Table of Contents

                        Executive Summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Scope of Report                                                                   

1.3                   Organization Structure                                                 

1.4                   Summary of Construction Works                              

1.5                   Summary of EM&A Programme Requirements        

2                      EM&A RESULTS                                                                         

2.1                   Air Quality                                                                               

2.2                   Noise Monitoring                                                                  

2.3                   Water Quality Monitoring                                              

2.4                   Dolphin Monitoring                                                            

2.5                   Bored Piling Monitoring                                                  

2.6                   EM&A Site Inspection                                                           

2.7                   Waste Management Status                                             

2.8                   Environmental Licenses and Permits                        

2.9                   Implementation Status of Environmental Mitigation Measures  

2.10                 Summary of Exceedances of the Environmental Quality Performance Limit                                                                                                       

2.11                 Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                         

3                      Future Key Issues                                                                

3.1                   Construction Activities for the Coming Quarter   

3.2                   Key Issues for the Coming Quarter                           

3.3                   Monitoring Schedule for the Coming Quarter   

4                      Conclusions and recommendations                         

 


List of Appendices

Appendix A

Project Organization for Environmental Works

Appendix B

Three Month Rolling Construction Programmes

Appendix C

Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D

Summary of Action and Limit Levels

Appendix E

EM&A Monitoring Schedules

Appendix F

Impact Air Quality Monitoring Graphical Presentation

Appendix G

Meteorological Data for the Reporting Month

Appendix H

Impact Noise Monitoring Graphical Presentation

Appendix I

Impact Water Quality Monitoring Graphical Presentation

Appendix J

Impact Dolphin Monitoring Survey Results

Appendix K

Event Action Plan

Appendix L

Quarterly Summary of Waste Flow Table

Appendix M

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

 

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the first quarterly EM&A report presenting the EM&A works carried out during the period from 31 October 2013 to 28 February 2014 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

October/ November 2013

Marine-based Works

¡P             Ground investigation (GI) work at marine piers;

¡P             Survey towers erection; and

¡P             Filling platform at seawall.

Land-based Works

¡P             Additional GI fieldwork, laboratory testing and permitting;

¡P             Application for tree felling and transplanting;

¡P             Site office relocation;

¡P             Fence relocation at Viaduct A, C and D;

¡P             Site offices erection; and

¡P             Temporary access bridge (TAB).

December 2013

Marine-based Works

¡P             Survey tower erection;

¡P             Marine piling platform installation;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             SOR¡¦s and Contractor¡¦s site offices erection at Area 5;

¡P             Satellite container offices erection along seawall;

¡P             Tree felling at Pak Mong area;

¡P             Fence relocation for Viaducts A, C & D;

¡P             Additional land GI, trial pits and laboratory testing; and

¡P             Utility surveys.

January 2014

Marine-based Works

¡P             Survey tower erection;

¡P             Marine piling platform installation;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             SOR¡¦s site offices erection at Area 5;

¡P             Satellite container offices erection along seawall (ie CEDD Access Road);

¡P             Fence relocation for Viaducts A, C & D;

¡P             Land piling at Viaduct B;

¡P             Additional land GI, trial pits and laboratory testing; and

¡P             Utility surveys.

February 2014

Marine-based Works

¡P             Marine piling platform installation;

¡P             Preparation works for marine piling at Viaduct B;

¡P             Survey tower erection;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             Satellite container offices erection along seawall;

¡P             Fence installation and relocation of Area 2, Viaduct A, B, C & D;

¡P             Land piling at Viaduct B;

¡P             Piling platform installation for Viaducts B, D & E; and

¡P             Additional land GI, trial pits & laboratory testing.

 

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                       23 sessions

1-hour TSP monitoring                                   23 sessions

Noise monitoring                                   23 sessions

Water quality monitoring                       51 sessions

Dolphin monitoring                                 8 sessions

Joint Environmental site inspection      17 sessions

Daily marine mammal exclusion zone monitoring was undertaken.  One sighting of Indo-Pacific humpback dolphin Sousa chinensis was recorded on 23 January 2014 during the exclusion zone monitoring.  The dolphin group of three was sighted within the marine mammal exclusion zone of the workfront of the landing platform by the marine mammal observer.  The marine works was subsequently suspended for the remaining day since the dolphin group was still present inside the exclusion zone until the end of the scheduled marine construction works.

Breaches of Action and Limit Levels for Air Quality

Two Action Level exceedances for 24-hr TSP were recorded from the air quality monitoring in this reporting period.  The exceedances were considered to be due to sporadic events from cumulatively anthropogenic activities in this area of Hong Kong and were unlikely to be due to the construction works under this Contract.  No Limit Level exceedance for 1-hr nor 24-hr TSP were detected within the reporting period.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.

