Page   

TABLE OF CONTENTS

 

Executive SUMMARY

 

1

INTRODUCTION

 

 

1

1.1

Basic Project Information

1

1.2

Project Organization

2

1.3

Construction Programme

2

1.4

 

 

Construction Works Undertaken During the Reporting Period

 

 

 

2

 

 

 

 

 

 

2

 

2.0

AIR QUALITY MONITORING

 

 

 

3

2.1

Monitoring Locations

3

2.2

Monitoring Requirements

3

2.3

Monitoring Results

 

4

 

 

 

 

 

 

3

NOISE MONITORING

5

3.1

Monitoring Locations

5

3.2

Monitoring Requirements

5

3.3

Monitoring Results

 

 

5

 

 

 

 

 

 

4

ENVIRONMENTAL SITE INSPECTION AND AUDIT

6

4.1

4.2

 

Site Inspection

Advice on the Solid and Liquid Waste Management Status

 

 

 

 

 

6

4.3

Environmental Licenses and Permits

6

4.4

Implementation Status of Environmental Mitigation Measures

7

4.5

Summary of Exceedance of the Environmental Quality Performance Limit

7

4.6

Summary of Complaints, Notification of Summons and Successful Prosecution

7

 

 

 

 

5

FUTURE KEY ISSUES

8

5.1

Construction Programme for the Coming Months

8

5.2

Environmental Site Inspection Schedule for the Coming Month

8

 

 

 

6

CONCLUSION

8

 

Conclusions

8

 

 

Figures

Figure 2

Air Quality and Noise Monitoring Stations for HKBCF

 

 

APPENDICES

Appendix A

Location of Works Areas

Appendix B

Project Organization for Environmental Works

Appendix C

Construction Programme

Appendix D

Event and Action Plan

Appendix E

Waste Flow Table

Appendix F

Environmental Licenses and Permits

Appendix G

Implementation Schedule for Environmental Mitigation Measures (EMIS)

Appendix H

Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions

Appendix I

Environmental Site Inspection Schedule

Appendix J

Complaint Investigation Report

 

 

 


 

Executive SUMMARY

 

This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/02 Hong Kong¡VZhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western Portion) (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨) and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the Contractor.

 

The Contract is part of Hong Kong ¡V Zhuhai ¡V Macao Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/H for HKBCF was issued on 19 January 2015. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract was started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014.

 

ETS-Testconsult Limited has been appointed by the Contractor to implement the Environmental Monitoring & Audit (EM&A) programme for the Contract in accordance with the Updated EM&A Manual for HKBCF (Version 1.0) and provide environmental team services to the Contract.

 

This is the Sixth Monthly Environmental Monitoring and Audit (EM&A) Report for the Contract which summaries findings of the EM&A works conducted during the reporting period from 01 May 2015 to 31 May 2015.

 

Site Activities

 

As informed by the Contractor, site activities were carried out in this reporting month:

 

¡±   Pre-Drilling Work in Portion C&F;

¡±   Trench Excavation for watermain and Cable & Duct work in Portion I;

¡±   UU Detection Works in Portion I; and

¡±   Pile Cap preparation in Portion H.

 

 

Environmental Monitoring and Audit Progress

 

The monthly EM&A programme was undertaken in accordance with the Updated EM&A Manual for HKBCF (Version 1.0). It should be noted that the air quality and noise monitoring works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7A and noise monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring stations are no longer covered under Contract No. HY/2010/02 and HY/2011/03. However,this is subject to ENPO¡¦s final decision on which ET should carry out the monitoring works at these stations.

 

The date of site inspection during the reporting period are listed below:

 

Environmental Site Inspection                07,15,21 and 28 May 2015

 

 

Breaches of Action and Limit Levels

 

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS6 by the Environmental Team of Contract No. HY/2011/03 during the reporting period.

