Contract No. HY/2013/01
Hong Kong-Zhuhai-Macao Bridge
Hong Kong Boundary Crossing Facilities ¡V Passenger Clearance Building
Quarterly EM&A Report No. 10
(Covering the Period from 1 January 2017 to 31 March 2017)
18 May 2017
Revision 1
Main
Contractor
Environmental Team
|
Contents
Executive Summary
1.4 Construction Works Undertaken During the Reporting Period
2.1 Summary of EM&A Requirements
3....... Environmental Monitoring and Audit 12
3.1 Air Quality Monitoring Results. 12
3.3 Water Quality Monitoring Results
3.4 Dolphins Monitoring Results
3.5 Implementation of Environmental Measures
3.6 Advice on the Solid and Liquid Waste Management Status
3.7 Environmental Licenses and Permits
4....... Summary of Exceedance, Complaint, Notification of Summons and Successful Prosecution
4.1 Summary of Exceedance of the Environmental Quality Performance Limit
4.2 Summary of Complaints, Notification of Summons and Successful Prosecution
5....... Comments, Recommendations and Conclusion
Figures
Figure 2.1 Location of Air Quality Monitoring Stations
Figure 2.2 Location of Noise Monitoring Stations
Figure 2.3 Location of Water Quality Monitoring Stations
Figure 2.4 Impact Dolphins Monitoring Line Transect Layout Map
Appendices
Appendix A Location of Works Areas
Appendix B Project Organization for Environmental Works
Appendix C Construction Programme
Appendix D Event and Action Plan
Appendix E Implementation Schedule for Environmental Mitigation Measures (EMIS)
Appendix F Site Audit Findings and Corrective Actions
Appendix G Waste Flow Table
Appendix H Environmental Licenses and Permits
Appendix I Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions
Executive Summary
This Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/01 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Passenger Clearance Building (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to Leighton ¡V Chun Wo Joint Venture (hereafter referred to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the Environmental Team (ET) by the Contractor.
The Contract is part of Hong Kong ¡V Zhuhai ¡V Macao Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract started on 26 September 2014 and the construction works of the Contract commenced on 6 October 2014.
Atkins China Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version1.0) and will be providing environmental team services to the Contract.
This is the tenth Quarterly EM&A Report for the Contract which summaries findings of the EM&A works during the reporting period from 1 January to 31 March 2017.
Environmental Monitoring and Audit Progress
The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality, noise, water quality and dolphin monitoring works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6, AMS7, noise monitoring at NMS2 and NMS3B, water quality monitoring at twenty-one stations (nine Impact Stations, seven Sensitive Receiver Stations and five Control/Far Field Stations) and dolphin monitoring works at twenty-three transects as part of EM&A programme if these monitoring stations/ transects are no longer covered under Contract Nos. HY/2010/02 and HY/2011/03. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations/transects.
The dates of environmental site inspection during the reporting period are listed below:
Environmental Site Inspection Date |
||
January 2017 |
February 2017 |
March 2017 |
4, 11, 18 and 25 |
1, 8, 15 and 22 |
1, 8, 15, 22 and 29 |
Breaches of Action and Limit Levels
Summary of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at station AMS6 shall be referred to the monthly EM&A Reports (for January, February and March 2017) prepared by Contract No. HY/2011/03.
There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7 by the Environmental Team of Contract No. HY/2010/02 during the reporting period.
There was no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.
There were two Action Level exceedances of turbidity, six Action Level exceedances and one Limit Level exceedance of suspended solids (SS) were recorded by the ET of Contract No. HY/2010/02 during the reporting period (for January, February and March 2017). After investigation, these exceedances were considered not likely to be caused by this Contract¡¦s activities. No follow-up action is required.
Impact dolphin monitoring results at all transects are reported in the EM&A Report prepared for Contract No. HY/2010/02.
Implementation of Environmental Measures
Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. Potential environmental impacts due to the construction activities were monitored and reviewed.
Complaint Log
There was one complaint received in relation to the environmental impact during the reporting period.
A summary of environmental complaints for this reporting period is as follows:
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
006 |
28 March 2017 |
Noise and Water Quality |
Notifications of Summons and Successful Prosecutions
There was no notification of summon or prosecution received during this reporting period.
