Contract No. HY/2010/02 ¡V Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities ¡V Reclamation Work (here below, known as ¡§the
Project¡¨) mainly comprises reclamation at the northeast of
the Hong Kong International Airport of
an area of
about 130-hectare for
the construction of an artificial island for the development of the Hong
Kong Boundary Crossing Facilities (HKBCF), and about 19-hectare for the
southern landfall of the Tuen Mun - Chek Lap Kok Link (TMCLKL). It is a
designated project and is governed by the current permits for the Project, i.e.
the amended Environmental Permits (EPs) issued on 06 August 2013
(EP-353/2009/G) and 28 January 2014 (EP-354/2009/B) (for TMCLKL Southern
Landfall Reclamation only).
Ove Arup & Partners Hong Kong Limited (Arup) was
appointed by Highways Department (HyD) as the consultants for the design and
construction assignment for the Project¡¦s reclamation works (i.e. the Engineer
for the Project).
China Harbour Engineering Company Limited (CHEC) was
awarded by HyD as the Contractor to undertake the construction work of the
Project.
ENVIRON Hong Kong Ltd. was employed by HyD as the
Independent Environmental Checker (IEC) and Environmental
Project Office (ENPO) for the Project.
AECOM Asia Co. Ltd. (AECOM) was appointed by CHEC to
undertake the role of Environmental Team for the Project for carrying out the
environmental monitoring and audit (EM&A) works.
The
construction phase of the Project under the EPs was commenced on 12 March 2012
and will be tentatively completed by early Year 2016. The EM&A programme,
including air quality, noise, water quality and dolphin monitoring and
environmental site inspections, was commenced on 12 March 2012.
This
report documents the findings of EM&A works conducted in the period between
1 March 2014 and 31 May 2014. As informed by the Contractor, major activities
in the reporting quarter were:-
Marine-based Works
-
Connecting arc cell installation
-
Laying geo-textile
-
Optimizing rubble mound seawalls
-
Conforming sloping seawalls
-
Sand filling
-
Rock filling
-
Maintenance of silt curtain & silt screen at sea water intake of
HKIA
-
Stone column installation
-
Band drain installation
-
Backfill cellular structure
-
Geotechnical Instrumentation works
-
Construction of temporary seawall
-
Portion D Construction of Access to Portion A
-
Surcharge laying
-
Construction of temporary pier at Portion A
-
Precast Yard setup
-
Seawall blocks for temporary construction
-
Vibro-compaction on surcharge
-
Construction of conveyors for public fill
-
Temporary bridge at Portion D
Land-based Works
-
Maintenance works of Site Office at Works Area WA2
-
Maintenance works of Public Works Regional Laboratory at Works Area
WA3
-
Geo-textile fabrication at Works Area WA2
-
Silt curtain fabrication at Works Area WA4
-
Installed sand bag at Works Area WA2
-
Maintenance of Temporary Marine Access at Works Area WA2
A summary of monitoring and audit activities conducted
in the reporting quarter is listed below:
24-hour
Total Suspended Particulates (TSP) monitoring
1-hour
TSP monitoring
|
16 sessions
16 sessions
|
Noise monitoring
|
13 sessions
|
Impact
water quality monitoring
|
39 sessions
|
Impact
dolphin monitoring
|
6 surveys
|
Joint
Environmental site inspection
|
13 sessions
|
Breaches
of Action and Limit Levels for Air Quality
All 1-Hour TSP results were below the Action
and Limit Level in the reporting quarter. One (1) 24-hour TSP results recorded
at AMS3B exceeded the Action Level. Investigation results show that the Action
level exceedance was not related to Project.
Breaches
of Action and Limit Levels for Noise
For construction noise, no exceedance was
recorded at all monitoring stations in the reporting period.
Breaches of Action and Limit Levels for Water Quality
Eight (8) Action Level
Exceedances were recorded at measured suspended solids (SS) values (in mg/L) in
the reporting quarter. One (1) Limit Level exceedance was recorded at measured
suspended solids (SS) values (in mg/L) in the reporting quarter. One (1) Action
level exceedance was recorded at measured turbidity values (in NTU) in the reporting
quarter. Investigation results shows that all the Action and Limit
Level Exceedance recorded were non-project related.
Breaches
of Action and Limit Levels for Impact Dolphin Monitoring
One (1) Limit Level exceedances
were recorded for Chinese White Dolphin
monitoring in the reporting quarter.
Triggering of Event and Action Plan for Impact Dolphin Monitoring
Event and Action Plan for Impact
Dolphin Monitoring was triggered. For detail of investigation, please refer to
appendix L.
Implementation Status
and Review of Environmental Mitigation Measures
Most of the recommended
mitigation measures, as included in the EM&A programme, were implemented
properly in the reporting quarter.
The recommended
environmental mitigation measures effectively minimize the potential
environmental impacts from the Project. The EM&A programme effectively
monitored the environmental impacts from the construction activities and ensure
the proper implementation of mitigation measures. No particular recommendation
was advised for the improvement of the programme.
Moreover, regular review
and checking on the construction methodologies, working processes and plants
were carried out to ensure the environmental impacts were kept minimal and recommended
environmental mitigation measures were implemented effectively.
Complaint,
Notification of Summons and Successful Prosecution
EPD
referred a complaint on 17 March 2014 from complainant who advised that there
was sea water colored in blue observed in vicinity of Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Facilities (HKBCF) where stone column installation
was taking place. The locations of stone column and impact water quality
monitoring data recorded between 12 ¡V 17 March14 were reviewed. In accordance
with the monitoring records, no discoloration of sea water or silty plume
appearance outside the seawall was observed during the water quality monitoring
between 12 ¡V 17 March14. Therefore the complaint is considered to be
non-project related.
EPD
referred a complaint from a complainant who advised that muddy water was found
being discharged from the construction site of Hong Kong-Zhuhai-Macau Bridge
Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Reclamation Works on 22 March
2014. With refer to the monitoring records on 21 March 2014 and the follow-up
site inspection audit conducted with the representatives of the Contractor and
Residential Engineer on 27 March 2014, since no discoloration of sea water or
silty plume appearance outside the perimeter silt curtain was observed, the
complaint is considered to be non-project related.
As
informed by the Contractor, a complaint was received by the Contractor on 25
March 14 concerning sand and dust emission from uncovered barges parking at the
sea area off the Tuen Mun Ferry Pier. However, base on the available
information, it cannot indicate that the air quality impact was caused by the
vessel of this Contract and therefore the complaint could not be concluded as
related to this Contract.
As informed by the Contractor,
further to the notification of summons received March 2014 due to works carried
out on 6 October 13 contrary to conditions of NCO, Cap.400. The Contractor
pledged guilty to the charge during the court appearance on 28 April 2014.
The Contractor has established noise control management system on restricted
hour works, to prevent future violation of conditions of NCOs,
Cap. 400.
As informed by the Contractor on
7 May 14, a complaint was received by the Contractor on 17 April 14 concerning
sand and dust emission from uncovered barges parking at the sea area off the
Tuen Mun Ferry Pier. However, because no extra information was received for this
complaint after the release of the latest investigation report, it is unable to
conclude whether the complaint is related to this Contract.
As informed by the Contractor on
30 May 2014, an environmental complaint had been received on 28 May 2014. The
complainant mentioned that waste such as earth and concrete were being felled
into the sea everyday at the Hong Kong-Zhuhai-Macao Bridge at location where
construction works are being conducted, causing pollution to the marine
environment. The construction programme and waste flow record provided by the Contractor has been reviewed. With
refer to the available information provided, it is concluded
that the complaint is unlikely to be related to this Contract.
1.1.1
Contract No. HY/2010/02 ¡V Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing
Facilities ¡V Reclamation Work (here below, known as ¡§the Project¡¨) mainly
comprises seawall
construction and reclamation at the northeast of
the Hong Kong International Airport of
an area of
about 130-hectare for
the construction of an artificial island for the development of the Hong
Kong Boundary Crossing Facilities (HKBCF), and about 19-hectare for the
southern landfall of the Tuen Mun - Chek Lap Kok Link (TMCLKL).
1.1.2
The
environmental impact assessment (EIA) reports (Hong Kong ¡V
Zhuhai ¡V Macao Bridge Hong Kong Boundary Crossing
Facilities ¡V EIA Report (Register No. AEIAR-145/2009) (HKBCFEIA) and Tuen Mun ¡V
Chek Lap Kok Link ¡V EIA Report (Register No. AEIAR-146/2009) (TMCLKLEIA), and
their environmental monitoring and audit (EM&A) Manuals (original EM&A
Manuals), for the Project were approved by Environmental Protection Department
(EPD) in October 2009.
