|
|
|
||||
|
|
|
||||
|
|
|
||||
|
|
AUES Job No.: TCS00715/14 |
|
|
||
|
|
|
|
|
||
|
|
Tuen Mun - Chek
Lap Kok Link Contract No. HY/2013/12 ¡V Northern Connection Toll Plaza and Associated Works |
|
|
||
|
|
|
|
|
||
|
|
4th Quarterly Environmental
Monitoring & Audit Summary Report ¡V (August to October 2015) |
|
|
||
|
|
Prepared
For |
|
|
||
|
|
CRBC
and Kaden Joint Venture |
|
|
||
Quality Index |
|||
Date |
Reference No. |
Prepared By |
Certified By |
26 November 2015 |
TCS00715/14/600/R0150v1 |
|
|
Ben
Tam (Environmental Consultant) |
T.W. Tam (Environmental Team Leader) |
This
report has been prepared by Action-United Environmental Services & Consulting
with all reasonable skill, care and diligence within the terms of the
Agreement with the client, incorporating our General Terms and Conditions of
Business and taking account of the resources devoted to it by agreement with
the client. We disclaim any responsibility to the client and others in
respect of any matters outside the scope of the above. This report is
confidential to the client and we accept no responsibility of whatsoever
nature to third parties to whom this report, or any part thereof, is made
known. Any such party relies upon the report at their own risk. |
Executive Summary
ES.01. This is the 4th Quarterly EM&A Summary Report
for the ¡§Tuen Mun - Chek Lap Kok Link - Northern Connection
Toll Plaza and Associated Works¡¨ under Environmental Permit No. EP-354/2009/D (hereinafter ¡¥¡¥the EP¡¦¡¦), covering the period from 1 August to 31 October 2015 (hereinafter ¡§Reporting Period¡¨).
Environmental Monitoring and
Audit Activities
ES.02. Environmental monitoring activities under
the EM&A programme in the Reporting Period are
summarized in the following table.
Environmental Aspect |
Environmental
Monitoring Parameters / Inspection |
Total Occasions |
Air Quality |
1-hour TSP |
450 |
24-hour TSP |
150 |
|
Cultural heritage inspection |
Grave G1 |
13 |
Landfill Gas Monitoring |
Oxygen; Methane & Carbon Dioxide |
75 days |
Landscape &Visual |
Landscape
&Visual Monitoring |
13 |
Joint Site Inspection / Audit |
IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing |
13 |
Breaches
of Action/Limit levels
ES.03.
In the Reporting Period, no exceedance was
recorded for the measured parameter under the Contract. The summary of breach of
monitoring performance is shown below.
Environmental
Aspect |
Monitoring Parameters |
Action Level |
Limit Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Air Quality |
1-hour TSP |
0 |
0 |
0 |
0 |
0 |
24-hour TSP |
0 |
0 |
0 |
0 |
0 |
|
Landfill Gas
Monitoring |
Oxygen |
0 |
0 |
0 |
0 |
0 |
Methane |
0 |
0 |
0 |
0 |
0 |
|
Carbon
Dioxide |
0 |
0 |
0 |
0 |
0 |
Environmental
Complaint
ES.04. In the Reporting
Period, two (2) environmental complaints were received on 3 August and 2
September 2015 regarding the soil/ muddy water caused by frequent dump trucks
in Lung Mun Road and River Trade Terminal and milky
water discharged from the drainage outlet near the Butterfly Beach, Tuen
Mun. Investigation for the
complaints has been conducted by the ET and the corresponding investigation
reports for the complaint have been submitted to relevant parties.
Notification of Summons and Successful Prosecutions
ES.05. No
environmental summons or successful prosecutions were recorded in the Reporting
Period.
Reporting Changes
ES.06. No
reporting changes were made in the Reporting Period.
Future key issues
ES.07. Druing dry
season, air quality mitigation measures such as watering of site area for 12
times per day and covering of exposed slopes should be fully implemented to
reduce construction dust impact as recommended in the EMIS.
ES.08. Moreover,
muddy water or other water pollutants from site surface runoff into the public
areas will be key environment issue.
Special attention should be paid on the water quality mitigation
measures to prevent surface runoff flow to public area.
ES.09. It was
reminded that good housekeeping practice should be maintained. Mosquito control measures should be properly
implemented to prevent mosquito breeding on site especially after rain.
Table of Contents
2 Contract
Organization and Construction progress
2.3 Summary of Environmental Submissions
3 Summary of Impact
monitoring Requirements
3.6 Derivation
of Action/Limit (A/L) Levels
3.7 Other
Environmental Aspects
4.2 Summary
of Monitoring Results
4.3 Action
and Limit (A/L) Levels Exceedance
7.2 Landscape
and Visual Inspection
8 Landfill Gas Hazard
Monitoring
8.2 Landfill
Gas Monitoring Result
9.2 Records
of Waste Quantities
11 Environmental Complaint and
Non-compliance
11.1 Environmental
Complaint, Summons and Prosecution
12 Implementation Status of
Mitigation Measures
13 Conclusions and Recommendations
List
of tables
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Table 3-1 Air
Quality Monitoring Stations under the Contract
Table 3-2 Enhanced
TSP Monitoring Plan ¡V Construction Phase
Table 3-3 Action
and Limit Levels for Impact Air Quality Monitoring
Table 4-1 Summary
of Air Quality Monitoring Exceedance
Table 8-1 Summary
of Landfill Gas Measurement Results in Reporting Period
Table 9-1 Summary
of Quantities of Inert C&D Materials
Table 9-2 Summary
of Quantities of C&D Wastes
Table 10-1 Site
Observations for the Contract for the Reporting Period
Table 10-2 Summary
of Reminders/Observations of Site Inspection
Table 11-1 Statistical
Summary of Environmental Exceedance
Table 11-2 Statistical
Summary of Environmental Complaints
Table 11-3 Statistical
Summary of Environmental Summons
Table 11-4 Statistical
Summary of Environmental Prosecution
Table 12-1 Environmental
Mitigation Measures
List of Annexes
Appendix
A Layout plan of the Project
Appendix B Layout plan of the Contract
Appendix
C Environmental Management
Organization Chart
Appendix
D Master Construction Programme
for
Appendix
E Monitoring Locations /
Sensitive Receivers for the Contract
Appendix
F Event and Action Plan
Appendix
G Landfill Gas Monitoring Graphical Plots
Appendix
H Waste Flow Table
Appendix
I Implementation Schedule for Environmental Mitigation Measures
1.1.1. CRBC-Kaden
Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) is commissioned by the
Highways Department (HyD) as the Main Contractor of
the Contract No. HY/2013/12 ¡V
Northern Connection Toll Plaza and Tunnel Section ((hereafter ¡§the Contract¡¨)
and this Contract is part of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project). The TM-CLK Link Project is a designated
project under Environmental Permit number EP-354/2009D issued on 13 March 2015. The layout Plan of the Project and the Contract are showed in Appendix A and B respectively.
