TABLE OF CONTENTS
Page |
|||
1 |
1-2 |
||
1.1 |
Basic
Project Information |
1 |
|
1.2 |
Project
Organization |
2 |
|
1.3 |
Construction Programme |
2 |
|
1.4 |
Construction Works
Undertaken During the Reporting Period |
2 |
|
|
|
|
|
2 |
3-4 |
||
2.1 |
Monitoring Locations |
3 |
|
2.2 |
Monitoring Requirements |
4 |
|
2.3 |
Monitoring Results |
4 |
|
|
|
|
|
3 |
5 |
||
3.1 |
Monitoring Locations |
5 |
|
3.2 |
Monitoring Requirements |
5 |
|
3.3 |
Monitoring Results |
5 |
|
|
|
|
|
4 |
6-7 |
||
4.1 |
Monitoring
Locations |
6 |
|
4.2 |
Monitoring
Requirements |
6 |
|
4.3 |
Monitoring
Locations |
7 |
|
|
|
|
|
5 |
8 |
||
5.1 |
Monitoring
Locations |
8 |
|
5.2 |
Monitoring
Requirements |
8 |
|
5.3 |
Monitoring
Locations |
8 |
|
|
|
|
|
6 |
9-10 |
||
6.1 |
Site
Inspection |
9 |
|
6.2 |
Advice on the
Solid and Liquid Waste Management Status |
9 |
|
6.3 |
Environmental Licenses and
Permits |
9 |
|
6.4 |
Implementation
Status of Environmental Mitigation Measures |
10 |
|
6.5 |
Summary
of Exceedance of the Environmental Quality Performance Limit |
10 |
|
6.6 |
Summary
of Complaints, Notification of Summons and Successful Prosecution |
10 |
|
|
|
|
|
7 |
11 |
||
7.1 |
Construction
Programme for the Coming Months |
11 |
|
7.2 |
Environmental Site
Inspection Schedule for the Coming Month |
11 |
|
|
|
|
|
8 |
11 |
||
8.1 |
Conclusions |
11 |
|
|
|
|
|
|
|
|
|
|
|||
Figure 1 |
Air Quality and Noise Monitoring Stations for HKBCF |
|
|
Figure 2 |
Water Quality Monitoring Stations(construction phases) |
|
|
Figure 3 |
Dolphin Monitoring Transect Line and Layout Map |
|
|
Table |
|
Table 1.1 |
Contact
Information of Key Personnel |
Table 2.1 |
Air Quality Monitoring Locations |
Table 2.2 |
Action and Limit Levels for 1-hour TSP |
Table 2.3 |
Action and Limit Levels for 24-hour TSP |
Table 3.1 |
Construction Noise Monitoring Locations
|
Table 3.2 |
Action and Limit Levels for
Construction Noise |
Table 4.1 |
Water Quality Monitoring
Stations(construction phases) |
Table 4.2 |
Action and Limit Levels for Water
Quality |
Table |
Action
and Limit Levels for Chinese White Dolphin Monitoring ¡V Approach to Define
Action Level ( |
Table 5.1b |
Action and Limit Levels for Chinese White Dolphin Monitoring ¡V |
Table 7.1 |
Derived Vale of Action Level (AL) and
Limit Level (LL) for Chinese White Dolphin Monitoring
Construction Activities for coming month |
|
|
APPENDICES |
|
Location of Works Areas |
|
Project Organization for Environmental
Works |
|
Construction Programme |
|
Event and Action Plan |
|
Waste Flow Table |
|
Environmental Licenses and Permits |
|
Implementation Schedule for
Environmental Mitigation Measures (EMIS) |
|
Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions |
|
Environmental Site Inspection Schedule |
|
Investigation
Report on Action or Limit Level Non-compliance |
|
|
|
This Monthly Environmental
Monitoring and Audit (EM&A) Report is
prepared for Contract HY/2013/02 Hong Kong¡VZhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western
Portion) (hereafter referred to as ¡§the Contract¡¨) for the Highways Department
of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to
China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨)
and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the
Contractor.
