TABLE OF CONTENTS
Page |
|||
|
|
||
1 |
1-2 |
||
1.1 |
Basic
Project Information |
1 |
|
1.2 |
Project
Organization |
2 |
|
1.3 |
Construction Programme |
2 |
|
1.4 |
Construction Works
Undertaken During the Reporting Period |
2 |
|
|
|
|
|
2 |
3-4 |
||
2.1 |
Monitoring Locations |
3 |
|
2.2 |
Monitoring Requirements |
4 |
|
2.3 |
Monitoring Results |
4 |
|
|
|
|
|
3 |
5 |
||
3.1 |
Monitoring Locations |
5 |
|
3.2 |
Monitoring Requirements |
5 |
|
3.3 |
Monitoring Results |
5 |
|
|
|
|
|
4 |
9-11 |
||
4.1 |
Site
Inspection |
9 |
|
4.2 |
Advice on the
Solid and Liquid Waste Management Status |
9 |
|
4.3 |
Environmental Licenses and
Permits |
10 |
|
4.4 |
Implementation
Status of Environmental Mitigation Measures |
10 |
|
4.5 |
Summary
of Exceedance of the Environmental Quality Performance Limit |
10 |
|
4.6 |
Summary
of Complaints, Notification of Summons and Successful Prosecution |
10 |
|
|
|
|
|
5 |
12 |
||
5.1 |
Construction
Programme for the Coming Months |
12 |
|
5.2 |
Environmental Site
Inspection Schedule for the Coming Month |
12 |
|
|
|
|
|
6 |
12 |
||
|
|
12 |
|
|
|
|
|
|
|||
Figure 1 |
Air Quality and Noise Monitoring Stations for HKBCF |
|
|
Table |
|
Table 1.1 |
Contact
Information of Key Personnel |
Table 2.1 |
Air Quality Monitoring Locations |
Table 2.2 |
Action and Limit Levels
for 1-hour TSP |
Table 2.3 |
Action and Limit Levels
for 24-hour TSP |
Table 3.1 |
Construction
Noise Monitoring
Locations |
Table 3.2 |
Action and Limit Levels
for Construction Noise |
Table 5.1 |
Construction Activities
for November 2015 |
APPENDICES |
|
Location of Works Areas |
|
Project Organization for Environmental
Works |
|
Construction Programme |
|
Event and Action Plan |
|
Waste Flow Table |
|
Environmental Licenses and Permits |
|
Implementation Schedule for
Environmental Mitigation Measures (EMIS) |
|
Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions |
|
Environmental Site Inspection Schedule |
|
Complaint Investigation
Report |
This Monthly Environmental
Monitoring and Audit (EM&A) Report is
prepared for Contract HY/2013/02 Hong Kong¡VZhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western
Portion) (hereafter referred to as ¡§the Contract¡¨) for the Highways Department
of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to
China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨)
and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the
Contractor.
The Contract is part of
ETS-Testconsult Limited has been appointed by
the Contractor to implement the Environmental Monitoring & Audit (EM&A)
programme for the Contract in accordance with the Updated EM&A Manual for
HKBCF (Version 1.0) and provide environmental team services to the Contract.
This is the Eleventh Monthly Environmental
Monitoring and Audit (EM&A) Report for the Contract which summaries
findings of the EM&A works conducted during the reporting
period from 01 October 2015 to 31 October 2015.
Site Activities
As informed by the Contractor, site activities were
carried out in
this reporting month:
¡±
Bored piles works in Portion D;
¡±
Abutment in Portion H;
¡±
Construction of temporary marine loading
and unloading point for segment delivery in Portion A1
at
Land Section. There haven¡¦t
any marine works during the reporting period.
¡±
UU Detection Works in Portion
I; and
¡±
Pit excavation work and duct laying in
Portion I;
Environmental Monitoring and Audit Progress
The monthly EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version
1.0). It should be noted that the air quality and noise monitoring works for
the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
The dates of site inspection during the
reporting period are listed below:
Environmental Site Inspection:
07, 16, 20
and 28 October
2015
Breaches
of Action and Limit Levels
Summary of
Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6
shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There was no Action and Limit Level exceedance
of 1-hr TSP level and 24-hr TSP level
recorded at station AMS
There was no Action and Limit Level exceedance
for noise recorded at
station NMS2 and station NMS3B by the Environmental Team of Contract No.
HY/2010/02 during the reporting period.
Complaint Log
There was a
complaint received by EPD from a resident of No. 1 Sky City Road East, HK
Skycity Marriott Hotel via EPD¡¦s hotline on 23 October 2015 and was forwarded
by EPD to the ENPO on 23 October 2015.Then the ENPO forwarded the complaint by
email to the R.E. (AECOM), the Contractor (China Harbour) and the ET
(ETS-Testconsult Ltd.) of Contract No. HY/2013/02 at 17:25 on 23 October 2015.