 

There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7A by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

Complaint Log

 

There was a complaint received by EPD from a public via EPD¡¦s hotline on 21 May 2015 and was forwarded by EPD to Highways Department and then the ENPO on 22 May 2015.Then the ENPO forwarded the complaint by email to the R.E. (AECOM), the Contractor (China Harbour) and the ET (ETS-Testconsult Ltd.) of Contract No. HY/2013/02 at 17:39 on 22 May 2015. The complainant complained that noise generation and dark smoke emission produced from plants undertaking at night-time works at HKBCF Project.

The above mentioned complaint follow-up inspection was performed by the ET of Contract No. HY/2013/02 on 23 May 2015.The complaint investigation report (Log No. 002) was issued by the ET of Contract No. HY/2013/02 and verified by the IEC/ENPO on 2 June 2015.

According to the investigation, the construction works of the Contractor of Contract No. HY/2013/02 during 18 May 2015 to 21 May 2015 was carried out from 08:00 to 18:00 and no any works and PME operation were undertaken at night-time. The complaint was found non-related to Contract No. HY/2013/02. The complaint investigation report (Log No. 002) was provided in Appendix J.

 

 

Notifications of Summons and Successful Prosecutions

 

There were no notifications of summons or prosecutions received during the reporting period.

 

Reporting Change

 

There was no reporting change in the reporting period.

 

Future Key Issues

 

The future key issues to be undertaken in the upcoming month are as follows:

 

¡±   Pre-Drilling Work in Portion C & F;

¡±   Bored Piles Works in Portion A1;

¡±   Trench Excavation for watermain and Cable & Duct work in Portion I;

¡±   UU Detection Works in Portion I; and

¡±   Pile Cap preparation in Portion H.

 


 

1         INTRODUCTION

 

1.1      Basic Project Information

 

1.1.1  This Monthly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2013/02 Hong Kong¡VZhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V Infrastructure Works Stage I (Western Portion) (hereafter referred to as ¡§the Contract¡¨) for the Highways Department of Hong Kong Special Administrative Region (HKSAR). The Contract was awarded to China Harbour Engineering Co., Ltd. (hereafter referred to as ¡§the Contractor¡¨) and ETS-Testconsult Limited was appointed as the Environmental Team (ET) by the Contractor.

 

1.1.2  The Contract is part of Hong Kong ¡V Zhuhai ¡V Macao Bridge HKBCF which is a ¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499) and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009) was prepared for the Project. The current Environmental Permit (EP) No. EP-353/2009/H for HKBCF was issued on 19 January 2015. These documents are available through the EIA Ordinance Register. Site preparation works of the Contract started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014. The works area of the Contract is shown in Appendix A.

 

1.1.3  The proposed works under this Contract comprise the following:

 

¡±   Construction of the viaducts and roads at the western portion of Hong Kong Boundary Crossing Facilities (HKBCF) mainly for connection with the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB), Hong Kong Link Road (HKLR), Hong Kong International Airport (HKIA) and the Tuen Mun-Chek Lap Kok Link (TM-CLKL);

 

¡±   Construction of the road modification at the SkyCity Interchange at Airport Island;

 

¡±   Construction of associated street lighting, street furniture, road marking, road signage, drainage, sewerage, fresh water and flushing water supply, irrigation, landscape, electrical and mechanical (E&M), utilities and services works;

 

¡±   Provisioning of civil engineering works and power supply installation for the Traffic Control and Surveillance System TCSS);

 

¡±   Other works in accordance with the Contract.

 

1.1.4 This is the Sixth Monthly Environmental Monitoring and Audit (EM&A) Report for the Contract which summaries the audit findings of the EM&A programme during the reporting period from 01 May 2015 to 31 May 2015.

 


 

1.2       Project Organization

 

1.2.1   The project organization structure and lines of communication with respect to the on-site environmental management structure is shown in Appendix B. The key personnel contact names and numbers are summarized in Table 1.1.

 

Table 1.1           Contact Information of Key Personnel

Party

Position

Name of Key Staff

Tel. No.

Fax No.

Engineer or Engineer¡¦s Representative   (AECOM Asia Co. Ltd.)

