As per the
requirements of the Contract Specific
Environmental Monitoring and Audit (EM&A) Manual (Section 5.8) ([1])
of Contract No. HY/2012/08
Tuen Mun - Chek Lap Kok Link (TM-CLKL) ¡V
Northern Connection Sub-sea Tunnel Section (the ¡§Contract¡¨), pilot tests
for silt removal efficiency of silt curtain (the ¡§Pilot Tests¡¨) are required
during the initial period of dredging and filling works. This Method
Statement presents the methodology of the Pilot Tests during Phase II
Reclamation.
According to the approved Environmental
Impact Assessment (EIA) of TM-CLKL (Sections
6.7.4.17 & 6.7.4.19) and the latest notification of construction
sequence ([2]),
the relevant silt curtain scenarios are listed in Table 1.1. The latest
construction design and silt curtain arrangements are shown in Figure 1.1.
Table 1.1 Summary
of Silt Curtain Scenarios as discussed in the EIA report (a)
Construction Activities |
Scenario |
Type of Silt Curtain |
Loss Reduction Factor |
Remarks (b) |
Justification |
Dredging Works |
A |
Cage-type
for grab dredger (1) |
80% |
ü |
Cage
type silt curtain will be deployed throughout the dredging works. |
|
B |
Single-layer
floating type silt curtain (2) |
75% |
û |
Single
layer silt curtain will not be deployed individually for dredging works. |
|
C |
Second
layer of floating silt curtain (3) |
50% |
û |
Not
used |
|
D |
Combined
silt curtains (1 + 2) |
95% |
ü |
Dredging
for seawall construction at the remaining section of Portion N-A during Phase
II Reclamation will be commenced in the fourth quarter of year 2016, in which
dredging will be undertaken inside the cage type silt curtain and a single
layer silt curtain will be deployed at Portion N-A parallel to the works
boundary. |
|
E |
Combined
silt curtains (1 + 2 + 3) |
97% |
û |
Not
used. |
|
F |
Combined
(2 + 3) |
87% |
û |
Not
used. |
Filling Activities |
G |
Single-layer
floating type silt curtain (4) |
45% |
ü û |
For
filling works in Phase II Reclamation, two options for construction method
are being considered (c): Option
1. Filling works will commence behind the completed seawall with a 100m gap
for marine access at Portion N-A.
A single-layer floating type silt curtain will be deployed at Portion
N-A parallel to the works boundary. Option
2. Filling works will commence after the completion of the fully enclosed
seawall with no gaps for marine access at Portion N-A, hence Scenario G will
not be applicable for this option.
The silt curtain will remain in place in accordance with Stage 5 of Figure 1.1 until the completion of marine works for
Phase-II Reclamation. |
|
H |
Second
layer of silt curtain (5) |
30% |
û |
Not
used. |
|
I |
Combined
silt curtains (4 + 5) |
61% |
û |
Not
used. |
*Notes |
|
|
|
|
|
(a) Sequence B in the approved EIA
report is not included which is related to the construction at Southern Landfall,
and thus is out of the scopes of this Contract. (b)
ü
= relevant to this Contract and Pilot Tests are proposed in this Method Statement; û
= not relevant or not used in this Contract, thus no Pilot Tests is proposed. (c)
Silt curtain efficiency test for Scenario G would only be conducted if the
Contractor proceeded to option 1 during Phase II Reclamation. |
The latest progress of dredging/ filling
works is summarized as follows:
Phase I Reclamation (Stage 1
to 4 in Figure 1.1)
¡P
Dredging for seawall
construction at Portions N-A, N-B and N-C has been completed in mid-July 2014;
¡P
Dredging in the middle of
Portion N-C has been completed in late-August 2014; and
¡P
The first phase reclamation
filling was commenced from Portion N-A in March 2014
and has been completed in the fourth quarter of year 2014.
Phase
II Reclamation (Stage 5 to 6 in Figure 1.1)
¡P
Dredging for seawall
construction at the remaining section of Portion N-A will commence in the
fourth quarter of year 2016; and
¡P
Filling behind seawall at
the remaining section of Portion N-A will commence in the fourth quarter of
year 2016.
