Table of Contents

                       

                        Executive Summary                                                              

1                      Introduction                                                                           

1.1                   Background                                                                            

1.2                   Scope of Report                                                                    

1.3                   Organization Structure                                                   

1.4                   Summary of Construction Works                                

2                      EM&A Results                                                                          

2.1                   Air quality                                                                                

2.2                   Water Quality Monitoring                                                

2.3                   Dolphin Monitoring                                                              

2.4                   EM&A Site Inspection                                                            

2.5                   Waste Management Status                                              

2.6                   Environmental Licenses and Permits                         

2.7                   Implementation Status of Environmental Mitigation Measures                                                                                  

2.8                   Summary of Exceedances of the Environmental Quality Performance Limit                                               

2.9                   Summary of Complaints, Notification of Summons and Successful Prosecutions                                                

3                      Future Key Issues                                                                 

3.1                   Construction Activities for the Coming Month     

3.2                   Key Issues for the Coming Month                                 

3.3                   Monitoring Schedule for the Coming Month          

4                      Conclusions and recommendations                            

4.1                   Conclusions                                                                            

 

                                          

Appendix A                         Project Organization for Environmental Works

Appendix B                         Construction Programme

Appendix C                         Environmental Mitigation And Enhancement Measure Implementation Schedules

Appendix D                         EM&A Monitoring Schedules

Appendix E                         Operational Phase Dolphin Monitoring Survey

Appendix F                        Cumulative Statistics On Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

Appendix G                         Waste Flow Table                                         

 

 

 

Executive Summary

Under Contract No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) in accordance with Environmental Permit No. EP-354/2009/A.  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO).  Subsequent applications for variation of environmental permits (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.  

The construction phase of the Contract commenced on 1 November 2013 and will tentatively be completed in 2021.  The impact monitoring of the EM&A programme, including air quality, water quality, marine ecological monitoring and environmental site inspections, were commenced on 1 November 2013.

This is the Ninety-fourth Monthly EM&A report presenting the EM&A works carried out during the period from 1 to 31 August 2021 for the Contract No. HY/2012/08 Northern Connection Sub-sea Tunnel Section (the “Contract”) in accordance with the Updated EM&A Manual of the TM-CLK Link Contract.  As informed by the Contractor, there was no major activities undertaken in the reporting period.

Termination proposal for construction EM&A programme was approved by EPD on 19 March 2021.  The construction phase EM&A programme of the Contract has been terminated since 19 March 2021. 

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.

                                                                                                                

 

A summary of monitoring and audit activities conducted in the reporting period is listed below:

Operational Phase Dolphin Monitoring              2 sessions

Implementation of Marine Mammal Exclusion Zone

No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period. 

Summary of Breaches of Action/Limit Levels

Breaches of Action and Limit Levels for Air Quality

No Action and Limit Level exceedance was recorded.

Environmental Complaints, Non-compliance & Summons

No non-compliance with EIA recommendations, EP conditions and other requirements associated with the construction of this Contract was recorded in this reporting period.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.

Reporting Change

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.

Upcoming Works for the Next Reporting Month

There are no major works to be undertaken in September 2021.

Future Key Issue

There are no major works to be undertaken in September 2021.

 

 

1                                    Introduction

1.1                               Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (VEP) (EP-354/2009/A) was issued on 8 December 2010.  Subsequent applications for variation of environmental permits (VEPs), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

Under Contract No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section of TM-CLKL while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO).

Layout of the Contract components is presented in Figure 1.1.

The construction phase of the Contract commenced on 1 November 2013 and will tentatively be completed in 2021.  The impact monitoring phase of the EM&A programme, including air quality, water quality, marine ecological monitoring and environmental site inspections, were commenced on 1 November 2013.

Termination proposal for construction EM&A programme was approved by EPD on 19 March 2021.  The construction phase EM&A programme of the Contract has been terminated since 19 March 2021. 

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.

1.2                               Scope of Report

This is the Ninety-fourth Monthly EM&A Report under the Contract No. HY/2012/08 Tuen Mun – Chek Lap Kok Link – Northern Connection Sub-sea Tunnel Section.  This report presents a summary of the environmental monitoring and audit works in August 2021.