The complainant complained that noise nuisance generated from the HZMB
construction site near
The above mentioned complaint follow-up inspection was performed by the
ET of Contract No. HY/2013/02 on 26 October 2015.The complaint investigation report (Log No. 004) was issued by the ET
of Contract No. HY/2013/02 and verified by the IEC/ENPO on 03 November 2015.
According to the investigation, the construction works of the Contractor
of Contract No. HY/2013/02 no any construction works was carried out after
23:00. There was only piling works carried out at Zone D & E from 08:00 to
23:00 and no any works and PME operation were undertaken at night-time from 16
to 23 October 2015 including the Sunday and Public Holiday which was fully
covered by the CNP no.GW-RS1098. No noise record was exceeded the Action and
Limit Level and no dark smoke emission produced from plants was observed in the
past week. Besides, two water lorries were deployed and kept spraying water on
site at least 8 times per day in the past week. The complaint was found
non-related to Contract No. HY/2013/02. The complaint investigation report (Log No. 004) was provided in Appendix J.
Notifications of Summons and Successful
Prosecutions
There were no
notifications of summons or prosecutions received during the reporting period.
Reporting Change
There was no reporting change in the reporting period.
Future
Key Issues
The future key
issues to be undertaken in the upcoming month are as follows:
¡±
Bored piles
works in Portion A1 &
D;
¡±
Pile Cap &
abutment in Portion H;
¡±
Construction of
temporary marine loading and unloading point for segment delivery in Portion A1.
(No any marine work in the upcoming month);
¡±
UU Detection
Works in Portion I; and
¡±
Pit excavation work and
duct laying in Portion I;
1.1 Basic Project
Information
¡±
Construction of the viaducts
and roads at the western portion of Hong Kong Boundary Crossing Facilities
(HKBCF) mainly for connection with the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB), Hong Kong Link Road
(HKLR), Hong Kong International Airport (HKIA) and the Tuen Mun-Chek Lap Kok
Link (TM-CLKL);
¡±
Construction of the road modification at the SkyCity Interchange
at
¡±
Construction of associated street lighting, street
furniture, road marking, road signage, drainage, sewerage, fresh water and
flushing water supply, irrigation, landscape, electrical and mechanical
(E&M), utilities and services works;
¡±
Provisioning of civil engineering works and power supply
installation for the Traffic Control and Surveillance System TCSS);
¡±
Other works in accordance with the
Contract.
1.2 Project Organization
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name of Key
Staff |
Tel. No. |
Fax No. |
Engineer or Engineer¡¦s
Representative (AECOM Asia
Co. Ltd.) |
Resident Engineer |
Mr.
Fred Yeung |
63308293 |
31525116 |
Environmental Project Office / Independent Environmental Checker
(Ramboll Environ Hong Kong Limited)
|
Environmental Project Office Leader |
Mr. Y. H. Hui |
34652888 |
34652899 |
Independent Environmental Checker |
Mr. Raymond Dai |
34652888 |
34652899 |
|
Environmental Site Supervisor |
Mr. Ray Yan |
51818165 |
34652899 |
|
Contractor (China Harbour Engineering
Co., Ltd.) |
Environmental Officer |
Mr. Richard Ng |
59770593 |
39150300 |
Environmental Supervisor |
Ms. Joy Chan |
54005086 |
39150300 |
|
Environmental Supervisor |
Ms. Selena Yang |
55122662 |
39150300 |
|
Environmental
Team (ETS-Testconsult Ltd.) |
Environmental
Team Leader |
Mr
C. L. Lau |
2946
7791 |
2695
3944 |
1.3 Construction Programme
1.4 Construction Works Undertaken
During the Reporting Period
¡±
Bored piles
works in Portion D;
¡±
Abutment in
Portion H;
¡±
Construction of temporary marine loading and unloading point for
segment delivery in Portion A1
at
Land Section. There
haven¡¦t any marine works during the reporting period.
