1.1 Background
1.2 Scope
of Report
1.3 Organization
Structure
1.4 Summary
of Construction Works
1.5 Summary
of EM&A Programme Requirements
2.1 Air
Quality
2.2 Noise
Monitoring
2.3 Water
Quality Monitoring
2.4 Dolphin
Monitoring
2.5 EM&A
Site Inspection
2.6 Waste
Management Status
2.7 Environmental
Licenses and Permits
2.8 Implementation
Status of Environmental Mitigation Measures
2.9 Summary
of Exceedances of the Environmental Quality Performance Limit
2.10 Summary
of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction
Activities for the Coming Quarter
3.2 Key
Issues for the Coming Quarter
3.3 Monitoring
Schedule for the Coming Quarter
4 Conclusions
and recommendations
4.1 Conclusions
List of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule
of Environmental Mitigation Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
Impact Air Quality
Monitoring Results and Graphical Presentation |
Appendix G |
|
Appendix H |
Impact Water Quality
Monitoring Results and Graphical Presentation |
Appendix I |
|
Appendix J |
|
Appendix K |
|
Appendix L |
Under Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern
Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker
(IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications for variation of
environmental permit (VEP), EP-354/2009/B
and EP-354/2009/C were granted on 28 January 2014 and 10 December 2014
respectively.
The
construction phase of the Contract commenced on 31 October 2013 and will be
tentatively completed by 2018. The
impact monitoring of the EM&A programme,
including air quality, noise, water quality and marine ecological monitoring as
well as environmental site inspections, commenced on 31 October 2013.
This
is the fifth quarterly EM&A report presenting the EM&A works carried
out during the period from 1 December 2014 to 28 February 2015 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
December
2014
Marine-based Works
¡P
Construction of Pile caps at Viaducts B & E;
¡P
Marine piling platform installation for Viaducts A, B,
C, D & E;
¡P
Marine Piling at Viaducts B, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
January 2015
Marine-based
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation for Viaducts A, B,
C, D & E;
¡P
Marine Piling at Viaducts B, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
February 2015
Marine-based
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour
TSP monitoring 17
sessions at ASR9; 18 sessions at ASR8A
1-hour
TSP monitoring 17
sessions at ASR9; 18 sessions at ASR8A
Noise
monitoring 17
sessions
Water quality monitoring 37
sessions
Dolphin
monitoring 6
sessions
Joint
Environmental site inspection 13
sessions
Breaches of Action and Limit Levels for Air Quality
No exceedance of Action and Limit Levels was recorded
for air quality monitoring in the reporting period.
Breaches of Action and Limit Levels for Noise
No exceedance of Action and Limit Levels was recorded
for construction noise monitoring in the reporting period.
Breaches of Action and Limit Levels for Water Quality
No exceedance
of Action and Limit Levels was recorded for impact water quality monitoring in
the reporting period.
Impact Dolphin Monitoring
Whilst one (1) Limit Level
exceedance was observed for the quarterly dolphin monitoring data between December
2014 and February 2015, no unacceptable impact from the construction activities
of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins
was noticeable from general observations during the dolphin monitoring in this
reporting quarter. The exceedance is
considered unlikely due to the works of this Project upon further
investigation.
Daily
marine mammal exclusion zone monitoring was undertaken during the period of
marine works under this Contract. Passive
Acoustic Monitoring (PAM) was also implemented for the detection of marine
mammal when marine works were carried out outside the daylight hours under this
Contract. No sighting of the
Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in
the monitoring period during the exclusion zone monitoring.
Environmental Complaints, Non-compliance & Summons
No environmental
complaint, notification of summons and successful prosecution was received in
the reporting period.
Reporting Change
There was no
reporting change required in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be
undertaken in the coming quarter include the following:
March 2015
Marine
Works
¡P
Construction of Pile caps at Viaducts B, C, D & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B, C, D & E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
April 2015
Marine
Works
¡P
Construction and installation of pile caps;
¡P
Marine piling platform installation &
uninstallation;
¡P
Pier construction;
¡P
Installation of launching gantry;
¡P
Marine piling; and,
¡P
Installation of pier head segment.
Land-based
Works
¡P
Construction and installation of pile caps;
¡P
Pier construction;
¡P
Drainage works;
¡P
Land piling;
¡P
Pre-drilling works;
¡P
Installation of pier head segment;
¡P
Additional land GI, trial pits & lab testing;
¡P
Tree survey, felling and transplanting;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
May 2015
Marine
Works
¡P
Construction and installation of pile caps;
¡P
Marine piling platform installation &
uninstallation;
¡P
Pier construction;
¡P
Installation of launching gantry;
¡P
Marine piling and
¡P
Installation of pier head segment.
Land-based
Works
¡P
Construction and installation of pile caps;
¡P
Pier construction;
¡P
Drainage works;
¡P
Land piling;
¡P
Pre-drilling works;
¡P
Installation of pier head segment;
¡P
Additional land GI, trial pits & lab testing;
¡P
Tree survey, felling and transplanting;
¡P
Relocation of MTRC fence; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the coming quarterly period are mainly associated with air quality, noise, marine
water quality, marine ecology and waste management issue.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau
Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based
on the estimated increase in cross boundary traffic, developments in the
Northwest New Territories (NWNT), and possible developments in North Lantau,
including the Airport developments, the Lantau Logistics Park (LLP) and the
Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).