1.1.2.
The construction works
of the Contract mainly include:-
a.
construction of an approximately 5.4 hectares
toll plaza and an associated footbridge;
b.
construction of associated carriageways including
approximately 0.74 kilometre land viaducts, and an
approximately 230 metres vehicular underpass to
connect the toll plaza and the roundabout at Lung Mun Road/Lung Fu Road;
c.
site formation for the construction of the
toll plaza, including associated slope works and natural terrain hazard
mitigation measures;
d.
modification and realignment of the existing
Lung Mun Road and Lung Fu Road; and
e.
associated
waterworks, drainage, sewerage and landscaping works, etc..
1.1.3.
Action-United Environmental Services & Consulting has been commissioned as an Independent ET to implement the
relevant EM&A program in accordance
with the approved EM&A Manual, as well as the associated duties.
1.1.4.
This is the 4th
Quarterly EM&A Summary Report covering the period
from 1
August to 31 October 2015.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Contract
Organization and Construction Progress
Section 3 Summary
of Impact Monitoring Requirements
Section 4 Air
Quality Monitoring
Section 5 Ecology
Monitoring
Section 6 Cultural
Heritage
Section 7 Landscape
and Visual
Section 8 Landfill
gas hazard Monitoring
Section 9 Waste
Management
Section 10 Site Inspections
Section 11 Environmental
Complaints and Non-Compliance
Section 12 Implementation
Status of Mitigation Measures
Section 13 Conclusions
and Recommendations
2.1.1
The Contract organization and contact details
of key personnel are shown in Appendix C.
2.2.1
In the Reporting Period, the major
construction activity conducted under the Contract is summarized in below. Moreover, the master construction
program is enclosed in Appendix D.
August 2015
Instrumentation and Monitoring
Site Formation ¡V Retaining Structure for Slope
TP_F, TP_G, TP_A and Associated Works, TP_B and Associated Works, TP_C and
Associated Works, TP_D and Associated Works, TP_E and Associated Works and
Upgrading Works
Toll Plaza Decking TD1, TD2
Toll Plaza Footbridge-Section 1
Retaining Structure RW_B-Section 1, RW_A
Bridge G1, G2,Bridge H1
Sewer Culvert 1 (TBM) ¡V Stage 4, Culvert 2 &
Culvert 3 and Existing Box Culvert
Natural Terrain Hazard Mitigation Measures
Vehicular Underpass TN-01
Road and Drainage Works for Lung Fu Road Roundabout
September 2015
Instrumentation and Monitoring
Site Formation ¡V Retaining Structure for Slope
TP_F, TP_G, TP_A and Associated Works, TP_B and Associated Works, TP_C and
Associated Works, TP_D and Associated Works, TP_E and Associated Works and
Upgrading Works
Toll Plaza Decking TD1, TD2
Toll Plaza Footbridge-Section 1
Retaining Structure RW_B-Section 1, RW_A
Bridge G1, G2,Bridge H1
Sewer Culvert 1 (TBM) ¡V Stage 4, Culvert 2 &
Culvert 3 and Existing Box Culvert
Natural Terrain Hazard Mitigation Measures
Vehicular Underpass TN-01
Road and Drainage Works for Lung Fu Road Roundabout
October 2015
Dismantling of HY/2012/04 Project Office at WA6
Instrumentation and Monitoring
Site Formation ¡V Retaining Structure for Slope
TP_F, TP_G, TP_A and Associated Works, TP_B and Associated Works, TP_C and
Associated Works, TP_D and Associated Works, TP_E and Associated Works and
Upgrading Works
Toll Plaza Decking TD1, TD2
Toll Plaza Footbridge-Section 1
Retaining Structure RW_B-Section 1, RW_A
Bridge G1, G2,Bridge H1
Sewer Culvert 1 (TBM) ¡V Stage 4, Culvert 2 &
Culvert 3 and Existing Box Culvert
Natural Terrain Hazard Mitigation Measures
Vehicular Underpass TN-01
Road and Drainage Works for Lung Fu Road Roundabout
2.3.1
In according to the EP, the required
documents have submitted to EPD for retention which listed in below:
Monitoring Plan on Construction Dust
(submission refer to Contract HY/2012/08)
Landscape and Visual Plan (not yet endorsed by EPD)
Waste Management Plan (endorsed by EPD on 16 March 2015)
Baseline Monitoring Report (not yet endorsed
by EPD)
2.3.2
Summary of
the relevant permits, licenses, and/or notifications on environmental protection
for the Project of each contracts are presented in Table 2-1.