The Contract is part of
ETS-Testconsult Limited has been appointed by
the Contractor to implement the Environmental Monitoring & Audit (EM&A)
programme for the Contract in accordance with the Updated EM&A Manual for
HKBCF (Version 1.0) and provide environmental team services to the Contract.
This is the Thirteen Monthly Environmental
Monitoring and Audit (EM&A) Report for the Contract which summaries
findings of the EM&A works conducted during the reporting
period from 01 December 2015 to 31 December 2015.
Site Activities
As informed by the Contractor, site activities were
carried out in
this reporting month:
¡±
Bored piles works in Portion A1 & D;
¡±
Pier & Abutment in Portion H & Pile Cap in
Portion D;
¡±
Formwork and falsework for bridge deck at Portion
H;
¡±
Temporary marine loading and unloading point for
segment delivery in Portion A1;
¡±
UU Detection Works in Portion I;
¡±
Pit excavation work and duct laying in Portion I;
Environmental Monitoring and Audit Progress
The monthly EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version
1.0). It should be noted that the air quality and noise monitoring works for
the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
Environmental Site Inspection:
02, 10, 18, 24
and 31 December
2015
Breaches
of Action and Limit Levels
Summary of
Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6
shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There was no Action and Limit Level exceedance
of 1-hr TSP level and 24-hr TSP level
recorded at station AMS
There was no Action and Limit Level exceedance
for noise recorded at
station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02
during the reporting period.
Since the marine construction works of temporary
loading and unloading point was carried out from 02 Dec 2015 to 30 Dec 2015,
water quality monitoring and impact dolphin monitoring are required from this
reporting month.
For water quality monitoring, one
Action Level exceedance
of SS at IS(Mf)11 during mid-flood tide was recorded
on 28 Dec 2015. After investigation, there is no adequate information to
conclude the recorded exceedance is related to this Contract. The Investigation Report No. 002 (including the
causes of exceedance, action taken and recommendation for mitigation) on Action
or Limit Level Non-compliance is provided in Appendix J. No Action and Limit Level exceedance was recorded on other date by the Environmental
Team of Contract No. HY/2010/02 during the
reporting period.
Impact dolphin monitoring results at all transects are reported in the EM&A Report
prepared for Contract No. HY/2010/02.
Complaint Log
There was no
complaint received in relation to the environmental impact during the reporting period.
Notifications of Summons and Successful
Prosecutions
There were no
notifications of summons or prosecutions received during the reporting period.
Reporting Change
There was no reporting change in the reporting period.
Future
Key Issues
The future key
issues to be undertaken in the upcoming month are as follows:
¡±
Bored piles
works in Portion A1, D, C1& F;
¡±
Pile Cap in Portion H & Pile Cap in
Portion D;
¡±
Formwork and falsework for deck of Bridge B1 at Portion H;
¡±
Construction of
temporary marine loading and unloading point for segment delivery in Portion A1;
¡±
UU Detection
Works in Portion I; and
¡±
Pit excavation work and
duct laying in Portion I.
1.1 Basic Project
Information
¡±
Construction of the viaducts
and roads at the western portion of Hong Kong Boundary Crossing Facilities
(HKBCF) mainly for connection with the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB), Hong Kong Link Road
(HKLR), Hong Kong International Airport (HKIA) and the Tuen Mun-Chek Lap Kok
Link (TM-CLKL);
¡±
Construction of the road modification at the SkyCity Interchange
at
¡±
Construction of associated street lighting, street
furniture, road marking, road signage, drainage, sewerage, fresh water and
flushing water supply, irrigation, landscape, electrical and mechanical
(E&M), utilities and services works;
¡±
Provisioning of civil engineering works and power supply
installation for the Traffic Control and Surveillance System TCSS);
¡±
Other works in accordance with the
Contract.
1.2 Project Organization
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name of Key Staff |
Tel. No. |
Fax No. |
Engineer or Engineer¡¦s
Representative (AECOM Asia
Co. Ltd.) |
Resident
Engineer |
Mr. Fred Yeung |
63308293 |
31525116 |
Environmental Project Office
/ Independent Environmental Checker (Ramboll Environ Hong Kong Limited) |
Environmental
Project Office Leader |
Mr. Y. H. Hui |
34652888 |
34652899 |
Independent
Environmental Checker |
Mr.