In order to cope with the anticipated traffic demand, two new road
sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM). The EIA Report was submitted under the
Environmental Impact Assessment Ordinance (EIAO) in August 2009. Subsequent to the approval of the EIA
Report (EIAO Register Number: AEIAR-146/2009),
an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director
of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December
2010. Further applications
for variation of environmental permit (VEP), EP-354/2009/B and EP-354/2009/C
were granted on 28 January 2014 and 10 December 2014 respectively.
Under
Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.
The
organization structure of the Contract is shown in Appendix A.
The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident
Engineer |
Kingman Chan |
3691 2950 |
3691 2899 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3547 2133 |
3465 2899 |
IEC |
Dr. F.C.
Tsang |
3547 2134 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy
Tam |
2271 3113 |
2723 5660 |
December
2014
Marine-based
Works
¡P
Construction of Pile caps at Viaducts B & E;
¡P
Marine piling platform installation for Viaducts A, B,
C, D & E;
¡P
Marine Piling at Viaducts B, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
January 2015
Marine-based
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation for Viaducts A, B,
C, D & E;
¡P
Marine Piling at Viaducts B, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
February 2015
Marine-based
Works
¡P
Construction of Pile caps at Viaducts B, C & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B
& C;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
The
locations of the construction activities are shown in Figure 1.3. The Environmental Sensitive Receivers in
the vicinity of the Project are shown in Figure 1.4.
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are
described in the following sections, which include:
¡P
Monitoring parameters;
¡P
Monitoring schedules for the reporting months and
forthcoming months;
¡P
Action and Limit levels for all environmental
parameters;
¡P
Event Action Plan;
¡P
Results and observations;
¡P
Environmental mitigation measures, as recommended in
the approved EIA Report; and
¡P
Environmental requirement in contract documents.
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are
summarized in the following sections.
The baseline
air quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡VMacao Bridge Hong
Kong Projects (HKZMB) during October 2011 has included the two monitoring
stations ASR9A and ASR9C for this project.
Thus, the baseline monitoring results and Action/ Limit Level presented
in HKZMB Baseline Monitoring Report ([1]) are
adopted for this Project.
Wind
data monitoring equipment was installed at Area 4 during the reporting period for
logging wind speed and wind direction.
The wind sensor was setup such that it was clear of obstructions or
turbulence caused by building. The
wind data monitoring equipment is recalibrated at least once every six months.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations and Monitoring Dates in this
Reporting Period
Monitoring Station (1) |
Monitoring Period |
Location |
Description |
Parameters & Frequency |
ASR8A |
2, 8, 11,
17, 23 and 29 December 2014; 2, 7, 13, 19, 22 and 28 January 2015; 3, 9, 12,
17, 23 and 26 February 2015 |
Area 4 |
On ground at
the Area 4 |
1-hour Total Suspended Particulates (1-hour
TSP, µg/m3), 3 times per day every 6 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour every 6 days |
ASR9 |
8, 11, 17,
23 and 29 December 2014; 2, 7, 13, 19, 22 and 28 January 2015; 3, 9, 12, 17,
23 and 26 February 2015 |
MTR Depot |
On the
ground nearby MTR Depot Entrance |
Note:
(1) Air Quality Monitoring Stations ASR9A and ASR9C at Siu
Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were
temporarily relocated to ASR9 and ASR8A respectively.
(2) Due
to the rejection of access to ASR8, the monitoring on 2 Dec 2014 at ASR8 was
cancelled.
Table
2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High
Volume Sampler (Model No. TE-5170) |
Wind Sensor |
Global Water (Wind
Speed Sensor: WE550; Wind Direction Sensor: WE570) |
Wind Anemometer for
calibration |
Lutron (Model No.
AM-4201) |
The Action and
Limit Levels of the air quality monitoring are provided in Appendix D. The Event and Action plan is presented
in Appendix J.
The schedules
for air quality monitoring in the reporting quarter are provided in Appendix E.
The monitoring
results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4,
respectively. Monitoring results
are presented graphically in Appendix F. Detailed impact air quality monitoring
results and meteorological information were reported in the Fourteenth to Sixteenth Monthly EM&A Report.
Table
2.3 Summary
of 1-hour TSP Monitoring Results in this Reporting Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
December 2014 |
ASR 8A |
122 |
63
- 298 |
394 |
500 |
ASR 9 |
137 |
96
- 232 |
393 |
500 |
|
January 2015 |
ASR 8A |
109 |
73
- 176 |
394 |
500 |
ASR 9 |
148 |
77
- 217 |
393 |
500 |
|
February
2015 |
ASR 8A |
118 |
68
- 211 |
394 |
500 |
ASR 9 |
132 |
68
- 241 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in this Reporting Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
December
2014 |
ASR 8A |
75 |
63
- 99 |
178 |
260 |
ASR 9 |
98 |
68
- 133 |
178 |
260 |
|
January 2015 |
ASR 8A |
76 |
57
- 99 |
178 |
260 |
|
ASR 9 |
97 |
64
- 123 |
178 |
260 |
February
2015 |
ASR 8A |
72 |
54
¡V 104 |
178 |
260 |
|
ASR 9 |
89 |
51
¡V 117 |
178 |
260 |
The major dust
sources in the reporting period include construction activities under the
Contract as well as nearby traffic emissions.