Table 2-1 Status
of Environmental Licenses and Permits of the Contracts
Type of Permit/
License |
Submission Date |
Reference/ License No. |
Date of Issue |
Date of Expiry |
|
1 |
Air pollution Control (Construction Dust)
Regulation |
06-08-2014 |
377719 |
06-08-2014 |
N/A |
2 |
Chemical Waste Producer Registration -
Waste Producers Number |
06-08-2014 |
5117422C389301 |
03-09-2014 |
N/A |
3 |
Water Pollution Control Ordinance -
Discharge License |
13-08-2014 |
WT00020065-2014 |
29-09-2014 |
30-09-2019 |
4 |
Waste Disposal Regulation - Billing Account
for Disposal of Construction Waste |
21-07-2014 |
7020460 |
01-08-2014 |
N/A |
5 |
CNP for Multiple
Task |
24-04-2015 |
GW-RW0225-15 |
13-05-2015 |
04-11-2015 |
6 |
CNP for MH5 |
05-05-2015 |
GW-RW0226-15 |
18-05-2015 |
17-11-2015 |
7 |
Permission to Transplant Pitcher Plant |
15-6-2015 |
(30) in AF CON 11/13 pt.4 |
23-6-2015 |
22-12-2015 |
8 |
Variation of Effluent Discharge License |
19-08-2015 |
Pending for approval |
3.1.1
The major construction activities under the Contract
are land-based and no marine work will be involved. In accordance with the Project EM&A
Manual requirements, the environmental aspects under the Contract shall be
included air quality, ecological, cultural heritage, landscape and visual,
landfill gas and site inspection during construction period. In addition, audit of the contractor¡¦s
implementation of the construction noise and land-based water quality pollution
control measures are also required for the Contract.
3.1.2
A summary of construction phase EM&A
requirements are presented in the
sub-sections below.
3.2.1
The construction phase air quality monitoring
shall cover the following parameters:
•
1-hour TSP; and
•
24-hour TSP
3.3.1
The air quality
monitoring stations for impact monitoring are listed in Table 3-1
and illustrated in Appendix E.
Table
3-1 Air
Quality Monitoring Stations under the Contract
ID |
Location |
Air monitoring station
Description |
ASR1 |
Tuen Mun Fireboat Station |
EM&A Manual |
ASR5 |
Pillar Point Fire Station |
EM&A Manual |
AQMS1 |
Previous River Trade Golf |
Enhanced TSP Level under EP condition 2.4 |
ASR6 |
Butterfly Beach Laundry |
Enhanced TSP Level under EP condition 2.4 |
ASR10 |
Butterfly Beach Park |
Enhanced TSP Level under EP condition 2.4 |
3.4.1
As per Condition 2.4 of the EP of TM-CLKL, an
enhanced monitoring plan on TSP level at Tuen Mun (¡§the Enhanced TSP Monitoring
Plan¡¨) is required to be submitted to the DEP for approval at least 1 month
before the commencement of construction of the Project. Details of the Enhanced TSP Monitoring
Plan under Contract No. HY/2012/08 could be found from the project website. The
air quality monitoring work under this Contract will follow the monitoring
requirement of enhanced TSP monitoring under the project.
3.4.2
The air quality monitoring requirements for
the Contract is summarized in Table 3-2.
Table
3-2 Enhanced
TSP Monitoring Plan ¡V Construction Phase
Condition |
Monitoring Parameter |
Monitoring Location |
Frequency |
Monitoring Requirement |
General |
1-hour TSP |
ASR1, ASR5, AQMS1, ASR6, ASR10 |
3 times per day every
six days |
Throughout the Northern
Connection, toll plaza and tunnel buildings construction works |
24-hour TSP |
ASR1, ASR5, AQMS1, ASR6, ASR10 |
Daily every six days |
||
Special |
1-hour TSP |
ASR1, ASR5, AQMS1, ASR6, ASR10 |
3 times per day every
three days |
Northern Connection During excavation
works for launching shaft, excavation work for Cut and Cover Tunnel and Cut
and Cover Tunnel Construction Toll Plaza During excavation,
slope works, construction of road and superstructures and wind erosion from
open sites and stockpiling areas Tunnel Buildings During excavation,
foundation works, construction of superstructures and wind erosion from open
sites and stockpiling areas |
24-hour TSP |
ASR1, ASR5, AQMS1, ASR6, ASR10 |
Daily every three days |
3.5.1
The 24-hour and 1-hour TSP levels shall be
measured by following the standard high volume sampling method as set out in
the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B.
3.5.2
The filter paper of 24-hour TSP measurement
shall be determined by HOKLAS accredited laboratory. A high volume sampler in
compliance with the following specifications shall be used for carrying out the
1-hr and 24-hr TSP monitoring:
(i)
0.6-1.7 m3/min (20-60
SCFM) adjustable flow range;
(ii)
equipped with a
timing/control device with +/- 5 minutes accuracy for 24 hours operation;
(iii)
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
(iv)
capable of providing a
minimum exposed area of 406 cm2 (63 in2);
(v)
flow control accuracy: +/-
2.5% deviation over 24-hr sampling period;
(vi)
equipped with a shelter
to protect the filter and sampler;
(vii) incorporated with an electronic mass flow rate controller or other
equivalent devices;
(viii) equipped with a flow recorder for continuous monitoring;
(ix)
provided with a peaked
roof inlet;
(x)
equipped with a
manometer;
(xi)
able to hold and seal
the filter paper to the sampler housing in a horizontal position;
(xii) easy to change the filter; and
(xiii) capable of operating
continuously for 24-hr period.
3.5.3
Calibration of dust monitoring equipment
shall be conducted by the ET upon installation and in bi-monthly intervals
during construction phase. The
transfer standard shall be traceable to the internationally recognized primary
standard and be calibrated annually. The calibration data shall be properly
documented for future reference by concerned parties, such as the IEC. All the
data shall be converted into standard temperature and pressure condition.
3.5.4
The filter paper of 24-hour TSP measurement
shall be determined by HOKLAS accredited laboratory.
3.5.5
If the ET proposes to use a direct reading
dust meter to measure 1-hr TSP levels on an ad hoc basis, he shall submit
sufficient information to the IEC to prove that the instrument is capable of
achieving a comparable result as that the High Volume Sampler (HVS) and may be
used for the 1-hr sampling. The
instrument should also be calibrated regularly and the 1-hr sampling shall be
checked periodically by the HVS to check the validity and accuracy of the
results measured by the direct reading method.
