Executive Summary
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
1.5 Summary of EM&A Programme
Requirements
2.1 Air Quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Dolphin Monitoring
2.5 EM&A Site Inspection
2.6 Waste Management Status
2.7 Environmental Licenses and
Permits
2.8 Implementation Status of
Environmental Mitigation Measures
2.9 Summary of Exceedances of the
Environmental Quality Performance Limit
2.10 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Activities for
the Coming Quarter
3.2 Key Issues for the Coming
Quarter
3.3 Monitoring Schedule for the
Coming Quarter
4 Conclusions and recommendations
4.1 Conclusions
List
of Appendices
Appendix A Project Organization for Environmental Works
Appendix B Three Month Rolling Construction Programmes
Appendix C Implementation Schedule of Environmental Mitigation
Measures (EMIS)
Appendix D Summary of Action and Limit Levels
Appendix E EM&A Monitoring Schedules
Appendix F Impact Air Quality Monitoring Results and Graphical
Presentation
Appendix G Impact Noise Monitoring Results and Graphical
Presentation
Appendix H Impact Water Quality Monitoring Results and Graphical
Presentation
Appendix I Impact Dolphin Monitoring Survey Results
Appendix J Event Action Plan
Appendix K Quarterly Summary of Waste Flow Table
Under
Contract No. HY/2012/07, Gammon
Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern
Connection Viaduct Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia
Company Limited was appointed by HyD as the
Supervising Officer. For implementation
of the environmental monitoring and audit (EM&A) programme
under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the
Environmental Team (ET). Ramboll Environ Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications for variation of
environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014
and 13 March 2015, respectively.
The southern landfall
of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by
Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D. Upon the agreement and confirmation between
the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07
in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.
Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.
The construction
phase of the Contract commenced on 31 October 2013 and will be tentatively
completed by 2018. The impact monitoring
of the EM&A programme, including air quality,
noise, water quality and marine ecological monitoring as well as environmental
site inspections, commenced on 31 October 2013.
This is the Fifteenth
Quarterly EM&A Report presenting the EM&A works carried out during the
period from 1 June 2017 to 31 August 2017 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
June 2017
Marine
Works
·
Uninstallation of marine piling platform;
·
Pier construction;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based
Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
July 2017
Marine Works
·
Uninstallation of marine piling platform;
·
Pier construction;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
August 2017
Marine Works
·
Uninstallation of marine piling platform;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour TSP
monitoring 17 sessions
1-hour TSP
monitoring 18 sessions
Noise monitoring 18 sessions
Water quality monitoring
([1]) 39
sessions
Dolphin
monitoring 6
sessions
Joint
Environmental site inspection 13 sessions
Breaches of Action and Limit Levels for Air Quality
No exceedance of
Action and Limit Levels was recorded for air quality monitoring in the
reporting period.
Breaches of Action and Limit Levels for Noise
No exceedance of
Action and Limit Levels was recorded for construction noise monitoring in the
reporting period.
Breaches of Action and Limit Levels for Water Quality
Thirty (30) Action
Level and fourteen (14) Limit Level of Dissolved Oxygen (DO) exceedances and
one (1) Action Level of Suspended Solids (SS) exceedances were recorded for water
quality impact monitoring in the reporting period.
Impact Dolphin Monitoring
One
(1) Limit Level exceedance was observed for the quarterly dolphin monitoring
data between June and August 2017. No
unacceptable impact from the construction activities of the TM-CLKL Southern
Connection Viaduct Section on Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese
White Dolphins) was noticeable from general observations during the dolphin
monitoring in this reporting quarter. The
exceedance is considered unlikely due to the works of this Project upon further
investigation.
Daily marine mammal exclusion zone monitoring was
undertaken during the period of marine works under this Contract. No Passive Acoustic
Monitoring (PAM) was implemented as the marine piling works were not carried
out outside the daylight hours in this reporting period. No sighting of the Chinese White Dolphin was recorded in the monitoring
period during the exclusion zone monitoring.
Environmental Complaints, Non-compliance & Summons
There was no
environmental complaint, notification of summons or successful prosecution
recorded in the reporting period
Reporting Change
There was no
reporting change in this reporting period.
Upcoming Works for the Next
Reporting Period
Works to be
undertaken in the coming quarter include the following:
September 2017
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Launching gantry operation;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
October 2017
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Launching gantry operation;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
November 2017
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Launching gantry operation;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the coming quarterly period are mainly associated with air quality, noise, marine
water quality, marine ecology and waste management issue.