In this
reporting period, a total of seventeen (17) monitoring events at ASR9 and eighteen
(18) monitoring event at ASR8A were undertaken within the reporting period, in
which no Action or Limit Level exceedance for 1-hour and 24-hour TSP for air
quality was recorded during the reporting period.
The baseline
noise monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong
Projects (HKZMB) during the period of 18 October to 1 November 2011 has
included the monitoring station NSR1 for this project. Thus, the baseline monitoring results
and Action/ Limit Level presented in HKZMB
Baseline Monitoring Report ([3]) are
adopted for this Project.
Monitoring
location was set up at NSR1 in accordance with the Updated EM&A Manual
since project commencement. Due to the rejection of access to Pak Mong Village, no noise monitoring at NSR1 was recorded on 2
December 2014. The Proposal of Alternative Dust and Noise Monitoring
Stations ([4])
was submitted to EPD on 2 December 2014, in which the noise monitoring
station was proposed to be
relocated to the Pak Mong Village Pavilion (NSR1A) in
accordance with the requirements of the Updated EM&A Manual.
Figure
2.2 shows the location of the monitoring station. Table
2.5 describes the details of the monitoring station.
Noise
monitoring was performed using sound level meter at the designated monitoring
station in the reporting quarter.
The deployed sound level meter complies with the International Electrotechnical Commission Publications (IEC) 651:1979
(Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to
check the sound level meter at a known sound pressure level. Brand and model of the equipment is given in Table 2.6.
Table 2.5 Location of Impact Noise
Monitoring Station and Monitoring Dates in this Reporting Period
Monitoring Station |
Monitoring Period |
Location |
Parameters & Frequency |
NSR1A |
December
2014 to February 2015 |
Pak Mong Village Pavilion |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10
and L90 would be recorded. At
least once a week |
Note: (1)
Noise Monitoring Station NSR1 at Pak Mong
Village proposed in accordance with the Updated EM&A was temporarily
relocated to NSR1A. (2) Due
to the rejection of access to NSR1, the monitoring on 2 December at NSR1 was
cancelled. |
Table 2.6 Noise Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion
NL-31 |
Acoustic
Calibrator |
Rion
NC-73 |
The Action and
Limit levels of the noise monitoring are provided in Appendix D. The Event and Action plan is presented
in Appendix J.
The schedules
for noise monitoring in the reporting quarter are provided in Appendix E.
The monitoring
results for noise monitoring are summarized in Table 2.7. Monitoring
results are presented graphically in Appendix G and
detailed impact noise monitoring results are reported in the Fourteenth to Sixteenth Monthly EM&A Report.
Table 2.7 Summary of Construction
Noise Monitoring Results at NSR1A in the Reporting Period
Month |
Average , dB(A), Leq (30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
December2014 |
62 |
61
¡V 62 |
75 |
January 2015 |
61 |
59
¡V 62 |
75 |
February
2015 |
60 |
56
¡V 61 |
75 |
The baseline
water quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge
Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all
monitoring stations except SR4a for the Project. Thus, the baseline monitoring results
except for station SR4a and Action/Limit Level presented in HKZMB Baseline
Monitoring Report ([5]) are
adopted for this Project. Baseline
water quality monitoring was conducted at station SR4a from 29 August to 24
September 2013.
Table 2.8 Locations
of Water Quality Monitoring Stations and the Corresponding Monitoring
Requirements
Station ID |
Type |
Coordinates |
*Parameters, unit |
Depth |
Frequency |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH(pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) ¡P
SS (mg/L) |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed.
If the water depth is less than 3m, mid-depth sampling only. If water depth less than 6m, mid-depth
may be omitted. |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract. |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station(Close
to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
Notes: In addition to the parameters presented monitoring location/position,
time, water depth, sampling depth, tidal stages, weather conditions and any
special phenomena or works underway nearby were also recorded. |
Table 2.9 summarizes the equipment used in the impact water quality monitoring programme.
Table
2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO, Temperature meter and Salinity |
YSI Pro2030 |
Turbidimeter |
HACH Model 2100Q |
pH meter |
HANNA HI8314 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
Water Depth Detector |
Speedtech Instrument SM-5 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
The schedules
for water quality monitoring in the reporting quarter are provided in Appendix E. No impact water quality monitoring was
conducted on 19 and 21 February 2015 due to suspension of marine works.
Impact water
quality monitoring was conducted at all designated monitoring stations in the
reporting period. Monitoring
results are presented graphically in Appendix H and
detailed impact water quality monitoring results were reported in the Fourteenth to Sixteenth Monthly EM&A Report.
In this
reporting period, a total of thirty-seven (37) monitoring events were
undertaken. There were SS results on
10, 14, 17 and 28 February recorded higher than the value of Action Level but
not exceeding 120% of upstream control station at the same tide of same day. The results were considered as natural
variation but not neither Action nor Limit Level exceedance. No Action or Limit Level exceedance was recorded
during the reporting quarter.