Breaches of Action and Limit Levels for Water Quality

One (1) exceedance of Action Level in depth-averaged SS was recorded for impact water quality monitoring in the reporting period.  The exceedance was considered not related to the construction works of this Contract upon further investigation.

Impact Dolphin Monitoring

Whilst one Action Level exceedance was observed for the quarterly dolphin monitoring data between December 2013 and February 2014, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations during the dolphin monitoring in this reporting quarter.  The exceedance is considered to be the natural variation of Chinese White Dolphin ranging pattern upon further investigation.  

Environmental Complaints, Non-compliance & Summons

One (1) complaint was referred by EPD on 12 November 2013 and was follow-up timely.  The complaint was considered to be not related to this Contract.

No notification of summons and successful prosecution was received in the reporting month.

Reporting Change

There was no reporting change required in the reporting period.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming quarter include the following:

Marine Works

¡P             Marine piling platform installation;

¡P             Marine piling at Viaduct B;

¡P             Survey tower erection;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             Satellite container offices erection along seawall;

¡P             Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P             Land piling at Viaduct B;

¡P             Piling platform installation for Viaducts B, D & E;

¡P             Additional land GI, trial pits & laboratory testing;

¡P             Utility surveys; and

¡P             Soil nail and excavation at slope at 9SE-B/C8.

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issues.

 


 

 

1                                             Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.  Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

 

1.2                                      Scope of Report

This is the First Quarterly EM&A Report under the Contract No. HY/2012/07 Tuen Mun ¡V Chek Lap Kok Link ¡V Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works from 31 October 2013 to 28 February 2014.

1.3                                      Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

HyD (Highway Department)

Senior Engineer

Steven Shum

2762 4133

3188 6614

 

Project Coordinator

Stanley Chan

2762 3406

3188 6614

 

 

 

 

 

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

Kingman Chan

3691 2950

3691 2899

 

ENPO / IEC

(ENVIRON Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2888

3465 2899

IEC

 

Tony Cheng

3465 2888

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Manager

 

Brian Kam

3520 0387

3520 0486

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Jovy Tam

2271 3113

2723 5660

1.4                                      Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The rolling construction programme for the period of 31 October 2013 to 28 February 2014 is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

November 2013

Marine-based Works

¡P             Ground investigation (GI) work at marine piers;

¡P             Survey towers erection; and

¡P             Filling platform at seawall.

Land-based Works

¡P             Additional GI fieldwork, laboratory testing and permitting;

¡P             Application for tree felling and transplanting;

¡P             Site office relocation;

¡P             Fence relocation at Viaducts A, C and D;

¡P             Site offices erection; and

¡P             Temporary access bridge (TAB).

December 2013

Marine-based Works

¡P             Survey tower erection;

¡P             Marine piling platform installation;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             SOR¡¦s and Contractor¡¦s site offices erection at Area 5;

¡P             Satellite container offices erection along seawall;

¡P             Tree felling at Pak Mong area;

¡P             Fence relocation for Viaducts A, C & D;

¡P             Additional land GI, trial pits and laboratory testing; and

¡P             Utility surveys.

January 2014

Marine-based Works

¡P             Survey tower erection;

¡P             Marine piling platform installation;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             SOR¡¦s site offices erection at Area 5;

¡P             Satellite container offices erection along seawall (ie CEDD Access Road);

¡P             Fence relocation for Viaducts A, C & D;

¡P             Piling platform installation for Viaduct B;

¡P             Additional land GI, trial pits and laboratory testing; and

¡P             Utility surveys.

February 2014

Marine-based Works

¡P             Marine piling platform installation;

¡P             Preparation works for marine piling at Viaduct B;

¡P             Survey tower erection;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             Satellite container offices erection along seawall;

¡P             Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P             Land Piling at Viaduct B;

¡P             Piling platform installation for Viaducts B, D & E; and

¡P             Additional land GI, trial pits & laboratory testing.

The general layout plan of the site showing the detailed works areas is shown in Figures 1.1 to 1.12.  The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.13.

The environmental mitigation measures implementation schedule are presented in Appendix C.

1.5                                      Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

-     Monitoring parameters;

-     Monitoring schedules for the reporting months and forthcoming months;

-     Action and Limit levels for all environmental parameters;

-     Event/ Action Plan;

-     Results and observations;

-     Environmental mitigation measures, as recommended in the Project EIA reports; and

-     Environmental requirement in contract documents.

2                                             EM&A RESULTS

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                                      Air Quality

The baseline air quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡VMacao Bridge Hong Kong Projects (HKZMB) during October 2011 has included the two monitoring stations ASR9A and ASR9C for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([1]) are adopted for this Project.

2.1.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact 1-hour TSP monitoring was conducted three (3) times every six (6) days while the highest dust impact was expected.  Impact 24-hour TSP monitoring was carried out once every six (6) days.  The Action and Limit Level of the air quality monitoring is provided in Appendix D.