Resident Engineer

Mr. Fred Yeung

63308293

31525116

Environmental Project Office / Independent Environmental Checker (Environ Hong Kong Limited) 

Environmental Project Office Leader

Mr. Y. H. Hui

34652888

34652899

Independent Environmental Checker

Mr. Raymond Dai

34652888

34652899

Environmental Site Supervisor

Mr. Ray Yan

51818165

34652899

Contractor (China Harbour Engineering Co., Ltd.)

Environmental Officer

Mr. K. F. Wong

93724383

39150300

Environmental Supervisor

Ms. Joy Chan

54005086

39150300

Environmental Supervisor

Ms. Selena Yang

55122662

39150300

Environmental Team (ETS-Testconsult Ltd.)

Environmental Team Leader

Mr C. L. Lau

2946 7791

2695 3944

 

 

 

1.3       Construction Programme

 

1.3.1    A copy of the Contractor¡¦s construction programme is provided in Appendix C.

 

 

 

1.4       Construction Works Undertaken During the Reporting Period

 

1.4.1     

A summary of the construction activities undertaken during this reporting period is shown below:

 

¡±     Pre-Drilling Work in Portion C & F;

¡±     Trench Excavation for watermain and Cable & Duct work in Portion I;

¡±     UU Detection Works in Portion I; and

¡±     Pile Cap preparation in Portion H.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2          AIR QUALITY MONITORING

 

2.1        Monitoring Locations

 

2.1.1    The air quality monitoring works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of the Contract or another ET of the HZMB project is required to conduct impact air quality monitoring at AMS6 and AMS7A as part of EM&A programme if these air quality monitoring stations are no longer covered under Contract No. HY/2010/02 and HY/2011/03. Figure 2 shows the locations of air monitoring stations.

 

Table 2.1       Air Quality Monitoring Locations

 

Identification No.

Location Description

AMS6(1)

Dragonair / CNAC (Group) Buidling

AMS7A(1)

Chu Kong Air-Sea Union Transportation Co. Ltd.

                     

Remarks:

(1)      The ET of this Contract should conduct impact air quality monitoring at the AMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

 

          

2.2        Monitoring Requirements

 

2.2.1       The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract Nos. HY/2010/02 and HY/2011/03.

 

2.2.2      The Action and Limit Levels for 1-hr TSP and 24-hr TSP are provided in Table 2.2 and Table 2.3 respectively.

 

 Table 2.2        Action and Limit Levels for 1-hour TSP

 

Monitoring Station.

Action Level,mg/m3

    Limit Level,mg/m3

 AMS6 ¡V Dragnair / SNAC (Group) Building (HKIA)

              360

              500

 AMS7A ¡VChu Kong Air-Sea Union Transportation Co. Ltd.

            370

            500

 

 

 

  Table 2.3        Action and Limit Levels for 24-hour TSP

 

Monitoring Station.

Action Level,mg/m3

    Limit Level,mg/m3

 AMS6 ¡V Dragnair / SNAC (Group) Building (HKIA)

              173

              260

 AMS7A ¡VChu Kong Air-Sea Union Transportation Co. Ltd.

            183

            260

 

 

2.2.3       The event and action plan is provided in Appendix D.

 

2.2.4       If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

 

 

 

 

2.3       Monitoring Results

 

2.3.1    The monitoring results for AMS6 and AMS7A are reported in the monthly EM&A Reports prepared for Contract Nos. HY/2011/03 and HY/2010/02 respectively.

 

2.3.2    There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS6 by the Environmental Team of Contract No. HY/2011/03 during the reporting period.

 

2.3.3    There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7A by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3         NOISE MONITORING

 

3.1       Monitoring Locations

 

3.1.1    The noise monitoring works for the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge HKBCF ¡V Reclamation Works. The ET of the Contract or another ET of the HZMB project is required to conduct noise monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring stations are no longer covered under Contract No. HY/2010/02. Figure 2 shows the locations of noise monitoring stations.

