table of Contents
Executive
Summary
1.1 Background
1.2 Scope
of Report
1.3 Organization
Structure
1.4 Summary
of Construction Works
2.1 Air
quality
2.2 Dolphin
Monitoring
2.3 EM&A
Site Inspection
2.4 Waste
Management Status
2.5 Environmental
Licenses and Permits
2.6 Implementation
Status of Environmental Mitigation Measures
2.7 Summary
of Exceedances of the Environmental Quality Performance Limit
2.8 Summary
of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction
Activities for the Coming Month
3.2 Key
Issues for the Coming Month
3.3 Monitoring
Schedule for the Coming Month
4 Conclusions
and recommendations
4.1 Conclusions
Under Contract
No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by
the Highways Department (HyD) to undertake the design and construction of the
Northern Connection Sub-sea Tunnel Section of the Tuen Mun – Chek Lap Kok Link
Project (TM-CLK Link Project) while AECOM Asia Company Limited was
appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong,
Limited (ERM) has been appointed as the Environmental Team (ET) in accordance
with Environmental Permit No.
EP-354/2009/A. Ramboll Hong Kong Ltd. was employed by HyD as
the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO). Subsequent
applications for variation of environmental permits (VEP), EP-354/2009/B, EP-354/2009/C and
EP-354/2009/D, were granted on 28
January 2014, 10 December 2014 and 13 March 2015, respectively.
The construction phase of the Project commenced on 1
November 2013 and will tentatively be completed by the end of 2018. The impact monitoring of the EM&A
programme, including air quality, water quality, marine ecological monitoring and
environmental site inspections, were commenced on 1 November 2013.
This is the Fifty-sixth Monthly EM&A report
presenting the EM&A works carried out during the period from 1 to 30 June
2018 for the Contract No. HY/2012/08 Northern Connection
Sub-sea Tunnel Section (the “Project”) in
accordance with the Updated EM&A Manual of the TM-CLK
Link Project. As informed by the
Contractor, major activities in the reporting period included:
Land-based Works
·
Box Culvert Extension at Works Area – Portion N-A;
·
Construction of North Ventilation Building – Portion
N-C;
·
Construction of Cross Passage Tympanum – TBM tunnel;
·
Cross Passage Lining Installation – TBM Tunnel;
·
Cross Passage Construction by Pipe Jacking – TBM
Tunnel;
·
Corbel & OVHD Construction – TBM Tunnel;
·
Parapet wall and fireboard Installation – TBM Tunnel;
·
Bulk Excavation – Portion S-A; and
·
CSM treatment, Jet Grouting works and D-wall
Construction
There was no dredging, reclamation or marine sheet
piling works in open waters during this reporting period.
A summary of monitoring and audit activities conducted
in the reporting period is listed below:
24-hour TSP Monitoring 10
sessions
1-hour TSP Monitoring 10
sessions
Impact Dolphin Monitoring 2 sessions
Joint Environmental Site Inspection 4 sessions
Implementation
of Marine Mammal Exclusion Zone
There was no dredging, reclamation or
marine sheet piling works in open waters during this reporting period.
Thus, Passive Acoustic Monitoring (PAM) and the day-time monitoring of Dolphin
Exclusion Zone (DEZ) by dolphin observers were not in effect during the reporting
period.
Summary of Breaches of Action/Limit Levels
Breaches of
Action and Limit Levels for Air Quality
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Summary of Marine Travel Route record
No non-compliance with EIA recommendations, EP conditions and other
requirements associated with the marine travel route record of this Contract
was recorded in June 2018.
Breaches
of Action and Limit Levels for Dolphin Monitoring .
Due
to monthly variation in dolphin occurrence within the survey area, it would be
more appropriate to draw conclusion on whether any unacceptable impacts on
dolphins have been detected in relation to the construction activities of this
Project in the quarterly EM&A reports, where comparison on distribution, group
size and encounter rates of dolphins between the quarterly impact monitoring
period and baseline monitoring period will be made.
Environmental Complaints, Non-compliance & Summons
No
non-compliance with EIA recommendations, EP conditions and other requirements
associated with the construction of this Contract was recorded in this
reporting period.