1.1.3
EPD
subsequently issued the
Environmental Permit (EP) for HKBCF in November 2009
(EP-353/2009) and the Variation of Environmental Permit (VEP) in June 2010
(EP-353/2009/A), November 2010 (EP-353/2009/B), November 2011 (EP-353/2009/C), March 2012
(EP-353/2009/D), October 2012 (EP-353/2009/E), April 2013 (EP-353/2009/F) and
August 2013 (EP-353/2009/G). Similarly, EPD issued the Environmental Permit
(EP) for TMCLKL in November 2009 (EP-354/2009) and the Variation of
Environmental Permit (VEP) in December 2010 (EP-354/2009/A) and January 2014
(EP-354/2009/B).
1.1.4
The
Project is a designated project and is governed by the current permits for the
Project, i.e. the amended EPs issued on 6 August 2013 (EP-353/2009/G) and 28
January 2014 (EP-354/2009/B) (for TMCLKL Southern Landfall Reclamation only).
1.1.5
A Project Specific EM&A Manual, which included all
project-relation contents from the original EM&A Manuals for the Project,
was issued in May 2012.
1.1.6
Ove Arup & Partners Hong Kong Limited (Arup) was
appointed by Highways Department (HyD) as the consultants for the design and
construction assignment for the Project¡¦s reclamation works (i.e. the Engineer
for the Project).
1.1.7
China Harbour Engineering Company Limited (CHEC) was
awarded by HyD as the Contractor to undertake the construction work of the
Project.
1.1.8
ENVIRON Hong Kong Ltd. was employed by HyD as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
1.1.9
AECOM Asia Co. Ltd. (AECOM) was appointed by CHEC to
undertake the role of Environmental Team for the Project for carrying out the
EM&A works.
1.1.10
The construction phase of the Project under the EPs was
commenced on 12 March 2012 and will be tentatively completed by early Year
2016.
1.1.11
According to the Project Specific EM&A Manual, there is
a need of an EM&A programme including air quality, noise, water quality and
dolphin monitoring and environmental site inspections. The EM&A programme
of the Project commenced on 12 March 2012.
1.2
Scope of Report
1.2.1
This is the
eighth quarterly EM&A Report under the Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Crossing Facilities ¡V Reclamation Works. This report
presents a summary of the environmental monitoring and audit works, list of
activities and mitigation measures proposed by the ET for the Project from 1 May
2014 to 31 May
2014.
1.3.1
The project organization structure is shown in Appendix A.
The key personnel contact names and numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party
|
Position
|
Name
|
Telephone
|
Fax
|
Engineer¡¦s Representative (ER)
(Ove
Arup & Partners Hong Kong Limited)
|
Chief Resident Engineer
|
Roger Marechal
|
2528 3031
|
2668 3970
|
IEC / ENPO
(ENVIRON Hong Kong Limited)
|
Independent Environmental Checker
|
Raymond Dai
|
3465 2888
|
3548 6988
|
Environmental Project Office Leader
|
Y.H. Hui
|
3465 2868
|
3465 2899
|
Contractor
(China Harbour Engineering
Company Limited)
|
General Manager (S&E)
|
Daniel Leung
|
3157 1086
|
2578 0413
|
Environmental Officer
|
Richard Ng
|
36932253
|
2578 0413
|
24-hour Hotline
|
Alan C.C. Yeung
|
9448 0325
|
--
|
ET
(AECOM
Asia Company Limited)
|
ET Leader
|
Echo Leong
|
3922 9280
|
2317 7609
|
1.4.1 The construction phase of the Project under the EP commenced
on 12 March 2012.
1.4.2 As informed by the Contractor, details of the major works
carried out in the reporting quarter are listed below:-
Marine-based Works
-
Connecting arc cell installation
-
Laying geo-textile
-
Optimizing rubble mound seawalls
-
Conforming sloping seawalls
-
Sand filling
-
Rock filling
-
Maintenance of silt curtain & silt screen at sea water intake of
HKIA
-
Stone column installation
-
Band drain installation
-
Backfill cellular structure
-
Geotechnical Instrumentation works
-
Construction of temporary seawall
-
Portion D Construction of Access to Portion A
-
Surcharge laying
-
Construction of temporary pier at Portion A
-
Precast Yard setup
-
Seawall blocks for temporary construction
-
Vibro-compaction on surcharge
-
Construction of conveyors for public fill
-
Temporary bridge at Portion D
Land-based Works
-
Maintenance works of Site Office at Works Area WA2
-
Maintenance works of Public Works Regional Laboratory at Works Area
WA3
-
Geo-textile fabrication at Works Area WA2
-
Silt curtain fabrication at Works Area WA4
-
Installed sand bag at Works Area WA2
-
Maintenance of Temporary Marine Access at Works Area WA2
1.4.3 The 3-month rolling construction programme of the Project
is shown in Appendix B.
1.4.4 The general layout plan of the Project site showing the
detailed works areas is shown in Figure 1.
1.4.5 The environmental mitigation measures implementation
schedule are presented in Appendix C.
2.1.1
The Project Specific EM&A Manual designated 4 air
quality monitoring stations, 2 noise monitoring stations, 21 water monitoring
stations (9 Impact Stations, 7 Sensitive Receiver Stations and 5 Control/Far
Field Stations) to monitor environmental impacts on air quality, noise and
water quality respectively. Pre-set and fixed transect line vessel based
dolphin survey was required in two AFCD designated areas (Northeast and
Northwest Lantau survey areas). The impact dolphin monitoring at each survey
area should be conducted twice per month.
2.1.2
For impact air quality monitoring, monitoring locations
AMS2 (Tung Chung Development Pier) and AMS7 (Hong Kong SkyCity Marriott Hotel)
were set up at the proposed locations in accordance with Project Specific
EM&A Manual. The conditional omission of Monitoring Station AMS6 was
effective since 19 November 2012. For monitoring location AMS3 (Ho Yu College),
as proposed in the Project Specific EM&A Manual, approval for carrying out
impact monitoring could not be obtained from the principal of the school.
Permission on setting up and carrying out impact monitoring works at nearby
sensitive receivers, like Caribbean Coast and Coastal Skyline, was also
sought. However, approvals for
carrying out impact monitoring works within their premises were not obtained.
Impact air quality monitoring was conducted at site boundary of the site office
area in Works Area WA2 (AMS3B) respectively. Same baseline and Action Level for
air quality, as derived from the baseline monitoring data recorded at Ho Yu
College, was adopted for this alternative air quality location.
2.1.3
For impact noise monitoring, monitoring locations NMS2
(Seaview Crescent Tower 1) was set up at the proposed locations in accordance
with Project Specific EM&A Manual. However, for monitoring location NMS3
(Ho Yu College), as proposed in the Project Specific EM&A Manual, approval
for carrying out impact monitoring could not be obtained from the principal of
the school. Permission on setting up and carrying out impact monitoring works
at nearby sensitive receivers, like Caribbean Coast and Coastal Skyline, was also
sought. However, approvals for
carrying out impact monitoring works within their premises were not obtained.
Impact noise monitoring was conducted at site boundary of the site office area
in Works Area WA2 (NMS3B) respectively. Same baseline noise level, as derived
from the baseline monitoring data recorded at Ho Yu College was adopted for
this alternative noise monitoring location.
2.1.4
In accordance with the Project Specific EM&A Manual,
twenty-one stations were designated for impact water quality monitoring. The
nine Impact Stations (IS) were chosen on the basis of their proximity to the
reclamation and thus the greatest potential for water quality impacts, the
seven Sensitive Receiver Stations (SR) were chosen as they are close to the key
sensitive receives and the five Control/ Far Field Stations (CS) were chosen to
facilitate comparison of the water quality of the IS stations with less
influence by the Project/ ambient water quality conditions.
2.1.5
Due to safety concern and topographical condition of the
original locations of SR4 and SR10B, alternative impact water quality
monitoring stations, naming as SR4(N) and SR10B(N), were adopted, which are
situated in vicinity of the original impact water quality monitoring stations
(SR4 and SR10B) and could be reachable. Same baseline and Action Level for
water quality, as derived from the baseline monitoring data recorded, were
adopted for these alternative impact water quality monitoring stations.
2.1.6
The monitoring locations used during the reporting quarter
are depicted in Figures 2, 3 and 4 respectively.
2.1.7
The Project Specific EM&A Manual also required
environmental site inspections for air quality, noise, water quality, chemical,
waste management, marine ecology and landscape and visual impact.