1.3                               Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

Highways Department

 

Engr 24/SD

Ken T.M. Cheng

2762 4062

3188 6614

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Roger Man

 

 

2293 6388

 

 

2293 6300

 

 

ENPO / IEC

(Ramboll Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2850

3465 2899

IEC

 

Brian Tam

9700 6767

3465 2899

 

 

 

 

Contractor

(Dragages – Bouygues Joint Venture)

Quality and Environmental Manager

Erwin Regalado

 

2507 1732

 

2293 7499

 

24-hour hotline

 

 

2293 7330

 

ET (ERM-HK)

ET Leader

Jasmine Ng

2271 3311

2723 5660

 

 

 

 

 

 

1.4                               Summary of Construction Works

The construction phase of this Contract was commenced on 1 November 2013.  The construction programme is shown in Appendix B.

As per DBJV’s information, there was no major activities undertaken in the reporting period.

The Environmental Sensitive Receivers in the vicinity of the Contract are shown in Figure 1.2.

The implementation schedule of environmental mitigation measures is presented in Appendix C.

 

2                                    EM&A Results

The EM&A programme required environmental monitoring for air quality, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections

2.1                               Air quality

Termination proposal for construction EM&A programme was approved by EPD on 19 March 2021.  The construction phase EM&A programme of the Contract has been terminated since 19 March 2021.

2.2                               Water Quality Monitoring

According to the Updated EM&A Manual, a operational phase water quality monitoring shall be performed monthly during the first year of Project operation at all designated monitoring stations including control stations.  The operation phase water quality monitoring shall be ceased after the first year of operation of the Project subject to the first year review.  Operational phase water quality monitoring commenced in June 2020 and completed in May 2021.

2.3                               Dolphin Monitoring

2.3.1                          Monitoring Requirements

Operational Phase dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, Contract No. HY/2012/08 has taken over the responsibility for implementation of dolphin monitoring from HZMB HKLR Contract No. HY/2011/03 since October 2019.

2.3.2                          Monitoring Equipment

Table 2.1 summarises the equipment used for the operational phase dolphin monitoring.

 

Table 2.1        Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Garmin 18X-PC

Geo One Phottix

 

Camera

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

 

Laser Binocular

Infinitor LRF 1000

 

Marine Binocular

Bushell 7 x 50 marine binocular with compass and reticules

 

Vessel for Monitoring

65 foot single engine motor vessel with viewing platform 4.5m above water level

 

2.3.3                          Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period and operational phase.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring and operational phase dolphin monitoring.

2.3.4                          Monitoring Location

The operational phase dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.1.  The co-ordinates of all transect lines are shown in Table 2.2 below.


Table 2.2        Operational Phase Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

815456

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805476

820800*

14

Start Point

817537

820220

2

End Point

805476

826654

14

End Point

817537

824613

3

Start Point

806464

821150*

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

821500*

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

821850*

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

822150*

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

822000*

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

821123

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

821303

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

821176

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818853

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

24*

Start Point

805476*

815900*

12

End Point

815542

824882

24*

End Point

805476*

819100*

Remarks: The coordinates of several starting and ending points have been revised due to the presence of a work zone to the north of the airport platform with intense construction activities in association with the construction of the third runway expansion for the Hong Kong International Airport.  Co-ordinates in red and marked with asterisk are revised co-ordinates of transect line.


2.3.5                          Monitoring Schedule for the Reporting Month

Dolphin monitoring was carried out on 3, 5, 9 and 24 August 2021.  The dolphin monitoring schedule for the reporting month is shown in Appendix D.

2.3.6                          Results & Observations

A total of 279.40 km of survey effort was collected, with 100% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility) in August 2021.  Among the two areas, 109.90 km and 169.50 km of survey effort were collected from NEL and NWL survey areas, respectively.  The total survey effort conducted on primary and secondary lines were 204.34 km and 75.06 km respectively.  The survey efforts are summarized in Appendix E.

No Chinese White Dolphins was sighted in the two sets of surveys in August 2021. 

No dolphin sighting was made in the proximity of the TM-CLKL alignment.

Encounter rates of Chinese White Dolphins are deduced from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below) in August 2021 with the results present in Tables 2.3 and 2.4.

Table 2.3        Individual Survey Event Encounter Rates

 

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

NEL

Set 1: August 3rd / 5th

0.0

0.0

Set 2: August 9th / 24th

0.0

0.0

NWL

Set 1: August 3rd / 5th

0.0

0.0

Set 2: August 9th / 24th

0.0

0.0

Note: Dolphin Encounter Rates are deduced from the Two Sets of Surveys (Two Surveys in Each Set ) in August 2021 in Northeast (NEL) and Northwest Lantau (NWL)

Table 2.4        Monthly Average Encounter Rates

 

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary   Lines Only

Both Primary and Secondary Lines

Primary   Lines Only

Both Primary and Secondary Lines

Northeast Lantau

0.0

0.0

0.0

0.0

Northwest Lantau

0.0

0.0

0.0

0.0

Note: Overall dolphin encounter rates (sightings per 100 km of survey effort) from all four surveys are conducted in August 2021 on primary lines only as well as both primary lines and secondary lines in Northeast and Northwest Lantau.