3.5.6
According to the Project EM&A Manual,
wind data monitoring equipment shall also be provided and set up for logging
wind speed and wind direction near the dust monitoring locations. The equipment installation location
shall be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
(i)
the wind sensors should
be installed on masts at an elevated level 10 m above ground so that they are
clear of obstructions or turbulence caused by the buildings;
(ii)
the wind data should be
captured by a data logger to be down-loaded for processing at least once a
month;
(iii)
the wind data monitoring
equipment should be re-calibrated at least once every six months; and
(iv)
wind direction should be
divided into 16 sectors of 22.5 degrees each.
3.6.1
The baseline monitoring results formed the
basis for determining the air quality criteria for the impact monitoring. The
ET shall compare the impact monitoring results with air quality criteria set up
for 24-hour TSP and 1-hour TSP.
Based on results of the approved Baseline Monitoring Report of HyD Contract HY/2012/08, the Action and Limit Levels for
impact dust monitoring are shown in Tables 3-3.
Table 3-3 Action and Limit Levels for Impact Air
Quality Monitoring
Air Quality Monitoring Stations |
24-hour TSP (£gg/m3) |
1-hour TSP (£gg/m3) |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
|
ASR1 |
213 |
260 |
331 |
500 |
ASR5 |
238 |
260 |
340 |
500 |
AQMS1 |
213 |
260 |
335 |
500 |
ASR6 |
238 |
260 |
338 |
500 |
ASR10 |
214 |
260 |
337 |
500 |
3.6.2
Should non-compliance of the environmental
quality criteria occurs, remedial actions will be triggered according to the Event
and Action Plan which presented in Appendix F.
Noise
3.7.1
The TM-CLKL EIA study stated that no existing
noise sensitive receiver (NSR) was identified within the Study Area at Tuen
Mun. Therefore, no noise monitoring
is required for the construction phase of the Contract.
3.7.2
Regular site inspections and audits will be
carried out during the construction phase in order to confirm the construction
works under the Contract comply with the regulatory noise requirements.
Water Quality
3.7.3
No marine works will be undertaken under the
Contract. Therefore, no water
quality monitoring is required for the construction phase of the Contract.
Ecology
3.7.4
No marine works will be undertaken under the
Contract and generated marine ecological impact, no dolphin monitoring is
required for the construction phase of the Contract.
3.7.5
During construction phase, the ET will
perform Pitcher Plants inspection at least once every week to report the growth
condition and protection measures.
Landscape and Visual
3.7.6
Measures to mitigate landscape and visual
impact during construction should be checked and monitored by a Registered
Landscape Architect to ensure compliance with the intended aims of the
mitigation measures in accordance with the EM&A Manual.
Cultural Heritage
3.7.7
Grave G1 as a heritage resource is situated
near the proposed toll plaza in Tuen Mun.
Site inspections should be undertaken at least once per week throughout
the construction period to ensure compliance with the intended aims of recommended
mitigation measures.
3.7.8
During EIA study, landfill gas hazards are
likely to be generated from the Pillar Point Valley (PPV) Landfill. Landfill gas monitoring is recommended
during construction of the Contract to ensure the works area is free of
landfill gas before the worker entered the concerned area.
4.1.1
The air quality impact monitoring and
enhanced Total Suspended Particulates (TSP) level monitoring at five proposed
locations are currently carried out by the ET of Contract HY/2012/08. Sharing of impact air quality monitoring
data between HY/2012/08 and HY/2013/12 is agreed by all relevant parties. The Contract is not required to conduct
its own dust monitoring exercise until the Contract HY/2012/08 ends.
4.2.1
In the Reporting Period, 1- hour and
24-hour TSP monitoring at the five proposed locations are continued to perform
by the ET of Contract HY/2012/08.
Therefore, no air quality monitoring was conducted by the ET of Contract
HY/2013/12. Details information of
air quality monitoring results could be referred to the Monthly EM&A
Reports of the Contract HY /2012 /08 (August 2015, September 2015 and October 2015).
4.3.1
According to the air quality monitoring
result provided by Contract HY/2012/08, no exceedances in 1-hour and 24-hour
TSP were recorded in the Reporting Period.
No Notification on Exceedances (NOEs) was issued by the ET of Contract
HY/2012/08. The summary of air
quality exceedance in the Reporting Period is shown in Table 4-1.
Table 4-1 Summary of Air Quality Monitoring Exceedance
Date of Exceedance |
Monitoring Station |
Air Quality Parameter |
Result |
Exceed |
NA |
NA |
NA |
-- |
-- |
4.4.1
No investigation for
exceedance is required for the Reporting Period.
5.1.1
According to the EM&A Manual
requirements, regularly
inspection for Pitcher Plants at least once every week to report it growth and protection
measure
situation shall be conducted during construction period.
5.2.1
In the Reporting Period, inspections for
implementation status of mitigation measures for the Pitcher Plants were
carried out by the ET on 4th,
11th, 18th, 25th August 2015 and 1st,
8th, 15th, 22nd, 29th September
2015 and 6th, 14th,
20th and 27th October 2015 . Trial transplantation of pitcher plant
from the nursery site to final receptor site was carried out on 15 April 2015
and transplantation of remaining 95% was carried out in 9th
and 10th September 2015.
5.2.2
During weekly site inspection at the nursery
zone before the transplantation to the receptor site, the transplanted Pitcher Plants in the
nursery zone were observed in fair to poor
condition. No construction
activities were conducted nearby the nursery zone and the Pitcher Plants were protected properly. Moreover, no repair or
maintenance is required for the protected facilities such as scaffold structure and chain link fence.
