Table of Contents
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Dolphin monitoring
2.5 EM&A Site inspection
2.6 Waste Management Status
2.7 Environmental Licenses and
Permits
2.8 Implementation Status of
Environmental Mitigation Measures
2.9 Summary of Exceedances of the
Environmental Quality Performance Limit
2.10 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Programme for
the Coming Months
3.2 Key Issues for the Coming
Month
3.3 Monitoring Schedule for the
Coming Month
4 Conclusions
and recommendations
4.1 Conclusions
List
of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule of Environmental Mitigation
Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
Impact Air Quality Monitoring Results and Graphical
Presentation |
Appendix H |
|
Appendix I |
|
Appendix J |
Impact Water Quality Monitoring Results and
Graphical Presentation |
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
Under Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker
(IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications
for variation of environmental permit (VEP), EP-354/2009/B and
EP-354/2009/C, were granted on 28 January 2014 and 10 December 2014,
respectively.
The construction phase of the Contract commenced on 31
October 2013 and will tentatively be completed by 2018. The impact monitoring of the EM&A programme, including air quality, noise, water quality and
marine ecological monitoring as well as environmental site inspections,
commenced on 31 October 2013.
This is the Sixteenth Monthly EM&A report
presenting the EM&A works carried out during the period from 1 to 28 February
2015 for the Southern Connection Viaduct Section in
accordance with the Updated EM&A Manual of the TM-CLK
Link Project. As informed by the
Contractor, major activities in the reporting period included:
Marine
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour
TSP monitoring 6
sessions
1-hour
TSP monitoring 6
sessions
Noise
monitoring 6
sessions
Impact Water
Quality Monitoring 10
sessions
Impact Dolphin
Monitoring 2
sessions
Joint
Environmental site inspection 4
sessions
Breaches of Action and Limit Levels for Air Quality
No exceedance
of Action and Limit Levels was recorded for construction air monitoring in the
reporting month.
Breaches of Action and Limit Levels for Noise
No exceedance
of Action and Limit Levels was recorded for construction noise monitoring in
the reporting month.
Breaches of Action and Limit Levels for Water Quality
No exceedance
of Action and Limit Levels was recorded for impact water quality monitoring in
the reporting month.
Impact Dolphin Monitoring
Whilst
one (1) Limit Level exceedance was observed for the quarterly dolphin
monitoring data between December 2014 and February 2015, no unacceptable impact
from the construction activities of the TM-CLKL Southern Connection Viaduct
Section on Chinese White Dolphins was noticeable from general
observations. Due to monthly
variation in dolphin occurrence within the study area, it would be more
appropriate to draw conclusion on whether any impacts on dolphins have been
detected related to the construction activities of the TM-CLKL Southern
Connection Viaduct Section in the quarterly EM&A reports, where comparison
on distribution, group size and encounter rates of dolphins between the
quarterly impact monitoring period and baseline monitoring period will be made.
Daily
marine mammal exclusion zone monitoring was undertaken during the period of
marine works under this Contract. Passive Acoustic Monitoring (PAM) was implemented
when the marine works were carried out outside the daylight hours in this
reporting month. No sighting of the Indo-Pacific humpback dolphin Sousa chinensis
(i.e. Chinese White Dolphin) was recorded in February 2015 during the exclusion
zone monitoring.
Environmental Complaints, Non-compliance & Summons
No
environmental complaint, notification of summons and successful prosecution was
received in the reporting month.
Reporting Change
There was no
reporting change required in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be
undertaken in the next monitoring period of March 2015 include the following:
Marine
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts A, C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of March 2015 are mainly associated with dust,
noise, marine water quality, marine ecology and waste management issues.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau
Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based
on the estimated increase in cross boundary traffic, developments in the
Northwest New Territories (NWNT), and possible developments in North Lantau,
including the Airport developments, the Lantau Logistics Park (LLP) and the
Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).