According to the
findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau
Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based on
the estimated increase in cross boundary traffic, developments in the Northwest
New Territories (NWNT), and possible developments in North Lantau, including
the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong –
Zhuhai – Macao Bridge (HZMB). In order
to cope with the anticipated traffic demand, two new road sections between NWNT
and North Lantau – Tuen Mun
– Chek Lap Kok Link
(TM-CLKL) and Tuen Mun
Western Bypass (TMWB) are proposed.
An Environmental
Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance
with the EIA Study Brief (No. ESB-175/2007)
and the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The EIA Report was
submitted under the Environmental Impact Assessment Ordinance (EIAO) in August
2009. Subsequent to the approval of the
EIA Report (EIAO Register Number: AEIAR-146/2009),
an Environmental Permit (EP-354/2009)
for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4
November 2009, and EP variation (EP-354/2009A)
was issued on 8 December 2010. Further applications for variation of
environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014
and 13 March 2015, respectively.
Under
Contract No. HY/2012/07, Gammon
Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia
Company Limited was appointed by HyD as the
Supervising Officer. For implementation
of the environmental monitoring and audit (EM&A) programme
under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the
Environmental Team (ET). Ramboll Environ Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.
The southern landfall
of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong
Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by
Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D. Upon the agreement and confirmation between
the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07
in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.
Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.
The organization
structure of the Contract is shown in Appendix
A. The key personnel contact names
and contact details are summarized in Table
1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD (Highways
Department) |
Project Coordinator |
Stanley Chan |
2762 3406 |
3188 6614 |
|
Senior Engineer |
Steven Shum |
2762 4133 |
3188 6614 |
SOR (AECOM Asia Company Limited) |
Chief Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident Engineer |
Kingman Chan |
3691 3950 |
3691 2899 |
ENPO / IEC (Ramboll Environ Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465
2850 |
3465 2899 |
IEC |
Dr. F.C. Tsang |
3465
2851 |
3465 2899 |
|
Contractor (Gammon Construction Limited) |
Environmental Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
June 2017
Marine
Works
·
Uninstallation of marine piling platform;
·
Pier construction;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based
Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
July 2017
Marine Works
·
Uninstallation of marine piling platform;
·
Pier construction;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
August 2017
Marine Works
·
Uninstallation of marine piling platform;
·
Launching gantry operation;
·
Installation of deck segment and pier head segment;
and
·
Construction of underslung truss scheme (no additional
seabed will be occupied other than those assumed in the approved EIA Report).
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
The locations of
the construction activities are shown in Figure 1.3. The
Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.4.
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are
described in the following sections, which include:
·
Monitoring parameters;
·
Monitoring schedules for the reporting months and
forthcoming months;
·
Action and Limit levels for all environmental
parameters;
·
Event Action Plan;
·
Results and observations;
·
Environmental mitigation measures, as recommended in
the approved EIA Report; and
·
Environmental requirement in contract documents.
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are
summarized in the following sections.
The baseline air
quality monitoring undertaken by the HZMB Projects during October 2011 included
the two monitoring stations ASR9A and ASR9C for this Project. Thus, the baseline monitoring results and
Action/Limit Level presented in HZMB Baseline Monitoring Report ([2])
are adopted for this Project.
1-hour TSP and 24-hour TSP monitoring were conducted at 2 alternative
air quality monitoring stations, ASR8A (Area 4) and ASR9 (entrance of MTR
Depot) during the reporting period in accordance with the requirement of the
Updated EM&A Manual. The monitoring
stations are indicated in Figure 2.1 and details
are presented in Table 2.1.
High Volume Samplers (HVSs) were used for carrying out 1-hour and 24-hour
TSP monitoring during the reporting period.
The HVSs meets all requirements of the Updated EM&A Manual. Brand and model of the equipment are given in
Table 2.2.
Wind data
monitoring equipment was installed at Area 4 during the reporting period for
logging wind speed and wind direction. The
wind sensor was setup such that it was clear of obstructions or turbulence
caused by building. The wind data
monitoring equipment is recalibrated at least once every six months.
