EXECUTIVE SUMMARY

This Final Environmental Monitoring and Audit (EM&A) Review Report is prepared for Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨ (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). Contract No. HY/2019/01 was awarded to China Harbour Engineering Co. Limited and Fugro Technical Services Limited (FTS) was appointed as the Environmental Team (ET) by the Contractor.

 

Contract No. HY/2019/01 is part of the ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities¡¨ (HZMB HKBCF) Project which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009) was prepared and approved. The current Environmental Permit (EP) for HKBCF, namely No. EP-353/2009/K, was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. Commencement of the Contract took place on 4 December 2019 and the construction site preparation works commenced in early February 2020.

 

Fugro Technical Services Limited (FTS) has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and is providing environmental team services for the Contract.

 

This is the Final EM&A Review Report for the Contract which summaries findings of the EM&A programme during the reporting period from 5 February 2020 to 4 January 2023 (the date of the contract ends).

 

Environmental Monitoring and Audit Progress

The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality, noise and the post-construction dolphin monitoring works for the Contract are covered by Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨.

 

Air Quality Monitoring

 

In accordance with the Contract Specific EM&A Manual, four air quality monitoring locations, namely AMS2, AMS3C, AMS6 and AMS7B were set up at the proposed locations. AMS2, AMS3C and AMS7B are covered by Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai- Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨

 

AMS6 is covered by Contract No. HY/2011/03 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road (HZMB HKLR) ¡V Section between Scenic Hill and HKBCF¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 as part of EM&A programme if this air quality monitoring station is no longer covered by Contract No. HY/2011/03. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations. The monitoring results for AMS6 are reported in the monthly EM&A Reports prepared for Contract No. HY/2011/03.

 

Due to the existing air quality monitoring location AMS7B would be hand over back to Airport Authority for their construction works. Air quality monitoring location AMS7B was temporary suspended, effective from 10 December 2020 to 30 September 2021. According to the email date 11 August 2021, EPD have no comment on the Proposal for Relocation of Monitoring Location AMS7B, the monitoring location AMS7B are proposed to be relocated by alternative monitoring location AMS7C for air quality monitoring. The monitoring location AMS7C has resumed air quality monitoring on 5 October 2021.

 

According to the EPD¡¦s reply email, EPD has no comment on the Proposal for Termination of Air quality and Noise Monitoring, the air quality monitoring for Contract No: HY/2019/01 have been terminated on 25 March 2022. The last monitoring was completed on 24 March 2022.

 

Noise Monitoring

 

In accordance with the Contract Specific EM&A Manual, two noise monitoring locations, namely NMS2 and NMS3C are covered under Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works.

 

Due to rejection from Ho Yu College (NMS3) for setting up a noise monitoring station at their school, an alternative location at site boundary of the site office area at Works Area WA2 (NMS3B) is proposed. Impact noise monitoring has been relocated from NMS3B to Ying Tung Estate Market Rooftop (NMS3C) on 20 August 2018 under Contract No. HY/2013/04. The same baseline and Action and Limit levels for noise, as derived from the baseline monitoring data recorded at Ho Yu College, are adopted for this alternative noise monitoring location.

 

According to the EPD¡¦s reply email, EPD has no comment on the Proposal for Termination of Air quality and Noise Monitoring, the noise monitoring for Contract No: HY/2019/01 have been terminated on 25 March 2022. The last monitoring was completed on 24 March 2022.

 

Ecology Monitoring

 

All marine-based construction activities for the HKBCF project were completed in January 2019. No marine-based construction activities will be undertaken under this Contract. However, the ET of this Contract or another ET of the HZMB is required to conduct post-construction dolphin monitoring in accordance with Section 10.7 of the updated EM&A Manual.

 

In accordance with the requirements of the updated EM&A manual, the dolphin monitoring programme have adopted the standard line-transect method (Buckland et al. 2001) to survey the pre-set and fixed transect lines defined by AFCD in the Northeast Lantau (NEL) and Northwest Lantau (NWL) survey areas. The layout map of the transect lines provided by AFCD is presented in Figure 4.