2.2.1
The environmental quality performance limits (i.e. Action
and/or Limit Levels) of air and water quality monitoring were derived from the baseline air and
water quality monitoring
results at the respective monitoring stations, while the environmental quality
performance limits of noise monitoring were defined in the EM&A Manual.
2.2.2
The environmental quality performance limits of air
quality, noise and water monitoring are given in Appendix D.
2.3.1
Relevant environmental mitigation measures were stipulated
in the Particular Specification and EPs (EP-353/2009/G and EP-354/2009/B) (for TMCLKL Southern Landfall
Reclamation only) for the Contractor to adopt. A list of environmental
mitigation measures and their implementation statuses are given in Appendix C.
3.1.1
In accordance with the Project Specific EM&A Manual, impact
1-hour Total Suspended Particulates (TSP) monitoring was conducted for at least
three times every 6 days, while impact 24-hour TSP monitoring was carried out
for at least once every 6 days at the 4 monitoring stations (AMS2, AMS3B, AMS6
and AMS7).
3.1.2
The
monitoring locations for impact air quality monitoring are depicted in Figure
2. However, for AMS6 (Dragonair/CNAC (Group) Building), permission on setting
up and carrying out impact monitoring works was sought, however, access to the
premise has not been granted yet on this report issuing date.
3.1.3
The weather was mostly sunny, with occasional cloudy and occasional rainy in the
reporting quarter. The major dust source in the reporting quarter
included construction activities from the Project, as well as nearby traffic
emissions.
3.1.4
The number of monitoring events and exceedances recorded in
each month of the reporting quarter are presented in Table 3.1 and Table 3.2
respectively.
Table
3.1 Summary of Number of
Monitoring Events for 1-hr & 24-hr TSP Concentration
Monitoring Parameter
|
Location
|
No. of monitoring events
|
March 14
|
April 14
|
May 14
|
1-hr TSP
|
AMS2
|
15
|
18
|
18
|
AMS3B
|
15
|
18
|
18
|
AMS7
|
15
|
18
|
18
|
24-hr TSP
|
AMS2
|
5
|
6
|
6
|
AMS3B
|
5
|
6
|
6
|
AMS7
|
5
|
6
|
6
|
Table
3.2 Summary
of Number of Exceedances for 1-hr & 24-hr TSP Monitoring
Monitoring Parameter
|
Location
|
Level of Exceedance
|
Level of Exceedance
|
March 14
|
April 14
|
May 14
|
1-hr TSP
|
AMS2
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
AMS3B
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
AMS7
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
|
Total
|
0
|
0
|
0
|
24-hr TSP
|
AMS2
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
AMS3B
|
Action
|
1
|
0
|
0
|
Limit
|
0
|
0
|
0
|
AMS7
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
|
Total
|
1
|
0
|
0
|
3.1.5
All 1-Hour TSP results were
below the Action and Limit Level in the reporting quarter. One (1) 24-hour TSP
results recorded at AMS3B exceeded the Action Level in the reporting quarter.
Investigation results show that the Action level exceedance was not related to
Project.
3.1.6
For the 24Hr TSP Action Level
exceedance recorded at AMS3B, a result of 178£gg/m3 was recorded on 11
March 14 (24-hr TSP).
3.1.6.1
According to information provided by the
Contractor, land-based construction activity such transloading stitched
geo-textile and transloading sand bags to barges was being undertaken at Works
Area WA2 during the monitoring period.
3.1.6.2
Functional checking on HVS at AMS3B was done.
Air flow of the HVS was checked and the flow was steady during the 24-hr TSP
sampling at AMS3B. The filter paper was re-weighted by the assigned HOKLAS
laboratory and the result was reconfirmed.
3.1.6.3
As refer to the wind data collected at wind
station at Works Area WA2 during the monitoring period on 10 and 11 March 14,
Southeast to South-southeast winds was prevailing during the monitoring
period. As such, the 24hr-TSP
exceedance is unlikely to be contributed by active works at the HKBCF ¡V
reclamations works which is located North to the monitoring location.
3.1.6.4
The 1-hr TSP values recorded at AMS3B on 11
March14, which are within the monitoring period of the 24-hr TSP, were 83£gg/ m3,
80£gg/ m3 and 81£gg/ m3 respectively. All measured values
are well below the Action and Limit Levels.
3.1.6.5
The measured 24-hr TSP values recorded at AMS2
and AMS7 (which are closer to the marine-based works areas) on the same
monitoring date were 111£gg/m3 and 90£gg/m3, which are
below the Action and Limit Levels.
3.1.6.6
The measured 24-hr TSP values recorded at
AMS3B on next monitoring date were 106£gg/m3, which did not exceed
the Action or Limit Level.
3.1.6.7
The following dust mitigation measures have
been implemented at Works Area WA2:
1. Works Area WA2¡¦s surface was
hard-paved, compacted or hydro-seeded (Please refer to attached layout map and
photo record (View B))
2. Vehicle washing facility was
provided at vehicle exit points,
3. Measures for preventing fugitive
dust emission are provided, e.g. canvas/tarpaulin covers.
View B (Hard paved surface observed at Works Area WA2)
3.1.6.8
The dust exceedance was therefore considered
not to be due to the Project works.
3.1.7
The event action plan is annexed
in Appendix L.
3.1.7.1 Meteorological information
collected from the wind station during the monitoring periods on the monitoring
dates, as shown in Figure 2, including wind speed and wind direction, is
annexed in Appendix H of monthly EM&A report March 2014.
3.2.1
Impact noise monitoring was conducted at the 2 monitoring
stations (NMS2 and NMS3B) for at least once per week during 07:00 ¡V 19:00 in the
reporting quarter.
3.2.2
The monitoring locations used during the reporting quarter are
depicted in Figure 2.
3.2.3
No Action
or Limit Level Exceedance of construction noise was recorded in the
reporting quarter.
3.2.4
Major noise sources during the noise monitoring included
construction activities of the Project and nearby traffic noise.
3.2.5
The number of impact noise monitoring events and exceedances are summarized in
Table 3.3 and Table 3.4 respectively
Table 3.3 Summary
of Number of Monitoring Events for Impact Noise
Monitoring
Parameter
|
Location
|
No.
of monitoring events
|
March 14
|
April 14
|
May 14
|
NMS2
|
4
|
5
|
4
|
NMS3B
|
4
|
5
|
4
|
Table 3.4 Summary
of Number of Monitoring Exceedances for Impact Noise
Monitoring Parameter
|
Location
|
Level of Exceedance
|
Level of Exceedance
|
March 14
|
April 14
|
May 14
|
NMS2
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
NMS3B
|
Action
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
|
Total
|
0
|
0
|
0
|
3.2.6
The graphical
plots of the trends of the monitoring results are provided in Appendix F. No specific trend of the
monitoring results or existence of persistent pollution source was noted.
3.2.7
The event action plan is annexed in Appendix L.
3.3
Water Quality Monitoring
3.3.1
The monitoring locations used during the reporting quarter
are depicted in Figure 3.
Table 3.5 Summary
of Water Quality Exceedances in March
14 ¡V May 14
Station
|
Exceedance
Level
|
DO (S&M)
|
DO (Bottom)
|
Turbidity
|
SS
|
Total
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
IS5
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 19 March 14
|
0
|
1
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS(Mf)6
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS7
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 31 March 14
|
0
|
1
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS8
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS(Mf)9
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 24 March 14
|
(2) 24 and 31
March 14
|
1
|
2
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS10
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 19 March 14
|
1
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS(Mf)11
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS(Mf)16
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
IS17
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 19 March 14
|
0
|
1
|
0
|
SR3
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 19 March 14
|
0
|
1
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR4(N)
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR5
|
Action
|
0
|
0
|
0
|
0
|
(1) 19 March 14
|
0
|
0
|
0
|
1
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR6
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
(1) 31 March 14
|
0
|
1
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR7
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR10A
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
SR10B
(N)
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
Total
|
Action
|
0
|
0
|
0
|
0
|
1
|
0
|
4
|
4
|
9
|
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
1
|
0
|
1
|
Note: S: Surface;
M: Mid-depth;
3.3.3
One (1) Limit level exceedance
of SS was recorded at IS17 at ebb tide; three (3) Action Level exceedances of SS
were recorded at IS5, SR3 at ebb tide and IS10 at flood tide; one (1) Action
Level Exceedance on Turbidity was recorded at SR5 at ebb tide on 19 March 14.
3.3.3.1 Please see above layout map
for work activities carried out on 19 March 14.