According to the EM&A Manual, Operational Phase Monitoring on dolphin monitoring shall be undertaken based upon the frequency of forty-eight, one-day survey events at a frequency of 2 per month over a period of 24 months following cessation of the construction.  The schedule for operational phase monitoring on dolphin monitoring in August 2021 is provided in Appendix D.

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.

2.3.7                          Implementation of Marine Mammal Exclusion Zone

No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period. 

2.4                               EM&A Site Inspection

Termination proposal for construction EM&A programme was approved by EPD on 19 March 2021.  The construction phase EM&A programme of the Contract has been terminated since 19 March 2021.

2.5                               Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period included mainly construction wastes (inert and non-inert).  Reference has been made to the waste flow table prepared by the Contractor (Appendix G).  The quantities of different types of wastes are summarized in Table 2.5.

Table 2.5   Quantities of Different Waste Generated in the Reporting Month

Month/Year

Inert Construction Waste (a) (tonnes)

Inert Construction Waste Re-used

(tonnes)

Non-inert Construction Waste (b) (tonnes)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

(Mp & Mf)

Mixed

(L+M)

August 2021

17

0

7

0

0

0

0

0

Notes:

 

(a)    Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)    Non-inert construction wastes include general refuse disposed at landfill.

(c)    Recyclable materials include metals, paper, cardboard, plastics, timber and others.

 

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly


For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.6                               Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.6 below.        

                                 


Table 2.6        Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-354/2009/D

13 March 2015

Throughout the Contract

HyD

Application for VEP on 3 March 2015 to supersede EP-354/2009/C

Construction Dust Notification

435068

27 June 2018

Throughout the Contract

DBJV

Northern Landfall

Construction Dust Notification

 

435505

12 July 2018

Throughout the Contract

DBJV

Southern Landfall

Chemical Waste Registration

5213-422-D2516-02

18 January 2017

Throughout the Contract

DBJV

Northern Landfall

 

Chemical Waste Registration

5213-951-D2591-01

25 May 2016

Throughout the Contract

DBJV

Southern Landfall

Construction Waste Disposal Account

7018108

28 August 2013

Throughout the Contract

DBJV

Waste disposal in Contract No. HY/2012/08

Waste Water Discharge License

WT00031435-2018

2 August 2018

31 August 2023

DBJV

Southern Landfall

Waste Water Discharge License

WT00034060-2019

25 July 2019

30 June 2024

DBJV

Northern Landfall (4 Discharge Point)

Notes:

 

HyD = Highways Department

DBJV = Dragages – Bouygues Joint Venture

VEP = Variation of Environmental Permit

                                      

 

                                   

 

                                        

 


2.7                               Implementation Status of Environmental Mitigation Measures

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures relevant to this Contract were implemented properly.

2.8                               Summary of Exceedances of the Environmental Quality Performance Limit

No Action and Limit Level exceedance of was recorded.

Cumulative statistics are provided in Appendix F.

2.9                               Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.2.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.

Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix F.  

 

                                 

3                                    Future Key Issues

3.1                               Construction Activities for the Coming Month

There are no major works to be undertaken in September 2021.

3.2                               Key Issues for the Coming Month

There are no major works to be undertaken in September 2021.

3.3                               Monitoring Schedule for the Coming Month

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.

 

 

4                                    Conclusions and recommendations

4.1                               Conclusions

This Ninety-fourth EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 31 August 2021, in accordance with the Updated EM&A Manual and the requirements of EP-354/2009/D.

Operational phase dolphin monitoring were carried out in this reporting month.

No Action and Limit Level exceedance was recorded.

No Chinese White Dolphins was sighted in the two sets of surveys in August 2021.      

No non-compliance event was recorded during the reporting period.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.

Termination proposal for construction EM&A programme was approved by EPD on 19 March 2021.  The construction phase EM&A programme of the Contract has been terminated since 19 March 2021.

In order to fulfil the EP’s and EM&A Manual’s requirements for TM-CLKL Project, Agreement No. HMWSD 1/2021 (EP) will take over the responsibility for implementation of operational phase dolphin monitoring from Contract No. HY/2012/08 from 1 September 2021 to 31 May 2022.