Phase II Reclamation will commence in
the fourth quarter of 2016 and will be completed in early 2017
tentatively. During the preparation
of this Method Statement, dredging
and filling works for Phase I Reclamation was completed. Tentative construction programme for Phase II reclamation
is provided in Annex B for reference.
In this Method Statement, the Pilot Tests are proposed for the pertinent
silt curtain scenarios considering in the EIA and the latest design under this Contract. As informed by the Contractor, the
construction method for Phase II Reclamation is detailed below:
Dredging Works
¡V Scenarios A & D
Dredging for seawall
construction at Portion N-A will be undertaken inside the cage type silt
curtain and a single layer silt curtain will be deployed at Portion N-A
parallel to the works boundary.
Under this construction method, silt curtain arrangement for Scenarios A
and D will take place (see Figure 1.2).
Filling Works
¡V Scenario G
For filling
works, two options for construction method are being considered:
Option 1 -
Filling works will commence behind the completed seawall with a 100m gap for
marine access at Portion N-A. A
single-layer floating type silt curtain will be deployed at Portion N-A
parallel to the works boundary. Under this construction method, silt curtain
arrangement for Scenarios G will take place (see Figure 1.3). The
actual Pilot Test scenario to be conducted will be based on the situation of
abovementioned construction method during Phase II Reclamation.
Option 2 -
Filling works will commence after the completion of the fully enclosed seawall
with no gaps for marine access at Portion N-A, hence Scenario G will not be
applicable for this option. The
silt curtain will remain in place in accordance with stage 5 of Figure 1.1 until the completion of marine works for
Phase-II Reclamation. The proposed
construction method for Option 2 is illustrated in Figure 1.4.
For scenarios A and D, given the
dredging area in Portion N-A is confined in nature and the reclaimed Northern
Landfall and the River Trade Terminal will act as a physical barrier to
restrict tidal flushing, significant tidal influence on the proposed Impact
monitoring stations is not envisaged.
Impact/Outer zone stations downstream of the dredging site are proposed
for ebb tide only due to the locations of the dredging site and the silt curtain
as shown in Figure 1.2. The monitoring locations are determined
based upon the locations of the dredging activities under the Contract and the
proposed silt curtain layout. In
addition, upstream Control Station for impact water quality monitoring will
also be monitored to facilitate comparison of the ambient water quality
conditions in the surrounding environment.
The proposed locations of the monitoring stations for the Pilot Tests of
scenarios A and D are illustrated in Figure 1.2 and detailed in Table 1.2.
Table 1.2 Monitoring
Stations for Pilot Tests of Silt Curtain Efficiency ¡V Dredging under Scenarios
A and D. Indicative locations are
presented.
Monitoring Stations |
Description |
Type of Silt Curtain |
Easting |
Northing |
DI |
Impact
zone ¡V area enclosed by the cage-type silt curtain |
/ |
812710 |
825093 |
DO1 |
Outer
zone ¡V downstream location at approximately 100 m from the cage-type silt
curtain |
Cage-type
(Scenario A) |
812775 |
825098 |
DO2 |
Outer
zone ¡V downstream location at approximately 100 m from the single layer
floating type silt curtain |
Combined
silt curtains (1+2) (Scenario D) |
812884 |
825101 |
CS4 (ebb) |
Upstream
control station during mid-ebb tide |
/ |
810025 |
824004 |
*Note: The
status and locations of the actual monitoring locations may change after
issue of this method statement. If this happens, the ET will agree with
the SOR, in consultation with the IEC/ENPO, to propose the alternative and
updated monitoring location. |
The Impact zone station DI is defined as
the active dredging area enclosed by the cage-type silt curtain, whilst the
Outer zone stations DO1 and DO2 are defined as at a distance approximately 100
m away from the cage-type silt curtain and 100 m away from the combined silt
curtains (1+2), respectively. Based
on the predictions in the approved EIA report ([3]),
this is expected to represent the extent of the zone of influence resulting
from marine construction activities under this Contract. The actual locations of these stations
will be determined on site based on the location of the dredging
activities. Since DI is located at
the immediate vicinity of the active dredging area within the cage-type silt
curtain, due to safety consideration and progress of dredging works, its
location may vary. The actual
location of monitoring stations will be updated in the monitoring report of the
Pilot Tests for any discrepancy from the proposed.
