Contract No. HY/2014/05
Hong
Kong-Zhuhai-Macao Bridge
Hong Kong Boundary
Crossing Facilities ¡V Remaining Ancillary Buildings and Facilities
Monthly EM&A Report
No. 11
(Covering the Period from
1 January 2017 to 31 January 2017)
15 February 2017
Revision 3
Main Contractor Environmental
Team
Contents
Executive
Summary
1.4 Construction
Works Undertaken During the Reporting Period
2....... Air Quality Monitoring
4....... Environmental Site Inspection and Audit
4.2 Advice
on the Solid and Liquid Waste Management Status
4.3 Environmental
Licenses and Permits
4.4 Implementation Status of Environmental Mitigation
Measures
4.5 Summary of Exceedance of the Environmental
Quality Performance Limit
4.6 Summary of Complaints, Notification of
Summons and Successful Prosecution
5.1 Construction Programme for the Coming Months
5.2 Environmental Site Inspection Schedule for
the Coming Month
Figures
Figure 2.1 Location of
Air Quality Monitoring Stations
Figure 3.1 Location of Noise
Monitoring Stations
Appendices
Appendix A Location of
Works Areas
Appendix B Project
Organization for Environmental Works
Appendix C Construction
Programme
Appendix D Event and
Action Plan
Appendix E Waste Flow Table
Appendix F Environmental Licenses and
Permits
Appendix G Implementation
Schedule for Environmental Mitigation Measures (EMIS)
Appendix H Statistics
on Environmental Complaints, Notification of Summons and Successful
Prosecutions
Appendix I[CK1]
Environmental Site Inspection
Schedule
Executive Summary
This
Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for
Contract No. HY/2014/05 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary
Crossing Facilities (HZMB HKBCF) ¡V Remaining Ancillary
Buildings and Facilities (includes the construction works of Contract No.
HY/2013/06 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities
¡V Automatic Vehicle Clearance Support System within Contract No. HY/2014/05
works area) (hereafter referred to as ¡§the Contract¡¨) for the Highways
Department of Hong Kong Special Administrative Region (HKSAR). Contract No.
HY/2014/05 was awarded to Leighton ¡V Chun Wo Joint Venture (construction works
of Contract No. HY/2013/06 was awarded to ATAL Technologies Limited within
Contract No. HY/2014/05 works area) (hereafter referred to as ¡§the Contractor¡¨)
and Atkins China Limited was appointed as the Environmental Team (ET) by the
Contractor.
Contract
No. HY/2014/05 (includes the construction works of Contract No. HY/2013/06
within Contract No. HY/2014/05 works area) is part of HZMB HKBCF Project which
is a ¡§Designated
Project¡¨ under Schedule 2 of the Environmental Impact Assessment Ordinance
(EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No.
AEIAR-145/2009) was prepared for the Project. The current
Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April 2016.
These documents are available through the EIA Ordinance Register. The
construction works
of the
Contract No.
HY/2014/05 commenced on 29 February 2016 while the construction works of the
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area commenced on
3 January 2017.
Atkins
China Limited has been appointed by the Contractor to implement the
Environmental Monitoring & Audit (EM&A) programme for the Contract in
accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and
will be providing environmental team services to the Contract.
This
is the eleventh monthly EM&A Report for the Contract No.
HY/2014/05 which summarizes findings of the EM&A works during the reporting
period from 1 to 31 January 2017 (includes the findings of the EM&A
programme of Contract No HY/2013/06 within Contract No. HY/2014/05 works area).
Environmental Monitoring and Audit Progress
The
monthly EM&A programme was undertaken in accordance with the Updated
EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality
and noise monitoring works for the Contract are covered by
Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works and
Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V
Section between Scenic Hill and HKBCF.
The ET of the Contract or another ET of the HZMB project is required to
conduct impact air quality monitoring at AMS6 and AMS7 and noise monitoring at
NMS2 and NMS3B as part of EM&A programme if these monitoring stations are
no longer covered under Contract Nos. HY/2010/02 and HY/2011/03. However,
this is subject to ENPO¡¦s final decision on which ET should carry out the
monitoring work at these stations.
The dates of site inspection for the Contract No. HY/2014/05
(includes Contract No. HY/2013/06 within Contract No. HY/2014/05 works area) during
the reporting
period are listed below:
Environmental Site Inspection: 4,
11, 18 and 25 January 2017
Breaches of Action and Limit Levels
Summary
of Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6
shall be referred to the monthly EM&A report prepared by Contract No.
HY/2011/03.
There
was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level
recorded at AMS7 by the Environmental Team of Contract No. HY/2010/02 during
the reporting period.
There
was no Action and Limit Level exceedance for noise recorded at NMS2 and NMS3B
by the Environmental Team of Contract No. HY/2010/02 during the reporting
period.