3.3.3.2 Exceedance recorded at IS10
during mid-flood tide is unlikely due to marine based construction activities
of the Project because:
3.3.3.3 With reference to the
information provided by the Contractor, same types of work were carried out at
almost the same locations on 17, 19 and 21 March 14, impact water quality
monitoring data recorded on 17 and 21 March 14 are all below the Action and
Limit Level which indicates active works were unlikely to adversely affect the water
quality at IS10.
3.3.3.4 With reference to
monitoring record and photo record taken on 19 and 20 March 2014, no silt plume
was observed on sea near the northwest part of the site which is close to IS10.
(Please see attached photo record)
3.3.3.5
Photo
of sea condition taken near the northwest part of the site (Near IS10) on 19
March 14
3.3.3.6 Photo of sea condition taken near the northwest part of the site (
Near IS 10) on 20 March 14
3.3.3.7 In accordance with the silt
curtain integrity checking record, no disconnection was observed at the
northwest part of site which is near IS10.
3.3.3.8 Turbidity level recorded at
IS10, SR5 and IS(Mf)11 were below the action and limit level. This indicates
the turbidity level at area near IS10 was not adversely affected.
3.3.3.9 The exceedance was likely
due to local effects in the vicinity of IS10.
3.3.3.10 As such, the exceedance
recorded at IS10 is unlikely to be project related.
3.3.3.11 For the action Level
Exceedance on Turbidity recorded at SR5 on 19 March 14.
3.3.3.12 in situ measurement was
repeated to confirm findings;
3.3.3.13 The monitoring location of
monitoring station SR5 is considered upstream to the active works of this project
during ebb tide. Therefore it appears that it was unlikely that the exceedance
recorded at SR5 was due to active construction activities of this project;
3.3.3.14 IEC, contractor and ER were
informed via email;
3.3.3.15 Monitoring data, all plant,
equipment and Contractor's working methods were checked;
3.3.3.16 Since it is considered that
the exceedance at SR5 is unlikely to be project related, as such, actions 5 - 7
under the EAP are not considered applicable.
3.3.3.17 Exceedance recorded at SR5
during mid-ebb tide are unlikely due to marine based construction activities of
the Project because:
3.3.3.18 With reference to the
information provided by the Contractor, same types of work were carried out at
almost the same locations on 17, 19 and 21 March 14, impact water quality
monitoring data recorded on 17 and 21 March 14 are all below the Action and
Limit Level which indicates active works were unlikely to adversely affect the
water quality at SR5.
3.3.3.19 The monitoring location of
monitoring station SR5 is considered upstream to the active works of this
project during ebb tide. Therefore it appears that it was unlikely that the
exceedance recorded at SR5 was due to active construction activities of this
project.
3.3.3.20 With reference to the silt
curtain checking record no defects was observed at parts of the perimeter silt
curtain which are close to the SR5.
3.3.3.21 The exceedance was likely
due to local effects in the vicinity of SR5.
3.3.3.22 As such, the exceedance
recorded at SR5 is unlikely to be project related.
3.3.3.23 Exceedance recorded at SR3
during mid-ebb tide are unlikely due to marine based construction activities of
the Project because:
3.3.3.24 With reference to the
information provided by the Contractor, same types of work were carried out at
almost the same locations on 17, 19 and 21 March 14, impact water quality
monitoring data recorded on 17 and 21 March 14 are all below the Action and
Limit Level which indicates active works were unlikely to adversely affect the
water quality at SR3.
3.3.3.25 The monitoring location of
monitoring station SR3 is considered upstream to the active works of this
project during ebb tide. Therefore it appears that it was unlikely that the
exceedance recorded at SR3 was due to active construction activities of this
project.
3.3.3.26 With reference to the silt
curtain checking record no defects was observed at parts of the perimeter silt
curtain which are close to the SR3.
3.3.3.27 The exceedance was likely
due to local effects in the vicinity of SR3.
3.3.3.28 As such, the exceedance
recorded at SR3 is unlikely to be project related.
3.3.3.29 Exceedance recorded at IS5
during mid-ebb tide are unlikely due to marine based construction activities of
the Project because:
3.3.3.30 With reference to the
information provided by the Contractor, same types of work were carried out at
almost the same locations on 17, 19 and 21 March 14, impact water quality
monitoring data recorded on 17 and 21 March 14 are all below the Action and
Limit Level which indicates active works were unlikely to adversely affect the
water quality at IS5.
3.3.3.31 The monitoring location of
monitoring station IS5 is considered upstream to the active works of this
project during ebb tide. Therefore it appears that it was unlikely that the
exceedance recorded at IS5 were due to active construction activities of this
project.
3.3.3.32 With reference to the silt
curtain checking record no defects was observed at parts of the perimeter silt
curtain which are close to the IS5.
3.3.3.33 The exceedance was likely
due to local effects in the vicinity of IS5.
3.3.3.34 As such, the exceedance
recorded at IS5 is unlikely to be project related.
3.3.3.35 Exceedance recorded at IS17
during mid-ebb tide are unlikely due to marine based construction activities of
the Project because:
3.3.3.36 With reference to the
information provided by the Contractor, same types of work were carried out at
almost the same locations on 17, 19 and 21 March 14, impact water quality
monitoring data recorded on 17 and 21 March 14 are all below the Action and
Limit Level which indicates active works were unlikely to adversely affect the
water quality at SR5, IS5, SR3 and IS17.
3.3.3.37 With reference to
monitoring record and photo record taken on 19 and 20 March 2014, no silt plume
was observed on sea near the northeast part of the site which is close to IS17.
(Please see attached photo record)
3.3.3.38 Photo of sea condition
taken near the northeast part of the site (Near IS17) on 19 March 14.
3.3.3.39 Photo of sea condition
taken near the northeast part of the site (Near IS17) on 20 March 14.
3.3.3.40 With reference to the silt
curtain checking record no defects was observed at parts of the perimeter silt
curtain which are close to the locations where the exceedance was recorded
during mid-ebb tide.
3.3.3.41 Turbidity level recorded at
IS(Mf)11, IS17 and IS(Mf)16 were below the action and limit level. This indicates the
turbidity level at area near IS17 was not adversely affected.
3.3.3.42 The exceedance is likely
due to local effects in the vicinity of IS17.
3.3.3.43 As such, the exceedance
recorded at IS17 is unlikely to be project related.
3.3.3.44 Nevertheless, the
Contractor was reminded to ensure provision of ongoing maintenance to the silt
curtains and to carry out maintenance work once defects were found.
3.3.3.45
Maintenance
work of the silt curtain was carried out by the Contractor on a daily basis
except Sunday and public holiday.
3.3.4
Two (2) Action Level exceedances
of SS were recorded at IS(Mf)9 were recorded during mid flood tide and mid ebb
tide respectively on 24 March 14.
3.3.4.1
Please see above layout map for work activities carried out on 24 March
14.
3.3.4.2
In accordance with the silt curtain integrity checking record, deficiency
such as missing segments at one end of the perimeter silt curtain at the
southern marine access was noted. This part of the perimeter silt curtain is
close to IS(Mf)9. The Contractor
was reminded to ensure provision of ongoing maintenance to the silt curtains
and to carry out maintenance work once defects were found and maintenance work
of the silt curtain was carried out by the Contractor on a daily basis except
Sunday and public holiday.
3.3.4.3
However, exceedances recorded at IS(Mf)9 recorded during mid-Ebb tide
and mid-Flood tide are unlikely due to marine based construction activities of
the Project because:
3.3.4.4
With reference to the information provided by the Contractor, same
types of work were carried out at almost the same locations on 21, 24 and 26
March 2014, impact water quality monitoring data recorded on 21 and 26 March
2014 are all below the Action and Limit Level which indicates active works as
shown on the layout map attached is unlikely to adversely affect the water
quality at IS(Mf)9.
3.3.4.5
Mitigation measures such as localised silt curtain was implemented for
stone column installation. (Please refer to the photo record)
3.3.4.6
Also, in accordance with the monitoring record, no silt plume was
observed to flow from the inside of the perimeter silt curtain to the outside
of the perimeter silt curtain during impact water quality monitoring on 24
March 2014. (Please refer to the photo attached which shows the sea condition
near IS(Mf)9 on 24 March 2014.)
3.3.4.7
Photo of silt curtain near south part of the site IS(Mf)9 on 24 March
2014.
3.3.4.8
With referred to the monitoring data, turbidity level recorded at IS7,
IS(Mf)9, IS8 and IS(Mf)16 were below the action and limit level. This indicates
the turbidity level at area near IS(Mf)9 was not adversely affected.