 

The ecological monitoring works for the HKBCF project are covered by Contract No. HY/2013/04 ¡§Hong Kong-Zhuhai-Macao-Bridge HKBCF ¡V Infrastructure Works Stage II (Southern Portion)¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct post-construction dolphin monitoring at 24 transects as part of EM&A programme if these transects are no longer covered by Contract No. HY/2013/04.

 

The dolphin survey results for all transects are reported in the monthly EM&A Reports prepared by Contract No. HY/2013/04 for February 2020.

 

From March 2020, the role of dolphin monitoring and data collection are under Contract No. HY/2012/08 ¡§Tuen Mun-Chek Lap Kok Link ¡V Northern Connection Sub-sea Tunnel Section¡¨. To avoid redundancy in the monitoring effort, the findings of Contract No. HY/2012/08 were used from March 2020 to February 2021.

 

According to the Proposal on Post-construction Dolphin Monitoring (PCDM) prepared by Contract No. HY/2013/04 which has been verified by ENPO and approved by EPD on 8 March 2019 (EPD ref. () in Ax(5) to E771/E1/100) , the completion date of the PCDM is in February 2021. Therefore, the reporting of Chinese White Dolphins monitoring works under this contract was suspended on 1 March 2021.

 

Dolphin Final Review Report was submitted on 28 November 2022 and verified by IEC on 2 December 2022. Details of the final review of dolphin monitoring for HKBCF are presented in Quarterly EM&A Report for December 2020 to February 2021.

 

Site Inspection

 

Site audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project site.

 

According to the EPD¡¦s letter (EPD ref. () in AX(12) in EP771/E1/100), EPD has no comment on the Proposal for Termination of EM&A Programme in Construction Phase, the site inspection for Contract No: HY/2019/01 have been terminated on 5 July 2022. The last inspection was completed on 29 June 2022.

 

Landscape and Visual Site Audit

 

To monitor and audit the implementation of landscape and visual mitigation measures, Bi-weekly landscape and visual site audits were carried out by a Registered Landscape Architect from July 2020 to January 2022.

 

As informed by AECOM, the commencement date of the 12-month establishment period for the landscape monitoring under this contract is 5 January 2022. Bi-monthly landscape and visual site audits would be conducted from 5 January 2022 to 4 January 2023.

 

Breaches of Action and Limit Levels

No Action and Limit Level exceedance was recorded for air quality monitoring in the reporting period. Also, no Action and Limit Level exceedance was recorded for construction noise monitoring in the reporting period.

 

Complaint Log

No complaints were received in the reporting period.

Notifications of any Summons and Successful Prosecutions

No notifications of summons and prosecutions were received in the reporting period.

 

 

Contents

EXECUTIVE SUMMARY  1

1.          INTRODUCTION   5

2.         EM&A REQUIREMENTS  8

3.         ENVIRONMENTAL MONITORING AND AUDIT  10

4.         ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE  13

5.         CONCLUSION AND RECOMMENDATION   14

 

 


Figures

Figure 1          The Site Layout Plan of the Contract 

Figure 2         The Location of the Air Quality Monitoring Station

Figure 3         The Location of the Noise Monitoring Station

Figure 4         Post-Construction Dolphin Monitoring Line Transect Layout Map

 


Appendices

Appendix A  Construction Programme

Appendix B  Project Organization Chart

Appendix C  Action and Limit Levels

Appendix D Event and Action Plan

Appendix E  Graphical Presentation of Air Quality Monitoring Results and Construction Noise Monitoring Results

Appendix F  Implementation Status of Environment Mitigation Measures (Construction Phase)

Appendix G  Implementation Status of Environment Mitigation Measures (Establishment Period)

Appendix H Summary of Site Audit in Reporting Period

Appendix I   Record of Outstanding Issues and Deficiencies

Appendix J   Waste Flow Table

Appendix K  Cumulative statistics on Environmental Complaints, Notifications of Summons and Successful Prosecutions

 


1.       INTRODUCTION

1.1    Background

1.1.1               Fugro Technical Services Limited was commissioned by China Harbour Engineering Co. Limited (also referred to as ¡§the Contractor¡¨) to undertake the Environmental Team (ET) services (including environmental monitoring and audit (EM&A)) for Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨.