In order to cope with the anticipated traffic demand, two new road
sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007) and
the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The
EIA Report was submitted under the Environmental Impact Assessment Ordinance
(EIAO) in August 2009. Subsequent
to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an
Environmental Permit (EP-354/2009)
for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4
November 2009, and EP variation (EP-354/2009/A)
was issued on 8 December 2010.
Under
Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications for variation of
environmental permit (VEP), EP-354/2009/B
and EP-354/2009/C, were granted
on 28 January 2014 and 10 December 2014, respectively.
The
organization structure of the Contract is shown in Appendix A. The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD
(Highways Department) |
Project
Coordinator |
Stanley Chan |
2762 3406 |
3188 6614 |
|
Senior
Engineer |
Steven Shum |
2762 4133 |
3188 6614 |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident
Engineer |
Kingman Chan |
3691 3950 |
3691 2899 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465 2888 |
3465 2899 |
IEC |
Dr. F.C.
Tsang |
3465 2828 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy
Tam |
2271 3113 |
2723 5660 |
Marine
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
The
locations of the construction activities are shown in Figure 1.3. The
Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.4.
Figure 1.3 Locations
of Construction Activities in the Reporting Month
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are
summarized in the following sections.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
Description |
Monitoring Dates |
ASR 9 |
MTR Depot |
On the
ground nearby MTR Depot Entrance |
3, 9, 12, 17,
23 and 26 February 2015 |
ASR 8A |
Area 4 |
On ground at
the works area, Area 4 |
3, 9, 12,
17, 23 and 26 February 2015 |
High Volume Samplers (HVSs) were used for carried out 1-hour and 24-hour
TSP monitoring on 3, 9, 12, 17, 23 and 26 February 2015 at ASR8A and ASR9 in
accordance with the requirements of the Updated EM&A Manual. The TSP monitoring stations are
illustrated in Figure 2.1 and detailed
in Table 2.1. Wind anemometer was deployed at Area 4
for logging wind speed and wind direction.
Copies of the calibration certificates for the
equipment are presented in Appendix E.
Details of the deployed equipment are given in Table 2.2.
Table 2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume
Sampler |
Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High
Volume Sampler (Model No. TE-5170) |
Wind Sensor |
Global Water
(Wind Speed Sensor: WE550; Wind Direction Sensor: WE570) |
Wind
Anemometer for calibration |
Lutron (Model
No. AM-4201) |
Table 2.3 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
118 |
68
- 211 |
394 |
500 |
ASR
9 |
132 |
68
- 241 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
72 |
54
¡V 104 |
178 |
260 |
ASR
9 |
89 |
51
¡V 117 |
178 |
260 |
All
1-hour and 24-hour TSP results were below the Action and Limit levels at all
monitoring locations in the reporting period. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Meteorological
information collected at ASR8A including
wind speed and wind direction is provided in Appendix H.
Noise
monitoring was performed on 3, 9, 12, 17, 23 and 26
February 2015 by using sound level meter at the designated monitoring
station NSR1A (Figure 2.2; Table 2.5)
in accordance with the requirements stipulated in the Updated EM&A
Manual. Acoustic calibrator was
deployed to check the sound level meters at a known sound pressure level. Details of the deployed equipment are
provided in Table 2.6. Copies of the calibration certificates
for the equipment are presented in Appendix E.