The loss reduction factor between impact
and outer zones of deployed silt curtain will be evaluated for the respective
scenario (see Section 1.2.9). Water quality monitoring at the Control
Station will be evaluated against Action and Limit Levels to identify any
exceedances found during the marine works under this Contract (see Section 1.2.9).
Given the Pilot Tests are aimed to
evaluate primarily on the efficiency of silt curtains where the majority of
marine works to be undertaken, no monitoring will be conducted for scenarios of
silt curtain and seawall combination.
Filling
Works ¡V Scenario G
For scenario G, two sets of monitoring
stations will be arranged, comprising both Impact zone and Outer zone of the
silt curtain. Given the filling
area is confined in nature and the reclaimed Northern Landfall and the River
Trade Terminal will act as a physical barrier to restrict tidal flushing, the
tidal influence on the proposed Impact monitoring stations is not
envisaged. The Impact/Outer zone
stations downstream of the filling site are proposed for ebb tide only due to
the locations of the filling site and the silt curtain as shown in Figure 1.3).
In addition, Control Station for impact water quality monitoring will
also be monitored to facilitate the comparison of ambient water quality
conditions in the surrounding environment.
The indicative locations of the monitoring stations for the Pilot Tests
for filling activities are illustrated in Figure 1.3 and detailed
in Table 1.3.
Table 1.3 Monitoring
Stations for Pilot Tests of Silt Curtain Efficiency ¡V Filling under Scenario
G. Indicative locations are
presented.
Monitoring Stations |
Description |
Type of Silt Curtain /
Barrier |
Easting* |
Northing* |
FI |
Impact
zone ¡V the active filling area |
/ |
812697 |
825069 |
FO |
Outer
zone - approximately 100 m downstream of the single-layer silt curtain |
Single-layer
floating type |
812781 |
825122 |
CS4 (ebb) |
Upstream
control station during mid-ebb tide |
/ |
810025 |
824004 |
*Note: The
status and locations of the actual monitoring location may change after issue
of this method statement. If this
happens, the ET will agree with the SOR, in consultation with the IEC/ENPO,
to propose the alternative and updated monitoring location. |
The Impact station FI is defined as the
active filling area enclosed by the single-layer silt curtain, whilst the Outer
zone station FO is defined as at a distance approximately 100 m downstream of
the single-layer silt curtain. Based on the predictions in the approved
EIA report, this is expected to represent the extent of the zone of influence
resulting from marine construction activities under this Contract. The actual locations of these stations
will be determined on site based on the location of the filling
activities. Since the FI is located
in the close proximity of the active filling area, due to safety consideration
and progress of filling activities, its location may vary.
The actual location of monitoring
stations will be updated in the monitoring results of the Pilot Tests for any
discrepancy from the proposed. The
loss reduction factor between impact and outer zone of deployed silt curtain
will be evaluated for the respective scenario (see Section 1.2.9). Current
measurements will be taken at Outer zone monitoring station during the course
of water quality monitoring for the ebb tide. Water quality monitoring at the Control
Station will be evaluated against Action and Limit Levels to identify any
exceedances found during the marine works under this Contract (see Section 1.2.9).
Given the Pilot Tests are aimed to
evaluate primarily on the efficiency of silt curtains where the majority of
marine works to be undertaken, no monitoring will be conducted for scenarios of
silt curtain and seawall combination.
In addition, the same geotextile material of silt curtain is deployed
within the site area of Contract No.
HY/2012/08, thus the findings from the Pilot Tests within the leading
seawall would be applicable for the same silt curtain arrangement elsewhere
(e.g. dredging and filling at Portion N-A in year 2016
during Phase II Reclamation) under this Contract.
The parameters that have been selected
for measurement in situ and in the
laboratory are those that were determined in the approved EIA report with
higher potential to be affected by the dredging and filling works (i.e.
suspended solids and turbidity) and other general water quality parameters (ie
dissolved oxygen, salinity and temperature).