Table 2.1 Locations of Impact Air Quality Monitoring Stations and
Monitoring Dates in this Reporting Period
Monitoring
Station (1) |
Monitoring
Period |
Location |
Description |
Parameters
& Frequency |
ASR8A |
2, 8, 14, 20, 26 and 29 June 2017 5, 11, 17, 20 and 26 July 2017 1, 7, 10, 16, 22, 28 and 31 August 2017 |
Area 4 |
On ground at the works area, Area 4 |
1-hour Total Suspended Particulates (1-hour
TSP, µg/m3), 3 times per day every 6 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for
24-hour every 6 days |
ASR9 |
MTR Depot |
On the ground nearby MTR Depot entrance |
Note:
(1)
Air
Quality Monitoring Stations ASR9A and ASR9C at Siu Ho Wan MTRC Depot proposed
in accordance with the Updated EM&A were relocated to ASR9 and ASR8A respectively.
(2) Changes in monitoring schedule are provided in Section
2.1.3.
Table 2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High
Volume Sampler |
Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170) |
Wind
Sensor |
Global
Water (Wind Speed Sensor: WE550; Wind Direction Sensor: WE570) |
Wind
Anemometer for calibration |
Lutron
(Model No. AM-4201) |
The Action and
Limit Levels of the air quality monitoring are provided in Appendix D. The Event and
Action plan is presented in Appendix J.
The schedules
for air quality monitoring in the reporting quarter are provided in Appendix E. 24-hour TSP at ASR8A and ASR9 on 22
August 2017 was canceled due to adverse weather.
The monitoring
results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively. Monitoring results are presented graphically
in Appendix F. Detailed impact air quality monitoring
results and meteorological information were reported in the Forty-fourth to Forty-sixth Monthly EM&A Reports.
Table 2.3 Summary of 1-hour TSP Monitoring Results in this Reporting
Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level
(µg/m3) |
Limit Level
(µg/m3) |
June 2017 |
ASR 8A |
60 |
38-97 |
394 |
500 |
ASR 9 |
89 |
41-147 |
393 |
500 |
|
July 2017 |
ASR 8A |
49 |
41-61 |
394 |
500 |
ASR 9 |
63 |
38-93 |
393 |
500 |
|
August 2017 |
ASR 8A |
55 |
13-163 |
394 |
500 |
ASR 9 |
74 |
15-212 |
393 |
500 |
Table 2.4 Summary of 24-hour TSP Monitoring Results in this Reporting
Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level
(µg/m3) |
Limit Level
(µg/m3) |
June 2017 |
ASR 8A |
42 |
38-45 |
178 |
260 |
ASR 9 |
46 |
41-51 |
178 |
260 |
|
July 2017 |
ASR 8A |
37 |
20-43 |
178 |
260 |
ASR 9 |
41 |
30-54 |
178 |
260 |
|
August 2017 |
ASR 8A |
30 |
15-71 |
178 |
260 |
ASR 9 |
39 |
20-61 |
178 |
260 |
The major dust
sources in the reporting period include construction activities under the
Contract as well as nearby traffic emissions.
In this
reporting period, a total of 18 monitoring events for 1-hour TSP and 17
monitoring events for 24-hour TSP were undertaken within the reporting period,
in which no Action or Limit Level exceedance for 1-hour and 24-hour TSP for air
quality was recorded during the reporting period.
The baseline
noise monitoring undertaken by the HZMB Projects during the period of 18
October to 1 November 2011 included the monitoring station NSR1 for this Project. Thus, the baseline monitoring results and
Action/ Limit Level presented in HZMB
Baseline Monitoring Report ([3])
are adopted for this Project.
In accordance
with the Updated EM&A Manual, impact noise monitoring should be conducted
once per week during the construction phase of the Contract.
Noise monitoring
was conducted at the alternative noise monitoring station, NSR1A (Pak Mong Village Pavilion) during the reporting period in
accordance with the requirement of Updated EM&A Manual. Figure 2.2 shows the
location of the monitoring station. Table 2.5 describes the details of the
monitoring station.
Noise monitoring
was performed using sound level meter at the designated monitoring station in
the reporting quarter. The deployed sound
level meter complies with the International Electrotechnical
Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1)
specifications. Acoustic calibrator was
deployed to check the sound level meter at a known sound pressure level. Brand and model of the
equipment is given in Table 2.6.
