connecting arc cell installation

-              Laying geo-textile

-              Sand blanket laying

-              Sand filling

-              Maintenance of silt curtain & silt screen at sea water intake of HKIA

-              Stone column installation

-              Band drain installation

-              Backfill cellular structure

-              Geotechnical Instrumentation works

-              Construction of temporary seawall

-              Ground investigation

-              Surcharge laying

-              Precast Yard setup

-              Seawall blocks for temporary construction

-              Construction of temporary assess from Portion D to Portion A

-              Construction of temporary pier at Portion A

-              Sand Drain

-              Vibro-compaction on surcharge

-              Rubble mound seawall construction

 

Land-based Works

-              Maintenance works of Site Office at Works Area WA2

-              Maintenance works of Public Works Regional Laboratory at Works Area WA3

-              Geo-textile fabrication at Works Area WA2

-              Installed sand bag at Works Area WA2

-              Silt curtain fabrication at Works Area WA4

-              Maintenance of Temporary Marine Access at Works Area WA2

 


A summary of monitoring and audit activities conducted in the reporting quarter is listed below:

24-hour Total Suspended Particulates (TSP) monitoring

1-hour TSP monitoring

 15 sessions

 15 sessions

Noise monitoring

 12 sessions

Impact water quality monitoring

39 sessions

Impact dolphin monitoring

  6 surveys

Joint Environmental site inspection

13 sessions

 

Breaches of Action and Limit Levels for Air Quality

 

All 1-Hour TSP results were below the Action and Limit Level in the reporting quarter. Six (6) 24-hour TSP results recorded among AMS2, AMS3A and AMS7 exceeded the Action Level and two (2) 24-hour TSP results recorded at AMS3A exceeded the Limit Level at in the reporting quarter. Investigation results show that the exceedances were not related to Project.

 

Breaches of Action and Limit Levels for Noise

 

For construction noise, no exceedance was recorded at all monitoring stations in the reporting quarter.

Breaches of Action and Limit Levels for Water Quality

Ten (10) Action Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter. Three (3) Limit Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter.

 

Investigation result shows that the Action Level Exceedance recorded at SR5 and Limit Level Exceedance recorded at  IS10 on 18 Dec 13 were related to Project.  Investigation result shows that other water quality exceedances were unlikely to be project-related.

 

Breaches of Action and Limit Levels for Impact Dolphin Monitoring

Two (2) Action Level exceedances were recorded for Chinese White Dolphin monitoring in the reporting quarter.

Triggering of Event and Action Plan for Impact Dolphin Monitoring

Event and Action Plan for Impact Dolphin Monitoring was triggered. For the detail of investigation, please refer to appendix L.

Implementation Status and Review of Environmental Mitigation Measures

Most recommended mitigation measures, as included in the EM&A programme, were implemented properly in the reporting quarter.

The recommended environmental mitigation measures effectively minimized the potential environmental impacts from the Project. The EM&A programme effectively monitored the environmental impacts from the construction activities and ensured the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.

Moreover, regular review and checking on the construction methodologies, working processes and plants were carried out to ensure environmental impacts were kept minimal and recommended environmental mitigation measures were implemented effectively. 


Complaint, Notification of Summons and Successful Prosecution

 

As informed by the Contractor on 5 Dec 13, there was one (1) noise complain related to a barge moving through the southern channel of HyD’s construction site after 23:00 on 8.11.2013. Site daily for barges was requested from the Contractor. Referring to the site daily provided by the Contractor, there was no barge operated after 18:25 on 08 Nov 13. The complaint is therefore considered unlikely to be related to the construction works.

As informed by the Contractor on 12 Dec 13. A complaint involves the leakage of sand from barges causing water discoloration at sea near Tuen Mun Pierhead Garden and sand material without properly covered was blown to the inside of the residential area which caused disturbance to residence. With refer to available information provided and monitoring data recorded on 09 Dec 13, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract

As informed by the Contractor on 6 Jan 14. A complaint involves barges loaded with sand material without properly covered was blown to the inside of the residential area of Tuen Mun Pierhead Garden which caused disturbance to residence. With refer to available information provided, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract.

EPD referred a complaint from complainant who advised that blackish mud was found along the edge of the construction site of Hong Kong-Zhuhai-Macao Bridge Hong Kong Project near the airport in the morning of 18 January 2014. Therefore in accordance with the investigation results, the complaint is therefore considered as not related to contract HY/2010/02.

No notification of summons and successful prosecution was received in the reporting period.

 

1             introduction

1.1          Background

1.1.1       Contract No. HY/2010/02 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Reclamation Work (here below, known as “the Project”) mainly comprises seawall construction and reclamation at the northeast  of  the  Hong  Kong  International  Airport  of  an  area  of  about  130-hectare  for  the construction of an artificial island for the development of the Hong Kong Boundary Crossing Facilities (HKBCF), and about 19-hectare for the southern landfall of the Tuen Mun - Chek Lap Kok Link (TMCLKL).

1.1.2       The  environmental  impact  assessment  (EIA)  reports  (Hong  Kong    Zhuhai    Macao  Bridge Hong Kong Boundary Crossing Facilities – EIA Report (Register No. AEIAR-145/2009) (HKBCFEIA) and Tuen Mun – Chek Lap Kok Link – EIA Report (Register No. AEIAR-146/2009) (TMCLKLEIA), and their environmental monitoring and audit (EM&A) Manuals (original EM&A Manuals), for the Project were approved by Environmental Protection Department (EPD) in October 2009. 

1.1.3       EPD  subsequently  issued  the  Environmental  Permit  (EP) for HKBCF in November 2009 (EP-353/2009) and the Variation of Environmental Permit (VEP) in June 2010 (EP-353/2009/A),  November  2010  (EP-353/2009/B), November  2011  (EP-353/2009/C), March 2012 (EP-353/2009/D), October 2012 (EP-353/2009/E), April 2013 (EP-353/2009/F) and August 2013 (EP-353/2009/G). Similarly, EPD issued the Environmental Permit (EP) for TMCLKL in November 2009 (EP-354/2009) and the Variation of Environmental Permit (VEP) in December 2010 (EP-354/2009/A) and January 2014 (EP-354/2009/B).

1.1.4       The Project is a designated project and is governed by the current permits for the Project, i.e. the amended EPs issued on 6 August 2013 (EP-353/2009/G) and 28 January 2014 (EP-354/2009/B) (for TMCLKL Southern Landfall Reclamation only).

1.1.5       A Project Specific EM&A Manual, which included all project-relation contents from the original EM&A Manuals for the Project, was issued in May 2012.

1.1.6       Ove Arup & Partners Hong Kong Limited (Arup) was appointed by Highways Department (HyD) as the consultants for the design and construction assignment for the Project’s reclamation works (i.e. the Engineer for the Project).

1.1.7       China Harbour Engineering Company Limited (CHEC) was awarded by HyD as the Contractor to undertake the construction work of the Project.

1.1.8       ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

1.1.9       AECOM Asia Co. Ltd. (AECOM) was appointed by CHEC to undertake the role of Environmental Team for the Project for carrying out the EM&A works.

1.1.10    The construction phase of the Project under the EPs was commenced on 12 March 2012 and will be tentatively completed by early Year 2016.

1.1.11    According to the Project Specific EM&A Manual, there is a need of an EM&A programme including air quality, noise, water quality and dolphin monitoring and environmental site inspections. The EM&A programme of the Project commenced on 12 March 2012.

1.2          Scope of Report

1.2.1       This is the eighth quarterly EM&A Report under the Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Reclamation Works. This report presents a summary of the environmental monitoring and audit works, list of activities and mitigation measures proposed by the ET for the Project from 1 December 2013 and 28 February 2014.


1.3          Project Organization

1.3.1       The project organization structure is shown in Appendix A. The key personnel contact names and numbers are summarized in Table 1.1.

  Table 1.1          Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

Engineer’s Representative (ER)

(Ove Arup & Partners Hong Kong Limited)

Chief Resident Engineer

Roger Marechal

2528 3031

2668 3970

IEC / ENPO

 (ENVIRON Hong Kong Limited)

Independent Environmental Checker

Raymond Dai

3465 2888

3548 6988

Environmental Project Office Leader

Y.H. Hui

3465 2868

3465 2899

Contractor

 

(China Harbour Engineering Company Limited)

General Manager (S&E)

Daniel Leung

3157 1086

2578 0413

Environmental Officer

Richard Ng

36932253

2578 0413

24-hour Hotline

Alan C.C. Yeung

9448 0325

--

ET

(AECOM Asia Company Limited)

ET Leader

Echo Leong

3922 9280

   2317 7609

 


1.4          Summary of Construction Works

1.4.1       The construction phase of the Project under the EP commenced on 12 March 2012.

1.4.2       As informed by the Contractor, details of the major works carried out in the reporting quarter are listed below:-

Marine-based Works

-              Cellular structure installation

-              Connecting arc cell installation

-              Laying geo-textile

-              Sand blanket laying

-              Sand filling

-              Maintenance of silt curtain & silt screen at sea water intake of HKIA

-              Stone column installation

-              Band drain installation

-              Backfill cellular structure

-              Geotechnical Instrumentation works

-              Construction of temporary seawall

-              Ground investigation

-              Surcharge laying

-              Precast Yard setup

-              Seawall blocks for temporary construction

-              Construction of temporary assess from Portion D to Portion A

-              Construction of temporary pier at Portion A

-              Sand Drain

-              Vibro-compaction on surcharge

-              Rubble mound seawall construction

 

Land-based Works

-              Maintenance works of Site Office at Works Area WA2

-              Maintenance works of Public Works Regional Laboratory at Works Area WA3

-              Geo-textile fabrication at Works Area WA2

-              Installed sand bag at Works Area WA2

-              Silt curtain fabrication at Works Area WA4

-              Maintenance of Temporary Marine Access at Works Area WA2

 

1.4.3       The 3-month rolling construction programme of the Project is shown in Appendix B.

1.4.4       The general layout plan of the Project site showing the detailed works areas is shown in Figure 1.

1.4.5       The environmental mitigation measures implementation schedule are presented in Appendix C.

 


2             Summary of EM&A Programme Requirements

2.1          Monitoring Parameters

2.1.1       The Project Specific EM&A Manual designated 4 air quality monitoring stations, 2 noise monitoring stations, 21 water monitoring stations (9 Impact Stations, 7 Sensitive Receiver Stations and 5 Control/Far Field Stations) to monitor environmental impacts on air quality, noise and water quality respectively. Pre-set and fixed transect line vessel based dolphin survey was required in two AFCD designated areas (Northeast and Northwest Lantau survey areas). The impact dolphin monitoring at each survey area should be conducted twice per month.