Air quality monitoring stations ASR9A and ASR9C in Siu Ho Wan MTRC Depot were the proposed locations in accordance with the Updated EM&A Manual.  However, authorization of getting access into Siu Ho Wan MTRC Depot is still being sought for the impact monitoring of the EM&A programme for the captioned Contract.  Air quality monitoring on 5 and 11 November 2013 was carried out just outside MTRC Depot at close proximity to the proposed locations, which was then temporarily relocated to the rooftop of Pak Mong Village Watch Tower (ASR 8) and Area 4 (ASR 8A) since 15 November 2013.  A proposal for setting up alternative air quality monitoring stations at ASR8A (Area 4) and ASR8 (Rooftop of Pak Mong Village Watch Tower) was submitted on 13 November 2013 which was subsequently approved.  Same baseline and Action Level for air quality, as derived from the baseline monitoring data recorded at Siu Ho Wan MTRC Depot, were adopted for these temporary air quality locations (Figure 2.1; Table 2.1).

Portable direct reading dust meters were used to carry out the 1-hour TSP monitoring on 5, 11 and 15 November 2013.  High Volume Samplers (HVSs) were used for carrying out 1-hour TSP monitoring on 21 and 27 November 2013 and in subsequent months due to the change of monitoring locations from Siu Ho Wan MTR Depot to Pak Mong Village Watch Tower and Area 4 where more reliable power supply is available to power the HVS.  24-hour TSP air quality monitoring was performed using HVS located at each designated monitoring station.  The HVS meets all requirements of the Updated EM&A Manual.  Brand and model of the equipment is given in Table 2.2. 

Wind data monitoring equipment was installed at fencing close to ASR9A (Siu Ho Wan MTRC Depot) since 5 November 2013.  It was then installed at the rooftop of Pak Mong Village Watch Tower since 15 November 2013 for logging wind speed and wind direction.  The wind sensor was setup at location clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.


Table 2.1        Locations of Impact Air Quality Monitoring Stations and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Period

Location

Description

Parameters & Frequency

ASR9A (1)

5, 11 November 2013

Siu Ho Wan MTRC Depot

 

On ground near security office

 

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times per day every 6 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour every 6 days

ASR9C (1)

5, 11 November 2013

Siu Ho Wan MTRC Depot

 

On ground near staff canteen

 

ASR8A

15, 21, 27 November 2013; 3, 9, 13, 19, 24 & 30 December 2013; 3, 9, 15, 21, 27 & 30 January 2014;

5, 8, 12, 18, 24 & 28 February 2014

 

Area 4

On ground at the Area 4

ASR8

15, 21, 27 November 2013; 3, 9, 13, 19, 24 & 30 December 2013; 3, 9, 15, 21, 27 & 30 January 2014;

5, 8, 12, 18, 24 & 28 February 2014

Pak Mong Village Watch Tower

Rooftop of the premise

Notes:

 

 

 

 

(1)   Air Quality Monitoring Stations ASR9A and ASR9C at Siu Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were temporarily relocated to ASR 8A and ASR8, respectively.

Table 2.2        Air Quality Monitoring Equipment

Equipment

Brand and Model

Portable direct reading dust meter
(1-hour TSP)

Sibata Digital Dust Monitor
(Model No. LD-3B)

 

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Sensor

Global Water WE550

2.1.2                               Action & Limit Levels

The Action and Limit Levels of the air quality monitoring is provided in Appendix D.  The Event and Action plan is presented in Appendix K.

2.1.3                               Monitoring Schedule for the Reporting Quarter

The schedules for air quality monitoring in the reporting quarter is provided in Appendix E.  

2.1.4                               Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively.  Monitoring results are presented graphically in Appendix F and detailed impact air quality monitoring data were reported in the First to Fourth Monthly EM&A Report.  

Table 2.3        Summary of 1-hour TSP Monitoring Results in this Reporting Period

Period

Station (1)

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

November 2013 to February 2014

ASR 9A/ASR8A

122

42 - 306

394

500

ASR9C/ASR8

133

42 - 361

393

500

Note:

(1)   Air Quality Monitoring Stations ASR9A and ASR9C were temporarily relocated to ASR 8A and ASR8, respectively, since 15 November 2013.

Table 2.4        Summary of 24-hour TSP Monitoring Results in this Reporting Period

Period

Station (1)

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

November 2013 to February 2014

ASR 9A/ASR8A

86

29 - 210

178

500

ASR9C/ASR8

92

29 - 205

178

500

Note:

(1)   Air Quality Monitoring Stations ASR9A and ASR9C were temporarily relocated to ASR 8A and ASR8, respectively, since 15 November 2013.