Table 2.5 Location of Impact Noise Monitoring Station and Monitoring
Dates in this Reporting Period
Monitoring Station |
Monitoring
Period |
Location |
Parameters
& Frequency |
NSR1A |
2, 8, 14, 20, 26 and 29 June 2017 5, 11, 17, 20 and 26 July 2017 1, 7, 10, 16, 22, 28 and 31 August 2017 |
Pak Mong Village Pavilion |
30-mins measurement
at each monitoring station between 0700 and 1900 on normal weekdays (Monday
to Saturday). Leq, L10 and L90 would be recorded. At least once
a week |
Note: (1)
Noise Monitoring Station NSR1 at Pak Mong
Village proposed in accordance with the Updated EM&A was relocated to
NSR1A. |
Table 2.6 Noise Monitoring Equipment
Equipment |
Brand
and Model |
Integrated Sound Level Meter |
Rion NL-31 / NL-52 |
Acoustic Calibrator |
Rion NC-73 |
The Action and
Limit levels of the noise monitoring are provided in Appendix D. The Event and
Action plan is presented in Appendix J.
The schedule for
construction noise monitoring in the reporting period is provided in Appendix E.
The monitoring
results for noise monitoring are summarized in Table 2.7. Monitoring
results are presented graphically in Appendix
G and detailed impact noise monitoring results are reported in the Forty-fourth to Forty-sixth Monthly EM&A Reports.
Table 2.7 Summary of Construction Noise Monitoring Results at NSR1A in
the Reporting Period
Month |
Average , dB(A), Leq
(30mins) |
Range, dB(A), Leq
(30mins) |
Limit Level, dB(A), Leq
(30mins) |
June 2017 |
62 |
61-62 |
75 |
July 2017 |
63 |
62-63 |
75 |
August 2017 |
63 |
61-64 |
75 |
The baseline
water quality monitoring undertaken by the HZMB Projects between 6 and 31
October 2011 included all monitoring stations except SR4a for the Project. Thus, the baseline monitoring results except
for station SR4a and Action/Limit Level presented in HZMB Baseline Monitoring
Report ([4])
are adopted for this Project. Baseline
water quality monitoring was conducted at station SR4a from 29 August to 24
September 2013.
Due to
Three-Runway System (3RS) marine construction works, an alternative water
quality control station CS(Mf)3(N) was proposed to
replace control station CS(Mf)3. The Proposal of Alternative Water Quality
Monitoring Station ([5]) was submitted to EPD on 31 March 2017 and granted
on 6 April 2017. Water quality monitoring at CS(Mf)3(N)
is undertaken since 2 May 2017. The
locations of the monitoring stations under the Contract are shown in Figures 2.3 and 2.4 and Table 2.8.
Results of water
quality monitoring for the period between June and July 2017 were adopted from
the published EM&A data of Contract
No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities – Reclamation Works ([6])([7]).
The locations of the monitoring stations covered by Contract No.
HY/2010/02 with those overlapped
with Contract No. HY/2012/07 are presented in Table 2.8.
Table 2.8 Locations of Water Quality Monitoring Stations and the
Corresponding Monitoring Requirements
Station
ID |
Type |
Coordinates |
*Parameters,
unit |
Depth |
Frequency |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(°C)
pH(pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
Dissolved Oxygen (DO) (mg/L and % of saturation) ·
Suspended Solid (SS) (mg/L) |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed.
If the water depth is less than 3m, mid-depth sampling only. If water depth less than 6m, mid-depth may
be omitted. |
Impact monitoring: 3 days per
week, at mid-flood and mid-ebb tides during the construction period of the
Contract. |
IS(Mf)16 |
Impact
Station (Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact
Station(Close to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive
receiver (Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive
receiver |
815247 |
818067 |
|||
SR4(N) |
Sensitive
receiver (Tai Ho) |
814705 |
817859 |
|||
CS(Mf)3(N) |
Control Station |
808814 |
822355 |
|||
CS(Mf)5 |
Control Station |
817990 |
821129 |
|||
Notes: In addition to the parameters presented
monitoring location/position, time, water depth, sampling depth, tidal
stages, weather conditions and any special phenomena or works underway nearby
were also recorded. Water Quality Monitoring Station CS(Mf)3
was relocated to CS(Mf)3(N) since 2 May 2017. Station SR4a is not covered by HY/2010/02. Data from Station SR4(N)
is considered representative of those from SR4a since they are located 50m
from each other and coral colonies, which is the SR concerned at SR4a, are
also presented along the seawall nearby SR4(N). |
Table 2.9 summarizes the equipment used in the impact water quality monitoring programme.