5.2.3
All the
pitcher plant had been transplanted to the final receptor site which is located
near Zone 9 and Zone 10. Random checking was performed for the
protected areas Zones 8, 9 and 10 during the weekly site inspections. The
Pitcher Plants at the protected areas was protected properly and the growth
also was in fair to poor condition. Moreover, no construction activities were
carried out nearby the protected areas of Pitcher Plants. The condition of
chain link fence is good and no repair or maintenance is required.
6.1.1
According to the EM&A Manual
requirements, regular inspection for heritage resource, Grave G1, shall be
audited by the ET at least once every week to ensure recommended mitigation
measures implemented during construction period. The aim of the survey is to
prevent any possible damage to the grave and to ensure the proposed mitigation
measures are implemented. The broad
scope of the audit will involve supervision of the following:
Non-contact effects of
the engineering works, such as vibration from pneumatic drills which could
cause damage, such as foundation or wall cracks and loosening of tiles or
fixtures; and
Contact between the
historic structures and equipment and materials associated with the engineering
works.
6.1.2
Specifically, the monitoring programme
will entail the following tasks:
The extent of the agreed
works areas should be regularly checked during the construction phase to ensure
the buffer is being maintained; and
Ensure no stockpiling or
equipment storage is affecting the structure.
6.1.3
In the event of non-compliance the
responsibilities of the relevant parties is detailed in the Event/ Action Plan
in Appendix F.
6.2.1
In the Reporting Period, site inspection for
the Grave G1 was undertaken on 4th,
11th, 18th, 25th August 2015 and 1st, 8th, 15th,
22nd, 29th September 2015 and 6th, 14th, 20th and 27th
October 2015. During site
inspection, buffer zone between the working area
and the Grave was maintained and no construction material
or equipment was stored nearby the Grave.
6.2.2
Mitigation measures undertaken by the
Contractor has fully implemented the EM&A Manual requirements.
7.1.1
According to EM&A Manual requirements,
monitoring of Contractor¡¦s operations during construction period to report on
Contractor¡¦s compliance should be carried out on weekly basis. Measure to mitigate landscape and visual
impact during construction should be checked and monitored by a Registered
Landscape Architect to ensure compliance with the intended aims of the
mitigation measures. Moreover, the
progress of the engineering works shall be regularly reviewed on site to
identify the earliest practical opportunities for the landscape works to be
undertaken.
7.2.1
In the Reporting Period, site inspection for
landscape and visual mitigation measures was undertaken by the Registered
Landscape Architect on 7th, 14th, 21st
and 28th August 2015 and 4th, 11th,
18th, 25th September 2015 and 2nd, 9th,
16th, 23rd and 30th October 2015.
7.2.2
Most of the landscape works such as planting
was not yet commenced. The detailed
inspection checklists can be referred to the Monthly EM&A Reports
(August 2015, September 2015 and October 2015) of the contract.
8.1.1
During EIA study, landfill gas hazards are
likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence,
regular landfill gas monitoring is recommended during construction of the
proposed toll plaza.
8.1.2
During construction, a Safety Officer should
be appointed to carry out the monitoring works. The monitoring frequency and
areas to be monitored should be set down prior to commencement of ground-works
either by the Safety Officer or an approved and appropriated qualified person.
The routine monitoring should be carried out in all excavations, manholes,
chambers, relocation of monitoring wells and any other confined spaces that may
have been created. All measurements in excavations should be made with the extended
monitoring tube located not more than 10 mm from the exposed ground surface.
Monitoring should be performed properly to make sure that the area is free of
landfill gas before any man enters in the area.
8.1.3
For excavations deeper than 1m, measurements should
be carried out:
at the ground surface
before excavation commences;
immediately before any
worker enters the excavation;
at the beginning of each
working day for the entire period the excavation remains open; and
periodically through the working day whilst workers are in the excavation.
8.1.4
For excavations between 300mm and 1m deep,
measurements should be carried out:
directly after the
excavation has been completed; and
periodically whilst the
excavation remains open
8.1.5
For excavations less than 300mm deep,
monitoring may be omitted, at the discretion of the Safety Officer or other
appropriately qualified person.
8.1.6
To ensure the accuracy of the monitoring
data, zeroing of the gas analyser shall be undertaken
at the start of each day¡¦s monitoring.
As part of the QA/QC, calibration of the gas analyser
shall be conducted at least once every two weeks according to the specification
of the manufacturer¡¦s operation manual.
8.2.1
In the Reporting Period, landfill gas
monitoring was conducted at the construction of Retaining Wall B and Retaining
Wall F and the locations are illustrated in Appendix E. A BIOGAS 5000 gas analyser was used for the landfill gas monitoring.
8.2.2
There were total 75 workings days monitoring were carried by the Safety Officer or
an approved and qualified persons in this reporting period. Table
8-1 is summarized landfill gas measurement results. Moreover, graphical plot are attached in
Appendix G.
Table 8-1 Summary
of Landfill Gas Measurement Results in Reporting Period
Landfill Gas Parameter |
Action
Level |
Limit
Level |
Detectable at Retaining Wall B |
Detectable at Retaining Wall F |
||
Min |
Max |
Min |
Max |
|||
Methane |
>10% LEL (>0.5%
v/v) |
>20% LEL (>1% v/v) |
0% |
0.2% |
0% |
0.2% |
Oxygen |
<19% |
<18% |
21.0% |
21.1% |
21.0% |
21.1% |
Carbon Dioxide |
>0.5% |
>1.5% |
0% |
0.2% |
0% |
0.2% |
8.2.3
The measurement results shown that slightly methane
concentration was detected and all oxygen concentration were
over 21.0% and Carbon Dioxide was between 0 and 0.2 %. No corrective action was required
accordingly.
9.1.1
Waste management was carried out by an on-site
Environmental Officer or an Environmental Supervisor from time to time.
9.2.1
All types of waste arising from the
construction work are classified into the following:
l Construction
& Demolition (C&D) Material;
l Chemical
Waste;
l General
Refuse; and
l Excavated
Soil.