Reporting Change
There was no reporting change during the reporting period.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Engineer
or Engineer¡¦s Representative |
Chief Resident Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Michael Tovey(1) |
||||
Environmental
Project Office / Independent Environmental Checker |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor
|
Project Manager |
Owen Leung |
9232 5750 |
3621 0180 |
Environmental Officer |
Michael Lee |
6461 8635 |
3621 0180 |
|
Environmental
Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
3958 7300 |
--- |
(1) Mr Michael Tovey took up the role of the Chief Resident Engineer from Mr Darrel Kingan effective from 1 March 2017.
¡P Bulk Excavation at Seawater pump house and Box Culvert (WA1);
¡P Pile Cropping (WA1);
¡P Pile Capping (WA1);
¡P Waterproofing (WA1);
¡P Tower Crane Lowering (WA1);
¡P Suspended Slab Construction (WA1);
¡P Backfilling (WA1);
¡P RC works (Seawater Pump House, Southern Drop Off Deck) (WA1);
¡P Formwork and falsework stripping (WA1);
¡P Column and Wall Construction (Seawater pump house, generator set building) (WA1);
¡P District Cooling System Pipework installation (WA1);
¡P Blockwork walls (WA1);
¡P Pipework and ductwork installation (WA1);
¡P Footings for roof erection/ Footing demolition works (WA1);
¡P Hanger rods for cable container (WA1);
¡P Wet trade works (WA1);
¡P Dry trade works (WA1);
¡P Launch Rail Installation (WA1);
¡P Facade Bracket for Cabins (WA1);
¡P Steel Roof Segment Travelling works (WA1);
¡P Mechanical, Electrical and Plumbing High Level Containment (WA1);
¡P Steel Roof Erection works (WA1);
¡P Trolley removal works (WA1);
¡P Baring Point loading/ unloading works (WA1);
¡P Plinth construction (WA1);
¡P Removal of Temporary Works (WA1);
¡P Window wall (WA1);
¡P Sothern Drop off Deck Construction (WA1);
¡P 11 KV electric cable installation by China Light Power (CLP) (WA1);
¡P Heat exchanger installation (WA1);
¡P District Cooling System chilled water pipe installation (WA1);
¡P Heavy Mechanical, Electrical and Plumbing plant set up in basement (WA1);
¡P Box Culvert RC works (WA1);
¡P Double Bow Truss installation (WA1); and
¡P Mullion Frame installation (WA1).
¡P Delivery of Steel Roof Segment by Marine Transportation (WA1);
¡P District Cooling System (DCS) intake RC works (WA1);
¡P District Cooling System (DCS) outfall construction works (WA1);
¡P Box Culvert Outfall construction work (WA1); and
¡P Bulk Excavation (DCS outfall) (WA1).
Table 2.1 Summary of Impact EM&A Requirements
Environmental Monitoring |
ID |
Location Description |
Air Quality |
AMS6(1) |
Dragonair/CNAC (Group) Building |
AMS7(1), (2) |
Hong Kong SkyCity Marriott Hotel |
|
Noise |
NMS2(3) |
Seaview Crescent |
NMS3B(3),(4) |
Site Boundary of Site Office Area at Works Area WA2 |
Remarks:
(1) The ET of this Contract should conduct impact air quality monitoring at the Air Monitoring Station listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.
(2) The original monitoring location was at Hong Kong SkyCity Marriott Hotel (AMS7). As the permission to carry out air quality monitoring at Hong Kong SkyCity Marriott Hotel was not granted after 31 January 2015, the monitoring location was relocated to Chu Kong Air-Sea Union Transportation Co. Ltd. (AMS7A) from 5 February 2015 to 30 December 2015. The alternative monitoring location at Chu Kong Air-Sea Union Transportation Co. Ltd. was approved by EPD on 5 February 2015. However, AMS7A was relocated back to its original location (AMS7-Hong Kong SkyCity Marriott Hotel) on 30 December 2015. The relocation of air quality monitoring location, AMS7A, back to AMS7 was approved by EPD on 21 December 2015.
(3) The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.
(4) The Action and Limit Levels for schools will be applied for this alternative monitoring location.