2.1.2       For impact air quality monitoring, monitoring locations AMS2 (Tung Chung Development Pier) and AMS7 (Hong Kong SkyCity Marriott Hotel) were set up at the proposed locations in accordance with Project Specific EM&A Manual. The conditional omission of Monitoring Station AMS6 was effective since 19 November 2012. For monitoring location AMS3 (Ho Yu College), as proposed in the Project Specific EM&A Manual, approval for carrying out impact monitoring could not be obtained from the principal of the school. Permission on setting up and carrying out impact monitoring works at nearby sensitive receivers, like Caribbean Coast and Coastal Skyline, was also sought.  However, approvals for carrying out impact monitoring works within their premises were not obtained. Impact air quality monitoring was conducted at site boundary of the site office area in Works Area WA2 (AMS3A) respectively. Same baseline and Action Level for air quality, as derived from the baseline monitoring data recorded at Ho Yu College, was adopted for this alternative air quality location.

2.1.3      For impact noise monitoring, monitoring locations NMS2 (Seaview Crescent Tower 1) was set up at the proposed locations in accordance with Project Specific EM&A Manual. However, for monitoring location NMS3 (Ho Yu College), as proposed in the Project Specific EM&A Manual, approval for carrying out impact monitoring could not be obtained from the principal of the school. Permission on setting up and carrying out impact monitoring works at nearby sensitive receivers, like Caribbean Coast and Coastal Skyline, was also sought.  However, approvals for carrying out impact monitoring works within their premises were not obtained. Impact noise monitoring was conducted at site boundary of the site office area in Works Area WA2 (NMS3A) respectively. Same baseline noise level, as derived from the baseline monitoring data recorded at Ho Yu College was adopted for this alternative noise monitoring location.

2.1.4      In accordance with the Project Specific EM&A Manual, twenty-one stations were designated for impact water quality monitoring. The nine Impact Stations (IS) were chosen on the basis of their proximity to the reclamation and thus the greatest potential for water quality impacts, the seven Sensitive Receiver Stations (SR) were chosen as they are close to the key sensitive receives and the five Control/ Far Field Stations (CS) were chosen to facilitate comparison of the water quality of the IS stations with less influence by the Project/ ambient water quality conditions.

2.1.5      Due to safety concern and topographical condition of the original locations of SR4 and SR10B, alternative impact water quality monitoring stations, naming as SR4(N) and SR10B(N), were adopted, which are situated in vicinity of the original impact water quality monitoring stations (SR4 and SR10B) and could be reachable. Same baseline and Action Level for water quality, as derived from the baseline monitoring data recorded, were adopted for these alternative impact water quality monitoring stations.

2.1.6      The monitoring locations used during the reporting quarter are depicted in Figures 2, 3 and 4   respectively.

2.1.7       The Project Specific EM&A Manual also required environmental site inspections for air quality, noise, water quality, chemical, waste management, marine ecology and landscape and visual impact.


2.2          Environmental Quality Performance (Action/Limit Levels)

2.2.1       The environmental quality performance limits (i.e. Action and/or Limit Levels) of air and water quality monitoring were derived from the baseline air and water quality monitoring results at the respective monitoring stations, while the environmental quality performance limits of noise monitoring were defined in the EM&A Manual.

2.2.2       The environmental quality performance limits of air quality, noise and water monitoring are given in Appendix D.

2.3          Environmental Mitigation Measures

2.3.1       Relevant environmental mitigation measures were stipulated in the Particular Specification and EPs (EP-353/2009/G and EP-354/2009/B) (for TMCLKL Southern Landfall Reclamation only) for the Contractor to adopt. A list of environmental mitigation measures and their implementation statuses are given in Appendix C.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3             MONITORING Results

3.1          Air Quality Monitoring

3.1.1       In accordance with the Project Specific EM&A Manual, impact 1-hour Total Suspended Particulates (TSP) monitoring was conducted for at least three times every 6 days, while impact 24-hour TSP monitoring was carried out for at least once every 6 days at the 4 monitoring stations (AMS2, AMS3A, AMS6 and AMS7).

3.1.2       The monitoring locations for impact air quality monitoring are depicted in Figure 2. However, for AMS6 (Dragonair/CNAC (Group) Building), permission on setting up and carrying out impact monitoring works was sought, however, access to the premise has not been granted yet on this report issuing date.

3.1.3       The weather was mostly sunny, with occasional cloudy and occasional rainy in the reporting quarter. The major dust source in the reporting quarter included construction activities from the Project, as well as nearby traffic emissions.

3.1.4       The number of monitoring events and exceedances recorded in each month of the reporting quarter are presented in Table 3.1 and Table 3.2 respectively.

Table 3.1          Summary of Number of Monitoring Events for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Location

No. of monitoring events

December 13

January 14

February 14

1-hr TSP

AMS2

15

15

15

AMS3A

15

15

15

AMS7

15

15

15

24-hr TSP

AMS2

5

5

5

AMS3A

5

5

5

AMS7

5

5

5

 

Table 3.2          Summary of Number of Exceedances for 1-hr & 24-hr TSP Monitoring

Monitoring Parameter

Location

Level of Exceedance

Level of Exceedance

December 13

January 14

February 14

1-hr TSP

AMS2

Action

0

0

0

Limit

0

0

0

AMS3A

Action

0

0

0

Limit

0

0

0

AMS7

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

24-hr TSP

AMS2

Action

0

0

0

Limit

0

0

0

AMS3A

Action

1

2

0

Limit

0

2

0

AMS7

Action

1

2

0

Limit

0

0

0

 

Total

2

6

0

 

3.1.5      All 1-Hour TSP results were below the Action and Limit Level in the reporting quarter. Six (6) 24-hour TSP results recorded among AMS2, AMS3A and AMS7 exceeded the Action Level and two (2) 24-hour TSP results recorded at AMS3A exceeded the Limit Level at in the reporting quarter. Investigation results show that the exceedances were not related to Project.


3.1.6      For the 24Hr TSP Action Level exceedance recorded at AMS3A, a result of 212mg/m3 was recorded on 11 Dec 13 (24-hr TSP).

3.1.6.1      According to information provided by the Contractor, land-based construction activity such as installation of sand bags, delivery of band drain material and stitching of Type 2 geotextile were being undertaken at Works Area WA2 during the monitoring period.

 

3.1.6.2      Functional checking on HVS at AMS3A was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.6.3      Photo records shows vehicle parking activities were observed inside an area at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA2. (Please also see photo and layout map attached for reference of site conditions (View A.))

 

3.1.6.4      As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 10 and 11 Dec 13 (as attached) east winds was prevailing during the monitoring period. Traffic activities at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA 2 may contribute to the measured dust levels at the monitoring station AMS3A.

 


Conditions of the construction sites near Works Area WA2:

 

View A: (Parking lot observed at nearby construction site which do not belongs to this Contract):

 

 

View B (Hard paved surface observed at Works Area WA2)

 

3.1.6.5      The 1-hr TSP values recorded at AMS3A on 11 Dec 13, which are within the monitoring period of the 24-hr TSP, were 84μg/m3, 88μg/m3 and 86μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.6.6      The measured 24-hr TSP values recorded at AMS2 and AMS7 (which are closer to the marine-based works areas) on the same monitoring date were 155μg/m3 and 165μg/m3 respectively, which are below the Action and Limit Levels.

 

3.1.6.7      The following dust mitigation measures have been implemented at Works Area WA2:

1.       Works Area WA2’s surface was hard-paved, compacted or hydro-seeded (Please refer to attached layout map and photo record (View B))

2.       Vehicle washing facility was provided at vehicle exit points,

3.       Measures for preventing fugitive dust emission are provided, e.g. canvas/tarpaulin covers.

 

3.1.6.8      The dust exceedance was therefore considered not to be due to the Project works.

 

3.1.6.9      The Contractor was recommended to continue implementing existing dust mitigation measures.

 

3.1.7      For the 24Hr TSP Action Level exceedance recorded at AMS7, a result of 186mg/m3 was recorded on 27 Dec 13 (24-hr TSP).

3.1.7.1      According to information provided by the Contractor during the monitoring period. Marine-based construction activity such as band drain, stone column installation and cellular structure installation was being undertaken at C2a, portion D and portion A.

 

3.1.7.2      Stone column was being installed at the seabed therefore it is considered that stone column installation at Portion D and Portion A is unlikely to contribute to the recorded 24hr-TSP exceedance.

 

3.1.7.3      Both band drain and cellular structure installation conducted at C2a, portion D and portion A are unlikely to contribute to the recorded 24hr-TSP exceedance due to no significant fugitive dust was expected to be generated in the process.

 

3.1.7.4      Excavators and generators were operated by ultra low sulphur diesel (ULSD) to minimize the possibility of air pollution have been implemented at throughout the construction site.

 

3.1.7.5     
Item8

Photo record below shows that the Contractor implemented dust control measures on works area of Portion A:

3.1.7.6      Functional checking on HVS at AMS7 was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS7. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.7.7      The 1-hr TSP values recorded at AMS7 on 27 Dec 13, which are within the monitoring days of the 24-hr TSP, were 89μg/m3, 89μg/m3 and 88μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.7.8      The measured 24-hr TSP values recorded at AMS2 and AMS3A on the same monitoring date were 93μg/m3 and 160 μg/m3 respectively, which are below the Action and Limit Levels.

 

3.1.7.9      On the other hand, according to observation made at the monitoring station AMS7, there was no non-project potential cause/activity at the surrounding of monitoring station AMS7 which might potentially contribute to the dust action level exceedance.

 

3.1.7.10    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 27 and 28 Dec 13 (as attached) southwest winds was prevailing during the monitoring period. Construction works carried out by this Contract is unlikely to cause dust exceedance at AMS7 under South-southwest prevailing wind direction.
The dust exceedance was therefore considered not to be due to the Project works.

 

3.1.7.11    The Contractor was recommended to continue implementing existing dust mitigation measures and the Contractor was reminded ensure to undertake watering at least 8 times per day on all exposed soil within the Project site and associated work areas throughout the construction phase.