9.2.2
Whenever possible, materials were reused
on-site as far as practicable. The
quantities of waste for disposal in the Reporting Period are summarized in Tables
9-1 and 9-2 and the Waste Flow Table is presented in Appendix H.
Table 9-1 Summary
of Quantities of Inert C&D Materials
Type of Waste |
Quantity |
Disposal
Location |
||
Aug 15 |
Sep 15 |
Oct 15 |
||
Reused in this
Project (Inert) (in '000 m3) |
21.142 |
12.275 |
12.486 |
- |
Reused in other Projects
(Inert) (in '000 m3) |
0 |
2.185 |
9.752 |
• Lam Tei
Quarry • Eco Park
K.wah Recycle Facilities • Lung Kwu
Tan Tailor Recycled Aggregates • Laintang BCP • TM-CLKL
C2 |
Disposal as Public
Fill (Inert) (in '000 m3) |
6.293 |
6.723 |
3.333 |
Tuen Mum Area 38 |
Table 9-2 Summary
of Quantities of C&D Wastes
Type of Waste |
Quantity |
Disposal Location |
||
Aug 15 |
Sep 15 |
Oct 15 |
||
Recycled Metal (in '000kg) |
0 |
0 |
0 |
- |
Recycled
Paper / Cardboard Packing (in '000kg) |
0 |
0 |
0 |
- |
Recycled
Plastic (in '000kg) |
0 |
0 |
0 |
- |
Chemical
Wastes (in '000kg) |
0 |
0 |
0 |
- |
General
Refuses (in '000m3) |
0.08 |
0.013 |
0.038 |
WENT |
9.2.3
To control the site performance on waste management, the Contractor
shall ensure that all solid and liquid waste management works are fully in
compliance with the relevant license/permit requirements, such as the effluent
discharge license and the chemical waste producer registration. The Contractor is also reminded to
implement the recommended environmental mitigation measures according to the Environmental Monitoring and Audit
Manual.
10.1.1
According to the approved EM&A Manual, the
environmental site inspection shall be formulation by ET Leader. Weekly environmental site inspections
should carry out to confirm the environmental performance.
10.1.2
During
the Reporting Period, 13
events of the joint site inspections were undertaken to evaluate the site
environmental performance. The
summaries of the findings during site inspection are presented in Tables
10-1 and 10-2.
Table
10-1 Site Observations for the Contract for
the Reporting Period
Date |
Findings
/ Deficiencies |
Follow-Up
Status |
4 August 2015 |
Housekeeping should be improved
at the works area near fire station. Also, sand bags and de-silting
facilities should be provided to divert and treat the surface runoff before
discharge from site. |
Housekeeping at the concerned works
area was improved. |
It was reminded that all
discharge points should be maintained properly to prevent any discharge of
turbid water. |
Not required for reminder. |
|
It was reminded that water spraying
should be increased for dusty construction activities to reduce dust impact. |
Not required for reminder. |
|
11 August 2015 |
Sand bags should be provided to
prevent overflow of cumulated stagnant water into the storm water drainage. |
The cumulated stagnant water was cleared. |
Free standing chemical containers
without drip tray was observed. (Central Devider) |
Free standing chemical containers
without drip tray were removed. |
|
It was reminded that earth bund should
be provided to divert the surface runoff to the de-silting facilities. Also,
the de-silting facilities should be installed ASAP. (Works area near fire
station) |
Not required for reminder. |
|
18 August 2015 |
Discharge of turbid water at the discharge
point near site office was observed. The Contractor should improve the
de-silting facilities and ensure the discharge water is complied with
discharge license requirement. |
No turbidity water discharged
from the de-silting facilities was observed. |
Sediment cumulated inside the storm water drainage near gate 2 was
observed, the Contractor was reminded to clear the sediment to aviod flushing
from site during rainstorm. |
Not required for reminder. |
|
25 August 2015 |
Free standing chemical containers
without drip tray was observed. (Retaining Wall B) |
Drip tray was provided for the
oil drums. |
It was reminded that dust
mitigation measures should be provided for the temporary stock pile area to
reduce dust impact. |
Not required for reminder. |
|
It was reminded that Sediment cumulated inside the discharge point
should be cleaned more frequency. |
Not required for reminder. |
|
1 September 2015 |
Earth bund or sand bags should be
provided for the manhole to prevent loose material discharge into the storm
water system. Also, the Contractor was reminded to replace broken sand bags
to maintain the earth bund functional. (Central Devider) |
Sediment cumulated inside the
gully was cleared and geotextile was provided to prevent loose material
discharged into the manhole. |
8 September 2015 |
Sediment cumulated inside the
discharge point was observed. The contractor should maintain the discharge
system properly to prevent discharge of muddy water. |
Earth bund was provided for the
casgate to prevent turbid water discharge. |
Chemical container without drip
tray was observed. (Retaining Wall B) |
Free standing chemical without
drip tray was removed. |
|
Oil layer was observed cumulated inside
the wheel washing bay. The contractor should clean up immediately to prevent
contamination. |
Oil layer inside the wheel
washing bay was cleared. |
|
The contractor is recommended to undertake
daily checking at the discharge point to make sure all the discharge water
comply with the discharge license requirement. |
Not required for reminder. |
|
15 September 2015 |
Oil drum without drip tray was
observed. |
Oil drum without drip tray was
removed. |
Discharge system at stream B
should be improved. Discharge water after treatment should not contaminated
by exposed soil. |
Discharge water at Stream B was
visual clear, sand bags and geotextile was installed at the downstream. |
|
It was reminded that water
spraying for the haul road and excavating / breaking activities to minimize
dust generation. |
Not required for reminder. |
|
22 September 2015 |
Drainage system at stream B
should be improved. Discharge water after treatment should not contaminated
by exposed soil. Also, sediment accumulated inside the stream should cleaned
frequently. |
Discharge water at Stream B was
visual clear, sand bags and geotextile was installed at the downstream. |
29 September 2015 |
Oil drum without drip tray was
observed near east portal. |
Oil drum without drip tray at
east portal was removed. |
It was reminded that tree
protection zone should be installed and improved for retaining trees area
near east portal. |
Not required for reminder. |