The major dust sources in the reporting period include construction activities under the Contract as well as nearby traffic emissions.

In this reporting period, a total of twenty-three monitoring events were undertaken within the reporting period, in which two Action Level exceedances for 24-hr TSP for air quality were recorded in one monitoring event.  Further explanation to the two Action Level exceedances is presented in Section 2.10.

Meteorological information collected at Pak Mong Village Watch Tower within the reporting period, including wind speed and wind direction, is provided in Appendix G.

2.2                                      Noise Monitoring

The baseline noise monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Projects (HKZMB) during the period of 18 October to 1 November 2011 has included the monitoring station NSR1 for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([2]) are adopted for this Project.

2.2.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact noise monitoring was conducted once per week during the construction phase of the Contract at NSR1. 

Monitoring location was set up at NSR 1 in accordance with the Updated EM&A Manual.  Figure 2.2 shows the location of the monitoring station.  Table 2.5 describes the details of the monitoring station.  

Noise monitoring was performed using sound level meter at each designated monitoring station.  The sound level meters deployed comply with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Brand and model of the equipment is given in Table 2.6.

Table 2.5        Location of Impact Noise Monitoring Station and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Period

Location

Parameters & Frequency

NSR 1

5, 11, 15, 21 & 27 November 2013; 3, 9, 13, 19, 24 & 30 December 2013; 3, 9, 15, 21, 27 & 30 January 2014;

5, 8, 12, 18, 24 & 28 February 2014

Pak Mong Village Watch Tower

Ÿ   30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

Ÿ   At least once a week

Table 2.6        Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-31

Acoustic Calibrator

Rion NC-73

2.2.2                               Action and Limit Levels

The Action and Limit Levels of the noise monitoring is provided in Appendix D.  The Event and Action plan is presented in Appendix K.

2.2.3                               Monitoring Schedule for the Reporting Quarter

The schedules for noise monitoring in the reporting quarter is provided in Appendix E.

2.2.4                               Results and Observations

The monitoring results for noise monitoring are summarized in Table 2.7.  Monitoring results are presented graphically in Appendix H and detailed impact noise monitoring data are reported in the First to Fourth Monthly EM&A Report.

Table 2.7        Summary of Construction Noise Monitoring Results at NSR1 in the Reporting Period

Period

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

November 2013 to February 2014

58

56 - 60

75

 

A total of twenty-three monitoring events were undertaken in the reporting period with no Action Level and Limit Level exceedance recorded at all monitoring stations in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix K.

Major noise sources during the noise monitoring included construction activities, nearby traffic noise and aircraft noise.

2.3                                      Water Quality Monitoring

The baseline water quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all monitoring stations except SR4a for the Project.  Thus, the baseline monitoring results except for station SR4a and Action/Limit Level presented in HKZMB Baseline Monitoring Report ([3]) are adopted for this Project.  Baseline water quality monitoring was conducted at station SR4a from 29 August to 24 September 2013. 

2.3.1                               Monitoring Requirements and Equipment

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period at seven (7) water quality monitoring stations in accordance with the Updated EM&A Manual (Figure 2.3; Table 2.8).  

Table 2.8        Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

¡P    SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

 

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract.

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

SR4

Sensitive receiver (Tai Ho Inlet)

814760

817867

SR4a

Sensitive receiver

815247

818067

CS(Mf)3

Control Station

809989

821117

CS(Mf)5

Control Station

817990

821129

*Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Table 2.9 summarizes the equipment used in the impact water quality monitoring programme. 

Table 2.9        Water Quality Monitoring Equipment

Equipment

Brand and Model

DO, Temperature meter and Salinity

YSI Pro2030

 

 

Turbidimeter

HACH Model 2100Q

 

pH meter   

HANNA HI8314

 

Positioning Equipment

Koden913MK2 with KBG-3 DGPS antenna

 

Water Depth Detector

Speedtech Instrument SM-5

 

Water Sampler

Kemmerer 1520 (1520-C25) 2.2L with messenger

2.3.2                               Action & Limit Levels

The Action and Limit Levels of the water quality monitoring is provided in Appendix D.
 

2.3.3                               Monitoring Schedule for the Reporting Quarter

The schedules for water quality monitoring in the reporting quarter are provided in Appendix E.

2.3.4                               Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting period.  Monitoring results are presented graphically in Appendix I and detailed impact water quality monitoring results were reported in the First to Fourth Monthly EM&A Report.    

In this reporting period, major marine construction works included marine piling platform installation, marine piling at Viaduct B and rockfill platform construction at Viaduct D landing.  In a total of fifty-one monitoring events undertaken in the reporting quarter, one Action Level exceedance for depth-averaged SS was recorded in one monitoring event on 26 November 2013 which was not due to the construction works of this Contract.  Further explanation to the Action Level exceedance is presented in Section 2.10.