3.1.8      For the 24Hr TSP Limit Level exceedance recorded at AMS3A, a result of 502mg/m3 was recorded on 07 Jan 14 (24-hr TSP). 

3.1.8.1      According to information provided by the Contractor, land-based construction activity such as stitching and transloading of Type 2 geotextile were being undertaken at Works Area WA2 during the monitoring period.

 

3.1.8.2      Functional checking on HVS at AMS3A was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.8.3      Photo records shows fugitive dust were generated by vehicle activities observed inside an area at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA2. (Please also see photo and layout map attached for reference of site conditions (View A.))

 

CIMG0748

View A (fugitive dust were observed at the parking lot of the nearby construction site which do not belongs to this Contract)

 

3.1.8.4      As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 06 and 07 Jan 14 (as attached) Southeast wind was prevailing during the monitoring period. Traffic activities at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA 2 may contribute to the measured dust levels at the monitoring station AMS3A.

 

3.1.8.5      The 1-hr TSP values recorded at AMS3A on 7 Jan 14, which are within the monitoring period of the 24-hr TSP, were 84μg/m3, 83μg/m3 and 83μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.8.6      The measured 24-hr TSP values recorded at AMS7 (which are closer to the marine-based works areas) on the same monitoring date was133μg/m3, which are below the Action and Limit Levels.

 

3.1.8.7      The measured 24-hr TSP values recorded at AMS3A on next monitoring date were 154μg/m3, which was below the Action and Limit Level.

 


3.1.8.8      The following dust mitigation measures have been implemented at Works Area WA2:

1.       Works Area WA2’s surface was hard-paved, compacted or hydro-seeded (Please refer to attached layout map and photo record (View B))

2.       Vehicle washing facility was provided at vehicle exit points,

3.       Measures for preventing fugitive dust emission are provided, e.g. canvas/tarpaulin covers.

 

3.1.8.9      The Contractor was recommended to continue implementing existing dust mitigation measures.

 

View B (Hard paved surface observed at Works Area WA2)

 

CIMG9167

 

 

The following figure is the General Layout of Works Area WA2

 


3.1.9      For the 24Hr TSP Action Level exceedance recorded at AMS2, a result of 185mg/m3 was recorded on 08 Jan 14 (24-hr TSP).

3.1.9.1      According to information provided by the Contractor during the monitoring period. Marine-based construction activity such as band drain, stone column installation and cellular structure installation was being undertaken at C2a, C2c, C1a, C1b, D, E1, E2, A and B.

 

3.1.9.2      Stone column was being installed at the seabed therefore it is considered that stone column installation at Portion E1, E2 and Portion B is unlikely to contribute to the recorded 24hr-TSP exceedance.

 

3.1.9.3      Both band drain or cellular structure installation conducted at C2a, C2b, C2c, C1a, C1b, E1, E2, A and B are unlikely to contribute to the recorded 24hr-TSP exceedance due to no significant fugitive dust was expected to be generated in the process.

 

3.1.9.4      Checking record of Jan 14 shows that plant engine is operated by ULSD.

 

3.1.9.5      With reference to the weekly joint site inspection records of 2, 9, 16, 22 and 29 of Jan 14, no dark smoke of was observed and this indicates that plant engines are properly maintained.

 

3.1.9.6      Excavators and generators were operated by ultra low sulphur diesel (ULSD) to minimize the possibility of air pollution have been implemented at throughout the construction site.

 

3.1.9.7      Functional checking on HVS at AMS2 was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS2. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.9.8      The 1-hr TSP values recorded at AMS2 on 7 Jan 14, were 84μg/m3, 83μg/m3 and 85μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.9.9      The measured 24-hr TSP values recorded at AMS7 (which is located closer to active works than AMS2) on 7 Jan 14 was 133μg/m3, which was below the Action and Limit Levels.

 

3.1.9.10    On the other hand, according to observation made at the monitoring station AMS2, there was no non-project potential cause/activity at the surrounding of monitoring station AMS2 which might potentially contribute to the dust action level exceedance.

 

3.1.9.11    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 7 and 8 Jan 14 (as attached),  East-southeast winds were prevailing during the monitoring period. Construction works carried out by this Contract are unlikely to cause dust exceedance at AMS2 under the abovementioned prevailing wind directions.

 

3.1.9.12    The dust exceedance was therefore considered not to be due to the Project works.

 

3.1.9.13    The Contractor was recommended to continue implementing existing dust mitigation measures and the Contractor was reminded ensure to undertake watering at least 8 times per day on all exposed soil within the Project site and associated work areas throughout the construction phase.

3.1.10    For the 24Hr TSP Action Level exceedance recorded at AMS3A, a result of 175mg/m3 was recorded on 18 Jan 14 (24-hr TSP).

3.1.10.1    According to information provided by the Contractor, land-based construction activities such as transloading land band equipment, accessories and installed sand bags were being undertaken at Works Area WA2 during the monitoring period.

 

3.1.10.2    Functional checking on HVS at AMS3A was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.10.3    Photo records shows vehicle parking activities were observed inside an area at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA2. (Please also see photo and layout map attached for reference of site conditions (View A.))

 

 

 

 

 

View A (parking lot observed at nearby construction site which do not belongs to this Contract)

CIMG2691

 

 

3.1.10.4    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 17 and 18 Jan 14 (as attached) South-southeast winds was prevailing during the monitoring period. Traffic activities at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA 2 may contribute to the measured dust levels at the monitoring station AMS3A.

 

3.1.10.5    The 1-hr TSP values recorded at AMS3A on 18 Jan 14, which are within the monitoring period of the 24-hr TSP, were 84μg/m3, 83μg/m3 and 85μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.10.6    The measured 24-hr TSP values recorded at AMS2 (which are closer to the marine-based works areas) on the same monitoring date were 124μg/m3, which were below the Action and Limit Levels.

 

3.1.10.7    The following dust mitigation measures have been implemented at Works Area WA2:

1.         Works Area WA2’s surface was hard-paved, compacted or hydro-seeded (Please refer to attached layout map and photo record (View B))

2.         Vehicle washing facility was provided at vehicle exit points,

3.         Measures for preventing fugitive dust emission are provided, e.g. canvas/tarpaulin covers.

 

 View B (Hard paved surface observed at Works Area WA2)

CIMG2672

 

 

3.1.10.8    The dust exceedance was therefore considered not to be related to the Project works.

 


3.1.11    For the 24Hr TSP Action Level exceedance recorded at AMS7, a result of 207mg/m3 was recorded on 18 Jan 14 (24-hr TSP).

3.1.11.1    According to information provided by the Contractor during the monitoring period. Marine-based construction activity such as band drain, stone column installation and cellular structure installation was being undertaken at all area except Portion D.

 

3.1.11.2   

Stone column was being installed at the seabed therefore it is considered that stone column installation at Portion C2a, Portion E2 and Portion B are unlikely to contribute to the recorded 24hr-TSP exceedance. For active works carried out on 18 Jan 14, please refer to the below layout map.

 

3.1.11.3    Both band drain or cellular structure installation which was conducted during the monitoring period are considered unlikely to contribute to the recorded 24hr-TSP exceedance due to no significant fugitive dust was expected to be generated in the process.

 

3.1.11.4    Excavators and generators were operated by ultra low sulphur diesel (ULSD) to minimize the possibility of air pollution have been implemented at throughout the construction site.

 

3.1.11.5    Checking record of Jan 14 shows that plant engine was operated by ULSD.

 

3.1.11.6    With reference to the weekly joint site inspection records of 2, 9, 16, 22 and 29 of Jan 14, no dark smoke of was observed and this indicates that plant engines are properly maintained. 

 

3.1.11.7    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 23 and 24 Jan 14, South-southeast winds was prevailing during the monitoring period. However, photo record attached shows that dust control measures was implemented by the Contractor.

 

 

 

 

 

 

 

 

Photo record showed that the Contractor implemented dust control measures on pelican barge loaded with rock/sand. The Contractor was reminded to continue to provide dust control measures on pelican barge loaded with rock/sand.

 

CIMG0856CIMG2361

 

Photo record showed that the Contractor implemented dust control measures such as wind-board installed on pelican barge. The Contractor was reminded to continue to provide such dust control measure.

 

Wind-board bWind-board a

 

 

3.1.11.8    Functional checking on HVS at AMS7 was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.11.9    The 1-hr TSP values recorded at AMS7 on 18 Jan 14, which are within the monitoring days of the 24-hr TSP, were 84μg/m3, 83μg/m3 and 83μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.11.10  The measured 24-hr TSP values recorded at AMS2 and AMS3A on the same monitoring date were 93μg/m3 and 160μg/m3 respectively, which are below the Action and Limit Levels.

 

3.1.11.11  On the other hand, according to observation made at the monitoring station AMS7, there was no non-project potential cause/activity at the surrounding of monitoring station AMS7 which might potentially contribute to the dust action level exceedance.

 

 

 

 

 

 

Photo shows the conditions of the surrounding near the monitoring station AMS7:

 

IMG-20130419-WA0022IMG-20130419-WA0021

IMG-20130419-WA0019IMG-20130419-WA0020

 

 

 

3.1.11.12  The dust exceedance was therefore considered not to be due to the Project works.

 


3.1.12    For the 24Hr TSP limit Level exceedance recorded at AMS3A, a result of 374mg/m3 was recorded on 24 Jan 14 (24-hr TSP).   

3.1.12.1    According to information provided by the Contractor, land-based construction activities such as transloading band drain material, sand bags and tidy up and clearance of site area were being undertaken at Works Area WA2 during the monitoring period.

 

3.1.12.2    Functional checking on HVS at AMS3A was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.12.3    Photo records shows vehicle parking activities were observed inside an area at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA2. (Please also see photo and layout map attached for reference of site conditions (View A.))

 

 

View A (parking lot observed at nearby construction site which do not belongs to this Contract)

CIMG2691

 

3.1.12.4    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 23 and 24 Jan 14 (as attached) Southeast winds was prevailing during the monitoring period. Traffic activities at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA 2 may contribute to the measured dust levels at the monitoring station AMS3A.

 

3.1.12.5    The 1-hr TSP values recorded at AMS3A on 24 Jan 14, which are within the monitoring period of the 24-hr TSP, were 84μg/m3, 82μg/m3 and 81μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.12.6    The measured 24-hr TSP values recorded at AMS2 and AMS7 (which are closer to the marine-based works areas) on the same monitoring date were 66μg/m3 and109μg/m3, which are below the Action and Limit Levels.