Complaint Log
There
was no complaint received in relation to the environmental impact during the
reporting period.
Notifications of Summons and Successful
Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
period.
Reporting Change
Construction
works of Contract No. HY/2013/06 has been conducted
within the works area of Contract No. HY/2014/05 since 3 January 2017.
Future Key Issues
The
future key issues to be undertaken in the upcoming month include:
For
Contract No. HY/2014/05
¡P
Earth
Works for Buildings 050A2
¡P
Raft
foundation for Buildings 032, 044, 045 and 050A2
¡P
Construction
of RC Structure of Buildings 022, 023, 025, 032, 044 and 045
¡P
Installation
of window wall of Buildings 045
¡P
ABWF
works (Internal Finishes) of Buildings 021, 025, 053, 058 and 059
¡P
ABWF
works (External Finishes) of Buildings 025, 032, 053, 058 and 059
¡P
ABWF
works (Roof Finishes) of Buildings 021 and 025
¡P
Dog
Swimming Pool of Building 022
¡P
Utilities
and Drainage installation of Building 053 and 058
For
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation at Buildings 025 and 032
For Contract No. HY/2014/05
(i)
Construction of the following
ancillary buildings and facilities including architectural and builder works,
structural steel canopy, reinforced concrete frames, foundations, curtain wall
facade, building services and electrical and mechanical works:
•
Public Toilets at Vehicle Clearance
Plaza (VCP);
•
Customs and Excise Department
(C&ED) Dangerous Good Store (Building 021);
•
Customs Detective Dog Base Building
(Building 022);
•
C&ED Outbound Cargo Examination
Building and Examination Platform (Building 023);
•
Inbound Private Car Annexure
(Building 025);
•
Outbound Private Car Annexure
(Building 032);
•
E&M maintenance Building
(Building 044);
•
Highways Depot & Administration
Building (Building 045);
•
Outbound X-ray Building (Building
053);
•
Outbound X-ray Scan Tunnel (Building
058); and
•
Inbound X-ray Scan Tunnel (Building
059).
(ii)
Construction of civil provisions,
cable containment and power supply for the following systems:
•
Extra Low Voltage (ELV) installed by
Contract No. HY/2013/03;
•
Automatic Vehicle Clearance Support
System (AVCSS) installed by Contract No. HY/2013/06; and
•
Gantry Type X-ray Vehicle Inspection
System installed by Contract No. HY/2014/04.
(iii)
Supply and installation of Mobile
X-ray Vehicle Inspection System and other standalone equipment;
(iv) Construction
of minor civil engineering works at the periphery of buildings;
(v)
Construction of minor Landscape
hardworks and softworks; and
(vi) Other
works which are shown on Drawings or specified in the Specification or which
may be ordered in accordance with the Contract.
For Contract No. HY/2013/06
within Contract No. HY/2014/05 works area
(i)
The Automatic Vehicle Clearance
Support System amid to increasing traffic flow for Hong Kong-Zhuhai-Macao
Bridge Hong Kong Boundary Crossing Facilities;
(ii)
Responsible for designs and develops a
set of tailor-made computer monitoring and control systems to for daily
security operation; and
(iii)
The Clearance Workstations at 72
vehicle clearance kiosks, Customs and Excise¡¦s inbound and outbound traffic control
centers as well as a Vehicle Tracking System
Table 1‑1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
For Contract No. HY/2014/05 |
||||
Engineer or Engineer¡¦s Representative |
Chief Resident Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker
(Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Albert Chan |
3973 0514 |
3621 0180 |
Environmental Officer |
Wu Yun Kau |
5505 8633 |
3621 0180 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint
hotline |
--- |
--- |
3958 7300 |
--- |
For Contract No. HY/2013/06 within Contract No.
HY/2014/05 works area |
||||
Engineer or Engineer¡¦s Representative |
Chief Resident Engineer |
Darrel Kingan |
3958 7339 |
3468 2076 |
Environmental Project Office / Independent Environmental Checker
(Ramboll Environ Hong Kong Limited) |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
|
Contractor |
Site Agent |
Mr. Eric Yim |
2565 3355 |
3162 5217 |
Environmental Officer |
Mr. W. Li |
2565 3137 |
3162 5217 |
|
Environmental Team |
Environmental Team Leader |
Keith Chau |
2972 1721 |
2890 6343 |
24 hours complaint hotline |
--- |
--- |
6509 0375 |
--- |
For Contract No. HY/2014/05
¡P
Earth
Works for Buildings 022 and 050A2
¡P
Raft
foundation for Buildings 022, 044, 045 and 050A2
¡P
Construction
of RC Structure of Buildings 021, 023, 023, 025, 032, 044 &045
¡P
Installation
of window wall of Buildings 022, 044 and 045
¡P
Blockwork
walls construction of Buildings 025 and 053
¡P
ABWF
works of Buildings 023, 025, 053& 058 and 059
For
Contract No. HY/2013/06 within Contract No. HY/2014/05 works area
¡P
Conceal
Conduit Installation Buildings 025 and 032
Table 2‑1 Construction
Dust Monitoring Locations
ID |
Location
Description |
AMS 6(1) |
Dragonair/CNAC (Group) Building |
AMS 7(1) |
Hong Kong SkyCity Marriott Hotel |
Remark:
(1) The ET of this Contract should conduct impact air
quality monitoring at the AMS listed in the table as part of EM&A programme
according to the latest notification
from ENPO when the monitoring station(s) is/are no longer covered by another ET
of the HZMB project.