Table 2.9 Water Quality Monitoring Equipment
Equipment |
Brand and Model
|
Multi-parameters (Dissolved Oxygen, Salinity, Turbidity,
Temperature, pH) |
YSI ProDSS / YSI 6920
V2 Sonde |
|
|
Positioning Equipment |
Furuno GP-170 |
Water Depth Detector |
Lowrance Mark 5x / Garmin Striker 4 |
Water Sampler |
WildCo Vertical Alpha Bottles 1120-2.2L
/1120-3.2L Aquatic Research Instrument Vertical/Horizontal Point Water Sampler
2.2L / 3.0L |
|
|
Notes: Water quality monitoring equipment used
for water quality monitoring for the period between June and July 2017 could
be referred to the published Monthly EM&A Reports of Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge Hong Kong
Boundary Crossing Facilities – Reclamation Works. Available at
http://www.hzmbenpo.com/ |
The schedules
for water quality monitoring in the reporting quarter are provided in Appendix E ([8]). Water quality monitoring on 23 August 2017
was canceled due to adverse weather.
In this
reporting period, a total of 39 monitoring events for impact water quality
monitoring were conducted at monitoring stations in the reporting period. Monitoring results are presented graphically
in Appendix H and detailed impact water quality monitoring
results were reported in the Forty-fourth
to Forty-sixth Monthly EM&A
Reports.
Thirty (30)
Action Level and fourteen (14) Limit Level of Dissolved Oxygen (DO) exceedances
and one (1) Action Level of Suspended Solids (SS) exceedances were recorded for
water quality impact monitoring in the reporting period. Actions were taken in accordance with the
Event Action Plan as presented in Appendix J.
Impact dolphin
monitoring is required to be conducted by a qualified dolphin specialist team
to evaluate whether there have been any effects on the Indo-Pacific humpback
dolphin Sousa chinensis (i.e. Chinese White Dolphin) from
the Contract. In order to fulfil the
EM&A requirements and make good use of available resources, the on-going
impact line transect dolphin monitoring data collected by HyD’s
Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong
Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities on the monthly basis is adopted to avoid duplicates of survey
effort.
Table 2.10 summarizes the equipment used for the impact dolphin
monitoring.
Table 2.10 Dolphin Monitoring Equipment
Equipment |
Model |
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for
Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single
engine motor vessel with viewing platform 4.5m above water level |
Dolphin
monitoring should cover all transect lines in Northeast Lantau (NEL) and the
Northwest Lantau (NWL) survey areas twice per month throughout the entire
construction period. The monitoring data
should be compatible with, and should be made available for, long-term studies
of small cetacean ecology in Hong Kong. In
order to provide a suitable long-term dataset for comparison, identical
methodology and line transects employed in baseline dolphin monitoring was
followed in the impact dolphin monitoring.
The impact
dolphin monitoring was carried out in the NEL and NWL along the line transect
as depicted in Figure 2.5a and 2.5b. The co-ordinates of all transect lines are
shown in Table 2.11 and 2.12 below ([11]).
Table 2.11 Impact Dolphin Monitoring Line Transect Co-ordinates (June
–July 2017)
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
||
1 |
Start
Point |
804671 |
815456 |
13 |
Start
Point |
816506 |
819480 |
1 |
End
Point |
804671 |
831404 |
13 |
End
Point |
816506 |
824859 |
2 |
Start
Point |
805475 |
815913 |
14 |
Start
Point |
817537 |
820220 |
2 |
End
Point |
805477 |
826654 |
14 |
End
Point |
817537 |
824613 |
3 |
Start
Point |
806464 |
819435 |
15 |
Start
Point |
818568 |
820735 |
3 |
End
Point |
806464 |
822911 |
15 |
End
Point |
818568 |
824433 |
4 |
Start
Point |
807518 |
819771 |
16 |
Start
Point |
819532 |
821420 |
4 |
End
Point |
807518 |
829230 |
16 |
End
Point |
819532 |
824209 |
5 |
Start
Point |
808504 |
820220 |
17 |
Start
Point |
820451 |
822125 |
5 |
End
Point |
808504 |
828602 |
17 |
End
Point |
820451 |
823671 |
6 |
Start
Point |
809490 |
820466 |
18 |
Start
Point |
821504 |
822371 |
6 |
End
Point |
809490 |
825352 |
18 |
End
Point |
821504 |
823761 |
7 |
Start
Point |
810499 |
820880 |
19 |
Start
Point |
822513 |
823268 |
7 |
End
Point |
810499 |
824613 |
19 |
End
Point |
822513 |
824321 |
8 |
Start
Point |
811508 |
821123 |
20 |
Start
Point |
823477 |
823402 |
8 |
End
Point |
811508 |
824254 |
20 |
End
Point |
823477 |
824613 |
9 |
Start
Point |
812516 |
821303 |
21 |
Start
Point |
805476 |
827081 |
9 |
End
Point |
812516 |
824254 |
21 |
End
Point |
805476 |
830562 |
10 |
Start
Point |
813525 |
820872 |
22 |
Start
Point |
806464 |
824033 |
10 |
End
Point |
813525 |
824657 |
22 |
End
Point |
806464 |
829598 |
11 |
Start
Point |
814556 |
818853 |
23 |
Start
Point |
814559 |
821739 |
11 |
End
Point |
814556 |
820992 |
23 |
End
Point |
814559 |
824768 |
12 |
Start
Point |
815542 |
818807 |
|
|
|
|
12 |
End
Point |
815542 |
824882 |
|
|
|
|
Table 2.12 Impact Dolphin Monitoring Line Transect Co-ordinates (August
2017)
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
815456 |
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805476 |
820800 |
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805476 |
826654 |
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
821150 |
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
821500 |
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
821850 |
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
822150 |
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
822000* |
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
821123 |
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
821303 |
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
821176 |
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818853 |
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
24 |
Start Point |
805476 |
815900 |
12 |
End Point |
815542 |
824882 |
24 |
End Point |
805476 |
819100 |
The Action and Limit
levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented in Appendix J.