 

3.1.12.7    The measured 24-hr TSP value recorded at AMS3A on next monitoring date was 183μg/m3, which exceeded the Action Level (The dust exceedance was considered not to be due to the Project works after investigation).

 

3.1.12.8    The following dust mitigation measures have been implemented at Works Area WA2:

1.         Works Area WA2’s surface was hard-paved, compacted or hydro-seeded (Please refer to attached layout map and photo record (View B))

2.         Vehicle washing facility was provided at vehicle exit points,

3.         Measures for preventing fugitive dust emission are provided, e.g. canvas/tarpaulin covers.

 

View B (Hard paved surface observed at Works Area WA2)

CIMG2672

 

3.1.12.9    The dust exceedance was therefore considered not to be due to the Project works.


3.1.13    For the 24Hr TSP Action Level exceedance recorded at AMS3A, a result of 183mg/m3 was recorded on 28 Jan 14 (24-hr TSP). And the 24hr-TSP results received on 4 Feb 14.

3.1.13.1    According to information provided by the Contractor, land-based construction activity such removing batch/rolls of materials off site area was being undertaken at Works Area WA2 during the monitoring period.

 

3.1.13.2    Functional checking on HVS at AMS3A was done. Air flow of the HVS was checked and the flow was steady during the 24-hr TSP sampling at AMS3A. The filter paper was re-weighted by the assigned HOKLAS laboratory and the result was reconfirmed.

 

3.1.13.3    Photo records shows vehicle parking activities were observed inside an area at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA2. (Please also see photo and layout map attached for reference of site conditions (View A.))

 

View A (parking lot observed at nearby construction site which do not belongs to this Contract)

CIMG2691

3.1.13.4    As refer to the wind data collected at wind station at Works Area WA2 during the monitoring period on 28 and 29 Jan 14 (as attached) South-southeast winds was prevailing during the monitoring period. Traffic activities at construction sites of nearby private development project which are close to the monitoring station AMS3A but beyond the site boundary of Works Area WA 2 may contribute to the measured dust levels at the monitoring station AMS3A.

 

3.1.13.5    The 1-hr TSP values recorded at AMS3A on 29 Jan 14, which are within the monitoring period of the 1-hr TSP, were 83μg/m3, 84μg/m3 and 82μg/m3 respectively. All measured values are well below the Action and Limit Levels.

 

3.1.13.6    The measured 24-hr TSP values recorded at AMS2 and AMS7 (which are closer to the marine-based works areas) on the same monitoring date were 106μg/m3 and129μg/m3, which are below the Action and Limit Levels.

 

3.1.13.7    The measured 24-hr TSP values recorded at AMS3A on next monitoring date were 79μg/m3, which did not exceed the Action or Limit Level.

 

3.1.13.8    The following dust mitigation measures have been implemented at Works Area WA2:

1.           Works Area WA2’s surface was hard-paved, compacted or hydro-seeded (Please refer to attached layout map and photo record (View B))

2.           Vehicle washing facility was provided at vehicle exit points,

3.           Measures for preventing fugitive dust emission are provided, e.g. canvas/tarpaulin covers.

 

View B (Hard paved surface observed at Works Area WA2)

CIMG2672

 

3.1.13.9    The dust exceedance was therefore considered not to be due to the Project works.

 

3.1.14    The graphical plots of the trends of the monitoring results are provided in Appendix E. No specific trend of the monitoring results or existence of persistent pollution source was noted.

3.1.15    The event action plan is annexed in Appendix L.

 


3.2       Noise Monitoring

3.2.1       Impact noise monitoring was conducted at the 2 monitoring stations (NMS2 and NMS3A) for at least once per week during 07:00 – 19:00 in the reporting quarter.

3.2.2       The monitoring locations used during the reporting quarter are depicted in Figure 2.

3.2.3      No Action or Limit Level Exceedance of construction noise was recorded in the reporting quarter.

3.2.4       Major noise sources during the noise monitoring included construction activities of the Project and nearby traffic noise.

3.2.5       The number of impact noise monitoring events and exceedances are summarized in Table 3.3 and Table 3.4 respectively

Table 3.3            Summary of Number of Monitoring Events for Impact Noise

Monitoring Parameter

Location

No. of monitoring events

December 13

January 14

February 14

NMS2

4

4

4

NMS3A

4

4

4

Table 3.4            Summary of Number of Monitoring Exceedances for Impact Noise

Monitoring Parameter

Location

Level of Exceedance

Level of Exceedance

December 13

January 14

February 14

NMS2

Action

0

0

0

Limit

0

0

0

NMS3A

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

 

3.2.6       The graphical plots of the trends of the monitoring results are provided in Appendix F. No specific trend of the monitoring results or existence of persistent pollution source was noted.

3.2.7      The event action plan is annexed in Appendix L.

 


3.3          Water Quality Monitoring

3.3.1       The monitoring locations used during the reporting quarter are depicted in Figure 3.

3.3.2       Ten (10) Action Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting Quarter. Three (3) Limit Level exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter.

Table 3.5          Summary of Water Quality Exceedances in Dec 13- Feb 14

Station

Exceedance Level

DO (S&M)

DO (Bottom)

Turbidity

SS

Total

Ebb

Flood

Ebb

Flood

Ebb

Flood

Ebb

Flood

Ebb

Flood

IS5

Action

0

0

0

0

0

0

0

(1)

10 Jan14

0

1

Limit

0

0

0

0

0

0

0

0

0

0

IS(Mf)6

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

IS7

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

IS8

Action

0

0

0

0

0

0

0

(1)

6 Jan14

0

1

Limit

0

0

0

0

0

0

0

(1)

20 Dec13

0

1

IS(Mf)9

Action

0

0

0

0

0

0

0

(1)

18 Dec13,

(2)

6, 15 Jan14

0

3

Limit

0

0

0

0

0

0

0

(1)

17 Jan14

0

1

IS10

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

(1)

18 Dec13

0

1

IS(Mf)11

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

IS(Mf)16

Action

0

0

0

0

0

0

0

(1)

21 Feb14

0

1

 Limit

0

0

0

0

0

0

0

0

0

0

IS17

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

SR3

Action

0

0

0

0

0

0

0

(1)

10 Jan14

0

1

Limit

0

0

0

0

0

0

0

0

0

0

SR4(N)

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

SR5

Action

0

0

0

0

0

0

0

(1)

18 Dec 13

0

1

Limit

0

0

0

0

0

0

0

0

0

0

SR6

Action

0

0

0

0

0

0

0

(1)

3 Jan14

0

1

Limit

0

0

0

0

0

0

0

0

0

0

SR7

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

SR10A

Action

0

0

0

0

0

0

0

(1)

6 Dec13

0

1

Limit

0

0

0

0

0

0

0

0

0

0

SR10B

(N)

Action

0

0

0

0

0

0

0

0

0

0

Limit

0

0

0

0

0

0

0

0

0

0

Total

Action

0

0

0

0

0

0

0

10

10

 

Limit

0

0

0

0

0

0

0

3

3

Note:        S: Surface;

   M: Mid-depth;

3.3.3      One (1) Action Level exceedance at measured Suspended Solids (mg/L) was recorded on 06 Dec 2013 at monitoring station SR10A at Mid-flood tide. For Action Level exceedances at measured Suspended Solids (mg/L), 28.2 mg/L was recorded at Monitoring Station SR10A.

3.3.3.1   For locations and type of active works carried out on 6 Dec 13, please refer to the above layout map.

3.3.3.2   IS(Mf)11 and IS10 are located downstream and closer to the active works than monitoring station SR10A during flood tide. Depth Averaged Suspended Solids (SS) values (in mg/L) recorded during  flood tide on the same day at IS(Mf)11 and IS10 were below the Action and Limit Level which indicates project work is unlikely to contribute to the action level exceedance recorded at SR10A.

3.3.3.3   The monitoring location of monitoring station SR10A are considered upstream and remote to the active works of this project during flood tide. Therefore it was unlikely that the exceedance recorded at SR10A during flood tide was due to active construction activities of this project.

3.3.3.4   The depth averaged SS (in mg/L) and depth averaged turbidity (in NTU) at CS(Mf)5 is 12mg/L and 18.7NTU respectively which is below the action and limit levels. This indicates that water quality at area closer to active works was not adversely affected.

3.3.3.5   The exceedance was likely due to local effects in the vicinity of SR10A.

3.3.3.6   Nevertheless, the Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.3.7   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.


3.3.4      One (1) action level exceedances at measured Suspended Solids (mg/L) was recorded on 18 Dec 2013 at monitoring station SR5 at Mid-flood tide and one (1) limit level exceedance at measured Suspended Solids (mg/L) was recorded on 18 Dec 2013 at monitoring station IS10 at Mid-flood tide. For Action Level exceedance at measured Suspended Solids (mg/L), 33.2mg/L were recorded at Monitoring Station SR5. For limit level exceedance at measured Suspended Solids (mg/L), 34.9 mg/L was recorded at Monitoring Station IS10. 

3.3.4.1   For locations and type of active works carried out on 18 Dec 13, please refer to the above layout map.

3.3.4.2   Exceedances recorded at SR5 and IS10 are likely due to marine based construction activities of the Project because:

3.3.4.3   With refer to monitoring record, appearance of water was not clear at IS10 and SR5 when compared with the appearance of water at IS(Mf)11 and IS17 during monitoring during Mid-flood tide on 18 Dec 13. This indicates the source of exceedance may not due to works activities at portion E1and E2 which is directly upstream of IS(Mf)11 and IS17. The relatively turbid water observed at IS10 and SR5 may due to activities at Portion C2a during flood tide.

3.3.4.4   As informed by the Contractor, active works like stone column and cellular structure installation were carried out at Portion C2a, E1, E2 and B on18 and 20 Dec 13. With review of the information provided by the Contactor, active works like stone column and cellular structure installation were both carried out at Portion C2a, E1, E2 and B on 16, 18 and 20 Dec 13 at almost the same location but no exceedance was recorded at monitoring station SR5, IS10 and IS(Mf)9 on 16 and 20 Dec 13 during mid flood tide. This indicates stone column and cellular structure installation were unlikely to cause the exceedance at monitoring station SR5, IS10 and IS(Mf)9 on 18 Dec 13.