1.1.2               Contract No. HY/2019/01 is part of the ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities¡¨ (HZMB HKBCF) Project which is a ¡§Designated Project¡¨ under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap. 499) and for which an EIA Report (Register No. AEIAR-145/2009) was prepared and approved. The current Environmental Permit (EP) for HKBCF, namely No. EP-353/2009/K, was issued on 11 April 2016. These documents are available through the EIA Ordinance Register. The general layout of the Project area is shown in Figure 1. Commencement of the Contract took place on 4 December 2019 and the construction site preparation works commenced in early February 2020.

1.1.3               This is the Final EM&A review report to document the findings of site inspection activities and EM&A programme carried out by the Contractor of Contract No. HY/2019/01 during the reporting period from 5 February 2020 to 4 January 2023 (the date of the contract ends) and is submitted to fulfil Condition 5.4 of the EP.

1.2    Project Description

1.2.1               The works to be executed under Contract No. HY/2019/01 include the following major items:

¡P       Landscaping and establishment works;

¡P       Irrigation system and associated drainage pumping system and facilities;

¡P       Erection and installation in the Passenger Clearance Building;

¡P       Public transport interchange (PTI) public toilet, satellite refuse collection point (RCP) and observation guard booths;

¡P       PTI cross boundary shuttle (CBS) / cross boundary coach (CBC) lanes and covered walkway;

¡P       Vehicle clearance plazas (VCP) vehicle kiosks and associate automatic vehicle clearance supporting system (AVCSS).

1.3    Project Organization

1.3.1               The Project Organization structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1.

Table 1.1              Contact Information of Key Personnel

Party

Position

Name

Telephone

Engineer or Engineer¡¦s

Representative

(AECOM Asia Co. Ltd.)

Senior Resident Engineer

Mr. Jason Yu

3748 8903

Resident Engineer

(until 31 December 2021)

Mr. Winston Wong

3748 8918

Resident Engineer

(until 31 August 2022)

Mr. Gordon Kok

3748 8967

Resident Engineer

(from 1 September 2022)

Mr. K.W. Wong

3748 8967

Environmental Project Office / Independent Environmental Checker

(Ramboll Hong Kong Limited)

(until 30 September 2022)

Environmental Project Office Leader

Mr. Y. H. Hui

3465 2888

Independent Environmental Checker (IEC)

(until 17 May 2020)

Mr. Ray Yan

34652836

Independent Environmental Checker (IEC)

(from 18 May 2020 to 11 April 2021)

Mr. Manson Yeung

9700 6767

Independent Environmental Checker (IEC)
(from 12 April 2021 to 30 April 2022)

Mr. Brian Tam

9700 6767

Independent Environmental Checker (IEC)

(from 1 May 2022 to 30 June 2022)

Mr. Adi Lee

9700 6767

Independent Environmental Checker (IEC)

(from 1 July 2022)

Mr. Brian Tam

9700 6767

Environmental Site Supervisor

(until 17 May 2020)

Mr. Manson Yeung

9700 6767

Environmental Site Supervisor

(from 18 May 2020)

Mr. K. C. Chan

3465 2882

Environmental Project Office / Independent Environmental Checker

(ANewR Consulting Limited)

(from 1 October 2022)

Environmental Project Office Leader

Mr. Louis Kwan

2618 2836

Independent Environmental Checker (IEC)

Mr. James Choi

2618 2836

Environmental Site Supervisor

Mr. Ricky Lau

2618 2836

Contractor

(China Harbour Engineering Co. Ltd)

Environmental Manager

Mr. Marko Chan

9427 2879

Environmental Officer

Mr. Matthew Wu

6076 2675

Environmental Team

(Fugro Technical Services Limited)

Environmental Team Leader

(ETL)

Mr. Calvin Leung

3565 4441

1.4    Construction Programme and Activities

1.4.1               The site layout plan of the Contract is shown in Figure 1.

1.4.2               The construction programme of this Contract is shown in Appendix A.

2.       EM&A REQUIREMENTS

2.1    Summary of EM&A Requirement

2.1.1               The EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality, noise and the post-construction dolphin monitoring works for the Contract are covered by Contract No. HY/2019/01 ¡§Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V Phase 2 and Other Works¡¨.