The dolphin
monitoring schedules for the reporting period are shown in Appendix E.
A total of 793.06
km
of survey effort was collected, with 97.8% of the total survey effort being
conducted under favourable weather conditions (i.e.
Beaufort Sea State 3 or below with good visibility). Among the two areas, 290.58 km and 502.48 km of survey
effort were conducted in NEL and NWL survey areas respectively. The total survey effort conducted on primary lines
was 575.14 km, while the effort on secondary lines was 217.92 km. Survey effort conducted on both primary and
secondary lines were considered as on-effort survey data. The survey efforts are summarized in Appendix I.
During the six
sets of monitoring surveys in June to August 2017, a total of twelve (12) groups of 34 Chinese White
Dolphins were sighted. All dolphin
sightings were made during on-effort, while eight of the twelve on-effort dolphin
sightings were made on primary lines. In
this quarterly period, all dolphin groups were sighted in NWL, no sighting of
dolphin was sighted in NEL. Summary
table of the dolphin sightings is shown in Appendix
II.
Encounter rates
of Chinese White Dolphins deduced from the survey effort and on-effort sighting
data from the primary transect lines under favourable
conditions (Beaufort 3 or below) in the reporting period with the results
presented in Tables 2.13 and 2.14.
Table 2.13 Individual Survey Event Encounter Rates
Survey Area |
Survey
period |
Encounter rate (STG) (no. of on-effort
dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI) (no. of dolphins
from all on-effort sightings per 100 km of survey effort) |
Primary
Lines Only |
Primary
Lines Only |
||
NEL |
Set 1: 14th/ 15th Jun 2017 |
0.0 |
0.0 |
Set 2: 20th / 26th Jun 2017 |
0.0 |
0.0 |
|
Set 3: 20th /24th Jul 2017 |
0.0 |
0.0 |
|
Set 4: 27th / 28th Jul 2017 |
0.0 |
0.0 |
|
Set 5: 7th / 15th Aug 2017 |
0.0 |
0.0 |
|
Set 6: 21st /31st Aug 2017 |
0.0 |
0.0 |
|
NWL |
Set 1: 14th/ 15th Jun 2017 |
0.00 |
0.00 |
Set 2: 20th / 26th Jun 2017 |
0.00 |
0.00 |
|
Set 3: 20th /24th Jul 2017 |
1.64 |
14.79 |
|
Set 4: 27th / 28th Jul 2017 |
0.00 |
0.00 |
|
Set 5: 7th / 15th Aug 2017 |
4.95 |
6.61 |
|
Set 6: 21st /31st Aug 2017 |
6.58 |
18.09 |
Note: Dolphin Encounter Rates are deduced from the six
sets of surveys (two surveys in each set) in the reporting period in Northeast
(NEL) and Northwest Lantau (NWL)
Table 2.14 Quarterly Average Encounter Rates
Survey Area |
Encounter rate (STG) (no. of on-effort dolphin sightings per 100 km of
survey effort) |
Encounter rate (ANI) (no. of dolphins from all on-effort sightings per
100 km of survey effort) |
||
June – August 2017 |
September -November 2011 |
June – August 2017 |
September -November 2011 |
|
Northeast
Lantau |
0.0 |
6.00 ± 5.05 |
0.0 |
22.19 ± 26.81 |
Northwest
Lantau |
2.20 ± 2.88 |
9.85 ± 5.85 |
6.58 ± 8.12 |
44.66 ± 29.85 |
Note: encounter
rates deduced from the baseline monitoring period (September – November 2011)
have been recalculated based only on survey effort and on-effort sighting data made
along the primary transect lines under favourable
conditions
Table 2.15 Comparison of Quarterly Average Group Sizes
|
Average Dolphin Group Size |
|
June – August 2017 |
September - November 2011 |
|
Overall |
2.83 ± 2.33 (n = 12) |
3.72 ± 3.13 (n = 66) |
Northeast Lantau |
--- |
3.18 ± 2.16 (n = 17) |
Northwest Lantau |
2.83 ± 2.33 (n = 12) |
3.92 ± 3.40 (n = 49) |
Although the
dolphins infrequently occurred along the alignment of TM-CLKL Southern Connection
Viaduct in the past and during the baseline monitoring period, it is apparent
that dolphin usage has been significantly reduced in both NEL and NWL, and many
individuals have shifted away from the important habitat around the Brothers
Islands.