Table 2.5 Location
of Impact Noise Monitoring Station
Monitoring Station |
Location |
Description |
Parameter |
Frequency and Duration |
Monitoring Dates |
NSR 1A |
Pak Mong Village Pavilion |
On the
ground at the village entrance |
30-minute
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10
and L90 would be recorded. |
At least
once per week |
3, 9, 12, 17, 23 and 26 February 2015 |
Table 2.6 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion
NL-31 |
Acoustic
Calibrator |
Rion
NC-73 |
Table 2.7 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Average , dB(A), Leq (30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
|
NSR
1A |
60 |
56
¡V 61 |
75 |
|
Table 2.8 Locations
of Impact Water Quality Monitoring Stations and its Corresponding Monitoring
Requirements
Station ID |
Type |
Coordinates |
*Parameters, unit |
Frequency |
Depth |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH (pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) ¡P
SS (mg/L) |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth may be omitted |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station
(Close to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
*Notes: |
Table 2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO and Salinity |
YSI Pro2030 |
Turbidity meter |
HACH Model 2100Q |
pH meter |
HANNA HI8314 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
Water Depth Detector |
Speedtech Instrument SM-5 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
Although
some results of depth-averaged SS were recorded higher than the values of
Action Level or Limit Level in the monitoring period, the results were not
higher than 120% of the upstream control at the same tide of the same day. Thus the results were considered as natural
variation. No Action and Limit
levels exceedances was recorded at all monitoring stations for impact water
quality monitoring in the reporting month.
No action is thus required to be undertaken in accordance with the Event
Action Plan presented in Appendix L.
Table
2.10 Dolphin
Monitoring Equipment
Equipment |
Model |
|
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single engine motor vessel with viewing platform 4.5m above
water level |
|
Table
2.11 Impact
Dolphin Monitoring Line Transect Co-ordinates
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
814577 |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815457 |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820690 |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
820847 |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
820892 |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818449 |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
|
The Action and
Limit levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented
in Appendix L.
Only
one (1) group of a single dolphin was sighted during the two sets of monitoring
surveys in February 2015. This single
sighting was made in NWL during the two sets of surveys in February while no
dolphin was sighted at all in NEL.
The single sighting was made on primary lines during on-effort search,
and it was not associated with operating fishing vessel. No sighting was
made in the proximity of the Project¡¦s alignment. The
distribution of dolphin sighting during the reporting month is shown in Figure 2.5.
Encounter rates of Chinese White Dolphins are deduced
from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below) in February 2015
are shown in Tables 2.12 and 2.13.
Table 2.12 Individual
Survey Event Encounter Rates
|
|
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
Primary
Lines Only |
Primary
Lines Only |
||
NEL |
Set 1: Feb 5th / 13th |
0.0 |
0.0 |
Set 2: Feb 16th / 25th |
0.0 |
0.0 |
|
NWL |
Set 1: Feb 5th / 13th |
1.4 |
1.4 |
Set 2: Feb 16th / 25th |
0 |
0 |
|
Note: Dolphin Encounter Rates are deduced
from the two sets of surveys ( two surveys in each set) in February 2015 in
Northeast (NEL) and Northwest Lantau (NWL) |
Table 2.13 Monthly
Average Encounter Rates
|
Encounter rate (STG)
(no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per
100 km of survey effort) |
||
Primary Lines Only |
Both Primary and Secondary Lines |
Primary Lines Only |
Both Primary and Secondary Lines |
|
Northeast Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest Lantau |
0.7 |
0.5 |
0.7 |
0.5 |
Note:
Overall dolphin encounter rates (sightings per 100km of survey effort)
from all four surveys are conducted in February 2015 on primary lines only as
well as both primary lines and secondary lines in Northeast and Northwest
Lantau
Whilst one (1) Limit Level exceedance was observed for
the quarterly dolphin monitoring data between December 2014 and February 2015. No unacceptable impact from the
construction activities of the TM-CLKL Southern Connection Viaduct Section on
Chinese White Dolphins was noticeable from general observations during the dolphin
monitoring in this reporting month.
Daily 250 m marine
mammal exclusion zone monitoring was undertaken during the period of marine
works activities being undertaken. Passive
Acoustic Monitoring (PAM) was implemented when the marine works marine works were
carried out outside the daylight hours in this reporting month. No sighting of Indo-Pacific humpback
dolphin Sousa chinensis
(i.e. Chinese White Dolphin) were recorded in February 2015 during the
exclusion zone monitoring.