 

 Table 3.1       Construction Noise Monitoring Locations

 

Identification No.

Location Description

NMS2(1)

Seaview Crescent

NMS3B(1) (2)

Site Boundary of Site Office Area at Works Area WA2

 

Remarks:

(1)    The ET of this Contract should conduct impact noise monitoring at the NMS listed in the table as part of EM&A programme according to latest notification from ENPO when the monitoring station(s) is/are no longer covered by another ET of the HZMB project.

(2)    The Action and Limit Levels for schools will be applied for this alternative monitoring location.

 

3.2        Monitoring Requirements

 

3.2.1   The monitoring requirements, monitoring equipment, monitoring parameters, frequency and duration, monitoring methodology, monitoring schedule, meteorological information are detailed in the monthly EM&A Reports prepared for Contract No. HY/2010/02.

 

3.2.2    The Action and Limit Levels for construction noise are provided in Table 3.2

 

Table 3.2        Action and Limit Levels for Construction Noise

 

Parameter

Action Level

Limit Level

07:00 ¡V 19:00 hours on normal weekdays

When one documented complaint is received

75 dB(A)*

         

 

                  Notes:

 If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.

* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination period.

 

 

3.2.3    The event and action plan is provided in Appendix D.

 

3.2.4    If exceedance(s) at these stations is/are recorded by the ET of the Contract or referred by the other ET under the HZMB project to the Contract, the ET of the Contract will carry out an investigation and findings will be reported in the monthly EM&A Report.

 

3.3        Monitoring Results

 

3.3.1    The monitoring results for NMS2 and NMS3B are reported in the monthly EM&A Reports prepared for Contract No. HY/2010/02. There was no exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

 

 


 

4          ENVIRONMENTAL SITE INSPECTION AND AUDIT

 

4.1        Site Inspection

 

4.1.1     Site Inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control mitigation measures for the project. During the reporting period,site inspections were carried out on 07,15,21and 28 May 2015.

 

4.1.2     Particular observations during the site inspections are described below:

 

07 May 2015

(a)      No observation was made.

 

15 May  2015

(a)        One excavator did not switch off while it was observed idle at Potion A1. The label was provided for reminding the driver to switch off the equipment while it was idle. This observation was closed on 21 May 2015.

 

21  May  2015

(a)      No observation was made.

 

 

28 May  2015

(a)      Oil stain was observed in the drip tray of the drill rig at Portion C. The Contractor was reminded to clean the oil stain. Follow-up actions for the outstanding observation will be inspected during the next site inspection.

(b)      Water spaying was observed insufficient for the breaking works at Portion I. The Contractor was reminded to enhance the frequency of watering. Follow-up actions for the outstanding observation will be inspected during the next site inspection.

 

 

 

 

4.2        Advice on the Solid and Liquid Waste Management Status

 

4.2.1     The Contractor registered as a chemical waste producer for the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.

 

4.2.2   No generation of excavated sediment for treatment during this reporting period. Excavated marine sediment will be treated using cement solidification/stabilization (Cement S/S) techniques and will be reused onsite for either backfilling or landscaping (e.g. berm material).

 

4.2.3     The monthly summary of waste flow table is detailed in Appendix E.

 

4.2.4     The Contractor was reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packing, Labelling and Storage of Chemical Waste.

 

4.3       Environmental Licenses and Permits

 

4.3.1     The valid environmental licenses and permits during the reporting period are summarized in Appendix F.

 

 

 

 

 

 

 

 

4.4        Implementation Status of Environmental Mitigation Measures

 

4.4.1     In response to the site audit findings, the Contractor carried out corrective actions.

 

4.4.2     The Contractor waters 8 times per day on all exposed soil within the project site and associated works areas when construction activities are being undertaken.

 

4.4.3     The Contractor was reminded to provide well-maintained plant operated on-site and plant served regularly;

 

4.4.4     The Contractor was reminded to switch off vehicles and equipment while not in use;

 

4.4.5     The Contractor was reminded to schedule the construction works to minimize noise nuisance etc.

 

4.4.6    A summary of the implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix G. Most of the necessary mitigation measures were implemented properly.