3.3.4.5   With refer to the silt curtain condition on 18 Dec 13, defects of the perimeter silt curtain was observed at northwest of the construction site.

 

3.3.4.6   As such, the exceedances recorded at IS10 and SR5 were considered as project related.

3.3.4.7   For action required under the action plan, please refer to Appendix L - Event Action Plan

3.3.4.8   Action taken under the action plan

1          Water sample was taken on site and was delivered to the laboratory and the SS was not measured in-situ, as a result it is not applicable to “Repeat in situ measurement to confirm findings”

2          With refer to the joint site inspection audit conducted on 19 Dec 13, sources of impact is likely due to the turbine activities and/or movement of vessel at shallow water (at near the entrance at southwestern of the Construction site and/or when vessel’s propeller was turn on at shallow water). The dispersion of turbid water from the inside of the perimeter silt curtain to the outside of the perimeter silt curtain is potentially due to defects of perimeter silt curtain at certain sections.

3          IEC, contractor, ER and EPD were informed on 3 January 13 through notification of exceedance via email;

4          Monitoring data was reviewed, plant, equipment and Contractor's working methods was checked during joint site inspection audit conducted on 19 Dec 13;

5          The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

6          As informed by the Contractor maintenance work for the defects of the northwest part of the perimeter silt curtain was conducted on 4 January 13.

7          Monitoring results show no recurrence of exceedance of SS at IS10 and SR5 on 20, 23 and 25 of Dec 2013.

 

3.3.4.9   The exceedances note at IS10 and SR5 on 18 Dec 13 were considered as project related. Although the silt curtain integrity checking record on 4 January 13 shows that the disconnected silt curtain observed on 18 Dec 13 at northwest of HKBCF were rectified, the effectiveness of such rectification will be closely monitored through impact water quality monitoring and inspected through regular site inspection audit. The Contractor was further reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.


3.3.5      One (1) action level exceedances at measured Suspended Solids (mg/L) was recorded on 18 Dec 2013 at monitoring station IS(Mf)9 at Mid-flood tide. For the Action Level exceedances at measured Suspended Solids (mg/L), 23.9 mg/L was recorded at Monitoring Station IS(Mf)9.

3.3.5.1   For locations and type of active works carried out on 18 Dec 13, please refer to the above layout map.

3.3.5.2   Exceedance recorded at IS(Mf)9 is unlikely due to marine based construction activities of the Project because:

3.3.5.3   With refer to the silt curtain condition on 18 Dec 13, no defects of the perimeter silt curtain was observed at south and southeast of the construction site.

3.3.5.4   The Depth averaged turbidity (in NTU) and depth averaged SS (in mg/L) of nearby monitoring station, such as IS7, IS8 and IS(Mf)16 were below the action and limit level, indicating the water quality at area nearby IS(Mf)9 was not adverse affected.

3.3.5.5   With referred to monitoring record, no turbid water or silt plume was observed when monitoring was conducted IS(Mf)9. (Please refer to the attached photo record for reference of sea condition)

3.3.5.6   As such, the exceedance recorded at IS(Mf)9 is considered to be non-project related.

3.3.5.7   The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.5.8   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.


3.3.6       One (1) Limit Level exceedance at measured Suspended Solids (mg/L) was recorded on 20 Dec 2013 at monitoring station IS8 at Mid-flood tide. For limit exceedance at measured Suspended Solids (mg/L), 44.1 mg/L was recorded at Monitoring Station IS8.

3.3.6.1    For locations and type of active works carried out on 20 Dec 13, please refer to the above layout map.

3.3.6.2   IS(Mf)9 and IS(Mf)16 are located closer to the active works than monitoring station IS8. Depth Average Suspended Solids (SS) values (in mg/L) recorded during the flood tide on the same day at IS(Mf)9 and IS(Mf)16 were below the Action and Limit Level which shows that the water quality closer to active works were not adversely affected. 

3.3.6.3   The monitoring location of monitoring station IS8 are considered located upstream to the active works of this project during flood tide. Therefore it was unlikely that the exceedances recorded at IS8 was due to active construction activities of this project.

3.3.6.4   When impact water quality monitoring was carried out during mid flood tide at monitoring location IS8 on 20 Dec 13, no defects of the perimeter silt curtain was observed and no silty plume were observed to flow from the inside to the outside of the site boundary.  (For reference, please see attached photo):

CIMG9918.JPG

3.3.6.5   Turbidity level (NTU) result recorded on 20 Dec 13 at IS8 during flood tide is 22.3 NTU which is below the Action and Limit Level, this indicates turbidity level was not adversely affected.

3.3.6.6   Nevertheless, the Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.6.7   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.

3.3.6.8   The exceedance was likely due to local effects in the vicinity of IS8.





3.3.7      One (1) Action Level exceedance at measured Suspended Solids (mg/L) was recorded on 03 Jan 2014 at monitoring station SR6 at Mid-flood tide. For Action Level exceedances at measured Suspended Solids (mg/L), 23.9 mg/L was recorded at Monitoring Station SR6.

3.3.7.1   For locations and type of active works carried out on 03 Jan 14, please refer to the above layout map.

3.3.7.2   When impact water quality monitoring was carried out during mid flood tide at monitoring location IS10, SR5 and SR6 on 3 Jan 14, no silty plume were observed to flow from the inside to the outside of  the nortwestern part of the perimeter silt curtain.

3.3.7.3   IS10, SR5 (located outside northwest part of the perimeter silt curtain) and IS(Mf)11 (located outside north part of the perimeter silt curtain) which are closer to the active works than monitoring station SR6. Depth Averaged Suspended Solids (SS) values (in mg/L) recorded during the flood tide on the same day at IS10, SR5 and IS(Mf)11 were below the Action and Limit Level which shows that the water quality closer to active works was not adversely affected. 

            CIMG1623.JPG

3.3.7.4   Turbidity level (NTU) results recorded on  03 Jan 14 at SR6, SR5, IS10 and IS(Mf)11 during flood tide are 20.8 NTU, 18.6 NTU, 17.8 NTU and 17.3 NTU which are below the Action and Limit Level, this indicates turbidity level of the area nearby was not adversely affected.

3.3.7.5   The exceedance was likely due to local effects in the vicinity of SR6.

 


3.3.8      Two (2) action level exceedances at measured Suspended Solids (mg/L) were recorded on 06 Jan 2014 at monitoring station IS(Mf)9 and at monitoring station IS8 at Mid-flood tide. For Action Level exceedance at measured Suspended Solids (mg/L), 24.4mg/L were recorded at Monitoring Station IS(Mf)9 and 25.4mg/L were recorded at Monitoring Station IS8. 

3.3.8.1   For works activities carried out on 06 Jan 14, please refer to the attached layout map.

3.3.8.2   The Depth averaged turbidity (in NTU) and depth averaged SS (in mg/L) of nearby monitoring station, such as IS7 and IS(Mf)16 were below the action and limit level, indicating the water quality at area nearby IS(Mf)9 and IS8 was not adverse affected.

3.3.8.3   The turbidity level (in NTU) at IS(Mf)9, IS8, IS7 and IS(Mf)16 were below the action and limit level and no silt plume was observed when monitoring was conducted IS(Mf)9 and IS8, this indicates that the turbidity level (in NTU) at IS(Mf)9, IS8, IS7 and IS(Mf)16 were not adversely affected.

CIMG2952.JPG

3.3.8.4   Also, with refer to the silt curtain condition on 06 Jan 14, no defects of the perimeter silt curtain was observed at south and southeast of the construction site.

3.3.8.5   The exceedances were likely due to local effects in the vicinity of IS(Mf)9 and IS8.

3.3.8.6   As such, the exceedances recorded at IS(Mf)9 and IS8 are considered non-project related.

3.3.8.7   The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.8.8   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.

 


3.3.9   Two (2) action level exceedances at measured Suspended Solids (mg/L) were recorded on 10 Jan 2014 at monitoring station IS5 and at monitoring station SR3 at Mid-flood tide. For Action Level exceedances at measured Suspended Solids (mg/L), 25.1 mg/L was recorded at Monitoring Station IS5 and 24.8 mg/L was recorded at Monitoring Station SR3.

3.3.9.1   For site activities carried out on 10 Jan 14, please refer to the below layout map.

 

3.3.9.2   Suspended solids values recorded at Impact Station IS(Mf) 6, IS(Mf)9 and IS7 located downstream and closer to active wor k than SR3 and IS5 were below the Action and Limit Level during the same tide on the same day. As such, active works is unlikely to cause exceedance to IS5 and SR3.

3.3.9.3   Same type of works was carried out at the same locations on 8, 10 and 13 Jan 14 but Suspended Solids values recorded at SR3 and IS5 on 8 and 13 Jan 14 are all below the Action and Limit Level during the same tide on the these days. As such, active works conducted on 10 Jan 14 are unlikely to cause exceedance to IS5 and SR3.

3.3.9.4   Turbidity level recorded at IS7, IS(Mf)6 and IS(Mf)9 were below the action and limit level. This indicated that area closer to active works was not adversely affected.

3.3.9.5   The exceedances were likely due to local effects in the vicinity of IS5 and SR3.

3.3.9.6   The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.9.7   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.

 

 

 

3.3.10    One (1) Action Level exceedance at measured Suspended Solids (mg/L) was recorded on 15 Jan 2014 at monitoring station IS(Mf)9 at Mid-flood tide. For the Action Exceedance at measured Suspended Solids (mg/L), 26.6 mg/L was recorded at Monitoring Station IS(Mf)9.

3.3.10.1 The Depth averaged turbidity (in NTU) and depth averaged SS (in mg/L) of nearby monitoring station, such as IS8, IS7 and IS(Mf)16 were below the action and limit level, indicating the water quality at area nearby IS(Mf)9 was not adverse affected.

3.3.10.2 Since the turbidity level (in NTU) at IS(Mf)9, IS8, IS7 and IS(Mf)16 were below the action and limit level and no silt plume was observed when monitoring was conducted IS(Mf)9, this indicates that the turbidity level (in NTU) at IS(Mf)9, IS8, IS7 and IS(Mf)16 were not adversely affected. Please refer to the photo record attached for sea condition recorded on 15 Jan 14 at southeast vessel entrance of the perimeter silt curtain (near monitoring station IS(Mf)9).