3.3.4.9
In addition, with referred to the monitoring data, the Suspended Solids
recorded at IS7, IS8 and IS(Mf)16 were below the action and limit level. This
indicates the Suspended Solids at areas next to IS(Mf)9 was not adversely
affected.
3.3.4.10 The exceedance
was likely due to local effects in the vicinity of IS(Mf)9.
3.3.4.11 As such, the
exceedance recorded at IS(Mf)9 is unlikely to be project related.
3.3.4.12 Nonetheless,
the Contractor was reminded to ensure provision of ongoing maintenance to the
silt curtains and to carry out maintenance work once defects were found.
3.3.4.13 Maintenance
work of the silt curtain was carried out by the Contractor on a daily basis
except Sunday and public holiday
3.3.5
Three (3) Action Level
exceedances of SS were recorded at IS(Mf)9, IS7 and SR6 during mid flood tide
on 31 March 2014.
3.3.5.1
Please see above layout map for work activities carried out on 31 March
14.
3.3.5.2
IS10 and SR5 which are located downstream and closer to active works
than SR6. No Action and Limit Level exceedance was recorded at IS10 and SR5
during mid flood tide on 31 March 2014 and this indicates that the water
quality noted at downstream and closer to active works were not adversely
affected, hence it is considered that the exceedance recorded at SR6 are not
related to the Project.
3.3.5.3
Same type of works was carried out at almost the same locations on 28
and 31 March 2014 but Suspended Solids values recorded at 28 March 2014 are all
below the Action and Limit Level during mid-flood tide, this indicates active
works as shown on the layout map attached is unlikely to contribute to the
exceedances recorded at IS(Mf)9, IS7 and SR6.
3.3.5.4
With reference to layout map attached, construction activity close to
IS(Mf)9 and IS7 such as band drain installation was conducted at southeast part
of portion B, since band drain is considered unlikely to cause silt plume.
Therefore, the exceedances are unlikely attributed to construction activity
close to IS(Mf)9 and IS7.
3.3.5.5
In accordance with the silt curtain integrity checking record, defects
such as missing segments at southern marine access at one end of the perimeter
silt curtain was noted. This part of the perimeter silt curtain is close to
IS(Mf)9. The Contractor was
reminded to ensure provision of ongoing maintenance to the silt curtains and to
carry out maintenance work once defects were found and maintenance work of the
silt curtain was carried out by the Contractor on a daily basis except Sunday
and public holiday.
3.3.5.6
However, in accordance with the monitoring record, no silt plume was
observed outside the perimeter silt curtain near IS(Mf)9 and IS7 on 31 March
2014. (Please refer to the photo below which shows the sea condition near
IS(Mf)9 on 31 March 2014.)
3.3.5.7
With referred to the monitoring data, turbidity level recorded at
IS(Mf)6, IS7, IS(Mf)9, IS8 and IS(Mf)16 were below the action and limit level.
This indicates the turbidity level at area near IS(Mf)9 and IS7 were not
adversely affected.
3.3.5.8
The exceedances are likely due to local effects in the vicinity of
IS(Mf)9, IS7 and SR6.
3.3.5.9
As such, the exceedances recorded at IS(Mf)9, IS7 and SR6 were unlikely
to be project related.
3.3.5.10 Nonetheless,
the Contractor was reminded to ensure provision of ongoing maintenance to the
silt curtains and to carry out maintenance work once defects were found.
3.3.5.11 Maintenance
work of the silt curtain was carried out by the Contractor on a daily basis
except Sunday and public holiday.
3.3.5.12 The event
action plan is annexed in Appendix L.
3.4.2
The impact dolphin monitoring conducted is vessel-based and
combines line-transect and photo-ID methodology, which have adopted similar
survey methodologies as that adopted during baseline monitoring to facilitate
comparisons between datasets.
3.4.3
The layout map of impact dolphin monitoring have been
provided by AFCD and is shown in Figure 4.
3.4.4
The effort summary and sighting details during the
reporting quarter are
shown in the Appendix H. A summary of key findings of the dolphin
surveys completed during the reporting quarter is shown below:
Table 3.6 Summary
of Key Dolphin Survey Findings in March ¡V May 2014
Number of Impact Surveys Completed^
|
6
|
Survey Distance Travelled under Favourable On-
Effort Condition
|
662.7km
|
Number of Sightings
|
15 sightings (11 sightings are ¡¨on effort¡¨
(which are all under favourable condition), 4 ¡§sightings are opportunistic¡¨)
|
Number of dolphin individual sighted
|
46 individuals (the best estimated group
size)
|
Dolphin Encounter Rate#
|
NEL: 0.0
NWL: 2.5
|
Dolphin Group Size
|
Average of NEL: 0.0
Average of NWL: 3.1
Varied from 1-12 individuals
|
Most Often frequent dolphin sighting area
|
Sha Chau and Lung Kwu Chau Marine Park, the
western limit of NWL.
|
Remarks:
^ Completion of line
transect survey of NEL and NWL survey area once was counted as one complete
survey.
# Dolphin Encounter Rate = (Sum of 1st 2nd, 3rd
month¡¦s total sighting/ Sum of 1st , 2nd,
3rd month¡¦s total effort)*100km (encounter
rates are calculated using on effort sightings made under favourable conditions
only.)
3.4.5
One
(1) Limit Level
exceedances were recorded
in the reporting quarter. The investigation results showed that there is no
evidence that exceedances are related to Project works are annexed in Appendix
L. Actions were taken according to the Event and Action Plan for impact dolphin
monitoring. Please refer to Appendix L for details of action taken.
*Quarterly Average Encounter Rate of Number of Dolphin Sightings (STG)
presents averaged encounter rates of the three monitored months in terms of
groups per 100km per survey event.
STG Encounter rate = (Average of (total number sighting/total effort) of
1st and 2nd completed survey# of 1st month+ Average of (total number
sighting/total effort) of 1st and 2nd completed survey# of 2nd month + Average
of (total number sighting/total effort) of 1st and 2nd completed survey# of 3rd
month)/3*100km
**Quarterly Average Encounter Rate of Total Number of Dolphins (ANI)
presents averaged encounter rates of the three monitored months in terms of
individuals per 100km per survey event.
ANI Encounter rate = (Average of (total number of Individual/total
effort) of 1st and 2nd completed survey# of 1st month+ Average of (total number
of Individual/total effort) of 1st and 2nd completed survey# of 2nd month +
Average of (total number of Individual/total effort) of 1st and 2nd completed
survey# of 3rd month +)/3*100km
3.4.6
Details of the comparison and analysis methodology and
their findings and discussions are annexed in Appendix H.
3.5.1 Site
Inspections were carried out on a weekly basis to monitor the implementation of
proper environmental pollution control and mitigation measures for the Project.
In the reporting quarter, 13 site inspections
were carried out. Recommendations on remedial actions were given to the
Contractors for the deficiencies identified during the site audits.
3.5.2
Particular observations during the site inspections are
described below:
Air Quality
3.5.3
Exposed soil observed fully loaded on barge at near Portion
D and C2a. The Contractor was reminded to provide dust control measures and
keep the surface of all exposed soil wet and the Contractor was reminded to use
suitable barge to store public fill to prevent potential runoff to the
surrounding. (Reminder)
3.5.4
Exposed earth was observed at Works Area of Portion A. The
Contractor was reminded to provide dust control measures such as to treat the
exposed earth by compaction. The Contractor provided dust control measures such
as to treat the exposed earth by compaction. (Closed)
3.5.5
Sprinkler system and sprinkler timer were observed properly
implemented at TKO Fill Bank Area 137. The Contractor was reminded to continue
proper implementation of sprinkler system to prevent potential generation of
fugitive dust. (Reminder)
3.5.6
Vehicle equipped with watering system was observed
implemented on exposed sand. The Contractor was reminded to continue to
implement such dust control measures 8 times per day. (Reminder)
3.5.7
Dark smoke was observed emitted by a vessel. The Contractor
was reminded that dark smoke emission from plant/equipment should be avoided.
(Reminder)
3.5.8
Fugitive dust was observed generated on site at Portion D.
The Contractor provided dust suppression measures such a compaction and
watering to exposed soil. The Contractor was reminded to review the
effectiveness of the abovementioned mitigation measures and to review the need
to provide enhancement on current measures. In addition, high pressure water
jet was observed at site entrance at Portion D, Nonetheless, the Contractor was
reminded to review the need to enhance the wheel washing facility to effectively
prevent potential trail of mud outside site boundary cause by site vehicles.