No
environmental complaint was received in this reporting period.
No environmental summons was received in this
reporting period.
Reporting Change
There was no reporting change required in the
reporting period.
Upcoming Works for the Next Reporting Month
Works to be undertaken in the next monitoring period of
July 2018 include the following:
Land-based Works
·
Construction of North Ventilation Building – Portion
N-C;
·
Construction of Cross Passage Tympanum – TBM tunnel;
·
Cross Passage Lining Installation – TBM Tunnel;
·
Parapet wall and fireboard Installation – TBM Tunnel
·
Corbel & OVHD Construction – TBM Tunnel;
·
Bulk Excavation – Portion S-A; and
·
CSM treatment, Jet Grouting works and D-wall
Construction;
There will be no dredging, reclamation or marine sheet
piling works in open waters during next reporting period.
Future Key Issue
Potential environmental impacts arising from the above
upcoming construction activities in the next reporting month of July 2018 are
mainly associated with dust, marine ecology and waste management issues.
According to the findings of the Northwest New
Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport
Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau
Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated
increase in cross boundary traffic, developments in the Northwest New
Territories (NWNT), and possible developments in North Lantau, including the
Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong –
Zhuhai – Macao Bridge (HZMB). In order
to cope with the anticipated traffic demand, two new road sections between NWNT
and North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western
Bypass (TMWB) are proposed.
An Environmental Impact Assessment (EIA) of TM-CLKL (the
Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007)
and the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The EIA Report was
submitted under the Environmental Impact Assessment Ordinance (EIAO) in August
2009. Subsequent to the approval of the
EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit
(EP-354/2009) for TM-CLKL was granted by the Director of Environmental
Protection (DEP) on 4 November 2009, and EP variation (VEP) (EP-354/2009/A) was
issued on 8 December 2010. Subsequent
applications for variation of environmental permits (VEPs), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28
January 2014, 10 December 2014 and 13 March 2015, respectively.
Under Contract
No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by
the Highways Department (HyD) to undertake the design and construction of the
Northern Connection Sub-sea Tunnel Section of TM-CLKL while AECOM
Asia Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong,
Limited (ERM) has been appointed as the Environmental Team (ET). Ramboll Hong
Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC)
and Environmental Project Office (ENPO).
Layout of the Contract components is
presented in Figure 1.1.
The organization structure of the Contract is shown in
Appendix A. The
key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Highways
Department |
Engr 22/HZMB |
Chow Man Lung,
Andrew |
2762 4110 |
2762 4110 |
SOR (AECOM Asia
Company Limited) |
Chief Resident
Engineer |
Roger Man Andrew
Westmoreland |
2293 6388 2293 6360 |
2293 6300 2293 6300 |
ENPO / IEC (Ramboll Hong
Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465
2850 |
3465 2899 |
IEC |
Dr. F.C. Tsang |
3465
2851 |
3465 2899 |
|
Contractor (Dragages – Bouygues Joint Venture) |
Environmental
Officer |
Bryan Lee |
2293 7323 |
2293 7499 |
|
24-hour
complaint hotline |
Rachel Lam |
2293 7330 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
Table 1.2 Summary of Construction Activities Undertaken during the
Reporting Period
Construction Activities Undertaken |
Land-based Works |
·
Box Culvert Extension at Works Area – Portion N-A; ·
Construction of North Ventilation Building – Portion
N-C; ·
Construction of Cross Passage Tympanum – TBM tunnel; ·
Cross Passage Lining Installation – TBM Tunnel; ·
Cross Passage Construction by Pipe Jacking – TBM
Tunnel; ·
Corbel & OVHD Construction – TBM Tunnel; ·
Parapet wall and fireboard Installation – TBM
Tunnel; ·
Bulk Excavation – Portion S-A; and ·
CSM treatment, Jet Grouting works and D-wall
Construction |
Figure 1.2 Locations of Construction Activities – June 2018
|
The EM&A programme required environmental
monitoring for air quality, water quality and marine ecology as well as environmental
site inspections for air quality, noise, water quality, waste management,
marine ecology and landscape and visual impacts. The EM&A requirements and related findings
for each component are summarized in the following sections
In accordance with the Updated EM&A Manual and the
Enhanced TSP Monitoring Plan, impact 1-hour TSP monitoring was conducted three
(3) times every six (6) days and impact 24-hour TSP monitoring was carried out once
every six (6) days when the highest dust impact was expected. 1-hr and 24-hr TSP monitoring frequency was
increased to three times per day every three days and daily every three days,
respectively, as excavation works for launching shaft commenced on 24 October
2014.