2.4                                      Dolphin Monitoring

2.4.1                               Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort.

2.4.2                               Monitoring Equipment

Table 2.10 summarises the equipment used for the impact dolphin monitoring.

Table 2.10      Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                               Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                               Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.4.  The co-ordinates of all transect lines are shown in Table 2.11 below.

Table 2.11      Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

814577

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805475

815457

14

Start Point

817537

820220

2

End Point

805477

826654

14

End Point

817537

824613

3

Start Point

806464

819435

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

819771

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

820220

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

820466

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

820690

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

820847

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

820892

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

820872

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818449

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

 

 

 

 

12

End Point

815542

824882

 

 

 

 

2.4.5                               Action & Limit Levels

The Action and Limit Levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix K.

2.4.6                               Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are shown in Appendix E.

2.4.7                               Results & Observations

A total of 1137.92 km of survey effort was collected, with 95.0% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility) in this reporting quarter.  Among the two areas, 428.91 km and 709.01 km of survey effort were collected from NEL and NWL survey areas respectively.  The total survey effort conducted on primary and secondary lines were 852.63 km and 285.29 km, respectively.  The survey efforts are summarized in Appendix J.

A total of 59 groups of 249 Chinese White Dolphin sightings were recorded during the two sets of surveys in this reporting quarter.  All except four sightings were made during on-effort search.  Fifty on-effort sightings were made on primary lines, while five other on-effort sightings were made on secondary lines.  During this reporting quarter, only three groups of 16 dolphins were sighted in NEL, while the other 56 groups of 233 dolphins were sighted in NWL.

For the detailed comparison of dolphin occurrence and usage of NEL and NWL survey area between the impact phase and baseline phase monitoring, only the quarterly data of December 2013 ¡V February 2014 from the impact phase monitoring was used in the present report to tally with the three-month period of baseline monitoring (September-November 2011).

Encounter rates of Chinese White Dolphins are deduced from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below with good visibility) in the reporting quarter with the results presented in Tables 2.12 and 2.13.

Table 2.12      Individual Survey Event Encounter Rates

 

 

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

 

 

Primary Lines Only

Primary Lines Only

NEL

Set 1: Dec 5th / 9th 

2.68

8.05

 

Set 2: Dec 13th/ 19th  

0.0

0.0

 

Set 3: Jan 7th/ 9th

0.0

0.0

 

Set 4: Jan 21st/ 23rd

0.0

0.0

 

Set 5: Feb 6th/ 12th

0.0

0.0

 

Set 6: Feb 14th/ 20th

0.0

0.0

NWL

Set 1: Dec 5th / 9th 

6.95

30.57

 

Set 2: Dec 13th/ 19th 

6.82

27.27

 

Set 3: Jan 7th/ 9th

10.00

39.99

 

Set 4: Jan 21st/ 23rd

11.84

50.33

 

Set 5: Feb 6th / 12th 

7.44

17.86

 

Set 2: Feb 14th/ 20th 

6.20

29.47

Note: Dolphin Encounter Rates are deduced from the Two Sets of Surveys (Two Surveys in Each Set) in the reporting quarter in Northeast (NEL) and Northwest Lantau (NWL)

Table 2.13      Monthly Average Encounter Rates

 

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

December 2013 ¡V February 2014

September 2011 ¡V November 2011

December 2013 ¡V February 2014

September 2011 ¡V November 2011

Northeast Lantau

0.45 ¡Ó 1.10

6.00 ¡Ó 5.05

1.34 ¡Ó 3.29

22.19 ¡Ó 26.81

Northwest Lantau

8.21 ¡Ó 2.21

9.85 ¡Ó 5.85

32.58 ¡Ó 11.21

44.66 ¡Ó 29.85

Note: Encounter rates deduced from the baseline monitoring period have been recalculated based only on survey effort and on-effort sighting data made along the primary transect lines under favourable conditions.

Group size of Chinese White Dolphins ranged from 1-12 individuals per group in North Lantau region during December 2013 to February 2014. The average dolphin group sizes from these three months were compared with the ones deduced from the baseline period in September to November 2011, as shown in Table 2.14.

Table 2.14      Average Dolphin Group Size

 

Average Dolphin Group Size

December 2013 ¡V February 2014

September 2011 ¡V November 2011

Overall

0.45 ¡Ó 1.10

6.00 ¡Ó 5.05

Northeast Lantau

8.21 ¡Ó 2.21

9.85 ¡Ó 5.85

Northwest Lantau

0.45 ¡Ó 1.10

6.00 ¡Ó 5.05

During this month of dolphin monitoring, no unacceptable impact from the construction activities of this Contract was recorded from the general observations.

Although the dolphins infrequently occurred along the alignment of TMCLKL southern connection viaduct section in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL.