Raymond Dai |
34652888 |
34652899 |
|
Environmental
Site Supervisor |
Mr.
Ray Yan |
51818165 |
34652899 |
|
Contractor
(China Harbour Engineering Co., Ltd.) |
Environmental
Officer |
Mr.
Richard Ng |
59770593 |
39150300 |
Environmental
Supervisor |
Ms.
Joy Chan |
54005086 |
39150300 |
|
Environmental
Supervisor |
Ms.
Selena Yang |
55122662 |
39150300 |
|
Environmental Team (ETS-Testconsult
Ltd.) |
Environmental Team Leader |
Mr C. L. Lau |
2946 7791 |
2695 3944 |
1.3 Construction Programme
1.4 Construction Works Undertaken
During the Reporting Period
¡±
Bored piles
works in Portion A1 & D;
¡±
Pier & Abutment in Portion H & Pile Cap in Portion D;
¡±
Formwork and falsework for bridge deck at Portion H;
¡±
Temporary marine loading and unloading point for segment delivery
in Portion A1;
¡±
UU Detection Works in Portion I; and
¡±
Pit
excavation work and duct laying in Portion I.
2.1 Monitoring
Locations
Table 2.1 Air Quality Monitoring
Locations
Identification No. |
Location
Description |
AMS6(1) |
Dragonair / CNAC
(Group) Buidling |
AMS |
|
Remarks:
(1)
The ET of this Contract should conduct impact air quality
monitoring at the AMS listed in the table as part of EM&A programme according
to latest notification from ENPO when the monitoring station(s) is/are no
longer covered by another ET of the HZMB project.
(2)
This location was relocated back to the original location AMS7
(located at Hong Kong SkyCity Marriott Hotel) of the updated EM&A Manual on
30 December 2015 and the air monitoring at AMS7 will be started in the next
reporting period.
2.2 Monitoring
Requirements
Table 2.2 Action
and Limit Levels for 1-hour TSP
Monitoring Station. |
Action Level,mg/m3 |
Limit Level,mg/m3 |
AMS6 ¡V Dragnair / SNAC (Group) Building
(HKIA) |
360 |
500 |
AMS |
370 |
500 |
Table 2.3 Action
and Limit Levels for 24-hour TSP
Monitoring Station. |
Action Level,mg/m3 |
Limit Level,mg/m3 |
AMS6 ¡V Dragnair / SNAC (Group) Building
(HKIA) |
173 |
260 |
AMS |
183 |
260 |
2.3 Monitoring
Results
3.1 Monitoring Locations
Table 3.1 Construction
Noise Monitoring
Locations
Identification No. |
Location
Description |
NMS2(1) |
|
NMS3B(1) (2) |
Site Boundary of Site Office Area at Works
Area WA2 |
Remarks:
(1) The ET of this Contract should
conduct impact noise monitoring at the NMS listed in the table as part of
EM&A programme according to latest notification from ENPO when the
monitoring station(s) is/are no longer covered by another ET of the HZMB
project.
(2) The Action and Limit Levels for
schools will be applied for this alternative monitoring location.
3.2 Monitoring
Requirements
Table 3.2 Action
and Limit Levels for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V
19:00 hours on normal weekdays |
When one documented
complaint is received |
75 dB(A)* |
|
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70
dB(A)
for schools and 65 dB(A) during school examination period.