High volume samplers (HVSs) were used to carry out the
1-hour and 24-hour TSP monitoring on 3, 6, 9, 12, 15, 18, 21, 24, 27 and 30
June 2018 at the five (5) air quality monitoring stations in accordance with the
requirements stipulated in the Updated EM&A Manual (Figure 2.1; Table 2.1).
Wind meter was installed at the rooftop
of ASR5 for logging wind speed and wind direction. Details of the equipment deployed are
provided in Table 2.2. Copies of the calibration certificates for the
equipment are presented in Appendix E.
Table
2.1 Locations of Impact Air Quality Monitoring Stations and
Monitoring Dates in this Reporting Period
Monitoring Station |
Monitoring Dates |
Location |
Description |
Parameters
& Frequency |
ASR1 |
3,
6, 9, 12, 15, 18, 21, 24, 27 and 30 June 2018 |
Tuen
Mun Fireboat Station |
Office |
TSP monitoring 1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3
times in every 6 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour in every 6 days Enhanced TSP monitoring
(commenced on 24 October 2014) 1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3
times in every 3 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour in every 3 days |
ASR5 |
|
Pillar
Point Fire Station |
Office |
|
AQMS1 |
|
Previous
River Trade Golf |
Bare
ground |
|
ASR6 |
|
Butterfly
Beach Laundry |
Office |
|
ASR10 |
|
Butterfly
Beach Park |
Recreational
uses |
Table 2.2 Air Quality
Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total
Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170) |
Wind Meter |
Davis (Model: Vantage Pro 2 (S/N: AS160104014) |
Wind Anemometer for calibration |
Lutron (Model No. AM-4201) |
The Action and Limit Levels of the air quality
monitoring is provided in Appendix D. The Event and Action plan is presented in Appendix J.
The schedule for air quality monitoring in June 2018
is provided in Appendix F.
The monitoring results for 1-hour TSP and 24-hour TSP
are summarized in Tables 2.3 and 2.4, respectively. Detailed impact air quality monitoring results
and graphical presentations are presented in Appendix G.
Table 2.3 Summary of 1-hour TSP Monitoring Results in this Reporting
Period
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR1 |
99 |
13
- 272 |
331 |
500 |
ASR5 |
129 |
43
- 230 |
340 |
500 |
AQMS1 |
88 |
44 –
149 |
335 |
500 |
ASR6 |
113 |
46
- 187 |
338 |
500 |
ASR10 |
74 |
39
- 109 |
337 |
500 |
Table 2.4 Summary of 24-hour TSP Monitoring Results in this Reporting
Period
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR1 |
65 |
37
- 136 |
213 |
260 |
ASR5 |
65 |
41
- 89 |
238 |
260 |
AQMS1 |
46 |
28 –
68 |
213 |
260 |
ASR6 |
52 |
18 –
87 |
238 |
260 |
ASR10 |
38 |
27
- 66 |
214 |
260 |
The weather condition during the monitoring period
varied from sunny to cloudy. The major
dust sources in the reporting period included construction activities under the
Contract as well as nearby traffic emissions.
A total of 10 1-hour TSP and 24-hour TSP monitoring
were undertaken in which no exceedance of 1-hour and 24-hour TSP was recorded
in this reporting month.
Meteorological information collected at the ASR5,
including wind speed and wind direction, is provided in Appendix H.
Seawall Enhancement Works at Northern Landfall has
been completed on 31 December 2017. Notification
of suspension of water quality monitoring has been approved by EPD on 2 March
2018.
Impact dolphin monitoring is required to be conducted
by a qualified dolphin specialist team to evaluate whether there have been any
effects on the dolphins. In order to
fulfil the EM&A requirements and make good use of available resources, the
on-going impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong
Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities on the monthly basis is adopted to avoid duplicates of survey
effort.