Table 2‑2 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
360 |
500 |
AMS 7 - Hong Kong SkyCity Marriott Hotel |
370 |
Table 2‑3
Action
and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
173 |
260 |
AMS 7 - Hong Kong SkyCity Marriott Hotel |
183 |
Table 3‑1 Construction
Noise Monitoring Locations
ID |
Location Description |
NMS2(1) |
Seaview
Crescent |
NMS3B(1)(2) |
Site Boundary
of Site Office
Area at Works Area WA2 |
Remarks:
(1)
The ET of
this Contract should conduct impact noise monitoring at the NMS listed in the
table as part of EM&A programme according to the latest notification from ENPO when the monitoring station(s)
is/are no longer covered by another ET of the HZMB project.
(2)
The Action
and Limit Levels for schools will be applied for this alternative monitoring
location.
Table 3‑2 Action
and Limit Level for Construction Noise
Parameter |
Action Level |
Limit Level |
07:00 ¡V 19:00 hours
on normal weekdays |
When one
documented complaint is received |
75 dB(A)* |
Notes :
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Limit level is 70 dB(A) for schools and 65 dB(A) during school examination period.
Table 4‑1 Summary
of Environmental Site Inspections for Contract No. HY/2014/05
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
28 December 2016 |
1.Chemical containers were placed on the
ground without drip tray at Building 023. |
1.Chemical
containers were removed at Building 023. |
4
January 2017 |
4 January 2017 |
No particular environmental issue was recorded during
the site inspection. |
Nil. |
Nil. |
11 January 2017 |
1.Chemical drums
were found without drip tray at Building 032. 2.Chemical drums
were found without proper chemical labels near a generator at Building 032. |
1.The drip tray were
provided for chemical container at Building 032. 2.The proper label
was provided for the chemical container at Building 032. |
18
January 2017 |
18 January 2017 |
1.The construction
waste were accumulated near Building 044. 2.Chemical label is
damaged on the chemical container at Building 032. 3.The chemical
container was found without drip tray at Building 023. |
1.Construction
waste was removed and site cleanliness has been maintained. 2.Chemical label
has been provided to the drum. 3.The chemical
container was removed at Building 023. |
25
January 2017 |
25 January 2017 |
1.A crawler crane
was found without NRMM label at Building 032. 2.Two chemical
containers were found without drip tray at Building 044. |
1.The Contractor
was reminded to ensure all non-road mobile machinery display NRMM labels
properly. 2.The Contractor
was reminded to provide the drip tray for chemical containers at Building
044. |
Follow-up
action undertaken by the Contractor will be inspected during the site
inspection to be undertaken in February 2017. |
Table
4‑2 Summary
of Environmental Site Inspections for Contract No. HY/2013/06 within Contract
No. HY/2014/05 works area
Date of Audit |
Observations |
Actions Taken by Contractor /
Recommendation |
Date of Observations Closed |
4 January 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
11 January 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
18 January 2017 |
No particular environmental issue was recorded during
the site inspection. |
Nil. |
Nil. |
25 January 2017 |
No particular environmental issue was recorded
during the site inspection. |
Nil. |
Nil. |
Table 5-1 Construction
Activities for February 2017
Site Area |
Description of Activities |
For Contract No. HY/2014/05 |
|
Buildings
050A2 |
Earth works |
Buildings
032, 044, 045 and 050A2 |
Raft foundation |
Buildings
022, 023, 025, 032, 044 and 045 |
Construction of reinforced concrete structure |
Buildings
045 |
Installation of window wall |
Buildings
021, 025, 053, 058 and 059 |
ABWF works (Internal Finishes) |
Buildings
025, 032, 053, 058 and 059 |
ABWF works (External Finishes) |
Buildings
021 and 025 |
ABWF works (Roof Finishes) |
Building
053 and 058 |
Utilities and Drainage installation |
Building
022 |
Dog swimming pool |
For Contract No. HY/2013/06 within Contract No. HY/2014/05 works area |
|
Buildings
025 and 032 |
Conceal Conduit Installation |