3.3 Monitoring Results
4.1
Monitoring
Locations
The water monitoring works for the Contract are
covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
Table 4.1 Water Quality Monitoring Stations (construction phases)
Station |
Description |
East |
North |
IS7 |
Impact Station
(Close to HKBCF construction site) |
812244 |
818777 |
IS10 |
Impact Station (Close
to HKBCF construction site) |
812577 |
820670 |
IS(Mf)11 |
Impact Station
(Close to HKBCF construction site) |
813562 |
820716 |
SR3 |
Sensitive
receivers (San Tau SSSI) |
810525 |
816456 |
SR4(N) |
Sensitive
receivers (Tai Ho) |
814705 |
817859 |
SR5 |
Sensitive receivers
(Artificial Reef in NE Airport) |
811489 |
820455 |
SR6 |
Sensitive
receivers (Sha Chau and |
805837 |
821818 |
SR7 |
Sensitive
receivers (Tai Mo Do) |
814293 |
821431 |
SR |
Sensitive
receivers (Ma Wan FCZ)1 |
823741 |
823495 |
SR10B(N)[1] |
Sensitive
receivers (Ma Wan FCZ)2 |
823683 |
823187 |
CS(Mf)3 |
Control Station |
809989 |
821117 |
CS(Mf)5 |
Control Station |
817990 |
821129 |
CS4 |
Control Station |
810025 |
824004 |
CS6 |
Control Station |
817028 |
823992 |
CSA [2] |
Control Station |
818103 |
823064 |
Note:
[1]: Additional monitoring station for Ma Wan
FCZ.
[2]: Additional control monitoring station
for Ma Wan FCZ
Remarks:
The ET of this
Contract should conduct impact water quality monitoring at the WQMS listed in
the table as part of EM&A programme according to latest notification from
ENPO when the monitoring station(s) is/are no longer covered by another ET of
the HZMB project. The ET of the
Contract shall communicate and share the monitoring data to the ET(s) of other
works contracts if the water quality monitoring station(s) is/are as part of
EM&A programme.
4.2
Monitoring
Requirements
The
monitoring requirements, monitoring equipment, monitoring parameters, frequency
and duration, monitoring methodology, monitoring schedule, meteorological
information are detailed in the monthly EM&A Reports prepared for Contract
Nos. HY/2010/02.
4.2.1
The event and
action plan is provided in Appendix D.
4.2.2
The Action and Limit Levels for Water Quality are provided in Table 4.2
Table 4.2 Action and Limit
Levels for Water Quality
Parameters |
Action |
Limit |
DO in mg/L
(Surface, Middle & Bottom) |
Surface and Middle
5.0 Bottom 4.7 |
Surface and Middle
4.2 (except 5 mg/L for FCZ) Bottom 3.6 |
SS in mg/L (depthaveraged) at
all monitoring stations and control stations |
23.5 and 120% of upstream control
station's SS at the same tide of the same day* |
34.4 and 130% of upstream control
station's SS at the same tide of the same day and 10mg/L for WSD Seawater
intakes* |
Turbidity in NTU (depth-averaged) |
27.5 and 120% of upstream
control station's turbidity at the
same tide of the same day* |
47.0 and 130% of upstream
control station's turbidity at the
same tide of the same day* |
* Remarks: Reference is made to EPD approval of
adjustment of water quality assessment
criteria issued and
became effective on 18 February 2013.
Notes: 1.
"depth-averaged" is calculated by taking the arithmetic means of
reading of all three
depths.
2. For DO, non-compliance of the water
quality limits occurs when monitoring result is
lower than the
limits.
3. For turbidity, SS, non-compliance of the
water quality limits occurs when monitoring
result is higher than
the limits.
4. All the figures given in the table are
used for reference only and the EPD may
amend the figures
whenever it is considered as necessary.
5. The 1%-ile of baseline data for dissolved
oxygen (surface and middle) and dissolved
oxygen (bottom) are 4.2mg/L and 3.6mg/L
respectively
4.3
Monitoring Result
Since the marine construction works of temporary loading and unloading
point was carried out from 02 Dec 2015 to 30 Dec 2015, water quality monitoring
is required from this reporting month.
The monitoring results for the monitoring stations showed in Table 4.1 are reported in the monthly EM&A
Report prepared for Contract No. HY/2010/02. One Action Level
exceedance of SS at IS(Mf)11 during
mid-flood tide was recorded on 28 Dec 2015. After investigation, there is no
adequate information to conclude the recorded exceedance is related to this
Contract. The Investigation Report No. 002 (including
the causes of exceedance, action taken and recommendation for mitigation) on
Action or Limit Level Non-compliance is provided in Appendix J. No Action and Limit Level exceedance was recorded on other date by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
5.1 Monitoring Locations
The dolphin monitoring
works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-
Remarks:
The ET
of this Contract should conduct impact dolphin monitoring as part of EM&A
programme according to latest notification from ENPO when the monitoring
station(s) is/are no longer covered by another ET of the HZMB project.