Impact dolphin
monitoring is required to be conducted by a qualified dolphin specialist team
to evaluate whether there have been any effects on the dolphins. In order to fulfil the EM&A
requirements and make good use of available resources, the on-going impact line
transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong
Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities on the monthly basis is adopted to avoid duplicates of survey
effort.
Table 2.10 summarises the equipment
used for the impact dolphin monitoring.
Table 2.10 Dolphin Monitoring Equipment
Equipment |
Model |
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single
engine motor vessel with viewing platform 4.5m above water level |
Dolphin monitoring
should cover all transect lines in Northeast Lantau (NEL) and the Northwest
Lantau (NWL) survey areas twice per month throughout the entire construction
period. The monitoring data should
be compatible with, and should be made available for, long-term studies of
small cetacean ecology in Hong Kong. In order to provide a suitable long-term
dataset for comparison, identical methodology and line transects employed in
baseline dolphin monitoring was followed in the impact dolphin monitoring.
The impact
dolphin monitoring was carried out in the NEL and NWL along the line transect
as depicted in Figure 2.4. The co-ordinates of all transect lines
are shown in Table 2.11 below.
Table 2.11 Impact
Dolphin Monitoring Line Transect Co-ordinates
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
814577 |
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815457 |
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820690 |
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
820847 |
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
820892 |
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818449 |
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
The action and
limit levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented
in Appendix J.
The dolphin
monitoring schedules for the reporting period are shown in Appendix E.
A total of
891.50 km of survey effort was collected, with 99.6% of the total survey effort
being conducted under favourable weather conditions
(i.e. Beaufort Sea State 3 or below with good visibility). Among the two areas, 347.05 km and
544.45 km of survey effort were conducted in NEL and NWL survey areas
respectively. The total survey
effort conducted on primary lines was 645.44 km, while the effort on secondary
lines was 246.06 km. Both survey
efforts conducted on primary and secondary lines were considered as on-effort
survey data. The survey efforts are
summarized in Appendix I.
During the six
sets of monitoring surveys in December 2014 to February 2015, a total of fifteen
(15) groups of fifty-two (52) Chinese White Dolphins were sighted. All dolphin sightings were made during
on-effort search. Twelve (12) of
the fifteen (15) on-effort sightings were made on primary lines, while the
other three (3) were made on secondary lines. No sighting was made in the proximity of
the Project¡¦s alignment. In this
quarterly period, all dolphin groups were sighted in NWL, while none of them
were sighted in NEL. Summary table
of the dolphin sightings is shown in Appendix I.
Encounter
rates of Chinese White Dolphins deduced from the survey effort and on-effort
sighting data from the primary transect lines under favourable
conditions (Beaufort 3 or below) in the reporting period with the results
presented in Tables 2.12 and 2.13.
Table 2.12 Individual Survey Event Encounter
Rates
Survey Area |
Survey period |
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
Primary
Lines Only |
Primary
Lines Only |
||
NEL |
Set 1: Dec 2nd/9th |
0.0 |
0.0 |
Set 2: Dec 15th/23rd |
0.0 |
0.0 |
|
Set 3: Jan 8th / 15th |
0.0 |
0.0 |
|
Set 4: Jan 27th / 29th |
0.0 |
0.0 |
|
Set 5: Feb 5th / 13th |
0.0 |
0.0 |
|
Set 6: Feb 16th / 25th |
0.0 |
0.0 |
|
NWL |
Set 1: Dec 2nd/9th |
2.8 |
5.6 |
Set 2: Dec 15th/23rd |
1.4 |
1.4 |
|
Set 3: Jan 8th / 15th |
4.3 |
21.6 |
|
Set 4: Jan 27th / 29th |
7.5 |
37.6 |
|
Set 5: Feb 5th / 13th |
1.4 |
1.4 |
|
Set 6: Feb 16th / 25th |
0.0 |
0.0 |
Note: Dolphin Encounter Rates are deduced from
the six sets of surveys (two surveys in each set) in the reporting period in
Northeast (NEL) and Northwest Lantau (NWL)
Table 2.13 Quarterly Average Encounter Rates
Survey Area |
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per
100 km of survey effort) |
||
December 2014 ¡V February 2015 |
September -November 2011 |
December 2014 ¡V February 2015 |
September -November 2011 |
|
Northeast Lantau |
0.00 |
6.00 ¡Ó 5.05 |
0.00 |
22.19 ¡Ó 26.81 |
Northwest Lantau |
2.91 ¡Ó 2.69 |
9.85 ¡Ó 5.85 |
11.27 ¡Ó 15.19 |
44.66 ¡Ó 29.85 |
Note:
encounter rates deduced from the baseline monitoring period have been
recalculated based only on survey effort and on-effort sighting data made along
the primary transect lines under favourable
conditions
Table 2.14 Comparison of Quarterly Average
Encounter Rates
|
Average Dolphin Group Size |
|
December 2014 ¡V February
2015 |
September -November 2011 |
|
Overall |
3.47 ¡Ó 2.29 (n = 15) |
3.72 ¡Ó 3.13 (n = 66) |
Northeast Lantau |
0.00 |
3.18 ¡Ó 2.16 (n = 17) |
Northwest Lantau |
3.47 ¡Ó 2.29 (n = 15) |
3.92 ¡Ó 3.40 (n = 49) |
Daily
marine mammal exclusion zone monitoring was undertaken during the period of
marine works under this Contract. Passive
Acoustic Monitoring (PAM) was also implemented for the detection of marine
mammal when marine works were carried out outside the daylight hours under this
Contract. No sighting of the
Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in
the monitoring period during the exclusion zone monitoring.