It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

2.4.8                               Marine Mammal Exclusion Zone Monitoring

Daily 250 m marine mammal exclusion zone monitoring was undertaken under this Contract.  One sighting of the Indo-Pacific humpback dolphin Sousa chinensis within the 250 m marine mammal exclusion zone of the landing platform workfront at TAB D was recorded on 23 January 2014 by the marine mammal observer during the daylight hours.  The marine construction work was subsequently suspended.  The Dolphin Intrusion Report is presented in the Appendix K of the Third Monthly EM&A Report.

2.5                                      Bored Piling Monitoring

Baseline bored piling monitoring, including land-based theodolite tracking, underwater noise monitoring and acoustic behavioural monitoring, were undertaken from September to October 2013 by qualified dolphin specialist.  Detailed baseline monitoring results and Action/ Limit Level are presented in the Baseline Monitoring Report ([4]) under this Contract.

Since marine bored piling was not carried out in the reporting quarter, no marine bored piling monitoring was being undertaken.

2.6                                      EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Seventeen (17) site inspections were carried out in the reporting quarter on 6, 13, 20, 27 November 2013; 4, 11, 18, 27 December 2013; 2, 9, 15, 22, 29 January 2014 and 7, 12, 20, 26 February 2014.

Key observations during the site inspections in this reporting period are summarized in Table 2.15.

Table 2.15      Specific Observations Identified during the Weekly Site Inspection in this Reporting Period

Inspection Date

Aspects

Environmental observations

Recommendations/ Remarks

6, 13, 20, 27 November 2013;

4, 11, 18, 27 December 2013;

2, 9, 15, 22, 29 January 2014;

7, 12, 20, 26 February 2014

 

Air Quality

¡P         Dust suppression measures should be implemented more frequently in Area 5.

¡P         Dust suppression measures should be implemented more frequently in Area 5.

¡P         Dust emission from generator in works site.

¡P         Dust emission from generator in works site.

Water Quality

¡P         Part of the floatation unit in one of the silt curtains was not properly maintained.

¡P         Part of the floatation unit in one of the silt curtains was not properly maintained.

¡P         More sandbags should be put around any gullies nearby to avoid excavated mud from construction site from running into it directly.

¡P         More sandbags should be put around any gullies nearby to avoid excavated mud from construction site from running into it directly.

Noise

¡P         No adverse observation was identified in the reporting period.

¢w

Marine Ecology

¡P         Daily 250 m marine mammal exclusion zone monitoring was implemented under this Contract. 

¢w

¡P         The first quarterly Coral Post-Translocation Monitoring was conducted on 17 January 2014 and the results were provided in the First Quarterly Post-Translocation Coral Monitoring Report.

¢w

¡P         Acoustic decoupling measures and marine vessel control for dredging works were implemented.

¢w

Chemical and waste management

¡P         Drip tray stopper was found missing for the generator in Area 5.

¡P         The Contractor should provide stoppers to all drip trays in use.

¡P         Floating debris and trash were observed within the silt curtain.

¡P         The Contractor should clear any floating debris and trash found within the silt curtain.

¡P         Stagnant water was found accumulated in the drip tray.

¡P         The Contractor should regularly clear any stagnant water accumulated in the drip tray.

¡P         Stockpiles were not covered properly by tarpaulin sheet.

¡P         Stockpiles should be covered properly by tarpaulin sheet.

¡P         Sandy excavated materials were observed in the ditch next to the trial pits.

¡P         Appropriate measures should be done to prevent sandy excavated materials from entering into any gullies or ditch nearby.

Landscape and visual impact

¡P         The existing tree within the Project Area was observed to be part of the fencing structure.

¡P         No trees within the Project Area should be served as a part of the fencing structure.

Miscellaneous

¡P         The Environmental Permit should be displayed conspicuously in the site entrance. 

¡P         The Environmental Permit should be displayed conspicuously in the site entrance. 

 

2.7                                      Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert), imported fill and recyclable materials.  Reference has been made to the waste flow table prepared by the Contractor (Appendix L).  The quantities of different types of wastes are summarized in Table 2.16. 

Table 2.16      Quantities of Different Waste Generated in the Reporting Period

Month/Year

Inert Construction Waste (a) (m3)

Imported Fill (m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (tonnes)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

November 2013

277

0

240

22.05

0

0

0

0

December 2013

114

0

20

28.04

19

0

0

0

January 2014

138

0

108

22.38

10,240

0

0

0

February 2014

2,901

2,766

124

10.67

780

0

0

0

Total

3,430

2,766

492

83.14

11,039

0

0

0

Notes:

(a)   Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)   Non-inert construction wastes include general refuse disposed at landfill.

(c)    Recyclable materials include metals, paper, cardboard, plastics, timber and others.