The
parameter to be measured in the laboratory for silt curtain efficiency
evaluation is:
¡P
Suspended solids (SS) (mg L-1)
In addition to the water quality
parameters, other relevant data will also be measured and recorded in Water
Quality Monitoring Logs, including the location of the sampling stations, water
depth, time, weather conditions, sea conditions, tidal stage, current direction
and velocity, special phenomena and work activities undertaken around the
monitoring and works area that may influence the monitoring results.
For water quality monitoring, the
following equipment will be used:
¡P
Dissolved Oxygen and
Temperature Measuring Equipment -
The instrument will be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
will be operable from a DC power source.
It will be capable of measuring: dissolved oxygen levels in the range of
0 - 20 mg L-1 and 0 - 200% saturation; and a temperature of 0 - 45 degrees
Celsius. It shall have a membrane
electrode with automatic temperature compensation complete with a cable of not
less than 35 m in length.
Sufficient stocks of spare electrodes and cables shall be available for
replacement where necessary (e.g. YSI Pro 2030 or an approved similar
instrument).
¡P
Turbidity
Measurement Equipment - The instrument
will be a portable, weatherproof turbidity-measuring. The equipment will be operated from a DC
power source, it will have a photoelectric sensor capable of measuring
turbidity between 0 - 1000 NTU (for example Hach 2100Q or an approved similar
instrument).
¡P
Salinity Measurement
Instrument - A portable salinometer
capable of measuring salinity in the range of 0 - 40 ppt
will be provided for measuring salinity of the water at each monitoring
location.
¡P
Water Depth Gauge
¡V A portable, battery-operated echo sounder (e.g. Seafarer 700 or a similar
approved instrument) will be used for the determination of water depth at each
designated monitoring station. This
unit will either be hand-held or affixed to the bottom of the work boat if the
same vessel is to be used throughout the monitoring period.
¡P
Current Velocity and
Direction ¡V A current meter capable of
measuring the velocity and direction of flow in the range of 0 ¡V 6 m/s (¡Ó 0.01
m/s) and 0¢X to 360¢X (¡Ó 2¢X), respectively, will be used (e.g. Falmouth
Scientific, Inc. 2-Dimensional Acoustic Current Meter or a similar approved
instrument). The specification of
the proposed current meter is provided in Annex C.
¡P
Positioning Device
¡V A Differential Global Positioning System (DGPS) shall be used during
monitoring to allow accurate recording of the position of the monitoring vessel
before taking measurements. The
DGPS should be suitably calibrated at appropriate checkpoint to verify that the
monitoring station is at the correct position before the water quality monitoring
commence.
¡P
Water Sampling
Equipment - A water sampler,
consisting of a PVC or glass cylinder of not less than two litres, which can be
effectively sealed with cups at both ends, will be used (e.g. Kahlsico Water Sampler 13SWB203 or an approved similar
instrument). The water sampler will
have a positive latching system to keep it open and prevent premature closure
until released by a messenger when the sampler is at the selected water
depth.
The specification of geotextile employed
as silt curtain under this Contract is provided in Annex C.
Prior to the Pilot Tests, the valid
calibration certificates of the monitoring equipment to be used in situ will be provided to the SOR, the
Contractor(s), and IEC/ENPO for agreement.
All valid calibration certificates will be attached to the monitoring
report. Examples of calibration
certificates are shown in Annex D.
1.2.5
Sampling
/ Testing Protocols
All in
situ monitoring instruments will be checked,
calibrated and certified by a laboratory accredited under HOKLAS ([4])
or any other international accreditation scheme before use. Responses of sensors and electrodes will
be checked with certified standard solutions before each use.
On-site calibration of field equipment
shall follow the ¡§Guide to On-Site Test
Methods for the Analysis of Waters¡¨, BS 1427: 2009. Sufficient stocks of spare parts shall
be maintained for replacements when necessary. Backup monitoring equipment shall also
be made available so that monitoring can proceed uninterrupted even when
equipment is under maintenance, calibration etc.