2.1.2               According to the Contract Specific EM&A Manual, air quality monitoring at station AMS2, AMS3C and AMS7B, and noise monitoring at station NMS2 and NMS3C are covered by Contract No. HY/2019/01. It should be noted that the air quality monitoring at station AMS6 is covered by Contract No. HY/2011/03. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 as part of EM&A programme if the impact air quality monitoring work is no longer covered by Contract No. HY/2011/03 respectively. However, this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring work at these stations.

2.1.3               Due to the existing air quality monitoring location AMS7B would be hand over back to Airport Authority for their construction works. Air quality monitoring location AMS7B was temporary suspended, effective from 10 December 2020 to 30 September 2021. According to the email date 11 August 2021, EPD have no comment on the Proposal for Relocation of Monitoring Location AMS7B, the monitoring location AMS7B are proposed to be relocated by alternative monitoring location AMS7C for air quality monitoring. The monitoring location AMS7C has resumed air quality monitoring on 5 October 2021.

2.1.4               Due to the rejection from Ho Yu College (NMS3) for setting up a noise monitoring station at their school, an alternative location at site boundary of the site office area at Works Area WA2 (NMS3B) is proposed. Impact noise monitoring has been relocated from NMS3B to Ying Tung Estate Refuse Collection Point (NMS3C) on 20 August 2018 under Contract No. HY/2013/04. The same baseline and Action and Limit levels for noise, as derived from the baseline monitoring data recorded at Ho Yu College, are adopted for this alternative noise monitoring location.

2.1.5               The air and noise locations are summarized in Table 2.1. The locations of the air quality and noise monitoring stations shown in Figure 2 and Figure 3, respectively.

Table 2.1              Air Quality and Noise Monitoring Location

Environmental Monitoring

Monitoring Station

Location

Air Quality

AMS2

Tung Chung Development Pier

AMS3C

Ying Tung Estate Market Rooftop

AMS6

Dragonair / CNAC (Group) Building (HKIA)

AMS7B

Third Runway Site Office

AMS7C

East Sea Rescue Berth ¡V Airport Fire Contingent

Noise

NMS2

Seaview Crescent

NMS3C

Ying Tung Estate Refuse Collection Point

Remarks:

1.        The ET of this Contract should conduct impact air quality monitoring at station AMS6 listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station is no longer covered by another ET of the HZMB project.

2.        The Limit Levels for schools will be applied for NMS3C.

2.1.6               All marine-based construction activities for the HKBCF project were completed in January 2019. No marine-based construction activities will be undertaken under this Contract. However, the ET of this Contract or another ET of the HZMB is required to conduct post-construction dolphin monitoring in accordance with Section 10.7 of the updated EM&A Manual.

2.1.7               In accordance with the requirements of the updated EM&A manual, the dolphin monitoring programme have adopted the standard line-transect method (Buckland et al. 2001) to survey the pre-set and fixed transect lines defined by AFCD in the Northeast Lantau (NEL) and Northwest Lantau (NWL) survey areas. The layout map of the transect lines provided by AFCD is presented in Figure 4.

2.1.8               The ecological monitoring works for the HKBCF project are covered by Contract No. HY/2013/04 ¡§Hong Kong-Zhuhai-Macao-Bridge HKBCF ¡V Infrastructure Works Stage II (Southern Portion)¡¨. The ET of the Contract or another ET of the HZMB project is required to conduct post-construction dolphin monitoring at 24 transects as part of EM&A programme if these transects are no longer covered by Contract No. HY/2013/04.

2.2    Monitoring Requirement

2.2.1               The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A report prepared for this Contract.

2.2.2               The air quality monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information for AMS6 are detailed in the monthly EM&A report prepared for Contract No. HY/2011/03.

2.3    Action and Limit Levels

2.3.1               The Action and Limit Levels for Air quality and noise monitoring have been set and are presented in Appendix C.

2.4    Event and Action Plans

2.4.1               The event and action plans for air quality and noise monitoring are presented in Appendix D.

2.5    Mitigation Measures

2.5.1               The Contractor had implemented environmental mitigation measures and requirements as stated in the EIA Reports, the EP and EM&A Manuals. The implementation status of the environmental mitigation measures during the reporting period is summarized in Appendix F (Construction Phase) and Appendix G (Establishment Period).