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.8                                      Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.17 below.


Table 2.17      Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-354/2009/A

8 Dec 2010

NA

HyD

Tuen Mun- Chek Lap Kok Link

 

Environmental Permit

EP-354/2009/B

28 Jan 2014

NA

 

HyD

Tuen Mun- Chek Lap Kok Link

 

Construction Dust Notification

361571

5 Jul 2013

NA

GCL

-

Construction Dust Notification

 

362093

17 Jul 2013

NA

GCL

for Area 23

Billing Account for Disposal

7017735

10 Jul 2013

End of Project

GCL

-

 

Chemical Waste Registration

5213-961-G2380-13

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

Chemical Waste Registration

5213-961-G2380-14

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

Chemical Waste Registration

5213-974-G2588-03

4 Nov 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

Construction Waste Disposal Account

7017735

10 Jul 2013

NA

GCL

Waste disposal in Contract HY/2012/07

Waste Water Discharge License

Nil

Application Ref. 368337

NA

GCL

Discharge for discharge points for Viaduct A & B

 

Construction Noise Permit

Nil

Application in process

NA

GCL

For Piling Works

Construction Noise Permit

GW-RW0660-13

27 Sep 2013

02 Feb 2014

GCL

For night works and works in general holidays

 

Construction Noise Permit

GW-RS1129-13

31 Oct 2013

30 Apr 2014

GCL

For night works and works in general holidays

 

Construction Noise Permit

GW-RS1186-13

23 Oct 2013

24 Dec 2013

GCL

For night works and works in general holidays

 

Construction Noise Permit

GW-RS1187-13

24 Oct 2013

28 Feb 2014

GCL

For night

 

Construction Noise Permit

GW-RW0925-13

19 Dec 2013

17 Apr 2014

GCL

Renewal of WA5 site office erection

 

Construction Noise Permit

GW-RS1423-13

11 Dec 2013

30 Apr 2014

GCL

Renewal for marine portion

 

Construction Noise Permit

GW-RS1413-13

17 Dec 2013

26 Mar 2014

GCL

For loading and unloading on NLH near viaduct A & B

 

Construction Noise Permit

GW-RS0034-14

14 Jan 2014

29 Mar 2014

GCL

For night works and works in general holiday

 

Construction Noise Permit

GW-RW0123-14

27 Feb 2014

27 Aug 2014

GCL

For night works and works in general holiday

 

Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal)

(4) in EP/MD/14-075

25 Sep 2013

NA

GCL

-

Marine Dumping Permit

EP/MD/14-075

28 January 2014

27 July 2014

GCL

-

Note: HyD ¡V Highway Department; GCL ¡V Gammon Construction Department


2.9                                      Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out all corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

2.10                                   Summary of Exceedances of the Environmental Quality Performance Limit

For air quality monitoring, a total of twenty-three monitoring events were undertaken and two Action Level exceedances were recorded in one monitoring event (Table 2.18).  Upon further investigation, the recorded exceedances in air quality monitoring were considered to be sporadic events of cumulative anthropogenic activities in this area of Hong Kong and the construction works under this Contract were unlikely the major cause of the recorded exceedances. 

For noise monitoring, a total of twenty-three monitoring events were undertaken in the reporting quarter and no exceedance of Action and Limit Levels were recorded.

For water quality monitoring, a total of fifty-one monitoring events were undertaken and one Action Level exceedance on depth-averaged Suspended Solids (SS) was recorded (Table 2.19).  Upon further investigation, no marine works were being carried out during the mid-ebb tide when exceedance was detected, suggesting that the Action Level exceedance was not due to the construction works of this Contract. 

In addition, the construction impact on depth-averaged SS was assessed to compare the quarterly mean values of depth-averaged SS with the relevant ambient mean value.  Results showed that the quarterly mean values of depth-averaged SS are well below the ambient mean values (Table 2.20).  Cumulative statistics on exceedances is presented in Appendix M. 

Table 2.18      Summary of Exceedances for Impact Air Quality Monitoring

Station

Exceedance Level

1-hr TSP

24-hr TSP

Number of Exceedances

1-hr TSP

24-hr TSP

Impact Air Quality Monitoring

ASR8A

Action Level

-

2013-12-13

0

1

 

Limit Level

-

-

0

0

ASR8

Action Level

-

2013-12-13

0

1

 

Limit Level

-

-

0

0

Table 2.19      Summary of Exceedances for Impact Water Quality Monitoring

Station

Exceedance Level (a)

DO (Surface and Middle)

DO (Bottom)

Turbidity (depth-averaged)

SS (depth-averaged)

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Impact Water Quality Monitoring

 

 

 

 

 

IS(Mf)9

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

IS(Mf)16

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

IS8

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

SR4

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

SR4a

AL

-

-

-

-

-

-

2013-11-26

-

 