Daily marine mammal exclusion zone monitoring was
undertaken during the period of marine works under this Contract. No sighting of Chinese White Dolphin was
recorded in the monitoring period during the exclusion zone monitoring.
Passive
Acoustic Monitoring (PAM) was decommissioned in this reporting period as no
marine piling works was carried out outside the daylight hours since September
2015. Daytime marine mammal exclusion
zone was still in effect to cater for temporary staging installation and
uninstallation works.
Site inspections
were carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures under the Contract. Thirteenth (13) site inspections were carried
out in the reporting quarter on 7, 14, 21 and 29 June 2017, 5, 12, 19 and 27 July 2017, 2, 9, 16, 24 and 31
August 2017.
Key observations
during the site inspections in this reporting period are summarized in Table 2.16.
Table 2.16 Specific Observations Identified during the Weekly Site
Inspection in this Reporting Period
Inspection
Date |
Location
& Environmental Observations |
Recommendations/
Remarks |
7
June
2017 |
Viaduct D (Pier D13) Accumulated general
refuse should be cleared regularly. Viaduct D (Pier D14) Drip tray under the
generator was observed not well plugged. Ramp D Chemical containers were
observed not placed in drip tray. |
Viaduct D (Pier D13) The Contractor was
reminded to clear accumulated general refuse. Viaduct D (Pier D14) The Contractor was
reminded to plug drip tray under the generator. Ramp D The Contractor was reminded to place chemical containers in drip tray. |
14 June 2017 |
Southern Landfall Portion A (Portion S-b) Chemical containers were
observed not placed in drip tray. Stagnant water inside
drip tray nearby the chemical containers should be cleared. |
Southern Landfall Portion A (Portion S-b) The Contractor was reminded to place chemical containers in drip tray. The Contractor was reminded to clear
stagnant water inside drip tray nearby the chemical containers. |
21 June 2017 |
Viaduct D (Pier D13) NRMM label should be displayed clearly on the
generator. Stagnant water inside
drip tray should be cleared. Viaduct B (Pier B16)
Exposed slope was observed not fully covered by
tarpaulin. Viaduct C (Pier C12)
Exposed stockpile was observed not fully covered
by tarpaulin. |
Viaduct D (Pier D13) The Contractor was reminded to display NRMM label
clearly on the generator. The Contractor was reminded to clear stagnant water
inside drip tray. Viaduct B (Pier B16)
The Contractor was reminded to fully cover exposed slope by tarpaulin. Viaduct C (Pier C12)
The Contractor was reminded to fully cover exposed stockpile by tarpaulin. |
29 June 2017 |
Viaduct E (Pier E6) Chemical containers were
observed not placed in drip tray. Stagnant water
inside drip tray should be cleared. Viaduct E (Pier E10) Chemical containers were
observed not placed in drip tray. |
Viaduct E (Pier E16) The Contractor was
reminded to place chemical containers in drip tray. The Contractor
was reminded to clear stagnant water inside drip tray. Viaduct E (Pier E10) The Contractor was
reminded to place chemical containers in drip tray. |
5
July
2017 |
Viaduct E (Pier E4) Chemical containers in
the deck were observed not placed in drip tray. NRMM label should be
provided on the generator. |
Viaduct E (Pier E4) The Contractor was
reminded to place chemical containers in drip tray. The Contractor was
reminded to provide NRMM label on the generator. |
12 July 2017 |
Southern Landfall Portion A (Portion S-c) Chemical container was
observed not placed in drip tray. |
Southern Landfall Portion A (Portion S-c) The Contractor was reminded to place chemical container in drip tray. |
19 July 2017 |
Viaduct E (Pier E12) General refuse should be cleared regularly. Viaduct E (Pier E11)
Chemical containers were observed not placed in
drip tray.