(Reminder)
Noise
3.5.9
Generator was observed without acoustic decoupling measures
on barge¤ÑÂ@ 3. The Contractor was reminded to install acoustic
decoupling measure prior to leaving Portion A. (Reminder)
Chinese White Dolphin
3.5.10
No adverse observation was identified in the reporting
month.
Water Quality
3.5.11
Chemical retaining bunding on barge SHB401 was not properly
plugged. The Contractor should seal the bunding entirely to retain leakage, if
any. The Contractor has sealed the bunding. (Closed)
3.5.12
Oil drum was not properly stored on barge §»¶§®c106,
Works Area of Portion A, barge ¤ÑÂ@3 and on temporary
rock bund. The Contractor should store oil drum within the chemical retaining
bunding. Drip tray was provided for the oil drum at barge §»¶§®c106 to
retain potential leakage. However, some oil drums were still observed not
properly stored. The Contractor should continue to store oil drum within the
bunding (Closed)
3.5.13
Generators at Portion A were placed on bare ground without
the provision of drip tray. The Contractor should provide mitigation measures
such as drip trays to prevent potential oil leakage. Drip tray was provided for
some of the generators to retain potential leakage. However, a generator was still
observed place on bare ground without the provision of drip tray. The
Contractor should continue to provide mitigation measures such as drip trays to
prevent potential oil leakage. (Closed)
3.5.14
Water was observed accumulated inside car tyre on barge AP3
and in side drip tray at C2a near the blue conveyor belts and other areas. The
Contractor was reminded to regularly clear water accumulated inside car tire
drip tray at C2a near the blue conveyor belts and kept the site clean and tidy.
The Contractor removed the car tyre and cleared the water inside drip tray at
C2a and kept the site clean and tidy. (Closed)
3.5.15
Tools were observed stored inside drip tray with oil drums
on barge AP3. The Contractor was reminded to properly store the equipments
other than oil drums at area outside drip tray. The Contractor removed the
equipments other than oil drums from area inside drip tray. (Closed)
3.5.16
Oil drum was observed not closed, the Contractor was
reminded that every chemical waste containers should be securely closed, correctly
placed and kept clean. The Contractor properly closed chemical waste
containers. (Closed)
3.5.17
Idle stone column installation was observed without
localised silt curtain at barge AP2. The Contractor was reminded that active
stone column installation shall be fullly enclosed by localised silt curtain
prior to operation. (Reminder)
3.5.18
Active stone column installation was observed not properly
enclosed. The Contractor is reminded that sufficient silt curtain shall be
installed to fully enclose the active stone column installation points. The
Contractor is provided silt curtain to fully enclose the active stone column
installation points. (Closed)
3.5.19
The Contractor was reminded that the chemical waste containers
should be kept in good condition and free from damage or any other defects
which may impair the performance of the containers (Closed)
3.5.20
Stockpile of soil was observed on barge AP3 at Portion D,
the Contractor was reminded to provide measures to prevent potential runoff
during rainstorm. (Reminder)
Chemical and Waste Management
3.5.21
General refuse and disconnected silt curtain were observed
not properly allocated on §»¶§®c106, Portion
A¡¦s waste collection point and on the way from Portion D to C2a. The
Contractor should keep the barge clean and tidy and collect the refuse
and the disconnected silt curtain presented in the water within and adjacent to
the works site. The refuse was
cleared. The Contractor was reminded to provide proper storage for general
refuse such as rubbish bin with lid. (Closed)
3.5.22
Big bag was observed
improperly stored on barge AP3. The Contractor was reminded to provide proper
storage for general refuse such as rubbish bin with lid. The Contractor cleared
the rubbish bag. The Contractor was reminded to provide proper storage for
general refuse such as rubbish bin with lid. (Closed)
3.5.23
Rubbish was observed at
the edge of Works Area at Portion A, temporary Rock Bund and on sea next to the
temporary rock bund. The Contractor was reminded to regularly clear the rubbish
on site and keep the site clean and tidy. Collection and clearing of rubbish
was observed conducted by the Contractor at certain areas of Works Area at
Portion A. However, rubbish was still observed at various locations on Works
Area of Portion A. The Contractor was reminded to continue provide rubbish bin,
regularly collect the rubbish on site and keep the site clean and tidy.
(Closed)
3.5.24
Stone and gravel were observed inside drip tray containing
oil drums. The Contractor was reminded to relocate the drip tray with the oil
drums to avoid the situation. The situation has been rectified. (Closed.)
3.5.25
Used band drains were observed stored on site at Portion A.
The Contractor was reminded to regularly collect and dispose the used band drain
materials. The Contractor cleared unwanted band drains regularly. Band drain
material and general refuse were observed at the road side at Portion A. The
Contractor cleared general refuse stored on site. Nonetheless, the Contractor
was reminded to clear unwanted band drain and other general refuse stored on
site regularly. (Reminder)
3.5.26
General refuse and disconnected silt curtain were observed
next to cellular structure, at Portion A¡¦s waste collection point and on the
way from Portion D to C2a. The Contractor was reminded to collect the refuse
and the disconnected silt curtain presented in the water within and adjacent to
the works site. The Contractor collected the refuse presented in the water
within and adjacent to the works site. The Contractor was reminded to review
the need to increase frequency to clear and dispose of the waste at waste
collection point to avoid accumulation. (Reminder)
Landscape and Visual Impact
3.5.27
No relevant works was carried out in the reporting Quarter.
Others
3.5.28
Rectifications of remaining
identified items are undergoing by the Contractor. Follow-up inspections on the
status on provision of mitigation measures will be conducted to ensure all
identified items are mitigated properly.
4
Advice on the Solid and Liquid
Waste Management Status
4.1.1
The Contractor registered as a chemical waste producer for
this project. Sufficient numbers of receptacles were available for general
refuse collection and sorting.
4.1.2
As advised by the Contractor, 3,588,233.0 m3 of
fill were imported for the Project use in the reporting period. 24 kg of paper/
carboard packaging and 40 kg of metal were generated, 2.4 tonnes of chemical
waste and 344.5 m3 of general refuse were generated and disposed of
in the reporting period. Monthly summary of waste flow table is detailed in
Appendix I.
4.1.3
The Contractor is advised to properly maintain on site
C&D materials and wastes collection, sorting and recording system, dispose
of C&D materials and wastes at designated ground and maximize reuse /
recycle of C&D materials and wastes. The Contractor is reminded to properly
maintain the site tidiness and dispose of the wastes accumulated on site
regularly and properly.
4.1.4
The Contractor is reminded that chemical waste containers
should be properly treated and stored temporarily in designated chemical waste
storage area on site in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes.
5.1.1
In response to the site audit findings, the Contractors
carried out corrective actions.
5.1.2
A summary of the Implementation Schedule of Environmental Mitigation
Measures (EMIS) is presented in Appendix C. Most of the recommended mitigation
measures are being upheld. Moreover, regular review and checking on the
construction methodologies, working processes and plants were carried out to
ensure the environmental impacts were kept minimal and recommended
environmental mitigation measures were implemented effectively.
5.1.3
Training of marine travel route for marine vessels operator
was given to relevant staff and relevant records were kept properly.
5.1.4
Regarding the implementation of dolphin monitoring and
protection measures (i.e. implementation of Dolphin Watching Plan, Dolphin
Exclusion Zone and Silt Curtain integrity Check), regular checks were conducted
by experienced MMOs within the works area to ensure that no dolphins were
trapped by the silt curtain area. There were no dolphins spotted within the
silt curtain during this quarter. The relevant procedures were followed and all
measures were well implemented. The silt curtains were also inspected in
accordance to the submitted plan.
6
Summary of Exceedances of the
Environmental Quality Performance Limit
6.1.1
All 1-Hour TSP results were below
the Action and Limit Level in the reporting quarter. One (1) 24-hour TSP
results recorded at AMS3B exceeded the Action Level in the reporting quarter.
Investigation results show that the Action level exceedance was not related to
Project.
6.1.2
For construction noise, no exceedance was recorded at all
monitoring stations in the reporting period.
6.1.3
Eight (8) Action Level Exceedances were recorded at
measured suspended solids (SS) values (in mg/L) in the reporting Quarter. One (1) Limit Level exceedance was recorded at measured
suspended solids (SS) values (in mg/L) in the reporting quarter. One (1) Action
level exceedance was recorded at measured turbidity values (in NTU) in the
reporting quarter. Investigation results shows that all the Action and Limit
Level Exceedance recorded were non-project related.