            CIMG2952.JPG

 

3.3.10.3 Also, with refer to the silt curtain condition on 15 Jan 14, no defects of the perimeter silt curtain was observed at south and southeast of the construction site.

3.3.10.4 The exceedance was likely due to local effects in the vicinity of IS(Mf)9.

3.3.10.5 As such, the action level exceedance recorded at IS(Mf)9 is considered non-project related.

3.3.10.6 The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.10.7 The Contractor was reminded that, with reference to EM&A manual Clause 9.1.1,  the vessel access opening of the perimeter silt curtain would be formed by two piece of silt-curtain with overlapping length of 150m minimum and a separation distance of about 50m.


3.3.11    One (1) Limit Level exceedance at measured Suspended Solids (mg/L) was recorded on 17 Jan 2014 at monitoring station IS(Mf)9 at Mid-flood tide. For action exceedance at measured Suspended Solids (mg/L), 36.8 mg/L was recorded at Monitoring Station IS(Mf)9.

3.3.11.1   The Depth averaged turbidity (in NTU) and depth averaged SS (in mg/L) of nearby monitoring station, such as IS8, IS7 and IS(Mf)16 were below the action and limit level, indicating the water quality at area nearby IS(Mf)9 was not adverse affected.

3.3.11.2   Since the turbidity level (in NTU) at IS(Mf)9, IS8, IS7 and IS(Mf)16 were below the action and limit level and no silt plume was observed when monitoring was conducted at IS(Mf)9. Please refer to the photo record below for sea condition near IS(Mf)9 on 17 Jan 14.

       CIMG2952.JPG

3.3.11.3   Also, with refer to the silt curtain condition on 17 Jan 14, no defects of the perimeter silt curtain was observed at south and southeast of the construction site.

3.3.11.4   The exceedance was likely due to local effects in the vicinity of IS(Mf)9.

3.3.11.5   As such, the limit level exceedance recorded at IS(Mf)9 is considered non-project related.

3.3.11.6   The Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

3.3.11.7   Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.3.12    One (1) Action Level Exceedance of measured Suspended Solids at 28.5 mg/L for Water Quality was recorded at IS(Mf)16 during Mid-flood tide on 21 Feb 14.

 

3.3.12.1   For active works carried out on 21 Feb 14, please refer to the above layout map.

 

3.3.12.2   Same type of works was carried out at the same location on 19, 21 and 24 Feb 14 but Suspended Solids values recorded at IS(Mf)16 on 19 and 24 Feb 14 were all below the Action and Limit Level during the same tide on the same day.

 

3.3.12.3   Location of IS(Mf)16 is located upstream to active works during mid flood tide, therefore it is unlikely that the exceedance was caused by active works which is located downstream to IS(Mf)16.

 

3.3.12.4   Suspended Solids values recorded at Impact Station nearest to monitoring station IS(Mf)16 such as IS17 and IS(Mf)9 were all below the Action and Limit Level during the same tide on the same day. This indicates that the SS level near IS(Mf)16 was not adversely affected.

 

3.3.12.5   Turbidity (in NTU) recorded at Impact Station IS(Mf)16, IS17 and IS(Mf)9 were all below the Action and Limit Level during the same tide on the same day. This indicates that the turbidity (in NTU) at the area close to IS(Mf)16 was not adversely affected.

 

3.3.12.6   Mitigation measures such as localised silt curtain for stone column installation was implemented on 21 Feb 14. 

 

3.3.12.7   With refer to the daily silt curtain integrity checking record of 21 Feb 14, no defects was observed along the part of the perimeter silt curtain located east of HKBCF-reclamation site which is next to IS(Mf)16. For the condition of the perimeter silt curtain condition near monitoring station IS(Mf)16, please refer to the photo record below:

 

    

 

3.3.12.8   The exceedance was likely due to local effects in the vicinity of IS(Mf)16.

 

3.3.12.9   The exceedance is considered as non-project related.

 

3.3.12.10Nevertheless, the Contractor was reminded to ensure provision of ongoing maintenance to the silt curtains and to carry out maintenance work once defects were found.

 

3.3.12.11Maintenance work of the silt curtain was carried out by the Contractor on a daily basis except on Sunday and public holiday.

 

3.3.13    The graphical plots of the trends of the monitoring results are provided in Appendix G. No specific trend of the monitoring results or existence of persistent pollution source was noted.


3.4          Dolphin Monitoring

3.4.1       In accordance with the Project Specific EM&A Manual, pre-set and fixed transect line vessel based dolphin survey was required in two AFCD designated areas (Northeast Lantau (NEL) and Northwest Lantau (NWL) survey areas). The impact dolphin monitoring at each survey area should be conducted twice per month.

3.4.2       The impact dolphin monitoring conducted is vessel-based and combines line-transect and photo-ID methodology, which have adopted similar survey methodologies as that adopted during baseline monitoring to facilitate comparisons between datasets.

3.4.3       The layout map of impact dolphin monitoring have been provided by AFCD and is shown in Figure 4.

3.4.4       The effort summary and sighting details during the reporting quarter are shown in the Appendix H. A summary of key findings of the dolphin surveys completed during the reporting quarter is shown below:

Table 3.6            Summary of Key Dolphin Survey Findings in Dec 2013- Feb 2014

Number of Impact Surveys Completed^

6

Survey Distance Travelled under Favourable On- Effort Condition

626.8km

Number of Sightings

26 sightings (21 sightings are ”on effort” (which are all under favourable condition), 5 “sightings are opportunistic”)

Number of dolphin individual sighted

107 individuals (the best estimated group size)

Dolphin Encounter Rate#

NEL: 0.5

NWL: 4.8

Dolphin Group Size

Average of NEL: 1

Average of NWL: 4.2

Varied from 1-13 individuals

Most Often frequent dolphin sighting area

Sha Chau and Lung Kwu Chau Marine Park, the western limit of NWL and one area to the north of the Hong Kong International Airport platform.

Remarks:
^ Completion of line transect survey of NEL and NWL survey area once was counted as one complete survey.

 # Dolphin Encounter Rate = (Sum of 1st 2nd, 3rd month’s total sighting/ Sum of 1st , 2nd, 3rd month’s total effort)*100km (encounter rates are calculated using on effort sightings made under favourable conditions only.)

 

3.4.5       Two (2) Action Level exceedances were recorded in the reporting quarter. The investigation results showed that there is no evidence that exceedances are related to Project works are annexed in Appendix L. Actions were taken according to the Event and Action Plan for impact dolphin monitoring. Please refer to Appendix L for details of action taken. 

Table 3.7          Summary of STG and ANI encounter rates  in Dec 2013- Feb 2014

NEL

NWL

Level Exceeded

 

STG*

0.5

4.5

Action

 

ANI**

0.5

20.7

Action

 

*Quarterly Average Encounter Rate of Number of Dolphin Sightings (STG) presents averaged encounter rates of the three monitored months in terms of groups per 100km per survey event.

STG Encounter rate = (Average of (total number sighting/total effort) of 1st and 2nd completed survey# of 1st month+ Average of (total number sighting/total effort) of 1st and 2nd completed survey# of 2nd month + Average of (total number sighting/total effort) of 1st and 2nd completed survey# of 3rd month)/3*100km

**Quarterly Average Encounter Rate of Total Number of Dolphins (ANI) presents averaged encounter rates of the three monitored months in terms of individuals per 100km per survey event.

ANI Encounter rate = (Average of (total number of Individual/total effort) of 1st and 2nd completed survey# of 1st month+ Average of (total number of Individual/total effort) of 1st and 2nd completed survey# of 2nd month + Average of (total number of Individual/total effort) of 1st and 2nd completed survey# of 3rd month +)/3*100km

 

3.4.6       Details of the comparison and analysis methodology and their findings and discussions are annexed in Appendix H.

3.5          Environmental Site Inspection and Audit

3.5.1       Site Inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. In the reporting quarter, 13 site inspections were carried out. Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site audits.

3.5.2       Particular observations during the site inspections are described below:

Air Quality

 

3.5.3       Dark smoke was observed generating from an excavator at works area of Portion A. The Contractor should provided maintenance to the machineries used on-site. (Closed)

3.5.4       Fugitive dust was observed when moisten rock material is being transferred by a barge installed with conveyor belt. The Contractor was reminded to enhanced dust control measures to prevent generation of fugitive dust. (Reminder)

3.5.5      Dry sand surface was observed on works area of Portion A. The Contractor was reminded to provide sufficient dust control measures. The Contractor provided dust control measures. The Contractor was reminded to continued to provide dust control measures on works area of Portion A. (Reminder)

3.5.6       An idle air compressor was observed without drip tray on steel cell. The Contractor was reminded to provide mitigation measures such as drip tray to air compressor prior to operation. An idle air compressor was observed without drip tray on steel cell. The Contractor should provide mitigation measures such as drip tray to air compressor prior to operation. (Closed)

3.5.7       Dark smoke was observed generating from an excavator and a loader at works area of Portion A. The machine was turned off. The Contractor is reminded to provide maintenance to the machineries used on-site so that emission of dark smoke could be effectively prevented. (Reminder)

Noise

3.5.8       Noise decoupling measure was observed to be missing from the generators on Hong Fai and SHB205 and on barge SHB210. Noise decoupling measures should be provided to the concerned generators. (Closed)

3.5.9      Insufficient acoustically decoupling measure of generator and water pumps was observed on barge FTB19, two generators on SHB 210 and 2 generators on FTB 21. The Contractor was advised to provide sufficient acoustic decoupling measure(s) such as acoustic mat to noisy equipments. The Contractor was reminded that insufficient/inadequate mitigation measures must be swiftly rectified. (Closed)

Chinese White Dolphin

 

3.5.10    No adverse observation was identified in the reporting month.

Water Quality

3.5.11    Turbid water was observed at the southwestern silt curtain entrance area. Refer to the photo taken and site observations, sources of impact likely due to the turbine activities and/or movement of vessel at shallow water (at near the entrance at southwestern of the Construction site and/or when vessel’s propeller was turn on at shallow water). The dispersion of turbid water from the inside of the perimeter silt curtain to the outside of the perimeter silt curtain is potentially due to defects of perimeter silt curtain at certain sections and/or insufficient overlapping at entrance/exit of the perimeter silt curtain. (Closed)

 