Site
inspections were carried out on a weekly basis to monitor the implementation of
proper environmental pollution control and mitigation measures under the
Contract. Thirteen (13) site
inspections were carried out in the reporting quarter on 3, 10, 17, 24 and 30
December 2014; 8, 14, 21 and 29 January 2015; 4, 13, 17 and 26 February 2015.
Key
observations during the site inspections in this reporting period are summarized
in Table 2.15.
Table 2.15 Specific
Observations Identified during the Weekly Site Inspection in this Reporting
Period
Inspection Date |
Location & Environmental Observations |
Recommendations/ Remarks |
3 December
2014 |
Seafront ¡P
Some chemical containers were not placed in drip
tray. ¡P
Oil stain was found nearby a drip tray for
generator. ¡P
A skip for waste was nearly full. ¡P
A sediment tank was under maintenance. Pier B7 ¡P
Gutter was found not well installed for waste water
collection. ¡P
Oil stain was found nearby a drip tray for
generator. Pier E12 ¡P
A chemical container was found not placed in drip
tray. |
Seafront ¡P
Chemical containers should be placed in drip tray ¡P
Oil stain should be removed to avoid run-off. ¡P
The contractor should clean up the waste on site
regularly. ¡P
The contractor should ensure the sedimentation tank
is available for site operation. Pier B7 ¡P
Gutter should be properly installed for waste water
collection. ¡P
Oil stain should be removed to avoid run-off. Pier E12 ¡P
Chemical containers should be placed in drip tray. |
10 December
2014 |
Site Access
9B ¡P
Checking record for wetsep
was missing. ¡P
Grouting material was accumulated at grouting
station. ¡P
The slope under works may generate dust. Viaduct B
(land) ¡P
A chemical container was found dripping and not
placed in drip tray. ¡P
Some drip trays for generator were not plugged or
plugged properly. ¡P
Oil stain was found under an excavator. |
Site Access
9B ¡P
Wetsep
should be checked regularly and the record should be filled. ¡P
Grouting material should be cleaned up regularly to
avoid runoff. ¡P
The contractor was reminded to water the slope
regularly. Viaduct B
(land) ¡P
Drip tray should be provided to the chemical
container. ¡P
Drip tray should be plugged properly. ¡P
Drip tray was recommended for the excavator. |
17 December
2014 |
Pier D7
(Barge Tung Shun 8) ¡P
A drip tray was not plugged. ¡P
A chemical container was not placed in drip tray. Pier D4
(Barge Kam Shun) ¡P
A generator was not placed on decoupling pad. ¡P
A label for coagulant was missing. |
Pier D7
(Barge Tung Shun 8) ¡P
The drip tray should be plugged. ¡P
The chemical container should be placed in drip
tray. Pier D4
(Barge Kam Shun) ¡P
The generator should be placed on decoupling pad. ¡P
Coagulant container should be labelled properly.. |
24 December
2014 |
Pier D13B ¡P
A drip tray for generator was no plugged. Pier C8 ¡P
Some chemical containers were not placed in drip
tray. Abutment D ¡P
The area was partially dry and unpaved. |
Pier D13B ¡P
The drip tray for generator should be plugged. Pier C8 ¡P
Chemical containers should be placed in drip tray. Abutment D ¡P
The contractor was reminded to water the unpaved
area 8 times a day. |
30 December
2014 |
Pier E12 ¡P
A dumping permit for Category L sediment was not
displayed. ¡P
A generator was placed without decoupling pad. Pier E13 ¡P
Stagnant water was accumulated in a drip tray. ¡P
A generator was placed without acoustic decoupling
pad. ¡P
Excessive soil was accumulated in the gutter. Area 1 ¡P
Stagnant water was accumulated in a drip tray. ¡P
Placement of material stack was too close to natural
habitat. |
Pier E12 ¡P
The updated permit should be placed at the
corresponding platform. ¡P
Generator on marine platform should be placed on
acoustic decoupling pad. Pier E13 ¡P
Drip tray should have enough volume to avoid
overflowing, so stagnant water should be removed. ¡P
Generator on marine platform should be placed on
acoustic decoupling pad. ¡P
Gutter should be cleaned up regularly. Area 1 ¡P
Drip tray should have enough volume to avoid
overflowing, so stagnant water should be removed. ¡P
The contractor should place the material stacks in
the designated area within the existing disturbed land. |
8 January
2015 |
Pier B2 ¡P
A generator was not placed on decoupling pad
properly Pier D6. ¡P
The updated dumping permit was not displayed. ¡P
A power pack was not placed on decoupling pad
properly. ¡P
The door of an operating air compressor was not
closed. ¡P
Some refuse was found on sea nearby platform. Barge M027
(next to pier E13) ¡P
A chemical container was not placed in drip trip. Pier E12 ¡P
A part of gutter
was not installed properly. |
Pier B2 and
D6 ¡P
Generators or power packs should be placed on
decoupling properly. ¡P
The updated dumping permit should be displayed. ¡P
Door of operating machine on marine platform should
be closed. ¡P