Table 2.5 summarises
the equipment used for the impact dolphin monitoring.
Table 2.5 Dolphin Monitoring Equipment
Equipment |
Model |
Global Positioning
System (GPS) |
Garmin 18X-PC Geo One Phottix |
Camera |
Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens |
Laser Binocular |
Infinitor LRF 1000 |
Marine Binocular |
Bushell 7 x 50 marine binocular with compass and reticules |
Vessel for Monitoring |
65 foot single engine motor vessel with viewing platform 4.5m above
water level |
Dolphin monitoring should cover all transect lines in Northeast
Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout
the entire construction period. The
monitoring data should be compatible with, and should be made available for,
long-term studies of small cetacean ecology in Hong Kong. In order to provide a suitable long-term
dataset for comparison, identical methodology and line transects employed in
baseline dolphin monitoring was followed in the impact dolphin monitoring.
The impact dolphin monitoring was carried out in the
NEL and NWL along the line transect as depicted in Figure 2.2. The co-ordinates of all transect lines are
shown in Table 2.6 below.
Table 2.6 Impact Dolphin Monitoring Line Transect Co-ordinates
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
|||
1 |
Start
Point |
804671 |
815456 |
13 |
Start
Point |
816506 |
819480 |
|
1 |
End
Point |
804671 |
831404 |
13 |
End
Point |
816506 |
824859 |
|
2 |
Start
Point |
805476 |
820800* |
14 |
Start
Point |
817537 |
820220 |
|
2 |
End
Point |
805476 |
826654 |
14 |
End
Point |
817537 |
824613 |
|
3 |
Start
Point |
806464 |
821150* |
15 |
Start
Point |
818568 |
820735 |
|
3 |
End
Point |
806464 |
822911 |
15 |
End
Point |
818568 |
824433 |
|
4 |
Start
Point |
807518 |
821500* |
16 |
Start
Point |
819532 |
821420 |
|
4 |
End
Point |
807518 |
829230 |
16 |
End
Point |
819532 |
824209 |
|
5 |
Start
Point |
808504 |
821850* |
17 |
Start
Point |
820451 |
822125 |
|
5 |
End
Point |
808504 |
828602 |
17 |
End
Point |
820451 |
823671 |
|
6 |
Start
Point |
809490 |
822150* |
18 |
Start
Point |
821504 |
822371 |
|
6 |
End
Point |
809490 |
825352 |
18 |
End
Point |
821504 |
823761 |
|
7 |
Start
Point |
810499 |
822000* |
19 |
Start
Point |
822513 |
823268 |
|
7 |
End
Point |
810499 |
824613 |
19 |
End
Point |
822513 |
824321 |
|
8 |
Start
Point |
811508 |
821123 |
20 |
Start
Point |
823477 |
823402 |
|
8 |
End
Point |
811508 |
824254 |
20 |
End
Point |
823477 |
824613 |
|
9 |
Start
Point |
812516 |
821303 |
21 |
Start
Point |
805476 |
827081 |
|
9 |
End
Point |
812516 |
824254 |
21 |
End
Point |
805476 |
830562 |
|
10 |
Start
Point |
813525 |
821176 |
22 |
Start
Point |
806464 |
824033 |
|
10 |
End
Point |
813525 |
824657 |
22 |
End
Point |
806464 |
829598 |
|
11 |
Start
Point |
814556 |
818853 |
23 |
Start
Point |
814559 |
821739 |
|
11 |
End
Point |
814556 |
820992 |
23 |
End
Point |
814559 |
824768 |
|
12 |
Start
Point |
815542 |
818807 |
24* |
Start Point |
805476* |
815900* |
|
12 |
End
Point |
815542 |
824882 |
24* |
End Point |
805476* |
819100* |
|
The Action and Limit levels of impact dolphin monitoring
are shown in Appendix D. The Event and Action plan is presented in Appendix J.
Dolphin monitoring was carried out on 5, 13, 19 and 27
of June 2018. The dolphin monitoring schedule
for the reporting month is shown in Appendix F.