 

 

 

4.5       Summary of Exceedance of the Environmental Quality Performance Limit

 

4.5.1  There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS6 by the Environmental Team of Contract No. HY/2011/03 during the reporting period.

 

4.5.2   There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7A by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

4.5.3  There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

 

4.6      Summary of Complaints, Notification of Summons and Successful Prosecution

 

4.6.1    There was a complaint received by EPD from a public via EPD¡¦s hotline on 21 May 2015 and was forwarded by EPD to Highways Department and then the ENPO on 22 May 2015.Then the ENPO forwarded the complaint by email to the R.E. (AECOM), the Contractor (China Harbour) and the ET (ETS-Testconsult Ltd.) of Contract No. HY/2013/02 at 17:39 on 22 May 2015. The complainant complained that noise generation and dark smoke emission produced from plants undertaking at night-time works at HKBCF Project.

The above mentioned complaint follow-up inspection was performed by the ET of Contract No. HY/2013/02 on 23 May 2015.The complaint investigation report (Log No. 002) was issued by the ET of Contract No. HY/2013/02 and verified by the IEC/ENPO on 2 June 2015.

According to the investigation, the construction works of the Contractor of Contract No. HY/2013/02 during 18 May 2015 to 21 May 2015 was carried out from 08:00 to 18:00 and no any works and PME operation were undertaken at night-time. The complaint was found non-related to Contract No. HY/2013/02. Although this complaint was non-related to Contract No. HY/2013/02, the Contractor of Contract No. HY/2013/02 was reminded to provide appropriate noise and smoke mitigation measures, such as switched off vehicles and equipment while not in use, scheduled the construction works to minimize noise nuisance and well-maintained plant operated on-site to minimize noise nuisance and dark smoke emission produced etc The complaint investigation report (Log No. 002) was provided in Appendix J.

 

4.6.2     There were no notifications of summons or prosecutions received during the reporting period.

 

4.6.3   Statistics on environmental complaints, notifications of summons and successful prosecutions are summarized in Appendix H.

 

 

 

 

5         FUTURE KEY ISSUES

 

5.1      Construction Programme for the Coming Months

 

5.1.1   As informed by the Contractor, the major construction activities for June 2015 are summarized in Table 5.1.

 

Table 5.1       Construction Activities for June 2015

 

Site Area

 Description of Activities

  Portion C & F

Pre-Drilling Work

  Portion A1

Bored Piles Works

Portion I

Trench Excavation for watermain and Cable & Duct work

  Portion I

UU Detection Works

Portion H.

Pile Cap preparation


 

 

5.2       Environmental Site Inspection Schedule for the Coming Month

 

5.2.1    The tentative schedule for weekly site inspections for June 2015 is provided in Appendix I.

 

 

 

6        CONCLUSION.

 

6.1     Conclusions

 

6.1.1   The site preparation work of the Contract was started on 25 July 2014 and the construction works of the Contract commenced on 24 November 2014.

 

6.1.2  There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS6 by the Environmental Team of Contract No. HY/2011/03 during the reporting period.

 

6.1.3  There was no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at station AMS7A by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

6.1.4  There was no Action and Limit Level exceedance for noise recorded at station NMS2 and station NMS3B by the Environmental Team of Contract No. HY/2010/02 during the reporting period.

 

6.1.5     There was a complaint was received by EPD from a public via EPD¡¦s hotline on 21 May 2015 and was to Highways Department and then the ENPO on 22 May 2015.Then the ENPO forwarded the complaint by email to the R.E. (AECOM), the Contractor (China Harbour) and the ET (ETS-Testconsult Ltd.) of Contract No. HY/2013/02 on 22 May 2015. After the investigation, the complaint was found non-related to Contract No. HY/2013/02.

 

6.1.6    There were no notifications of summons or prosecutions received during the reporting period.