The contractor should clean up the site and
surrounding area regularly to keep tidy and litter free. Barge M027
(next to pier E13) ¡P
Chemical container should be placed in drip tray. Pier E12 ¡P
Gutter on platform should be installed properly. |
14 January
2015 |
Pak Mong ¡P
Stagnant water was accumulated in a drip tray. Slope B/C9 ¡P
Refuse was accumulated in the drainage. Site Access
5D ¡P
Wheel washing facility was incomplete. |
Pak Mong ¡P
Drip tray should have enough capacity to avoid
overflowing. Slope B/C9 ¡P
Drainage should be cleaned up regularly to avoid
blockage. Site Access
5D ¡P
The contractor was reminded to ensure waste water
from wheel washing will be treated before discharge. |
21 January
2015 |
Barge Chang Sheung 307 (near platform E4) ¡P
A chemical container was not placed in drip tray. Pier A1 ¡P
A drip tray for generator was not plugged. |
Barge Chang Sheung 307 (near platform E4) ¡P
Chemical container should be placed in drip tray. Pier A1 ¡P
Drip tray should be plugged properly. |
29 January
2015 |
Pier E13 AB ¡P
A drip tray for generator was not plugged. Seafront ¡P
Some chemical containers on pontoon were not placed
in drip tray. Pier D14 ¡P
The ground was unpaved and dry. |
Pier E13 AB
and Seafront ¡P
Chemical containers and generators should be placed
in plugged drip tray. Pier D14 ¡P
The contractor was reminded to implement the
watering programme for effective dust suppression. |
4 February
2015 |
Area 1 ¡P
The ground was dry. ¡P
Washing facility at the entrance was incomplete. ¡P
Soil stockpile was not covered. ¡P
Refuse was accumulated in drainage. ¡P
A drip tray for generator was not plugged. |
Area 1 ¡P
The contractor was reminded to implement the
watering programme for dust suppression. ¡P
Wheel washing should be provided at the entrance. ¡P
Soil stockpile should be covered by tarpaulin sheet
or wet to avoid dust emission. ¡P
Drainage should be cleaned up regularly. ¡P
Drip trays should be plugged. |
13 February
2015 |
Pier D5 ¡P
A generator was not well placed on acoustic
decoupling pad. Pier B1 ¡P
Sediment was accumulated in the gutter. Barge Tung
Shun 88 (next to Pier D2) ¡P
Label for marine sediment was not displayed. Pier B2 ¡P
A part of gutter was not properly installed. |
Pier D5 ¡P
Machine on marine platform should be well placed on
decoupling pad. Pier B1 ¡P
Gutter should be cleaned regularly. Barge Tung
Shun 88 (next to Pier D2) ¡P
Label for marine sediment should be displayed. Pier B2 ¡P
Gutter should be properly installed. |
17 February
2015 |
Seafront
near Pier B8 ¡P
A drip tray for generator was not plugged. Pier D12A ¡P
Some chemical containers were not placed in drip
tray. ¡P
Grouting material was found not covered. Pier D10 ¡P
Sandbags were found insufficient to avoid waste
water discharging offsite. |
Seafront near Pier B8 ¡P
Drip trays should be plugged. Pier D12A ¡P
Chemical containers should be covered and placed in
drip tray. ¡P
Stockpile of grouting material should be covered. Pier D10 ¡P
Sufficient sandbags should be provided to avoid any
runoff of waste water. |
26 February
2015 |
Pier C1 ¡P
Gutter was not properly installed. |
Pier C1 ¡P
Gutter should be properly installed to ensure no
waste water runoff from platform. |
Wastes
generated during this reporting period include mainly construction wastes
(inert and non-inert), imported fill, recyclable
materials, chemical waste and marine sediments (Categories L & M). Reference has been made to the waste
flow table prepared by the Contractor (Appendix K). The quantities of different types of
wastes are summarized in Table 2.16.
Table 2.16 Quantities
of Different Waste Generated in the Reporting Period
Month / Year |
Inert Construction Waste (a)
(m3) |
Imported Fill (m3) |
Inert Construction Waste
Re-used (m3) |
Non-inert Construction Waste (b)
(tonnes) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
||||
Category L |
Category M |
||||||||||
December 2014 |
15,987 |
0 |
3,020 |
130,970 |
147 |
0 |
337 |
275 |
|||
January 2015 |
12,474 |
115 |
990 |
132,170 |
91 |
0 |
178 |
487 |
|||
February
2015 |
5,759 |
0 |
436 |
141,020 |
112 |
400 |
801 |
333 |
|||
Total |
34,220 |
115 |
4,446 |
404,160 |
350 |
400 |
1,316 |
1,095 |
|||
Notes: |
|||||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. |
|||||||||||
The Contractor
was advised to properly maintain on site C&D materials and waste
collection, sorting and recording system, dispose of C&D materials and
wastes at designated ground and maximize reuse/ recycle of C&D materials
and wastes. The Contractor was also
reminded to properly maintain the site tidiness and dispose of the wastes
accumulated on site regularly and properly.
For
chemical waste containers, the Contractor was reminded to treat properly and
store temporarily in designated chemical waste storage area on site in
accordance with the Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes.