1.2.6
Laboratory
Measurement and Analysis
All
laboratory work shall be carried out in a HOKLAS accredited laboratory ([5]). Water samples of about 1,000 mL shall be
collected at the monitoring and control stations for carrying out the
laboratory analyses. Water samples
for SS measurements will be collected in high density polythene bottles, packed
in ice (cooled to 4¢X C without being frozen), and delivered to a HOKLAS
laboratory as soon as possible after collection.
The
determination work shall start within the next working day after collection of
the water samples. The SS laboratory
measurements shall be provided to the ET within 7 working days upon the receipt
of the samples. The analyses shall
follow the standard methods as described in APHA Standard Methods for
the Examination of Water and Wastewater, 19th Edition, unless
otherwise specified (APHA 2540D for SS) with a detection limit of 0.5 mg L-1.
The submitted information should include
pre-treatment procedures, instrument use, Quality Assurance/Quality Control
(QA/QC) details (such as blank, spike recovery, number of duplicate samples
per-batch etc), detection limits and accuracy. The QA/QC details shall be in accordance
with requirements of HOKLAS or another internationally accredited scheme.
Monitoring will be conducted at all
designated stations at mid-ebb tide in the course of dredging activities. The tentative monitoring schedule is
presented in Table 1.4.
Table 1.4 Tentative
Monitoring Schedule of Background Monitoring and Pilot Tests for Dredging
Scenarios |
Tide |
Monitoring |
Monitoring stations |
Quantities |
Time |
Frequency |
Scenarios
A and D |
Mid-ebb |
Background
Monitoring |
DI,
DO1, DO2 & CS4 |
£U
n = 2 replicates x 3 depths x 4 stations x 1 monitoring event = 24 |
Prior
to Pilot Test when no dredging works is carried out under this Contract |
One
set of measurement at each stations when no dredging works is undertaken
under this Contract at ebb tide |
|
|
Pilot
Test |
DI,
DO1 & DO2 |
£U
n = 2 replicates x 3 depths x 3 stations x 4 monitoring events = 72 |
Within
¡Ó2 hours from the predicted mid-ebb tide during the period of dredging works |
Every
1-hour (time= hr-1, hr-2, hr-3, hr-4) during the 4-hour of Pilot Tests at ebb
tide |
|
|
Impact
Monitoring |
CS4* |
£U
n = 2 replicates x 3 depths x 1 station x 1 monitoring event = 6 |
Within
¡Ó2 hours from the predicted mid-ebb tide during the period of dredging works |
One
set of measurement at the Control station within ¡Ó2 hours from the predicted
mid-ebb tide during the period of dredging works |
*Note:
Monitoring events for Control Station CS4 will only be carried out once in
the same manner as the impact marine water quality monitoring. |
Background monitoring will be conducted
at the designated monitoring stations prior to any dredging activities take
place of the day under this Contract.
The background monitoring is to investigate whether the change in the
ambient environmental condition irrespective to any dredging activities take
place under this Contract.
Upon dredging commenced, water samples
for SS laboratory analysis will be collected with the in situ parameters measurements starting from Outer zone (e.g. DO1,
DO2) and eventually at Impact zone Station (e.g. DI). Per each monitoring event, the in situ measurements and SS sampling
will be conducted every one hour for 4-hour in the predicted mid-ebb tide. Monitoring at the respective Control
Station (i.e. CS4) will be undertaken in the same manner as the impact marine
water quality EM&A for this Contract as to compare the water quality from
the dredging site with the ambient water quality.
For a better understanding of the
relationships between loss reduction factor and the dredging activities,
information such as dredging rate and dredged volume during the pilot test,
actual location of dredging works, will be recorded and reported together with
the monitoring results.
Filling Activities ¡V Scenario G
Monitoring will be conducted at all
designated stations at mid-ebb tide in the course of reclamation filling. The tentative monitoring schedule is
presented in Table 1.5.