Table 2.14 Specific
Observations Identified during the Weekly Site Inspections in this Reporting
Month
Inspection
Date |
Environmental
Observations |
Recommendations/
Remarks |
4 February 2015 |
Area 1 ¡P
The ground was dry. ¡P
Washing facility at the entrance was incomplete. ¡P
Soil stockpile was not covered. ¡P
Refuse was accumulated in drainage. ¡P
A drip tray for generator was not plugged. |
Area 1 ¡P
The contractor was reminded to implement the
watering programme for dust suppression. ¡P
Wheel washing should be provided at the entrance. ¡P
Soil stockpile should be covered by tarpaulin sheet
or wet to avoid dust emission. ¡P
Drainage should be cleaned up regularly. ¡P
Drip trays should be plugged. |
13 February 2015 |
Pier D5 ¡P
A generator was not well placed on acoustic
decoupling pad. Pier B1 ¡P
Sediment was accumulated in the gutter. Barge Tung Shun 88 (next to Pier D2) ¡P
Label for marine sediment was not displayed. Pier B2 ¡P
A part of gutter was not properly installed. |
Pier D5 ¡P
Machine on marine platform should be well placed on decoupling
pad. Pier B1 ¡P
Gutter should be cleaned regularly. Barge Tung Shun 88 (next to Pier D2) ¡P
Label for marine sediment should be displayed. Pier B2 ¡P
Gutter should be properly installed. |
17 February 2015 |
Seafront near Pier B8 ¡P
A drip tray for generator was not plugged. Pier D12A ¡P
Some chemical containers were not placed in drip
tray. ¡P
Grouting material was found not covered. Pier D10 ¡P
Sandbags were found insufficient to avoid waste
water discharging offsite. |
Seafront
near Pier B8 ¡P
Drip trays should be plugged. Pier D12A ¡P
Chemical containers should be covered and placed in
drip tray. ¡P
Stockpile of grouting material should be covered. Pier D10 ¡P
Sufficient sandbags should be provided to avoid any
runoff of waste water. |
26 February 2015 |
Pier C1 ¡P
Gutter was not properly installed. |
Pier C1 ¡P
Gutter should be properly installed to ensure no
waste water runoff from platform. |
The Contractor
has rectified all of the observations identified during environmental site
inspections in the reporting month.
The Contractor
has submitted application form for registration as chemical waste producer
under the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
Wastes
generated during this reporting period include mainly construction wastes
(inert and non-inert), recyclable materials, chemical waste and marine sediment
(Categories L & M). Reference
has been made to the waste flow table prepared by the Contractor (Appendix M).
The quantities of different types of wastes are summarized in Table 2.15.
Table 2.15 Quantities
of Different Waste Generated in the Reporting Period
Month/Year |
Inert C&D Materials (a)
(m3) |
Imported Fill (m3) |
Inert Construction Waste
Re-used (m3) |
Non-inert Construction Waste (b)
(kg) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
|
Category L |
Category M (Mp
& Mf) |
|||||||
February 2015 |
5,759 |
0 |
436 |
141,020 |
112 |
400 |
801 |
333 |
Notes: |
||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber, felled trees
and others. |
The Contractor
was advised to properly maintain on site C&D materials and waste
collection, sorting and recording system, dispose of C&D materials and
wastes at designated ground and maximize reuse/ recycle of C&D materials
and wastes. The Contractor was also
reminded to properly maintain the site tidiness and dispose of the wastes
accumulated on site regularly and properly.
For chemical
waste containers, the Contractor was reminded to treat properly and store
temporarily in designated chemical waste storage area on site in accordance
with the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes.
The status of
environmental licensing and permit is summarized in Table 2.16 below.