The status of
environmental licensing and permit is summarized in Table 2.17 below.
Table
2.17 Summary
of Environmental Licensing and Permit Status
License/ Permit |
License or Permit No. |
Date of Issue |
Date of Expiry |
License/ Permit Holder |
Remarks |
Environmental Permit |
EP-354/2009/C |
10-Dec-14 |
N/A |
HyD |
Tuen Mun- Chek
Lap Kok Link |
Chemical Waste Producer Registration |
5213-951-G2380-17 |
12-Jun-14 |
NA |
GCL |
Viaducts A, B, C, D & E |
Chemical Waste Producer Registration |
5213-961-G2380-13 |
10-Oct-13 |
NA |
GCL |
Area1 adjacent to Cheung Ting Road, Siu Ho Wan |
Chemical Waste Producer Registration |
5213-961-G2380-14 |
10-Oct-13 |
NA |
GCL |
Area 2 adjacent to Cheung Tung Road, Pak Mong Village |
Chemical Waste Producer Registration |
5213-974-G2588-03 |
04-Nov-13 |
NA |
GCL |
WA5 adjacent to Cheung Tung Road, Yan O |
Construction Dust Notification |
361571 |
05-Jul-13 |
NA |
GCL |
NA |
Construction Dust Notification |
362093 (for WA23) |
17-Jul-13 |
NA |
GCL |
NA |
Construction Noise Permit for night works and works in
general holidays |
GW-RS0078-15 |
28-Jan-15 |
29-Jul-15 |
GCL |
For Plant mobilization using tractor |
Construction Noise Permit for night works and works in
general holidays |
GW-RS0137-15 |
12-Feb-14 |
15-Aug-15 |
GCL |
Pre-casted pile cap shell installation at E10-E13 |
Construction Noise Permit for night works and works in
general holidays |
GW-RS0206-15 |
24-Feb-15 |
30-Apr-15 |
GCL |
B9-B16 Pier Head Segments Erection |
Construction Noise Permit for night works and works in
general holidays |
GW-RS0700-14 |
21-Jul-14 |
31-Dec-14 |
GCL |
For loading & unloading on NLH near Viaduct A & B
(renewed to GW-RS1386-14) |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1032-14 |
25-Sep-14 |
28-Mar-15 |
GCL |
For Load unload at NLH near Viaduct D |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1129-14 |
17-Oct-14 |
31-Dec-14 |
GCL |
For Safety Fences at Pier D9 |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1130-14 |
20-Oct-14 |
22-Apr-15 |
GCL |
For Plant mobilization using tractor |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1135-14 |
17-Oct-14 |
15-Dec-14 |
GCL |
For TTA Case 60-2 Ch.1.3E-3.6E (updated to GW-RS1383-14) |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1188-14 |
30-Oct-14 |
31-Dec-14 |
GCL |
For TTA Cases 50 Airport Road-5.3 (updated to GW-RS1403-14) |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1225-14 |
31-Oct-14 |
02-May-15 |
GCL |
For Broad Permit |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1383-14 |
15-Dec-14 |
28-Feb-15 |
GCL |
TTA Case 060-12 Ch.1.0-4.2 |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1386-14 |
15-Dec-14 |
15-Mar-15 |
GCL |
TTA Case 009 Ch.2.3E-4.2E |
Construction Noise Permit for night works and works in
general holidays |
GW-RS1403-14 |
15-Dec-14 |
28-Feb-15 |
GCL |
TTA Case 050 Series Airport Rd to NLH Ch.5.3 |
Construction Noise Permit for night works and works in
general holidays |
GW-RW0093-15 |
26-Feb-15 |
26-Aug-15 |
GCL |
General works at WA5 |
Construction Noise Permit for night works and works in
general holidays |
GW-RW0640-14 |
28-Aug-14 |
27-Feb-15 |
GCL |
General works at WA5 |
Construction Noise Permit for Piling Works |
Nil |
NA |
NA |
GCL |
NA |
Construction Waste Disposal Account |
7017735 |
10-Jul-13 |
NA |
GCL |
NA |
Construction Waste Disposal Account |
7019470 |
03-Mar-14 |
NA |
GCL |
Vessel CHIT Account |
Effluent Discharge License |
WT00019017-2014 |
13-May-14 |
31-May-19 |
GCL |
Marine Portion |
Effluent Discharge License |
WT00019018-2014 |
13-May-14 |
31-May-19 |
GCL |
Land Portion |
Marine Dumping Permit |
EP/MD/15-066 |
28-Jul-14 |
27-Jan-15 |
GCL |
For dumping Type I sediment |
Marine Dumping Permit |
EP/MD/15-161 |
25-Nov-14 |
31-Dec-14 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Marine Dumping Permit |
EP/MD/15-186 |
01-Jan-15 |
31-Jan-15 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Marine Dumping Permit |
EP/MD/15-203 |
28-Jan-15 |
27-Jul-15 |
GCL |
For dumping Type I sediment |
Marine Dumping Permit |
EP/MD/15-234 |
27-Feb-15 |
31-Mar-15 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Table 2.18 Comparison
between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended
Solids
Station |
Baseline Mean |
Ambient Mean (a) |
Quarterly Mean (December 2014 to
February 2015) |
|||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|
CS(Mf)3 |
9.2 |
12.8 |
12.0 |
16.6 |
12.8 |
12.8 |
CS(Mf)5 |
9.2 |
11.5 |
11.9 |
14.9 |
12.8 |
12.7 |
SR4 |
10.3 |
12.3 |
13.4 |
16.0 |
12.5 |
12.4 |
SR4a |
9.1 |
9.8 |
11.9 |
12.7 |
12.4 |
12.4 |
IS8 |
11.3 |
13.5 |
14.6 |
17.6 |
12.5 |
12.2 |
IS(Mf)9 |
10.9 |
14.3 |
14.2 |
18.5 |
12.3 |
12.1 |
IS(Mf)16 |
11.4 |
10.3 |
14.8 |
13.4 |
12.3 |
12.3 |
Notes: |
||||||
(a)
Ambient mean value is defined as a 30% increase of the baseline mean value |
One (1) Limit Level
exceedance was recorded for impact dolphin monitoring in this reporting
quarter. Following the review of
the monitoring data and marine works details as per the procedure stipulated in
the Event and Action Plan of the Updated EM&A Manual, there is no evidence
showing that the sources of impact directly related to the construction works
under this Contract that may have affected the dolphin usage in the NEL region. Investigation findings were detailed in Appendix L.