¡±
UU Detection Works in Portion I; and
¡±
Pit
excavation work and duct laying in Portion I;
2.1 Monitoring
Locations
Table 2.1 Air Quality Monitoring
Locations
Identification No. |
Location
Description |
AMS6(1) |
Dragonair / CNAC
(Group) Buidling |
AMS |
|
Remarks:
(1) The ET of this Contract should
conduct impact air quality monitoring at the AMS listed in the table as part of
EM&A programme according to latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
2.2 Monitoring
Requirements
Table 2.2 Action
and Limit Levels for 1-hour TSP
Monitoring Station. |
Action Level,mg/m3 |
Limit Level,mg/m3 |
AMS6 ¡V Dragnair / SNAC (Group) Building
(HKIA) |
360 |
500 |
AMS |
370 |
500 |
Table 2.3 Action and Limit Levels for 24-hour TSP
Monitoring Station. |
Action Level,mg/m3 |
Limit Level,mg/m3 |
AMS6 ¡V Dragnair / SNAC (Group) Building
(HKIA) |
173 |
260 |
AMS |
183 |
260 |
2.3 Monitoring Results
3.1 Monitoring Locations
Table 3.1 Construction Noise Monitoring
Locations
Identification No. |
Location
Description |
NMS2(1) |
|
NMS3B(1) (2) |
Site Boundary of Site Office Area at Works
Area WA2 |
Remarks:
(1) The ET of this Contract should
conduct impact noise monitoring at the NMS listed in the table as part of
EM&A programme according to latest notification from ENPO when the
monitoring station(s) is/are no longer covered by another ET of the HZMB
project.
(2) The Action and Limit Levels for
schools will be applied for this alternative monitoring location.
3.2 Monitoring
Requirements
Table 3.2 Action and Limit Levels for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V
19:00 hours on normal weekdays |
When one documented
complaint is received |
75 dB(A)* |
|
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70
dB(A)
for schools and 65 dB(A) during school examination period.
3.3 Monitoring Results
4 ENVIRONMENTAL
SITE INSPECTION AND AUDIT
4.1 Site
Inspection
07 October 2015
(a) No
observation was made during this site inspection.
16 October 2015
(a) No observation was made during this site
inspection.
20 October 2015
(a) Oil container was
observed stored improperly was observed at Portion H. The Oil container was removed.
This observation was closed on 28 October 2015.
28 October 2015
(a) No observation was made during this site
inspection.
4.2 Advice on the Solid and
Liquid Waste Management Status
4.3 Environmental Licenses and
Permits
4.4
Implementation Status of Environmental Mitigation Measures
4.5 Summary of
Exceedance of the Environmental Quality Performance Limit
4.6 Summary of Complaints, Notification of
Summons and Successful Prosecution
The above mentioned complaint follow-up inspection was performed by the
ET of Contract No. HY/2013/02 on 26 October 2015.The complaint investigation report (Log No. 004) was issued by the ET
of Contract No. HY/2013/02 and verified by the IEC/ENPO on 03 November 2015.
Refer to the
above mentioned inspection, since no any construction works was carried out
after 23:00 and no works and PME operation were undertaken at night-time. The
construction works was carried out from 08:00 to 23:00 hours for all days which
was fully covered by the CNP no. GW-RS1098. No noise record was exceeded the
Action and Limit Level and no dark smoke emission produced from plants was
observed and also kept spraying water on site at least 8 times per day in the
past week. This complaint was found non-related to Contract No. HY/2013/02.
Although this
complaint was non-related to Contract No. HY/2013/02, the Contractor of
Contract No. HY/2013/02 was reminded to provide suitable mitigation measures to
reduce the noise and duct impact and dark smoke emission produced during the
construction works. The complaint was found
non-related to Contract No. HY/2013/02.
The complaint investigation report (Log No. 004) was provided in Appendix J.
5.1 Construction Programme for the
Coming Months
Table 5.1 Construction Activities for November 2015
Site Area |
Description
of Activities |
Portion A1 &D |
Bored
Piles Works |
Portion I |
Pit excavation work and duct laying |
Portion I |
UU Detection Works |
Portion H. |
Pile Cap &
abutment |
Portion A1 |
Construction of
temporary marine loading and unloading point for segment delivery. ( No any marine work in the
upcoming month ) |
5.2 Environmental
Site Inspection Schedule for the Coming Month
6 CONCLUSION.
6.1 The
site preparation work of the Contract was started on 25 July 2014 and the
construction works of the Contract commenced on 24 November 2014.
6.2 Summary of Action and
Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be
referred to the monthly EM&A report prepared by Contract No. HY/2011/03.
6.3 There
was no Action and Limit Level
exceedance of 1-hr TSP level and 24-hr TSP
level recorded at station AMS
6.4 There was
no Action and Limit Level
exceedance for noise recorded
at station NMS2 and station NMS3B by the Environmental Team of Contract No.
HY/2010/02 during the reporting period.
6.5 There
was a complaint was received by EPD from a resident of No. 1 Sky City Road
East, HK Skycity Marriott Hotel via EPD¡¦s hotline on 23 October 2015 and was
forwarded by EPD to the ENPO on 23 October 2015.Then the ENPO forwarded the
complaint by email to the R.E. (AECOM), the Contractor (China Harbour) and the
ET (ETS-Testconsult Ltd.) of Contract No. HY/2013/02 at 17:25 on 23 October
2015. After the investigation, the complaint was found non-related to Contract
No. HY/2013/02.
6.6 There were no
notifications of summons or prosecutions received during the reporting period.
- END OF REPORT -