Table 2.2 Impact Water Quality Monitoring Stations
Station |
Description |
East |
North |
IS5 |
Impact Station (Close to HKBCF construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station (Close to HKBCF construction site) |
812101 |
817873 |
IS7 |
Impact Station (Close to HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station (Close to HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact Station (Close to HKBCF construction site) |
813273 |
818850 |
IS10 |
Impact Station (Close to HKBCF construction site) |
812577 |
820670 |
Impact Station (Close to HKBCF construction site) |
813562 |
820716 |
|
Impact Station (Close to HKBCF construction site) |
814328 |
819497 |
|
IS17 |
Impact Station (Close to HKBCF construction site) |
814539 |
820391 |
SR3 |
Sensitive receivers (San Tau SSSI) |
810525 |
816456 |
SR4(N) |
Sensitive receivers (Tai Ho) |
814705 |
817859 |
SR5 |
Sensitive receivers (Artificial Reef in NE Airport) |
811489 |
820455 |
SR6 |
Sensitive receivers (Sha Chau and Lung Kwu Chau Marine Park) |
805837 |
821818 |
SR7 |
Sensitive receivers (Tai Mo Do) |
814293 |
821431 |
SR10A |
Sensitive receivers (Ma Wan FCZ) 1 |
823741 |
823495 |
SR10B(N) |
Sensitive receivers (Ma Wan FCZ) 2 |
823683 |
823187 |
CS(Mf)3 |
Control Station |
809989 |
821117 |
CS(Mf)5 |
Control Station |
817990 |
821129 |
CS4 |
Control Station |
810025 |
824004 |
CS6 |
Control Station |
817028 |
823992 |
CSA |
Control Station |
818103 |
823064 |
Table 2.3 Impact Dolphin Monitoring Line Transect Co-ordinates (Provided by AFCD)
Transect ID |
HK Grid System |
Long Lat in WGS84 |
||
X |
Y |
Long |
Lat |
|
1# |
804671 |
815456 |
113.870287 |
22.277678 |
804671 |
831404 |
113.869975 |
22.421696 |
|
2# |
805475 |
815913 |
113.878079 |
22.281820 |
805477 |
826654 |
113.877896 |
22.378814 |
|
3 |
806464 |
819435 |
113.887615 |
22.313643 |
806464 |
822911 |
113.887550 |
22.345030 |
|
4 |
807518 |
819771 |
113.897833 |
22.316697 |
807518 |
829230 |
113.897663 |
22.402113 |
|
5 |
808504 |
820220 |
113.907397 |
22.320761 |
808504 |
828602 |
113.907252 |
22.396462 |
|
6 |
809490 |
820466 |
113.916965 |
22.323003 |
809490 |
825352 |
113.916884 |
22.367128 |
|
7# |
810499 |
820880 |
113.926749 |
22.326757 |
810499 |
824613 |
113.926688 |
22.360464 |
|
8# |
811508 |
821123 |
113.936539 |
22.328966 |
811508 |
824254 |
113.936486 |
22.357241 |
|
9# |
812516 |
821303 |
113.946320 |
22.330606 |
812516 |
824254 |
113.946279 |
22.357255 |
|
10* |
813525 |
820827 |
113.956112 |
22.326321 |
813525 |
824657 |
113.956066 |
22.360908 |
|
11# |
814556 |
818853 |
113.966155 |
22.304858 |
814556 |
820992 |
113.966125 |
22.327820 |
|
12 |
815542 |
818807 |
113.975726 |
22.308109 |
815542 |
824882 |
113.975647 |
22.362962 |
|
13 |
816506 |
819480 |
113.985072 |
22.314192 |
816506 |
824859 |
113.985005 |
22.362771 |
|
14 |
817537 |
820220 |
113.995070 |
22.320883 |
817537 |
824613 |
113.995018 |
22.360556 |
|
15 |
818568 |
820735 |
114.005071 |
22.325550 |
818568 |
824433 |
114.005030 |
22.358947 |
|
16 |
819532 |
821420 |
114.014420 |
22.331747 |
819532 |
824209 |
114.014390 |
22.356933 |
|
17 |
820451 |
822125 |
114.023333 |
22.338117 |
820451 |
823671 |
114.023317 |
22.352084 |
|
18 |
821504 |
822371 |
114.033556 |
22.340353 |
821504 |
823761 |
114.033544 |
22.352903 |
|
19 |
822513 |
823268 |
114.043340 |
22.348458 |
822513 |
824321 |
114.043331 |
22.357971 |
|
20 |
823477 |
823402 |
114.052695 |
22.349680 |
823477 |
824613 |
114.052686 |
22.360610 |
|
21 |
805476 |
827081 |
113.877878 |
22.382668 |
805476 |
830562 |
113.877811 |