Two groups of 7 Chinese White Dolphins sightings were
recorded during the two sets of surveys in June 2018. All dolphin sightings were made in NWL, while
none was sighted in NEL. All dolphin
sightings were made during on-effort search and one of the two were made on primary
lines. None of the dolphin groups were
associated with any operating fishing vessel.
No dolphin sighting was made in the proximity
of the TM-CLKL alignment. The distribution of dolphin sightings during the
reporting month is shown in Figure 2.3.
Encounter rates of Chinese White Dolphins are deduced
from the survey effort and on-effort sighting data made under favourable
conditions (Beaufort 3 or below) in June 2018 with the results present in Tables 2.7 and 2.8.
Table 2.7 Individual Survey Event Encounter Rates
|
Encounter rate (STG) (no. of on-effort dolphin sightings per 100 km of
survey effort) |
Encounter rate (ANI) (no. of dolphins from all on-effort sightings per
100 km of survey effort) |
|
Primary Lines Only |
Primary Lines Only |
||
NEL |
Set 1: June 5th
/ 13th |
0.0 |
0.0 |
Set 2: June 19th
/ 27th |
0.0 |
0.0 |
|
NWL |
Set 1: June 5th
/ 13th |
0.0 |
0.0 |
Set 2: June 19th
/ 27th |
1.9 |
3.8 |
Note: Dolphin Encounter Rates
are deduced from the Two Sets of Surveys (Two Surveys in Each Set) in June 2018
in Northeast (NEL) and Northwest Lantau (NWL)
Table 2.8 Monthly Average Encounter Rates
|
Encounter rate (STG) (no. of on-effort dolphin sightings per 100
km of survey effort) |
Encounter rate (ANI) (no. of dolphins from all
on-effort sightings per 100 km of survey effort) |
||
Primary
Lines Only |
Both Primary and Secondary Lines |
Primary
Lines Only |
Both Primary and Secondary Lines |
|
Northeast Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest Lantau |
0.9 |
1.3 |
1.8 |
4.7 |
Note:
Overall dolphin encounter rates (sightings per 100 km of survey effort) from
all four surveys are conducted in June 2018 on primary lines
only as well as both primary lines and secondary lines in Northeast and
Northwest Lantau.
Due
to monthly variation in dolphin occurrence within the survey area, it would be
more appropriate to draw conclusion on whether any unacceptable impacts on dolphins
have been detected in relation to the construction activities of this Project
in the quarterly EM&A reports, where comparison on distribution, group size
and encounter rates of dolphins between the quarterly impact monitoring period
and baseline monitoring period will be made.
There was no dredging, reclamation or
marine sheet piling works in open waters during this reporting period.
Thus, Passive Acoustic Monitoring (PAM) and the day-time monitoring of Dolphin
Exclusion Zone (DEZ) by dolphin observers were not in effect during the
reporting period.
Site inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and mitigation
measures under the Contract. In the
reporting month, four (4) site inspections were carried out on 6, 13, 20 and 27
June 2018.
Key observations and recommendations during the site
inspections in this reporting period are summarized in Table 2.9.