5.2 Monitoring
Requirements
The
monitoring requirements, monitoring equipment, monitoring parameters, frequency
and duration, monitoring methodology, monitoring schedule, meteorological
information are detailed in the monthly EM&A Reports prepared for Contract
Nos. HY/2010/02.
5.2.1
The event and
action plan is provided in Appendix D.
5.2.2
The Action and Limit Levels for Chinese White Dolphin Monitoring are provided in Table
Table
to
Define Action Level (
|
|
|
NEL |
NWL |
|
Action Level |
(STG < 70% of
baseline) & (ANI < 70% of baseline) |
(STG < 70% of
baseline) & (ANI < 70% of baseline) |
Limit Level |
[(STG < 40% of
baseline) & (ANI < 40% of baseline)] AND [ (STG < 40%
of baseline) & (ANI < 40% of baseline)] |
For North Lantau Social Cluster, action level will be trigger if either
NEL or NWL fall below the
criteria; limit level will be triggered if both NEL and NWL fall below
the criteria.
Table 5.1(b) Derived Value
of Action Level (
White
Dolphin Monitoring
|
|
|
NEL |
NWL |
|
Action Level |
STG < 4.2) & (ANI < 15.5 ) |
(STG < 6.9) & (ANI < 31.3) |
Limit Level |
[(STG < 2.4) & (ANI < 8.9)] AND [(STG
< 3.9) & (ANI < 17.9)] |
5.3 Monitoring
Result
Since the marine construction works of temporary loading
and unloading point was carried out from 02 Dec 2015 to 30 Dec 2015, impact
dolphin monitoring is required from this reporting month.
The dolphin survey results for all transects are reported in the monthly EM&A Reports prepared for Contract No.
HY/2010/02.
6 ENVIRONMENTAL
SITE INSPECTION AND AUDIT
6.1 Site
Inspection
24 November 2015
(a) Chemical container without drip tray was observed
at Portion H. A drip tray was provided. This observation was closed on 2
December 2015.
02 December 2015
(a) Chemical
waste container was observed improperly stored at Portion H. The Chemical waste
container was removed. This observation was closed on 10 December 2015.
10 December 2015
(a) No
observation was made during this site inspection.
18 December 2015
(a) Chemical container
without drip tray was observed at Portion D. A drip tray was provided for the
chemical container. This observation was closed on 24 December 2015.
24 December 2015
(a) Unsealed
water safety barriers were observed at Portion D. The water safety barriers
were sealed. This observation was closed on 31 December 2015.
(b) General refuses were
observed at Portion D. The refuses were collected. This observation was closed
on 31 December 2015.
31 December 2015
(a) No observation was made during this site
inspection.
6.2 Advice on the Solid and
Liquid Waste Management Status
6.3 Environmental Licenses and
Permits
The valid
environmental licenses and permits during the reporting period are summarized
in Appendix F.
6.4 Implementation Status of Environmental Mitigation
Measures
6.5 Summary of
Exceedance of the Environmental Quality Performance Limit
6.6 Summary of
Complaints, Notification of Summons and Successful Prosecution
7.1 Construction
Programme for the Coming Months
Table
7.1 Construction
Activities for Coming Month
Site Area |
Description
of Activities |
Portion A1, D, C1 &
F |
Bored
Piles Works |
Portion I |
Pit excavation work and duct laying |
Portion I |
UU Detection Works |
Portion H. |
Pile Cap &
abutment |
Portion H. |
Formwork and
falsework for deck of Bridge B1 |
Portion D. |
Pile Cap |
Portion A1 |
Temporary
marine loading and unloading point for segment delivery |
7.2 Environmental
Site Inspection Schedule for the Coming Month
8 CONCLUSION.
8.1 Conclusions
- END OF REPORT -