Table 2.16 Summary
of Environmental Licensing and Permit Status
License/
Permit |
License
or Permit No. |
Date of Issue |
Date of Expiry |
License/
Permit Holder |
Remarks |
Environmental Permit |
EP-354/2009/C |
10 Dec 2014 |
N/A |
HyD |
Tuen Mun- Chek Lap Kok Link |
Construction Dust Notification |
361571 |
5 Jul 2013 |
N/A |
GCL |
|
Construction Dust Notification |
362093 |
17 Jul 2013 |
N/A |
GCL |
For Area 23 |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan) |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong Village) |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (WA5 adjacent to Cheung Tung Road, Yam O) |
Chemical Waste Registration |
5213-951-G2380-17 |
12 Jun 2014 |
N/A |
GCL |
Viaducts A, B, C, D & E |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
N/A |
GCL |
- |
Construction Waste Disposal Account |
7019470 |
3 Mar 2014 |
N/A |
GCL |
Vessel CHIT Account |
Waste Water Discharge License |
WT00019017-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for marine portion |
Waste Water Discharge License |
WT00019018-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for land portion |
Construction
Noise Permit |
Nil |
N/A |
N/A |
GCL |
For Piling Works |
Construction
Noise Permit for night works and works in general holidays |
GW-RW0640-14 |
28 Aug 2014 |
27 Feb 2015 |
GCL |
General works at WA5 |
Construction
Noise Permit for night works and works in general holidays |
GW-RS1032-14 |
25 Sep 2014 |
28 Mar 2015 |
GCL |
For Load unload at NLH near Viaduct D |
Construction
Noise Permit for night works and works in general holidays |
GW-RS0078-15 |
28 Jan 2015 |
29 Jul 2015 |
GCL |
For Plant mobilization using tractor |
Construction
Noise Permit for night works and works in general holidays |
GW-RS1225-14 |
31 Oct 2014 |
2 May 2015 |
GCL |
For Broad Permit |
Construction
Noise Permit for night works and works in general holidays |
GW-RS1386-14 |
15 Dec 2014 |
15 Mar 2015 |
GCL |
TTA Case 009 Ch.2.3E-4.2E |
Construction
Noise Permit for night works and works in general holidays |
GW-RS1406-15 |
24 Feb 2015 |
30 Apr 2015 |
GCL |
B9-B16 Pier Head Segments Erection |
Construction
Noise Permit for night works and works in general holidays |
GW-RS0137-15 |
12 Feb 2014 |
15 Aug 2015 |
GCL |
Pre-casted pile cap shell installation at E10-E13 |
Construction
Noise Permit for night works and works in general holidays |
GW-RS0084-15 |
28 Jan 2015 |
30 Apr 2015 |
GCL |
Pier B8 formwork erection |
Marine
Dumping Permit |
EP/MD/15-203 |
28 Jan 2015 |
27 Jul 2015 |
GCL |
For dumping Type I sediment |
Marine
Dumping Permit |
EP/MD/15-234 |
27 Feb 2015 |
31 Mar 2015 |
GCL |
For dumping
Type I (Dedicated Site) and Type II sediment |
No complaint,
notification of summons and prosecution was received in the reporting period.
Statistics on
complaints, notifications of summons, successful prosecutions are summarized in
Appendix N.
Marine
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation & uninstallation;
¡P
Marine Piling at Viaducts A, C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of March 2015 are mainly associated with dust,
noise, marine water quality, marine ecology and waste management issues.
This Sixteenth
Monthly EM&A Report presents the findings of the EM&A activities
undertaken during the period from 1 to 28 February 2015, in accordance with the
Updated EM&A Manual and the requirements of the Environmental Permit (EP-354/2009/C).
Only one (1) group
of a single dolphin was sighted during the two sets of monitoring surveys in
February 2015. This single sighting
was made in NWL during the two sets of surveys in February while no dolphin was
sighted at all in NEL. No sighting
was made in the proximity of the Project¡¦s alignment. One (1) Limit Level exceedances was observed for the
quarterly dolphin monitoring data between December 2014 and February 2015. During this month of dolphin monitoring, no
unacceptable impact from the construction activities of the TM-CLKL Southern
Connection Viaduct Section on Chinese White Dolphins was noticeable from
general observations.
The ET will
keep track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation
measures.