Table 2.9 Specific Observations and Recommendations during the Weekly
Site Inspection in this Reporting Month
Inspection Date |
Observations |
Recommendations/ Remarks |
6 June 2018 |
Works
Area – Portion N-A Drip
tray should be provided for the chemical containers. Extra
water pumps should be used to pump off the stagnant water during heavy
raining. Works
Area – Portion S-B Stagnant
water should be pumped off. Reminder from the SOR Works
Area - Portion S-B The
breaker tip should be wrapped with soundproof mat. |
Works
Area – Portion N-A The
Contractor was reminded to provide drip tray for the chemical containers. The
Contractor was reminded to pump off the stagnant water during heavy raining. Works
Area – Portion S-B The
Contractor was reminded to pump off the stagnant water. Reminder from the SOR Works
Area - Portion S-B The
Contractor was reminded to wrap the breaker tip with soundproof mat. |
13
June 2018 |
Works
Area – Portion N-C Stagnant
water should be pumped off to the Wetsep. Works
Area – Portion S-A Stagnant
water should be removed. Reminder from the SOR Works
Area - Portion N-A The
breaker tip should be wrapped with soundproof mat. |
Works
Area – Portion N-C The
Contractor was reminded to pump off the stagnant water to the Wetsep. Works
Area – Portion S-A The
Contractor was reminded to remove the stagnant water. Reminder from the SOR Works
Area - Portion N-A The
Contractor was reminded to wrap the breaker tip with soundproof mat. |
20 June 2018 |
Works
Area – Portion N-A Stagnant
water should be pumped off. Works
Area – Portion S-B Drip
tray should be provided to the chemical containers. Reminder from the SOR Works
Area - Portion N-A The
broken water barriers should be replaced and covered with lids. Works
Area – Portion S-A The
broken water barriers should be replaced. |
Works
Area – Portion N-A The
Contractor was reminded to pump off the stagnant water. Works
Area – Portion S-B The
Contractor was reminded to provided chemical containers for the drip tray. Reminder from the SOR Works
Area - Portion N-A The
Contractor was reminded to replace the broken water barriers and cover them
with lids. Works
Area – Portion S-A The
Contractor was reminded to replace the broken water barriers. |
27
June 2018 |
Works
Area - Portion N-A General
refuse should be put into the rubbish bin. Works
Area - Portion S-B Stagnant
water in the drip tray should be removed. |
Works
Area - Portion N-A The
Contractor was reminded to put the general refuse into the rubbish bin. Works
Area - Portion S-B The
Contractor was reminded to remove the stagnant water in the drip tray. |
The Contractor has rectified all of the observations
as identified during environmental site inspections in the reporting month.
The Contractor had submitted application form for
registration as chemical waste producer under the Contract. Sufficient numbers of receptacles were
available for general refuse collection and sorting.
Wastes generated during this reporting period included
mainly construction wastes (inert and non-inert), chemical wastes and marine
sediment. Reference has been made to the
waste flow table prepared by the Contractor (Appendix L). The quantities of different types of wastes
are summarized in Table 2.10.
Table 2.10 Quantities of Different Waste Generated in the Reporting Month
Month/Year |
Inert Construction Waste (a)
(tonnes) |
Inert Construction Waste Re-used (tonnes) |
Non-inert Construction Waste (b)
(tonnes) |
Imported
Fill (m3) (d) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
||
|
Category L |
Category M (Mp & Mf) |
|||||||
June 2018 |
102,987 |
55,385 |
408 |
0 |
1,060 |
0 |
0 |
0 |
|
|
Notes: |
|
|||||||
|
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. (d) The
origin of imported fill is from Contract
No. HY/2013/03. |
|
|||||||
The Contractor was advised to properly maintain on
site C&D materials and waste collection, sorting and recording system,
dispose of C&D materials and wastes at designated ground and maximize
reuse/ recycle of C&D materials and wastes.
The Contractor was also reminded to properly maintain the site tidiness
and dispose of the wastes accumulated on site regularly and properly.
For chemical waste containers, the Contractor was
reminded to treat properly and store temporarily in designated chemical waste
storage area on site in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes.
The status of environmental licensing and permit is
summarized in Table 2.11 below.