6.1.4
One (1) limit level exceedances of Chinese White Dolphin
monitoring were recorded in the reporting quarter. Investigation results show
that there is no evidence that exceedances are related to Project works. Event and Action Plan for Impact Dolphin
Monitoring was triggered. For detail of investigation, please refer to appendix
L.
6.1.5
Cumulative statistics on exceedances is provided in
Appendix J.
7
Summary of Complaints, Notification
of Summons and Successful Prosecutions
7.1.1
The Environmental Complaint Handling Procedure is annexed
in Figure 5.
7.1.2
EPD referred a complaint on 17 March 2014 from complainant
who advised that there was sea water colored in blue observed in vicinity of
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Facilities (HKBCF) where stone
column installation was taking place. The complainant suspected that the
filling material was stained and contaminated the sea water after being filled
into the sea.
7.1.2.1 Staining
material, stained filling material or blue colored sea water was not observed
during a follow-up site in section audit conducted with the representatives of
the Contractor, Residential Engineer and IEC/ENPO on 20 March 14. The photo
record taken during the joint site inspection audit was attached.
7.1.2.2 The
locations of stone column installation (please refer to the attached layout map
for the locations of stone column installation) and impact water quality
monitoring data recorded between 12 ¡V 17 March14 were reviewed. In accordance
with the monitoring records, no discoloration of sea water or silty plume
appearance outside the seawall was observed during the water quality monitoring
between 12 ¡V 17 March14. Also, no
Action/ Limit level exceedance of water quality was recorded in the vicinities
where stone column installation was carried out.
7.1.2.3 In
addition, mitigation measure for active stone column installation such as
localised silt curtain was implemented in March 14. Please see below photo record for
reference.
7.1.2.4 Therefore,
with reference to the available information, it is indicated that the
abovementioned sea water colored in blue observed in vicinity of HKBCF is
unlikely to be project related.
7.1.3
EPD referred a complaint from a complainant who advised
that muddy water was found being discharged from the construction site of Hong
Kong-Zhuhai-Macau Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V
Reclamation Works on 22 March 2014.
7.1.3
7.1.3.1
No silt plume or muddy water was observed being discharged from
HKBCF ¡V Reclamation Works during a follow-up site inspection audit conducted
with the representatives of the Contractor and Residential Engineer 27 March
2014. Please see below photo record for reference.
7.1.3.2
The locations of stone column installation (please refer to
the attached layout map for the locations of stone column installation) and
impact water quality monitoring data recorded on 21 March 2014 were reviewed.
In accordance with the monitoring records, no discoloration of sea water or
silty plume appearance outside the perimeter silt curtain was observed during
the water quality monitoring conducted on 21 March 2014. Also, no Action/ Limit level exceedance
of water quality was recorded in the vicinities where stone column
installations were carried out.
7.1.3.3
In addition, with referred to the photo record attached,
mitigation measure for active stone column installation such as localised silt
curtain was implemented in March 2014.
Please see below photo record for reference.
7.1.3.4
Therefore, with reference to the available information, it
is indicated that the abovementioned complaint of muddy water which was found
being discharged from the construction site of Hong Kong-Zhuhai-Macau Bridge
HKBCF ¡V Reclamation Works on 22 March 2014 is unlikely to be project related.
7.1.3.5
Nevertheless, the Contractor was recommended to continue
implementing existing water quality mitigation measures.
7.1.4
As informed by the Contractor, a complaint was received by
the Contractor on 25 March 14 concerning sand and dust emission from uncovered
barges parking at the sea area off the Tuen Mun Ferry Pier.
7.1.4
7.1.4.1
As informed by the Contractor 7-10 trips of sand barges per
week would stay at the concerned area.
7.1.4.2
However, base on the available information; it is unable to
conclude whether the complaint it is project related, because:
1.There is
no sufficient information provided by the complainant to make sure that the
concerned barges are related to this project.
2.The sand
barges at the construction site of the reclamation works were regularly checked
and so far, all sand barges were observed equipped with watering equipment.
3.Photo
record below shows that watering equipment was used to keep the sand filling
material wet.
7.1.4.3
Photo record shows that watering equipment was provided on
pelican barge loaded with sand for watering of sand filling material to keep
the sand material wet:
7.1.4.4
Nevertheless, the Contractor was reminded to continue to
properly implement all dust mitigation measures.
7.1.4.5
The Contractor was advised to ensure to continue the
provision of fugitive dust mitigation measures to barges loaded with filling
material such as watering to sand filling material on sand barges to keep the
surface of stockpile of filling material wet.
7.1.4.6
As informed by the Contractor, skipper of all working
barges would be reminded to beware and to pay particular attention to the issue
concerning sand and dust emission from uncovered barges parking at the sea area
off the Tuen Mun Ferry Pier.
7.1.5
As informed by the Contractor,
further to the notification of summons received March 2014 due to works carried
out on 6 October 13 contrary to conditions of NCO, Cap.400. The Contractor
pledged guilty to the charge during the court appearance on 28 April 2014.
7.1.5
7.1.5.1
The Contractor has established noise control management system
on restricted hour works, to prevent future violation of conditions of NCOs,
Cap. 400, actions taken include:
-
Nominate CNP Supervisors to
daily check CNP compliance
-
Setup a white board system to
present the works, with locations & no. of machineries, needed to be
carried out during restricted hours
-
Erect CNP markers for
demarcation on site
-
Provide relevant training to
staff
7.1.5.2
Regular site audit and inspection and monitoring records show
no information of recurrence of non-compliance in the reporting month.
7.1.5.3
No notification of summons was received in April.
7.1.6
As informed by the Contractor on
7 May 14, a complaint was received by the Contractor on 17 April 14 concerning
sand and dust emission from uncovered barges parking at the sea area off the
Tuen Mun Ferry Pier.
7.1.6
7.1.6.1
As informed by the Contractor 7-10 trips of sand barges per
week would stay at the concerned Area.
7.1.6.2
However, because no extra information was received for this
complaint after the release of last investigation report, with referred to the
available information; it is unable to conclude whether the complaint is
related to this Contract because:
1.
There is no sufficient information provided by the
complainant to make sure that the concerned barges are related to this project.
2.
The sand barges at the construction site of the
reclamation works were regularly checked and so far, all sand barges were
observed equipped with watering equipments.
3.
Photo record below shows that watering equipment
was used to keep the sand filling material wet.
7.1.6.3
Photo record shows that watering equipment was provided on
pelican barge loaded with sand for watering of sand filling material to keep
the sand material wet:
7.1.6.4
Nevertheless, the Contractor was reminded to continue to
properly implement all dust mitigation measures.
7.1.6.5
The Contractor was advised to ensure to continue the
provision of fugitive dust mitigation measures to barges loaded with filling
material such as watering to sand filling material on sand barges to keep the
surface of stockpile of filling material wet.
7.1.6.6
As informed by the Contractor, skipper of all working
barges would further be reminded to beware and to pay particular attention to
the issue concerning sand and dust emission from uncovered barges parking at
the sea area off the Tuen Mun Ferry Pier.
7.1.7
As informed by the Contractor on
30 May 2014, an environmental complaint had been received on 28 May 2014. The complainant
mentioned that waste such as earth and concrete were being felled into the sea
everyday at the Hong Kong-Zhuhai-Macao Bridge at location where construction
works are being conducted, causing pollution to the marine environment.
7.1.7
7.1.7.1
Site inspections were conducted and project documents were
reviewed, please see the following for details of investigation actions and
results:
7.1.7.2
Regular site inspection was conducted on 29 May 2014 and a
follow up site inspection was conducted on 5 June 2014 at HKBCF Reclamation
Works, waste such as concrete and earth were not observed being felled into the
sea.
7.1.7.3
The waste flow record provided by the Contractor has been
reviewed (please see attached), the waste flow record shows that waste
described by the complainant (i.e. concrete or earth) were not generated by
this Contract.
7.1.7.4
In addition, the construction programme provided by the
Contractor (Please see construction program attached) has been reviewed and it
is noted that concrete and earth were not used as marine fill for any on-going
construction activities of this Contract in May 2014. Also, all filling works were conducted
inside the designated work zone inside the site boundary of HKBCF Reclamation
Works. Furthermore, impact water
quality monitoring result of May 2014 has been reviewed and no impact water
quality exceedance was recorded in May 2014, this indicates that the works
carried by this Contract is unlikely to cause pollution to the marine
environment.
7.1.7.5
As such, with referred to the available information, it is
concluded that the complaint is unlikely to be related to this Contract.
7.1.7.6
Nevertheless, the Contractor was reminded to continue to
properly implement all water quality mitigation measures and strictly follow
the waste handling procedure according of this Contract.