Table 1.5 Tentative
Monitoring Schedule of Background Monitoring and Pilot Tests for Filling
Scenario |
Tide |
Monitoring |
Monitoring stations |
Quantities |
Time |
Frequency |
Scenario
G |
Mid-ebb |
Background
Monitoring |
FI,
FO & CS4 |
£U
n = 2 replicates x 3 depths x 3 stations x 1 monitoring event = 18 |
Prior
to Pilot Test when no filling works is carried out under this Contract |
One
set of measurement at each stations when no filling works is undertaken
under this Contract at ebb tide |
|
|
Pilot
Test |
FI
& FO |
£U
n = 2 replicates x 3 depths x 2 stations x 4 monitoring events = 48 |
Within
¡Ó2 hours from the predicted mid-ebb tide during the period of filling works |
Every
1-hour (time= hr-1, hr-2, hr-3, hr-4) during the 4-hour of Pilot Tests at
ebb tide |
|
|
Impact
Monitoring |
CS4* |
£U
n = 2 replicates x 3 depths x 1 station x 1 monitoring event = 6 |
Within
¡Ó2 hours from the predicted mid-ebb tide during the period of filling works |
One
set of measurement at the Control station within ¡Ó2 hours from the predicted
mid-ebb tide during the period of filling works |
Background monitoring will be conducted
at the designated monitoring stations prior to any filling activities take
place of the day under this Contract.
The background monitoring is to investigate whether the change in the
ambient environmental condition irrespective to any filling activities take
place under this Contract.
Upon filling commenced, water samples
for SS laboratory analysis will be collected with the in situ parameters measurements starting from Outer zone (eg. FO) and eventually at Impact zone Station (eg. FI). Per each
monitoring event, the in situ
measurements and SS sampling will be conducted every one hour for 4-hour in the
predicted mid-ebb tide. Monitoring
at the respective Control Station (i.e. CS4) will be undertaken in the same
manner as the impact marine water quality EM&A for this Contract as to
compare the water quality from the filling site with the ambient water quality.
For a better understanding of the
relationships between loss reduction factor and the filling activities,
information such as filling rate during the pilot test, number of dump barge
used, types of filling material used, actual location of filling works,
distance between filling activities and FI station, will be recorded and
reported together with the monitoring results.
Each station will be sampled and
measurements will be taken at three depth, 1 m below sea surface, mid-depth and
1 m above the seabed. Duplicate (2)
readings of the in situ measurements
and duplicate (2) SS samples will be made at each water depth at each
station. For stations that are less
than 3 m in depth, only the mid depth sample will be taken. For stations that are less than 6 m in
depth, the mid-depth station will be omitted.
As the
QA/QC procedures for the in-situ measurement
of DO and Turbidity, where the difference in value between the first and
subsequent measurements at a certain depth is more than 25% of the value of the
first measurement, the measurements should be discarded and further
measurements should be taken to confirm the values.
Safety is the highest priority during
sampling works and it will cease should conditions warrant ensuring the safety
of the staff. The risk assessment
of health and safety for silt curtain installation and related works is
provided in Annex E.
The efficiency of the silt curtains will
be evaluated against the relevant loss reduction factor for suspended solids (Table 1.6 & 1.7) with reference to the
approved EIA of TM-CLKL (Table D6-1
in Appendix D6a).
For Scenario A,
Loss Reduction Factor = 100* [(SS (in) -
SS (out)) / SS (in)]
where
SS(in) = DI
SS(out) = DO1.
For Scenario D,
Loss Reduction Factor = 100* [(SS (in) -
SS (out)) / SS (in)]
where
SS(in) = DI
SS(out) = DO2.
For Scenario G,
Loss Reduction Factor = 100* [(SS (in) -
SS (out)) / SS (in)]
where
SS(in) = FI
SS(out) = FO.