Table 2.11 Summary of Environmental Licensing and Permit Status
License/ Permit |
License or Permit No. |
Date of Issue |
Date of Expiry |
License/ Permit Holder |
Remarks |
Environmental
Permit |
EP-354/2009/D |
13
March 2015 |
Throughout
the Contract |
HyD |
Application for VEP on 3 March 2015 to supersede EP-354/2009/C |
Construction
Dust Notification |
363510 |
19
August 2013 |
Throughout
the Contract |
DBJV |
Northern Landfall |
Construction
Dust Notification |
403620 |
10 June 2016 |
Throughout
the Contract |
DBJV |
Southern Landfall |
Chemical
Waste Registration |
5213-422-D2516-02 |
18 January 2017 |
Throughout
the Contract |
DBJV |
Northern Landfall |
Chemical
Waste Registration |
5213-951-D2591-01 |
25 May 2016 |
Throughout
the Contract |
DBJV |
Southern Landfall |
Construction
Waste Disposal Account |
7018108 |
28
August 2013 |
Throughout
the Contract |
DBJV |
Waste disposal in Contract No. HY/2012/08 |
Construction
Waste Disposal Account |
7021715 |
17
April 2018 |
17
July 2018 |
DBJV |
Vessel Disposal |
Waste
Water Discharge License |
WT00017707-2013 |
18
November 2013 |
30
November 2018 |
DBJV |
For site WA18 |
Waste
Water Discharge License |
WT00019248-2014 |
5
June 2014 |
30
June 2019 |
DBJV |
For site Portion N6 and Reclamation Area E |
Waste
Water Discharge License |
WT00025944-2016 |
15 December 2016 |
31 December 2021 |
DBJV |
Southern Landfall |
Marine
Dumping Permit |
EP/MD/19-001 |
28 May 2018 |
27 June 2018 |
DBJV |
Type 1 (Dedicated site) and Type 2 (Confined Marine
Disposal) |
Construction
Noise Permit |
GW-RW0538-17 |
16 April 2018 |
15 October 2018 |
DBJV |
For
Urmston Road in front of Pillar Point |
Construction Noise Permit |
PP-RS0026-17 |
3 April 2017 |
31 July 2018 |
DBJV |
Southern Landfall (Percussive Piling) |
Construction Noise Permit |
GW-RW0060-18 |
20 February 2018 |
19 August 2018 |
DBJV |
WA23
@ Tsing Yi |
Construction Noise Permit |
GW-RS0027-18 |
22 January 2018 |
14 July 2018 |
DBJV |
Southern
Landfall |
Notes: |
|||||
HyD
= Highways Department DBJV
= Dragages – Bouygues Joint Venture VEP
= Variation of Environmental Permit |
In response to the site audit findings, the
Contractors carried out all corrective actions.
A summary of the Implementation Schedule of
Environmental Mitigation Measures (EMIS) is presented in Appendix C. The
necessary mitigation measures relevant to this Contract were implemented
properly.
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Cumulative statistics are provided in Appendix K.
The Environmental Complaint Handling Procedure is provided
in Figure 2.4.
No
environmental complaint was received in this reporting period.
No environmental summons was received in this
reporting period.
Statistics on complaints, notifications of summons and
successful prosecutions are summarized in Appendix K.
As informed by the Contractor, the major works for the
Project in June 2018 are summarized in Table
3.1.
Table
3.1 Construction Works to Be Undertaken in the Coming Month
Works to be undertaken |
Land-based
Works ·
Construction of North Ventilation Building – Portion
N-C; ·
Construction of Cross Passage Tympanum – TBM tunnel; ·
Cross Passage Lining Installation – TBM Tunnel; ·
Parapet wall and fireboard Installation – TBM Tunnel ·
Corbel & OVHD Construction – TBM Tunnel; ·
Bulk Excavation – Portion S-A; and ·
CSM treatment, Jet Grouting works and D-wall
Construction; There will be no dredging, reclamation or marine
sheet piling works in open waters during next reporting period. |
Potential environmental impacts arising from the above
upcoming construction activities in the next reporting month of July 2018 are
mainly associated with dust, marine ecology, water quality and waste management
issues.
The tentative schedule for environmental
monitoring in July 2018 is provided in Appendix F.
This Fifty-sixth Monthly EM&A
Report presents the findings of the EM&A activities undertaken during the
period from 1 to 30 June 2018, in accordance with the Updated EM&A Manual
and the requirements of EP-354/2009/D.
Air quality (including 1-hour TSP and 24-hour TSP) and
dolphin monitoring were carried out in this reporting month.
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Two groups of 7 Chinese White Dolphins sightings were
recorded during the two sets of surveys in June 2018. All dolphin sightings were made in NWL, while
none was sighted in NEL. All dolphin
sightings were made during on-effort search and one of the two were made on primary
lines. None of the dolphin groups were
associated with any operating fishing vessel.
Environmental site inspection was carried out four (4)
times in June 2018. Remedial
actions recommended for the deficiencies identified during the site audits were
properly implemented by the Contractor.
No non-compliance event was recorded during the
reporting period.
No
environmental complaint was received in this reporting period.
No environmental summons was received in this
reporting period.
The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.