LL

-

-

-

-

-

-

-

-

CS(Mf)3

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

CS(Mf)5

AL

-

-

-

-

-

-

-

-

 

LL

-

-

-

-

-

-

-

-

 

Total AL Exceedances

0

0

0

0

0

0

1

0

 

Total LL Exceedances

0

0

0

0

0

0

0

0

Note: (a) AL = Action Level; LL = Limit Level

Table 2.20      Comparison between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended Solids

Station

Baseline Mean

Ambient Mean (a)

Quarterly Mean (October/November 2013 to February 2014)

 

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

IS(Mf)9

10.90

14.25

14.17

18.53

6.77

6.70

IS(Mf)16

11.40

10.33

14.82

14.43

6.59

6.14

IS8

11.26

13.51

14.64

17.56

6.26

6.50

SR4

10.29

12.30

13.38

15.99

6.67

6.38

SR4a

9.10

9.80

11.83

12.74

6.50

6.42

CS(Mf)3

9.20

12.76

11.96

16.59

6.16

6.07

CS(Mf)5

9.17

11.47

11.92

14.91

6.16

6.13

Grand Total

10.27

12.27

13.35

15.95

6.42

6.29

Notes:

(a) Ambient mean value is defined as a 30% increase of baseline value

2.11                                   Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.5.

One (1) complaint was referred by EPD to various parties of the HZMB projects on 12 November 2013 regarding the noise nuisance arising from the operation or towing of barges by tug boats during restricted hours, particularly during the period from 23:00 to 07:00 of next day by HZMB Projects in the waters outside Tung Chung New Development Pier and near the barging point of CEDD¡¦s construction site of Site Formation at Tung Chung Areas 53 and 54.

With reference to the Contractor¡¦s site dairy of 12 November 2013, no site activity was undertaken after 18:00 on the concerned day.  Thus, the noise complaint was considered as non-project related.

No notification of summons and prosecution was received in the reporting period.

Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix M.

3                                             Future Key Issues

3.1                                      Construction Activities for the Coming Quarter

As informed by the Contractor, the major works for the Contract in the coming quarter are summarized below:

Marine Works

¡P             Marine piling platform installation;

¡P             Marine piling at Viaduct B;

¡P             Survey tower erection;

¡P             Construction of rockfill platform at Viaduct D landing; and

¡P             Additional marine GI and laboratory testing.

Land-based Works

¡P             Satellite container offices erection along seawall;

¡P             Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P             Land piling at Viaduct B;

¡P             Piling platform installation for Viaducts B, D & E;

¡P             Additional land GI, trial pits & laboratory testing;

¡P             Utility surveys; and

¡P             Soil nail and excavation at slope 9SE-B/C8.

3.2                                      Key Issues for the Coming Quarter

Potential environmental impacts arising from the above upcoming construction activities are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issues.

3.3                                      Monitoring Schedule for the Coming Quarter

Impact monitoring for air quality, noise, marine water quality and marine ecology (include dolphin monitoring and post-translocation coral monitoring) are scheduled to continue for the next reporting period. 

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not considered to be necessary at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.

4                                             Conclusions and recommendations

This First Quarterly EM&A Report presents the findings of the EM&A activities undertaken during the period from 31 October 2013 to 28 February 2014, in accordance with the Updated EM&A Manual and the requirements of EP-354/2009/B.   

Air quality (including 1-hour TSP and 24-hour TSP), noise, marine water quality and dolphin monitoring were carried out in the reporting period.  Two Action Level exceedances for 24-hr TSP were recorded during the reporting period.  One Action Level exceedance for depth-averaged SS was recorded in marine water quality impact monitoring during the reporting period.  Investigation findings showed that the Project works were unlikely to be the major cause of the recorded exceedances in air quality and water quality monitoring. 

A total of 59 groups of 249 Chinese White Dolphin sightings were recorded during the two sets of surveys from November 2013 to February 2014.  During this month of dolphin monitoring, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations. Although the dolphins infrequently occurred along the alignment of TMCLKL southern connection vaiduct section in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL.  It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the construction works of the Contract, and whether suitable mitigation measure can be applied to revert the situation.

Environmental site inspection was carried out seventeen (17) times in the reporting period.  Recommendations on remedial actions provided for the deficiencies identified during the site audits were properly implemented by the Contractor.  No non-compliance event was recorded during the reporting period.

No complaint and summons/ prosecution was received during the reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not recommended at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.  The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 


 



([1]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([2]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([3]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([4]) Agreement No. CE 48/2011 (EP) Baseline Environmental Monitoring for Tuen Mun-Chek Lap Kok Link Southern Connection Viaduct Section.  Baseline Environmental Monitoring Report.  Submitted on 19 February 2014 and subsequently approved by EPD.