Table
1.6 Loss Reduction
Factor of Silt-removal Efficiency for Dredging
Parameter |
Scenario |
Loss Reduction Factor |
Loss Reduction Criteria |
Suspended
Solids (SS) in mg/L (Depth-averaged (a)) |
A |
100*
[ (SS (in) - SS (out)) / SS (in)] (b) |
Loss
reduction factor ≥ 80% |
|
D |
100*
[ (SS (in) - SS (out)) / SS (in)] (b) |
Loss
reduction factor ≥ 95% |
Notes: |
|
||
a. ¡§Depth-averaged¡¨ is calculated by taking the
arithmetic means of reading of all three depths. |
|||
b. (out): represents mean measurement of SS at Outer zone
(e.g. Monitoring station DO1/DO2) of dredging works during the same tidal
cycle. (in): represents mean measurement of SS at Impact zone
(e.g. Monitoring station DI) of dredging works during the same tidal cycle. |
Table 1.7 Loss
Reduction Factor of Silt-removal Efficiency for Filling
Parameter |
Scenario |
Loss Reduction Factor (b) |
Loss Reduction Criteria |
Suspended
Solids (SS) in mg/L (Depth-averaged (a)) |
G |
100*
[ (SS (in) - SS (out)) / SS (in)] |
Loss
reduction factor ≥ 45% |
|
|
|
|
Notes: |
|
||
a. ¡§Depth-averaged¡¨ is calculated by taking the
arithmetic means of reading of all three depths. |
|||
b. (out): represents mean measurement of SS at Outer zone
(e.g. Monitoring station FO) of filling activities during the same tidal
cycle. (in): represents mean measurement of SS at Impact zone
(e.g. Monitoring station FI) of filling activities during the same tidal
cycle. |
Since the proposed
Control Station (i.e. CS4) is adopted from the Contract Specific EM&A Manual, the Action and Limit Levels for
the Water Quality Monitoring will also be adopted from the manual (please refer to Section 5.12 of the manual)
([6]).
Water quality monitoring at the Control Station will be evaluated
against Action and Limit Levels (Table
1.8).
Table 1.8 Action
and Limit Levels for Water Quality Monitoring
Parameter |
Action Level# |
Limit Level# |
DO in mg/L (a), (e) |
Surface and Middle |
Surface and Middle |
|
5.0 mg/L |
4.2 mg/L |
|
Bottom |
Bottom |
|
4.7 mg/L |
3.6 mg/L |
Turbidity in NTU (Depth-averaged (b), (c)) |
120% of upstream control station at the same tide of
the same day and 95%-ile of baseline data, i.e., 27.5 NTU |
130% of upstream control station at the same tide of
the same day and 99%-ile of baseline data, i.e., 47.0 NTU |
SS in mg/L (Depth-averaged (b), (c)) |
120% of upstream control station at the same tide of
the same day and 95%-ile of baseline data, i.e., 23.5 mg/L |
130% of upstream control station at the same tide of
the same day and 10mg/L for WSD Seawater Intakes at Tuen Mun and 99%-ile of
baseline data, i.e., 34.4 mg/L |
Notes: |
|
|
# Baseline data: data from HKZMB Baseline Water
Quality Monitoring between 6 and 31 October 2011. |
||
(a) For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits. |
||
(b) ¡§Depth-averaged¡¨ is calculated
by taking the arithmetic means of reading of all three depths. |
||
(c) For turbidity and SS,
exceedance of the water quality occurs when monitoring result is higher than
the Action/Limit levels. |
||
(d) All figures given in the table
are used for reference only, and EPD may amend the figures whenever it is
considered as necessary. |
||
(e) The 1%-ile of baseline data for
surface and middle DO is 4.2 mg/L, whilst for bottom DO is 3.6 mg/L. |
In respect to the construction phase
EM&A marine works, the ET will prepare and submit the monitoring results of
the Pilot Tests for Silt Curtain Efficiency within 30 working days following
the completion of the monitoring.
Copies of the monitoring results of the Pilot Tests for Silt Curtain
Efficiency will be submitted to the following: the Contractor(s), the SOR, the
IEC/ENPO and the EPD as appropriate.
The ET will liaise with the relevant parties on the exact number of
copies required.
As stated in the Contract Specific EM&A Manual ([7]),
regardless of the measured efficiency of the silt curtain system, the event and
action plan provided in the Contract
Specific EM&A Manual will only be based on the monitoring results at
the designated monitoring stations.
Should exceedance of the Action/Limit
Levels are reported at the Control Station, the Event and Action Plan of Water
Quality stipulated in Table 5.3, Section 5.12 of the Contract Specific EM&A Manual shall be followed ([8]).
([2])
The
notification of change in construction sequence was submitted to ENPO in
September 2014 and was subsequently approved by EPD on 7 October 2014. The approved notification of change in
construction sequence is presented in Annex A.