 

3.       ENVIRONMENTAL MONITORING AND AUDIT

3.1    Air Quality Monitoring Results

3.1.1               1-hour TSP and 24-hour TSP impact monitoring at AMS2, AMS3C, AMS7B/ AMS7C were carried out in the reporting period, the monitoring results are reported in the monthly EM&A Report prepared for this Contract. The graphical presentation of 1-hr TSP and 24-hr TSP are presented in Appendix E.

3.1.2               There was no Action / Limit Level exceedance of 1-hour TSP level and 24-hour TSP level at AMS2, AMS3C and AMS7B/ AMS7C was recorded during the reporting period.

3.1.3               The monitoring results for AMS6 are reported in the monthly EM&A Reports prepared for Contract No. HY/2011/03.

3.1.4               Summary of Action and Limit Level exceedance of 1-hour TSP level and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

3.1.5               According to the EPD¡¦s reply email, EPD has no comment on the Proposal for Termination of Air quality and Noise Monitoring, the air quality monitoring for Contract No: HY/2019/01 have been terminated on 25 March 2022. The last monitoring was completed on 24 March 2022.

3.2    Noise Monitoring Results

3.2.1               Construction noise monitoring were carried out in the reporting period, the monitoring results for NMS2 and NMS3C are reported in the monthly EM&A Reports prepared for this Contract. The graphical presentation of noise monitoring data are presented in Appendix E.

3.2.2               There was no Action / Limit Level exceedance for construction noise at NMS2 and NMS3C was recorded during the reporting period.

3.2.3               According to the EPD¡¦s reply email, EPD has no comment on the Proposal for Termination of Air quality and Noise Monitoring, the noise monitoring for Contract No: HY/2019/01 will be terminated on 25 March 2022. The last monitoring was completed on 24 March 2022.

3.3    Ecology Monitoring

3.3.1               The dolphin survey results for all transects are reported in the monthly EM&A Reports prepared by Contract No. HY/2013/04 for February 2020.

3.3.2               From March 2020, the role of dolphin monitoring and data collection are under Contract No. HY/2012/08 ¡§Tuen Mun-Chek Lap Kok Link ¡V Northern Connection Sub-sea Tunnel Section¡¨. To avoid redundancy in the monitoring effort, the findings of Contract No. HY/2012/08 were used from March 2020 to February 2021.

3.3.3               According to the Proposal on Post-construction Dolphin Monitoring (PCDM) prepared by Contract No. HY/2013/04 which has been verified by ENPO and approved by EPD on 8 March 2019 (EPD ref. () in Ax(5) to E771/E1/100) , the completion date of the PCDM is in February 2021. Therefore, the reporting of Chinese White Dolphins monitoring works under this contract was suspended on 1 March 2021.

3.3.4               Dolphin Final Review Report was submitted on 28 November 2022 and verified by IEC on 2 December 2022. Details of the final review of dolphin monitoring for HKBCF are presented in Quarterly EM&A Report for December 2020 to February 2021.

3.4    Site Inspection

3.4.1               Site audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project site. In the reporting period, a total of 125 site inspections were carried out. Details of observations recorded during the site inspections are summarized in Appendix H.

3.4.2               According to the EPD¡¦s letter (EPD ref. () in AX(12) in EP771/E1/100), EPD has no comment on the Proposal for Termination of EM&A Programme in Construction Phase, the site inspection for Contract No: HY/2019/01 have been terminated on 5 July 2022. The last inspection was completed on 29 June 2022.

3.5    Landscape and Visual Site Audit

3.5.1               To monitor and audit the implementation of landscape and visual mitigation measures, a total of 39 Bi-weekly landscape and visual site audits were carried out in the reporting period by a Registered Landscape Architect.

3.5.2                              As informed by AECOM, the commencement date of the 12-month establishment period for the landscape monitoring under this contract is 5 January 2022. Bi-monthly landscape and visual site audits will be conducted from 5 January 2022 to 4 January 2023. A total of 6 bi-monthly landscape and visual site audit was carried out in the 12-month establishment period by the IEC, the engineer, the contractor and the ET¡¦s Registered Landscape Architect.