22.414103 |
|
22 |
806464 |
824033 |
113.887520 |
22.355164 |
806464 |
829598 |
113.887416 |
22.405423 |
|
23 |
814559 |
821739 |
113.966142 |
22.334574 |
814559 |
824768 |
113.966101 |
22.361920 |
|
Remarks: (a) *Due to the presence of deployed silt curtain systems at the site boundaries of the Contract, some of the transect lines shown in Figure 2.4 could not be fully surveyed during the regular survey. Transect 10 is reduced from 6.4km to approximately 3.6km in length due to the HKBCF construction site. Therefore the total transect length for both NEL and NWL combined is reduced to approximately 108km. (b) #Coordinates for transect lines 1, 2, 7, 8, 9 and 11 have been updated in respect to the Proposal for Alteration of Transect Line for Dolphin Monitoring approved by EPD on 19 August 2015. |
Table 2.4 Action and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS6 ¡V Dragonair/CNAC (Group) Building (HKIA) |
360 |
500 |
AMS7 ¡V Hong Kong SkyCity Marriott Hotel |
370 |
Table 2.5 Action and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS6 ¡V Dragonair/CNAC (Group) Building (HKIA) |
173 |
260 |
AMS7 ¡V Hong Kong SkyCity Marriott Hotel |
183 |
Table 2.6 Action and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
Notes :
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination period.
Table 2.7 Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
DO in mg L-1 (Surface, Middle & Bottom) |
Surface and Middle |
|
SS in mg L-1 (depth-averaged) at all monitoring stations and control stations |
23.5 and 120% of upstream control station's SS at the same tide of the same day* |
34.4 and 130% of upstream control station's SS at the same tide of the same day and 10mg/L for WSD Seawater intakes* |
27.5 and 120% of upstream control station's turbidity at the same tide of the same day* |
47.0 and 130% of upstream control station's turbidity at the same tide of the same day* |
Table 2.8 Action and Limit Levels for Chinese White Dolphin Monitoring - Approach to Define Action Level (AL) and Limit Level (LL)
|
North Lantau Social Cluster |
|
|
NEL |
NWL |
Action Level |
(STG < 70% of baseline) & (ANI < 70% of baseline) |
(STG < 70% of baseline) & (ANI < 70% of baseline) |
Limit Level |
[(STG < 40% of baseline) & (ANI < 40% of baseline)] AND [ (STG < 40% of baseline) & (ANI < 40% of baseline)] |
Table 2.9 Derived Value of Action Level (AL) and Limit Level (LL) for Chinese White Dolphin Monitoring
|
North Lantau Social Cluster |
|
|
NEL |
NWL |
Action Level |
(STG < 4.2) & (ANI < 15.5 ) |
(STG < 6.9) & (ANI < 31.3) |
Limit Level |
[(STG < 2.4) & (ANI <8.9)] AND [ (STG < 3.9)& (ANI < 17.9)] |
Table 3.1 Action and Limit Levels exceedance for Water Quality
Monitoring Station |
Monitoring Time |
Measured depth averaged (in mg/L) |
Level Exceeded |
Monitoring Date |
Mid-Flood tide (Turbidity) (in NTU) |
||||
SR4(N) |
15:30 |
33.6 |
Action |
24 March 2017 |
IS8 |
15:37 |
34.9 |
Action |
24 March 2017 |
Mid-Flood tide (Suspended Solids) (in mg/L) |
||||
IS8 |
13:32 |
26.5 |
Action |
6 February 2017 |
SR7 |
09:35 |
23.6 |
Action |
15 February 2017 |
SR4(N) |
15:30 |
29.5 |
Action |
24 March 2017 |
IS8 |
15:37 |
47.0 |
Limit |
24 March 2017 |
Mid-Ebb tide (Suspended Solids) (in mg/L) |
||||
SR6 |
11:29 |
23.8 |
Action |
10 February 2017 |
SR4(N) |
11:32 |
26.6 |
Action |
24 March 2017 |
IS8 |
11:26 |
29.3 |
Action |
24 March 2017 |
Table 4.1 A Summary of Environmental Complaints for the Reporting Month
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaints |
006 |
28 March 2017 |
Noise and Water Quality |