|
6 October 2015 |
Bypass stream water contaminated
by exposed surface was observed. Tarpaulin sheets should be provided to
prevent the storm water contact with the exposed soil. (East Portal) |
Tarpaulin was provided to prevent
storm water contaminated by explosed surface. |
Stagnant water cumulated inside
the drip tray was observed after the rainstorm. The contractor should clean
the water to maintain the drip tray is functional. (Near Retaining Wall B) |
Stagnant water cumulated inside
the drip tray was cleared |
|
Turbid water discharged from
Stream A & B was observed. All discharge from site should comply with the
discharge license requirement. (Stream A and Stream B) |
Sand bags were provided to prevent
muddy water discharged into the outlet before de-silting. (Stream A) Bypass pipe and tarpaulin sheet
was installed and no turbid water
discharge was observed. (Stream
B) |
|
14 October 2015 |
Stagnant water cumulated inside the
drip tray near contractor¡¦s office was observed. |
Stagnant water cumulated inside
the drip tray was removed. |
As a reminder, water spraying
should be applied for the haul road during the dry season and under the
contract requirement water spraying should at least 12 times per day. |
Not required for reminder. |
|
20 October 2015 |
Stagnant water cumulated on site
was observed near Retaining Wall B, the contractor should remove the stagnant
water to prevent mosquito breeding. |
Stagnant water cumulated near
retaining wall B was removed. |
The Contractor was reminded that
proper label should be provided for the chemical containers storage on site. |
Not required for reminder. |
|
27 October 2015 |
No adverse environmental issue
was observed. |
NA |
Table
10-2 Summary
of Reminders/Observations of Site Inspection
Reporting Period |
Date of site inspection |
Nos. of findings / reminders |
|
August 2015 |
4th, 11th,
18th and 25th August 2015 |
11 |
Completed |
September 2015 |
1st, 8th, 15th,
22nd and 29th September 2015 |
11 |
Completed |
October 2015 |
6th, 14th,
20th and 27th October 2015 |
7 |
Completed |
10.1.3
In the
Reporting Period, no non-compliance was recorded,
however, 29 observations/ reminders were
recorded during the site inspections.
Minor deficiencies found
in the weekly site inspection were in general rectified within the specified
deadlines. The environmental
performance of the Project was therefore considered satisfactory.
Inspection Checklist for Vulnerable to Contaminated Water Discharge
10.1.4
Follow to the complain about
discharge of milky water to Bufferfuly Beach on 28 July 2015. The Contractor
proposed to carry out bi-weekly inspections (weekly Safety and Environmental
inspections plus weekly inspections by inspectorate team) for site areas that
are vulnerable to incidental contaminated water discharge, such as wastewater
treatment facilities and associated discharge points, drainage system inlets
and outfalls. The inpsection for
vulnerable to contaminated water discharge was conducted by the Contractor on
28 August 2015. As requested by the
EPD, the associated inspection checklist were presented in the Monthly EM&A
Report ¡V August 2015.
10.1.5
Following to the complain about
discharge of milky water to Bufferfuly Beach on 2 September 2015. The
Contractor proposed to carry out daily inspection of wastewater treatment
facilities, concerned discharge points, drainage inlets and outlets during
typhoon or wet season. The
inpsection for vulnerable to contaminated water discharge was conducted by the
Contractor from 9 September 2015.
As requested by the EPD, the associated inspection checklist were
presented in the Monthly EM&A Report ¡V September 2015 and October 2015.
10.1.6
In addition, specific inspections would
also be conducted before and after adverse weather to ensure necessary remedial
works would be carried out timely. Should incidental contaminated water
discharge be found at the inlet of the associated drainage system, a specific
inspection of the relevant drainage pipes would be conducted for traces of
deposit, and follow up actions would be taken when necessary.
11.1.1 For the
Contract, no summons and prosecution were received in the Reporting
Period. Moreover, no exceedances of
the environmental performance limit (Action and Limit Level) were
recorded. However, two (2) environmental complaints were
received on 3 August and 2 September 2015 regarding the soil/ muddy water
caused by frequent dump trucks in Lung Mun Road and River Trade Terminal and
milky water discharged from the drainage outlet near the Butterfly Beach, Tuen
Mun.
11.1.2 Follow up actions have been undertaking
by the Contractor to resolve the deficiencies. Investigation for the
complaints has been conducted by the ET and the corresponding investigation
reports for the complaint have been submitted to relevant parties and presented
in the Monthly EM&A Report (August
2015 and September 2015). The statistical summary table of
environmental exceedance, complaint, summons and prosecution is presented in Tables
11-1, 11-2, 11-3 and 11-4.
Table 11-1 Statistical
Summary of Environmental Exceedance
Reporting Period |
Environmental Aspect / Parameter |
Environmental Performance |
Event
Exceedance |
||
Reporting
Period |
Previous
Periods |
Cumulative |
|||
1
August 2015 ¡V 31 October 2015 |
Air Quality - 1-hr TSP |
Action Level |
0 |
4 |
4 |
Limit Level |
0 |
0 |
0 |
||
Air Quality - 24-hr
TSP |
Action Level |
0 |
0 |
0 |
|
Limit Level |
0 |
0 |
0 |
Table 11-2 Statistical
Summary of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
23 October 2014 ¡V 31 July 2015 |
1 |
1 |
Water |
1
August 2015 ¡V 31 October 2015 |
2 |
3 |
Water (2) Dust (1) |
Table
11-3 Statistical
Summary of Environmental Summons
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
23 October 2014 ¡V 31 July 2015 |
0 |
0 |
NA |
1
August 2015 ¡V 31 October 2015 |
0 |
0 |
NA |
Table
11-4 Statistical
Summary of Environmental Prosecution
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
23 October 2014 ¡V 31 July 2015 |
0 |
0 |
NA |
1
August 2015 ¡V 31 October 2015 |
0 |
0 |
NA |
12.1.1
The environmental mitigation measures that recommended
in the Environmental Mitigation and Enhancement Measures Implementation
Schedule (EMIS) for in the Project EM&A Manual covered the issues of air quality, cultural heritage, ecology, landfill gas hazard, landscape & visual, noise, water and waste. The updated EMIS for the Contract is
shown in Appendix I.