March
2015
Marine Works
¡P
Construction of Pile caps at Viaducts B, C, D & E;
¡P
Marine piling platform installation &
uninstallation;
¡P
Marine Piling at Viaducts C & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Channel re-construction at Area 1;
¡P
Land Piling at Viaducts B, C & D;
¡P
Pre-drilling works at Viaduct A;
¡P
Construction of pile cap at Viaducts B, C, D & E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
April 2015
Marine
Works
¡P
Construction and installation of pile caps;
¡P
Marine piling platform installation &
uninstallation;
¡P
Pier construction;
¡P
Installation of launching gantry;
¡P
Marine piling; and,
¡P
Installation of pier head segment.
Land-based
Works
¡P
Construction and installation of pile caps;
¡P
Pier construction;
¡P
Drainage works;
¡P
Land piling;
¡P
Pre-drilling works;
¡P
Installation of pier head segment;
¡P
Additional land GI, trial pits & lab testing;
¡P
Tree survey, felling and transplanting;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
May 2015
Marine
Works
¡P
Construction and installation of pile caps;
¡P
Marine piling platform installation &
uninstallation;
¡P
Pier construction;
¡P
Installation of launching gantry;
¡P
Marine piling and
¡P
Installation of pier head segment.
Land-based
Works
¡P
Construction and installation of pile caps;
¡P
Pier construction;
¡P
Drainage works;
¡P
Land piling;
¡P
Pre-drilling works;
¡P
Installation of pier head segment;
¡P
Additional land GI, trial pits & lab testing;
¡P
Tree survey, felling and transplanting;
¡P
Relocation of MTRC fence; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
Potential environmental
impacts arising from the above upcoming construction activities are mainly
associated with air quality, noise, marine water quality, marine ecology and
waste management issues.
Impact
monitoring for air quality, noise, marine water quality and dolphin monitoring are
scheduled to continue for the next reporting period.
The monitoring
programme has been reviewed and was considered as
adequate to cater for the nature of works in progress.
This Fifth Quarterly
EM&A Report presents the findings of the EM&A activities undertaken
during the period from 1 December 2014 to 28 February 2015, in accordance with
the Updated EM&A Manual and the requirements of the Environmental Permit (EP-354/2009/C).
Neither Action
Level nor Limit Level exceedances were observed for air quality, noise and water
quality impact monitoring in this reporting period.
A total of
fifteen (15) groups of fifty-two (52) Chinese White Dolphins were sighted during
the six sets of surveys from December 2014 to February 2015. Whilst one (1) Limit Level exceedance was
recorded for the quarterly dolphin monitoring data between December 2014 and February
2015, no unacceptable impact from the activities of this Contract on Chinese
White Dolphins was noticeable from the general observations. It is critical to monitor the dolphin
usage in North Lantau region in the upcoming quarters, to determine whether the
dolphins are continuously affected by the various construction activities in
relation to the HZMB-related works, and whether suitable mitigation measure can
be applied to revert the situation.
Environmental
site inspection was carried out thirteen (13) times in the reporting period. Recommendations on remedial actions were
given to the Contractor for the deficiencies identified during the site audits.
The monitoring
programme has been reviewed and was considered as
adequate to cater for the nature of works in progress. Change to the
monitoring programme was thus not recommended at this stage. The monitoring programme will be
evaluated as appropriate in the next reporting period. The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
([1])
Agreement No. CE 35/2011 (EP)
Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong
Kong Projects - Investigation. Baseline
Environmental Monitoring Report (Version C). Submitted on 8 March 2012 and
subsequently approved by EPD.
([2])
The Proposal of Alternative Dust and Noise
Monitoring Stations with the agreement letter from IEC and SOR was
submitted to EPD on 2 December 2014, and subsequently replied with no objection
on 4 December 2014.
(1)
Agreement No. CE 35/2011 (EP)
Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong
Kong Projects - Investigation. Baseline
Environmental Monitoring Report (Version C). Submitted on 8 March 2012 and
subsequently approved by EPD.