CONTENTS

 

EXECUTIVE SUMMARY

                                                                                                                                                       

1.        INTRODUCTION

1.1     Background

1.2     Project Description

1.3     Project Organisation

1.4     Construction Programme

1.5     Construction Works undertaken during the Reporting Period

2.        AIR QUALITY MONITORING

2.1     Monitoring Locations

2.2     Monitoring Requirements

2.3     Monitoring Results

3.        NOISE MONTIORING

3.1     Monitoring Locations

3.2     Monitoring Requirements

3.3     Monitoring Results

4.        WATER QUALITY MONITORING

4.1     Monitoring Locations

4.2     Monitoring Requirements

4.3     Monitoring Results

5.        ECOLOGY MONITORING

5.1     Monitoring Locations

5.2     Monitoring Requirements

5.3     Monitoring Results

6.        DISPOSAL OF MARINE SEDIMENT EXTRACTED FROM BORED PILING WORKS

6.1   Background

6.2   Dumping Arrangements

6.3   Quantity Disposed

7.        ENVIRONMENTAL SITE INSPECTION AND AUDIT

7.1     Site Inspection

7.2     Advice on the Solid and Liquid Waste Management Status

7.3     Environmental Licenses and Permits

7.4     Implementation Status of Environmental Mitigation Measures

7.5     Summary of Exceedance of the Environmental Quality Performance Limit

7.6     Summary of Complaints, Notification of Summons and Successful Prosecution

8.        FUTURE KEY ISSUES

8.1     Construction Programme for the Coming Months

8.2     Environmental Site Inspection Schedule for the Coming Month

9.        CONCLUSIONS

 

APPENDICES

 

A      Location of Works Areas

B      Project Organization for Environmental Works

C      Construction Program

D      Event / Action Plan

E      Waste Flow Table

F      Environmental Licenses and Permits

G      Implementation Schedule for Environmental Mitigation Measures (EMIS)

H      Statistics on Environmental Complaints, Notification of Summons and Successful Prosecutions

I        Environmental Site Inspection Schedule

 

FIGURES

 

Figure 1                 Air Quality Monitoring Stations

Figure 2                 Noise Monitoring Stations

Figure 3                 Water Quality Monitoring Stations

Figure 4                 Ecological Monitoring Transect Line and Layout Map