3.6    Advice on the Solid and Liquid Waste Management Status

3.6.1               The Contractor registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting. 

3.6.2               The summary of waste flow table is detailed in Appendix J.

3.6.3               If off-site disposal is required, the excavated marine mud from the land-based works shall be disposed of at the designated disposal sites within Hong Kong as allocated by the Marine Fill Committee or other locations as agreed by the Director. The Contractor shall ensure no spilling and overflowing of materials during loading / unloading / transportation is allowed.

3.6.4               The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

4.       ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE

4.1    Environmental Exceedance

4.1.1                              No Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3C, AMS7B and AMS7C in the reporting period.

4.1.2                              Summary of Action and Limit Level exceedance of 1-hour TSP level and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

4.1.3                              No Action and Limit Level exceedance was recorded for construction noise monitoring at station NMS2 and NMS3C in the reporting period.

4.2    Complaints, Notification of Summons and Prosecution

4.2.1               No environmental complaint, notification of summons and successful prosecution were received in the reporting period.

4.2.2               Cumulative complaint log, summaries of complaints, notification of summons and successful prosecutions are presented in Appendix K.

5.       CONCLUSION AND RECOMMENDATION

5.1    Conclusions

5.1.1                              No Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS2, AMS3C, AMS7B and AMS7C in the reporting period.

5.1.2                              Summary of Action and Limit Level exceedance of 1-hour TSP level and 24-hour TSP level at AMS6 shall be referred to the monthly EM&A report prepared by Contract No. HY/2011/03.

5.1.3                              No Action and Limit Level exceedance was recorded for construction noise monitoring at station NMS2 and NMS3C in the reporting period.

5.1.4               According to the EPD¡¦s reply email, EPD has no comment on the Proposal for Termination of Air quality and Noise Monitoring, the air quality and noise monitoring for Contract No: HY/2019/01 have been terminated on 25 March 2022. The last monitoring was completed on 24 March 2022.

5.1.5               The dolphin survey results for all transects are reported in the monthly EM&A Reports prepared by Contract No. HY/2013/04 for February 2020 and Contract No. HY/2012/08 for March 2020 to February 2021.

5.1.6               According to the Proposal on Post-construction Dolphin Monitoring (PCDM) prepared by Contract No. HY/2013/04 which has been verified by ENPO and approved by EPD on 8 March 2019 (EPD ref. () in Ax(5) to E771/E1/100) , the completion date of the PCDM is in February 2021. Therefore, the reporting of Chinese White Dolphins monitoring works under this contract was suspended on 1 March 2021.

5.1.7               Dolphin Final Review Report was submitted on 28 November 2022 and verified by IEC on 2 December 2022. Details of the final review of dolphin monitoring for HKBCF are presented in the Quarterly EM&A Report for December 2020 to February 2021.

5.1.8               Site audits were carried out by ET on weekly basis to monitor the implementation of proper environmental management practices and mitigation measures in the Project site. In the reporting period, a total of 125 site inspections were carried out.

5.1.9               To monitor and audit the implementation of landscape and visual mitigation measures, a total of 39 Bi-weekly landscape and visual site audits were carried out in the reporting period by a Registered Landscape Architect.

5.1.10            According to the EPD¡¦s letter (EPD ref. () in AX(12) in EP771/E1/100), EPD has no comment on the Proposal for Termination of EM&A Programme in Construction Phase, the site inspection for Contract No: HY/2019/01 have been terminated on 5 July 2022. The last inspection was completed on 29 June 2022.

5.1.11            As informed by AECOM, the commencement date of the 12-month establishment period for the landscape monitoring under this contract is 5 January 2022. Bi-monthly landscape and visual site audits will be conducted from 5 January 2022 to 4 January 2023. Total 6 bi-monthly landscape and visual site audit was carried out in the 12-month establishment period by the IEC, the engineer, the contractor and the ET¡¦s Registered Landscape Architect.

5.1.12            Referring to the Contractor¡¦s information, no environmental complaint, notification of summons and successful prosecution was received in the reporting period.

5.1.13            The date of the contract ends would be 4 January 2023.

5.2    Comment and Recommendations

5.2.1               The recommended environmental mitigation measures, as proposed in the EIA reports and EM&A Manuals shall be effectively implemented to minimize the potential environmental impacts from the Project. The EM&A programme would effectively monitor the environmental impacts generated from the construction activities and ensure the proper implementation of mitigation measures.