12.1.2
The Contractor shall implement the required
environmental mitigation measures according to the EM&A Manual as subject to
the site condition. The environmental mitigation measures implemented by the
Contract in this Reporting Period are summarized in Table 12-1 and Appendix I.
Table 12-1 Environmental
Mitigation Measures
Issues |
Environmental Mitigation Measures |
Air Quality |
¡P Maintain damp / wet surface
on access road ¡P Keep slow speed in the sites ¡P All vehicles must use wheel
washing facility before off site ¡P Sprayed water during rock
breaking works ¡P During transportation by truck, materials loaded lower than
the side and tail boards, and covered before transport ¡P Compacted all soil stockpiles ¡P Part of the exposed slopes covered geotextile net |
Cultural Heritage |
¡P Set a buffer zone between the working area
and the Grave ¡P All construction materials and equipment store far from
the Grave ¡P Inspection the Grave to ensure provision mitigation
measures effective |
Ecology |
¡P
Wire fencing provided
for temporary protect Pitcher Plants ¡P
Undertake weekly
inspection of Pitcher Plants |
Landfill Gas Hazard |
¡P
Landfill Gas
measurement undertake during trench excavation |
Water Quality |
¡P Temporary drainage system
provide for surface runoff prevent discharge to public area ¡P Wastewater to be treated by
sedimentation tank before discharge. |
Noise |
¡P Restrain operation time of
plants from 07:00 to 19:00 on any working day except for Public Holiday and
Sunday. ¡P Keep good maintenance of
plants ¡P The noisy plants or works
provide mobile noise barriers ¡P Shut down the plants when
not in used |
Waste and Chemical
Management |
¡P On-site sorting prior to
disposal ¡P Follow requirements and
procedures of the ¡§Trip-ticket System¡¨ ¡P
Predict required quantity of concrete accurately ¡P Collect the unused fresh concrete at designated
locations in the sites for subsequent disposal |
General |
¡P The site was generally kept
tidy and clean. |
13.1.1 This is 4th Quarterly EM&A
report presenting the monitoring results and inspection findings for the
Reporting Period from 1 August 2015 to 31 October 2015.
13.1.2 No air
quality monitoring including 1-hour and 24-hour TSP exceedance was recorded in
the Reporting Period. Although air quality monitoring result complied with the performance
criteria, the Contractor was reminded to fully implement the dust control
measures.
13.1.3 In this
Reporting Period, no noise complaint was
received by RE, the Contractor, ENPO or HyD. No Action Level exceedances were triggered and no NOE or the associated corrective actions were therefore issued.
13.1.4 Site
inspection for landscape and visual was conducted on weekly basis by the
Landscape Architect to ensure if the existing condition compliance with the
intended aims of the mitigation measures.
Most of the landscape works such as planting was not yet commenced.
13.1.5 Site
inspection was performed for the transplanted Pitcher Plants in the nursery
site and protected Zones 8 to 10.
The transplanted Pitcher Plant in nursery site was protected by the
scaffold structure which surrounded by chain link fencing and the protected
Pitcher Plants in Zones 8 to 10 were fenced off by chain link fencing. The condition of the transplanted
pitcher plant was in fair to poor condition. No construction activities were found to
conduct nearby the nursery site and protection zones.
13.1.6 Trial transplantation of pitcher plant from the nursery site to final
receptor site was carried out on 15 April 2015 and a total of 5% of pitcher
plant was transplanted.
Transplantation of remaining 95% was carried out in 9th and 10th
September 2015.
13.1.7 Landfill
gas monitoring was conducted at the construction of Retaining Wall B and
Retaining Wall F by the Safety Officer.
The monitoring results shown no exceedances were triggered.
13.1.8 In the
Reporting Period, two (2) environmental complaints were received on 3 August
and 2 September 2015 regarding the soil/ muddy water caused by frequent dump
trucks in Lung Mun Road and River Trade Terminal and milky
water discharged from the drainage outlet near the Butterfly Beach, Tuen
Mun. Investigation for the
complaints has been conducted by the ET and the corresponding investigation
reports for the complaint have been submitted to relevant parties.
13.1.9
No notifications of summons, or
successful prosecution were received by the Contractor during the Reporting
Period.
13.1.10During the Reporting Period, 13 events of the joint site inspections were
undertaken to evaluate the site environmental performance. No adverse environmental impacts were observed during the weekly site
inspection and environmental audit of the Reporting Period, indicating the
implemented mitigation measures for air quality, construction noise and water
quality were effective. Minor
deficiencies found in the weekly site inspection were in general rectified
within the specified deadlines. The
environmental performance of the Project was therefore considered satisfactory.
13.1.11For cultural
heritage, the buffer zone between the working area and the Grave was observed
and no construction material or equipment was stored nearby.
13.1.12No documented complaint,
notification of summons or successful prosecution is received by the Contract.
13.2.1 During dry
season, air quality mitigation measures such as watering of site area for 12
times per day and covering of exposed slopes should be fully implemented to
reduce construction dust impact as recommended in the EMIS.
13.2.2 Moreover,
muddy water or other water pollutants from site surface runoff into the public
areas will be key environment issue.
Special attention should be paid on the water quality mitigation
measures to prevent surface runoff flow to public area.
13.2.3 Moreover,
good practice for daily housekeeping is reminded. In addition, clean-up of the
waste skips and wastewater treatment system should be increased to ensure these
facilities functional and effective.
13.2.4 Stagnant
water should be removed as soon as possible after rain to prevent mosquito
breeding on site.
.