3.5.12    The Contractor was advised to regularly evaluate the integrity of the perimeter silt curtain by reviewing the results obtained from daily checking or/and monthly diver inspections specified by the Silt Curtain Deployment Plan. The Contractor was advised to provide sufficient mitigation measures and swiftly carry out maintenance once defects of the perimeter silt curtain are found during the above mentioned daily checking and/or monthly diver inspection. (Closed)

3.5.13    Oil drums, chemical containers and generator were observed without the provision of drip trays at Portion, on barge天駿3, on barge SHB205, on temporary rock bund and on Portion A. The Contractor provided drip trays to oil drums, chemical container and generator to retain leakage, if any. (Closed)

3.5.14    An oil drum was observed to be not properly plugged at works area of Portion A. The Contractor provided measures to seal the opening of oil drums to avoid leakage. (Closed)

3.5.15    Containers of chemical to be used and chemical waste were misplaced together in Hong Fai. The Contractor should store the chemical and chemical waste separately. (Closed)

3.5.16    Movable lighting machineries were observed to be placed on bare ground of Portion D, on SHB205 and at works area at Portion A without the provision of drip trays. It was observed that drip trays were provided to movable lighting machineries at temporary rock bund and at works area at portion A and on SHB205. The contractor was advised to continue to provide drip tray or equivalent measures to retain potential oil leakage to movable lighting machineries. (Closed)

3.5.17    Trays of oil drums were found to be placed near to the shore. The Contractor should secure the oil drums with drip tray away from the shore to ensure no washing off of oil occurs. (Closed)

3.5.18    Oil stain was observed on barge FTB19 and SHB205. The Contractor was advised to clear the oil stain using absorbent material. (Closed)

3.5.19    Waste water was observed accumulated inside drip trays on FTB21 and the Contractor was reminded to clear the waste water regularly to prevent runoff or accidental spillage (Reminder)

3.5.20    Defect was observed within a bunding and waste oil water mixture was observed on the barge surface. The Contractor was reminded to rectify the defects observed and cleared the oil waste using chemical absorbent material and dispose the chemical absorbent material as chemical waste. (Closed)

3.5.21    Oil stain was observed on temporary rock bund. The Contractor was advised to clear the oil stain using absorbent material. (Closed)

3.5.22    During site inspection audit, sandfilling seem to be conducted at one end of the temporary rock bund. The Contractor was reminded to conduct sandfilling behind at least 200m leading temporary rock bund/seawall. (Reminder)

3.5.23    Disconnected silt curtain was observed at the western side of the silt curtain. The Contractor was advised to provide sufficient mitigation measures and swiftly carry out maintenance once defects of the perimeter silt curtain are found during the daily checking and/or monthly diver inspection. (Closed)

3.5.24    Localised silt curtain was not observed when stone column installation. The Contractor was reminded to provide mitigation measures such as localized silt curtain to active stone column installation points. (Closed)

3.5.25    Gap was observed between the bunding and the barge surface. The Contractor was reminded to properly seal the gap between the bunding and barge surface to prevent potential oil leakage. (Closed)

3.5.26    Oil stain was observed on temporary rock bund, The Contractor was reminded to clear the oil stain on temporary rock bund. (Closed)

 

Chemical and Waste Management

3.5.27    Rubbish bin was observed without being covered; the Contractor was reminded to properly store general waste and covers all rubbish bins. The Contractor properly store general waste and covers all rubbish bins. (Closed).

3.5.28    General refuse was scattered on sea water and along the shore near Portion D. The Contractor was reminded to clear the refuse in timely manner and keep site clean and tidy. The Contractor cleared the refuse in timely manner and keeps site clean and tidy. (Closed)

3.5.29    Movable lighting machineries were observed to be placed on bare ground of Portion D without the provision of drip trays. Drip trays were observed to be provided to movable lighting machineries at temporary rock bund and at works area at portion A. The contractor was advised to continue to provide drip tray or equivalent measures to retain potential oil leakage to movable lighting machineries. An ineffective leakage preventive measure for movable lighting machineries at Portion D was pending for Contractor’s rectification. (Closed)

3.5.30    Defect was observed within a bunding and waste oil water mixture was observed on the barge surface. The Contractor was reminded to rectify the defects observed and cleared the oil waste using chemical absorbent material and dispose the chemical absorbent material as chemical waste. (Closed)

3.5.31    Litter and general refuse was observed on sea and land at works area of Portion D and at the edge of the works area of Portion A and in the water within and adjacent to the works site between steel cell# 37 and steel cell# 38. The Contractor was reminded to regularly clear the litter and general refuse at this area. The Contractor was cleared the litter and general refuse at these areas. (Closed)


3.5.32    Construction waste such as band drain was observed along the northern edge of works area at Portion A and on edge of temporary rock bund. The Contractor was advice to properly store and dispose construction waste such as band drain. (Closed)

3.5.33    Construction waste such as band drain was observed along the northern edge of works area at Portion A and on edge of temporary rock bund. The Contractor was advice to properly store and disposes construction waste such as band drain. (Closed)

3.5.34    Bags of general refuses were observed stored on barge surface. The Contractor was reminded to regularly collect and dispose the general refuse regular. (Reminder)

Landscape and Visual Impact

 

3.5.35    No relevant works was carried out in the reporting Quarter.

Others

 

3.5.36    Rectifications of remaining identified items are undergoing by the Contractor. Follow-up inspections on the status on provision of mitigation measures will be conducted to ensure all identified items are mitigated properly.

4             Advice on the Solid and Liquid Waste Management Status

4.1          Summary of Solid and Liquid Waste Management

4.1.1      The Contractor registered as a chemical waste producer for this project. Sufficient numbers of receptacles were available for general refuse collection and sorting.

4.1.2      As advised by the Contractor, 3,437,422.6 m3 of fill were imported for the Project use in the reporting period. 420 kg of paper/ carboard packaging and 100 kg of metal were generated, 4 tonnes of chemical waste and 110.5 m3 of general refuse were generated and disposed of in the reporting period. Monthly summary of waste flow table is detailed in Appendix M.

4.1.3      The Contractor is advised to properly maintain on site C&D materials and wastes collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse / recycle of C&D materials and wastes. The Contractor is reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

4.1.4      The Contractor is reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

 


5             Implementation Status of Environmental Mitigation Measures

5.1          Implementation Status of Environmental Mitigation Measures

5.1.1       In response to the site audit findings, the Contractors carried out corrective actions.

5.1.2      A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C. Most of the recommended mitigation measures are being upheld. Moreover, regular review and checking on the construction methodologies, working processes and plants were carried out to ensure the environmental impacts were kept minimal and recommended environmental mitigation measures were implemented effectively. 

5.1.3      Training of marine travel route for marine vessels operator was given to relevant staff and relevant records were kept properly.

5.1.4      Regarding the implementation of dolphin monitoring and protection measures (i.e. implementation of Dolphin Watching Plan, Dolphin Exclusion Zone and Silt Curtain integrity Check), regular checks were conducted by experienced MMOs within the works area to ensure that no dolphins were trapped by the silt curtain area. There were no dolphins spotted within the silt curtain during this quarter. The relevant procedures were followed and all measures were well implemented. The silt curtains were also inspected in accordance to the submitted plan.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6             Summary of Exceedances of the Environmental Quality Performance Limit

6.1          Summary of Exceedances of the Environmental Quality Performance Limit

6.1.1       All 1-Hour TSP results were below the Action and Limit Level in the reporting quarter. Six (6) 24-hour TSP results recorded among AMS2, AMS3A and AMS7 exceeded the Action Level and two (2) 24-hour TSP results recorded at AMS3A exceeded the Limit Level at in the reporting quarter. Investigation results show that the exceedances were not related to Project.

6.1.2       For construction noise, no exceedance was recorded at all monitoring stations in the reporting period.

6.1.3       Ten (10) Action Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter. Three (3) Limit Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter.

6.1.4       Investigation results shows that the Action Level Exceedance recorded at SR5 and Limit Level Exceedance recorded at  IS10 on 18 Dec 13 were related to project. Investigation results show that other water quality exceedances unlikely to be non-project related.

6.1.5       Two (2) Action level exceedances of Chinese White Dolphin monitoring were recorded in the reporting quarter. Investigation results show that there is no evidence that exceedances are related to Project works.  Event and Action Plan for Impact Dolphin Monitoring was triggered. For detail of investigation, please refer to appendix L.

6.1.6       Cumulative statistics on exceedances is provided in Appendix J.

 


7             Summary of Complaints, Notification of Summons and Successful Prosecutions

7.1          Summary of Environmental Compliants, Notification of Summons and Successful Prosecutions

7.1.1       The Environmental Complaint Handling Procedure is annexed in Figure 5.

7.1.2       As informed by the Contractor on 5 Dec 13, one (1) noises related complain of a barge moving through the southern channel of HyD’s construction site after 23:00 on 8.11.2013. Site daily for barges was requested from the Contractor and as refer to the site daily provided by the  Contractor, there was no barge operated after 18:25 on 08 Nov 13. The complaint is therefore considered not likely to be related to the construction works.

7.1.2.1   The Contractor was remind to continue to properly implement the existing noise mitigation measures i.e. to well maintain all plant and equipment in good condition to avoid noise generation and to turn off or throttled down idle equipment. The Contractor was reminded to inform related parties when environmental complain was received to ensure future timely reporting of any complaints/ enquiry.

7.1.3       As informed by the Contractor on 12 Dec 13. A complaint involves the leakage of sand from barges causing water discoloration at sea near Tuen Mun Pierhead Garden and sand material without properly covered was blown to the inside of the residential area which caused disturbance to residence.

7.1.3.1   Regarding the leakage from work barges causing water pollution near Tuen Mun Pierhead Garden , it is noted that all project related vessels (including sand barges) are designated with a regular marine travel route to the site, but the regular travel route plan of this project does not specify the travel route passing through the at area at sea near Tuen Mun Pierhead Garden and with refer to photo record, Contractor would water the sand material to keep the sand material wet to prevent generation of fugitive dust.

7.1.3.2   With refer to available information provided and monitoring data recorded on 09 Dec 13, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract.

7.1.3.3   The Contractor was advised to ensure the regular travel routes for all project related vessels (including sand barges) were being strictly followed and all vessels should have regular maintenance to ensure that all Sand Barge functioning well.