7.1.7.7
No notification of summons and successful prosecutions was
received in May.
7.1.8
Statistics on complaints,
notifications of summons and successful prosecutions are summarized in Appendix
N.
8.1
Comments on mitigation
measures
8.1.1
According
to the environmental site inspections performed in the reporting quarter, the
following recommendations were provided:
Air
Quality Impact
l All
working plants and vessels on site should be regularly inspected and properly
maintained to avoid dark smoke emission.
l All vehicles should be washed to
remove any dusty materials before leaving the site.
l Haul roads should be sufficiently
dampened to minimize fugitive dust generation.
l Wheel washing facilities should be
properly maintained and reviewed to ensure properly functioning.
l Temporary exposed slopes and open
stockpiles should be properly covered.
l Enclosure should be erected for
cement debagging, batching and mixing operations.
l Water spraying should be provided to suppress fugitive dust for any dusty
construction activity.
Construction
Noise Impact
l Quieter powered mechanical
equipment should be used as far as possible.
l Noisy operations should be
oriented to a direction away from sensitive receivers as far as possible.
l Proper and effective noise
control measures for operating equipment and machinery on-site should be
provided, such as erection of movable noise barriers or enclosure for noisy
plants. Closely check and replace the sound insulation materials regularly
l Vessels and equipment operating
should be checked regularly and properly maintained.
l Noise Emission Label (NEL) shall
be affixed to the air compressor and hand-held breaker operating within works
area.
l Better scheduling of construction
works to minimize noise nuisance.
l Acoustic decoupling measures
should be properly implemented for all existing and incoming construction
vessels with continuous and regularly checking to ensure effective
implementation of acoustic decoupling measures.
Water
Quality Impact
l Regular review and maintenance of
silt curtain systems, drainage systems and desilting facilities in order to
make sure they are functioning effectively.
l Construction of seawall should be
completed as early as possible.
l Regular inspect and review the
loading process from barges to avoid splashing of material.
l Silt, debris and leaves
accumulated at public drains, wheel washing bays and perimeter u-channels and
desilting facilities should be cleaned up regularly.
l Silty effluent should be treated/
desilted before discharged. Untreated effluent should be prevented from
entering public drain channel.
l Proper drainage channels/bunds
should be provided at the site boundaries to collect/intercept the surface
run-off from works areas.
l Exposed slopes and stockpiles should
be covered up properly during rainstorm.
Chemical
and Waste Management
l All types of wastes, both on land
and floating in the sea, should be collected and sorted properly and disposed
of timely and properly. They should be properly stored in designated areas
within works areas temporarily.
l All chemical containers and oil
drums should be properly stored and labelled.
l All plants and vehicles on site
should be properly maintained to prevent oil leakage.
l All kinds of maintenance works should
be carried out within roofed, paved and confined areas.
l All drain holes of the drip trays
utilized within works areas should be properly plugged to avoid any oil and
chemical waste leakage.
l Oil stains on soil surface and
empty chemical containers should be cleared and disposed of as chemical waste.
l Regular review should be
conducted for working barges and patrol boats to ensure sufficient measures and
spill control kits were provided on working barges and patrol boats to avoid
any spreading of leaked oil/chemicals.
Landscape
and Visual Impact
l All existing,
retained/transplanted trees at the works areas should be properly fenced off
and regularly inspected.
8.2
Recommendations on EM&A Programme
8.2.1
The impact monitoring programme for air quality, noise, water
quality and dolphin ensured that any deterioration in environmental condition
was readily detected and timely actions taken to rectify any non-compliance.
Assessment and analysis of monitoring results collected demonstrated the
environmental impacts of the Project. With implementation of recommended
effective environmental mitigation measures, the Project¡¦s environmental
impacts were considered as environmentally acceptable. The weekly environmental
site inspections ensured that all the environmental mitigation measures
recommended were effectively implemented.
8.2.2
The recommended environmental mitigation measures, as
included in the EM&A programme, effectively minimize the potential
environmental impacts from the Project. Also, the EM&A programme effectively
monitored the environmental impacts from the construction activities and ensure
the proper implementation of mitigation measures. No particular recommendation
was advised for the improvement of the programme.
8.3
Conclusions
8.3.1
The construction phase and EM&A programme of the
Project commenced on 12 March 2012.
8.3.2
All 1-Hour TSP results were below the Action and Limit
Level in the reporting quarter. One (1) 24-hour TSP results recorded at AMS3B
exceeded the Action Level. Investigation results show that the Action level
exceedance was not related to Project.
8.3.3
For construction noise, no exceedance was recorded at all
monitoring stations in the reporting period.
8.3.4
Eight (8) Action Level Exceedances were recorded at measured
suspended solids (SS) values (in mg/L) in the reporting Quarter. One (1) Limit
Level exceedance was recorded at measured suspended solids (SS) values (in
mg/L) in the reporting quarter. One (1) Action level exceedance was recorded at
measured turbidity values (in NTU) in the reporting quarter.
8.3.5
Investigation results shows that all the Action and Limit
Level Exceedance recorded were non-project related.
8.3.6
One (1) Limit Level exceedances were recorded for Chinese
White Dolphin monitoring in the reporting quarter. Investigation results show
that there is no evidence that exceedances are related to Project works.
8.3.7
Environmental site inspection was carried out thirteen
times in the reporting quarter. Recommendations on remedial actions were given
to the Contractors for the deficiencies identified during the site audits.
8.3.8
EPD referred a complaint on 17 March 2014 from complainant
who advised that there was sea water colored in blue observed in vicinity of
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Facilities (HKBCF) where stone
column installation was taking place. The locations of stone column and impact
water quality monitoring data recorded between 12 ¡V 17 March 14 were reviewed.
In accordance with the monitoring records, no discoloration of sea water or
silty plume appearance outside the seawall was observed during the water
quality monitoring between 12 ¡V 17 March 14. Therefore the complaint is
considered to be non-project related.
8.3.9
EPD referred a complaint from a complainant who advised
that muddy water was found being discharged from the construction site of Hong
Kong-Zhuhai-Macau Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V
Reclamation Works on 22 March 2014. With refer to the monitoring records on 21
March 2014 and the follow-up site inspection audit conducted with the
representatives of the Contractor and Residential Engineer on 27 March 2014,
since no discoloration of sea water or silty plume appearance outside the
perimeter silt curtain was observed, the complaint is considered to be non-project
related.
8.3.10
As informed by the Contractor, a complaint was received by
the Contractor on 25 March 14 concerning sand and dust emission from uncovered
barges parking at the sea area off the Tuen Mun Ferry Pier. However, base on
the available information, it cannot indicate that the air quality impact was
caused by the vessel of this Contract and therefore the complaint could not be
concluded as related to this Contract.
8.3.11
As informed by the Contractor, further to the notification
of summons received March 2014 due to works carried out on 6 October 13
contrary to conditions of NCO, Cap.400. The Contractor pledged guilty to
the charge during the court appearance on 28 April 2014. The Contractor has
established noise control management system on restricted hour works, to
prevent future violation of conditions of NCOs, Cap. 400.
8.3.12
As informed by the Contractor on 7 May 14, a complaint was
received by the Contractor on 17 April 14 concerning sand and dust emission
from uncovered barges parking at the sea area off the Tuen Mun Ferry Pier.
However, because no extra information was received for this complaint after the
release of the latest investigation report, it is unable to conclude whether
the complaint is related to this Contract.
8.3.13
As informed by the Contractor on 30 May 2014, an
environmental complaint had been received on 28 May 2014. The complainant
mentioned that waste such as earth and concrete were being felled into the sea
everyday at the Hong Kong-Zhuhai-Macao Bridge at location where construction
works are being conducted, causing pollution to the marine environment. The
construction programme and waste flow record provided by the Contractor has
been reviewed. With refer to the available information provided, it is
concluded that the complaint is unlikely to be related to this Contract.
8.3.14
Apart from the above mentioned monitoring, most of the
recommended mitigation measures, as included in the EM&A programme, were
implemented properly in the reporting quarter.
8.3.15
The recommended environmental mitigation measures
effectively minimize the potential environmental impacts from the Project. The
EM&A programme effectively monitored the environmental impacts from the
construction activities and ensure the proper implementation of mitigation
measures. No particular recommendation was advised for the improvement of the
programme.
8.3.16
Moreover, regular review and checking on the construction
methodologies, working processes and plants were carried out to ensure the
environmental impacts were kept minimal and recommended environmental
mitigation measures were implemented effectively.