7.1.3.4   The Contractor was advised to ensure to continue the provision of fugitive dust mitigation measures to barges loaded with filling material such as watering to sand filling material on sand barges to keep the surface of stockpile of filling material wet.

7.1.3.5   Photo record shows that watering equipment is provided on pelican barge loaded with sand for watering of sand filling material to keep the sand material wet.

CIMG0061

 


7.1.4      As informed by the Contractor on 6 Jan 14. A complaint involves barges loaded with sand material without properly covered was blown to the inside of the residential area of Tuen Mun Pierhead Garden which caused disturbance to residence. With refer to available information provided, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract.

7.1.6.1   Site visit was conducted on 9 Jan 14 and it was observed during the site investigation that watering equipment was provided on pelican barge loaded with sand for watering of sand filling material to keep the surface of sand material wet. This is consistent with HyD’s reply to Oriental Daily Newspaper that the Contractor would water the sand material to keep the sand material wet to prevent generation of fugitive dust.

7.1.6.2   Photo record shows that watering equipment is provided on pelican barge loaded with sand for watering of sand filling material.

CIMG2361

 

7.1.6.3   During the follow-up site visit conducted on 9 Jan 14, after interview with the skipper of the pelican barge, it was noted that pelican barge is designated with a regular marine travel route to the site, however the regular travel route plan of this project does not specify the travel route passing through the at area at sea near Tuen Mun Pierhead Garden.

7.1.6.4   Therefore it is considered the complaint is unlikely to be related to this project.


 

7.1.7       EPD referred a complaint from complainant who advised that blackish mud was found along the edge of the construction site of Hong Kong-Zhuhai-Macao Bridge Hong Kong Project near the airport in the morning of 18 January 2014

7.1.7.1   With refer to the site daily of 16, 17 and 18 Jan 14 provided by the Contractor (China Harbour Engineering Company Ltd), no excavation and dredging activities were conducted on site. This indicates that the blackish mud found along the edge of the construction site of this contract near the airport in the morning of 18 January 2014 was unlikely related to this project.

7.1.7.2   A follow up joint site inspection with the representatives of the Contractor, Residential Engineer and IEC/ENPO was conducted on 22 Jan 2014. Excavation and dredging activities were not observed within the site boundary of HKBCF during the joint site inspection audit.

7.1.7.3   Therefore in accordance with the abovementioned observations, the complaint is therefore considered as not related to contract HY/2010/02.

7.1.8       No notification of summons and successful prosecution was received in the reporting period.

7.1.9       No environmental notification of Summons and Successful Prosecutions was received in the reporting quarter.

7.1.10    Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix J.


8           Comments, recommendations and Conclusions

8.1        Comments on mitigation measures

8.1.6       According to the environmental site inspections performed in the reporting quarter, the following recommendations were provided:

Air Quality Impact

l  All working plants and vessels on site should be regularly inspected and properly maintained to avoid dark smoke emission.

l  All vehicles should be washed to remove any dusty materials before leaving the site.

l  Haul roads should be sufficiently dampened to minimize fugitive dust generation.

l  Wheel washing facilities should be properly maintained and reviewed to ensure properly functioning.

l  Temporary exposed slopes and open stockpiles should be properly covered.

l  Enclosure should be erected for cement debagging, batching and mixing operations.

l  Water spraying should be provided to suppress fugitive dust for any dusty construction activity.

Construction Noise Impact

l  Quieter powered mechanical equipment should be used as far as possible.

l  Noisy operations should be oriented to a direction away from sensitive receivers as far as possible.

l  Proper and effective noise control measures for operating equipment and machinery on-site should be provided, such as erection of movable noise barriers or enclosure for noisy plants. Closely check and replace the sound insulation materials regularly

l  Vessels and equipment operating should be checked regularly and properly maintained.

l  Noise Emission Label (NEL) shall be affixed to the air compressor and hand-held breaker operating within works area.

l  Better scheduling of construction works to minimize noise nuisance.

l  Acoustic decoupling measures should be properly implemented for all existing and incoming construction vessels with continuous and regularly checking to ensure effective implementation of acoustic decoupling measures.

Water Quality Impact

l  Regular review and maintenance of silt curtain systems, drainage systems and desilting facilities in order to make sure they are functioning effectively.

l  Construction of seawall should be completed as early as possible.

l  Regular inspect and review the loading process from barges to avoid splashing of material.

l  Silt, debris and leaves accumulated at public drains, wheel washing bays and perimeter u-channels and desilting facilities should be cleaned up regularly.

l  Silty effluent should be treated/ desilted before discharged. Untreated effluent should be prevented from entering public drain channel.

l  Proper drainage channels/bunds should be provided at the site boundaries to collect/intercept the surface run-off from works areas.

l  Exposed slopes and stockpiles should be covered up properly during rainstorm.

 


 

Chemical and Waste Management

l  All types of wastes, both on land and floating in the sea, should be collected and sorted properly and disposed of timely and properly. They should be properly stored in designated areas within works areas temporarily.

l  All chemical containers and oil drums should be properly stored and labelled.

l  All plants and vehicles on site should be properly maintained to prevent oil leakage.

l  All kinds of maintenance works should be carried out within roofed, paved and confined areas.

l  All drain holes of the drip trays utilized within works areas should be properly plugged to avoid any oil and chemical waste leakage.

l  Oil stains on soil surface and empty chemical containers should be cleared and disposed of as chemical waste.

l  Regular review should be conducted for working barges and patrol boats to ensure sufficient measures and spill control kits were provided on working barges and patrol boats to avoid any spreading of leaked oil/chemicals.

 

Landscape and Visual Impact

l  All existing, retained/transplanted trees at the works areas should be properly fenced off and regularly inspected.

 

8.2        Recommendations on EM&A Programme

8.2.6       The impact monitoring programme for air quality, noise, water quality and dolphin ensured that any deterioration in environmental condition was readily detected and timely actions taken to rectify any non-compliance. Assessment and analysis of monitoring results collected demonstrated the environmental impacts of the Project. With implementation of recommended effective environmental mitigation measures, the Project’s environmental impacts were considered as environmentally acceptable. The weekly environmental site inspections ensured that all the environmental mitigation measures recommended were effectively implemented.

8.2.7       The recommended environmental mitigation measures, as included in the EM&A programme, effectively minimize the potential environmental impacts from the Project. Also, the EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.

 


8.3        Conclusions

8.3.1       The construction phase and EM&A programme of the Project commenced on 12 March 2012.

8.3.2       All 1-Hour TSP results were below the Action and Limit Level in the reporting quarter. Six (6) 24-hour TSP results recorded among AMS2, AMS3A and AMS7 exceeded the Action Level and two (2) 24-hour TSP results recorded at AMS3A exceeded the Limit Level at in the reporting quarter. Investigation results show that the exceedances were not related to Project.

8.3.3       For construction noise, no exceedance was recorded at all monitoring stations in the reporting period.

8.3.4       Ten (10) Action Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter. Three (3) Limit Level Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in the reporting quarter.

8.3.5       Investigation results shows that the Action Level Exceedance of SS recorded at SR5 and Limit Level Exceedance recorded at  IS10 on 18 Dec 13 were related to project. Investigation results show that other water quality exceedances unlikely to be non-project related.

8.3.6       Two (2) Action Level exceedances were recorded for Chinese White Dolphin monitoring in the reporting quarter. Investigation results show that there is no evidence that exceedances are related to Project works.

8.3.7       Environmental site inspection was carried out thirteen times in the reporting quarter. Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site audits.

8.3.8       As informed by the Contractor on 5 Dec13, one complaint was noted on 12 Nov regarding a barge moving through the southern channel. After investigation, the noise complaint was considered as non-project related.

8.3.9       As informed by the Contractor, complaint received from Penta-Ocean – Gitanes Joint Venture (CV/2012/03) mentioned that the formation works of the Contaminated Mud Pit CMP1 to the South of the Brothers (CMP1 of SB) which has been completed in mid-August 2013 and the pit has been commissioned for receiving contaminated marine mud from other projects starting from 16 August 2013. However, it was recently observed that some of the project vessels of HY/2010/02 (photos taken on 20 Nov 2013 are attached) had berthed within the said pit and those anchorages would likely cause disruption to the underlying contaminated mud and thus induce unfavourable contamination impact to the surrounding marine environment. In this regard, they reminded the contractor to avoid berthing of their vessels within the boundary of CMP1 of SB thereafter for the sake of environmental concern. After investigation, the complaint was considered as non-project related

8.3.10    As informed by the Contractor on 12 Dec 13. A complaint involves the leakage of sand from barges causing water discoloration at sea near Tuen Mun Pierhead Garden and sand material without properly covered was blown to the inside of the residential area which caused disturbance to residence. With refer to available information provided and monitoring data recorded on 09 Dec 13, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract.

8.3.11    As informed by the Contractor on 27 Dec 13. A complaint involves barges loaded with sand material without properly covered was blown to the inside of the residential area of Tuen Mun Pierhead Garden which caused disturbance to residence. With refer to available information provided, it cannot indicate that the water quality impact and air quality impact were caused by the vessel of this Contract and therefore the complaint could not be concluded as related to this Contract.

8.3.12    As informed by the Contractor on 6 Jan 14. A complaint involves barges loaded with sand material without properly covered was blown to the inside of the residential area of Tuen Mun Pierhead Garden which caused disturbance to residence. With refer to available information provided. It is considered the complaint is unlikely to be related to this project.


8.3.13    EPD referred a complaint from complainant who advised that blackish mud was found along the edge of the construction site of Hong Kong-Zhuhai-Macao Bridge Hong Kong Project near the airport in the morning of 18 January 2014. After receipt of the complaint, site daily was reviewed and follow-up investigation has been conducted and excavation and dredging activities were not observed within the site boundary of HKBCF during the joint site inspection audit. Therefore in accordance with the investigation results, the complaint is considered as not related to contract HY/2010/02.

8.3.14    No notification of summons and successful prosecution was received in the reporting period.

8.3.15    Apart from the above mentioned monitoring, most of the recommended mitigation measures, as included in the EM&A programme, were implemented properly in the reporting quarter.

8.3.16    The recommended environmental mitigation measures effectively minimize the potential environmental impacts from the Project. The EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.

8.3.17    Moreover, regular review and checking on the construction methodologies, working processes and plants were carried out to ensure the environmental impacts were kept minimal and recommended environmental mitigation measures were implemented effectively.