Air compressor was observed not fully placed in
drip tray. |
Viaduct E (Pier E12) The Contractor was reminded to clear general
refuse regularly. Viaduct E (Pier E11)
The Contractor was reminded to place chemical containers in drip tray.
The Contractor was reminded to fully place the air compressor in drip tray. |
27 July 2017 |
Ramp C (Area I) Chemical containers on
the deck were observed not placed in drip tray. General refuse should be cleared regularly. Viaduct C (Pier C15) Stockpile was
observed not being fully covered by tarpaulin. Ramp D (Area I) Chemical containers were
observed not placed in drip tray. Watering should be
provided on unpaved road. |
Ramp C (Area I) The Contractor was
reminded to place chemical containers on the deck in drip tray. The Contractor
was reminded to clear general
refuse regularly. Viaduct C (Pier C15) The Contractor was reminded
to fully cover stockpile by tarpaulin. Ramp D (Area I) The Contractor was
reminded to place chemical containers in drip tray. The Contractor was
reminded to provide watering on unpaved road. |
2
August
2017 |
Viaduct B (Pier B16) General refuse in the skip
should be cleared. Viaduct B (Pier B11) Chemical containers in
the deck were observed not placed in drip tray. |
Viaduct B (Pier B16) The Contractor was
reminded to clear general refuse in the skip. Viaduct B (Pier B11) The Contractor was
reminded to place chemical containers in drip tray. |
9 August 2017 |
Viaduct E (Pier E11) Chemical container was
observed not placed in drip tray. General refuse in the
skip should be cleared. |
Viaduct E (Pier E11) The Contractor was reminded to place chemical container in drip tray. The Contractor was
reminded to clear general refuse in the skip. |
16 August 2017 |
Southern Landfall Portion A (HKBCF Portion S-c) Watering on exposed area should be applied more
frequently. Chemical labels should be provided to the
chemical containers. |
Southern Landfall Portion A (HKBCF Portion S-c) The Contractor was reminded to apply watering on
exposed area.
The Contractor was reminded to provide chemical
labels to the chemical containers. |
24 August 2017 |
Viaduct E (Pier E11) Chemical container was observed not placed in drip tray. Stagnant water was observed inside drip tray. |
Viaduct E (Pier E11) The Contractor was reminded to place chemical container in drip tray. The Contractor was reminded to clear stagnant water inside drip tray. |
31 August 2017 |
Viaduct E (Pier E4) Chemical containers on
the deck were observed not placed in drip tray. General refuse should be cleared regularly. Southern Landfall Portion A (HKBCF Portion S-c) General refuse should be cleared regularly. |
Viaduct E (Pier E4) The Contractor was
reminded to place chemical containers on the deck in drip tray. The Contractor
was reminded to clear general
refuse regularly. Southern Landfall Portion A (HKBCF Portion S-c) The Contractor was
reminded to clear general
refuse regularly. |
Wastes generated
during this reporting period include mainly construction wastes (inert and
non-inert), recyclable materials, chemical waste and marine sediment. Reference has been made to the waste flow
table prepared by the Contractor (Appendix K). The quantities of different types of wastes
are summarized in Table 2.17.
Table 2.17 Quantities of Different Waste Generated in the Reporting Period
Month / Year |
Inert Construction Waste (a) (m3) |
Imported Fill (m3) |
Inert Construction Waste Re-used (m3) |
Non-inert Construction Waste (b) (kg) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
||||||||
Category L |
Category M |
||||||||||||||
June 2017 |
4,394 |
0 |
98 |
148,600 |
63 |
0 |
0 |
0 |
|
||||||
July 2017 |
4,921 |
0 |
696 |
159,980 |
91 |
800 |
1,056 |
0 |
|
||||||
August 2017 |
3,897 |
0 |
0 |
159,230 |
56 |
0 |
0 |
0 |
|
||||||
Total |
13,212 |
0 |
794 |
467,810 |
210 |
800 |
1,056 |
0 |
|
||||||
Notes: |
|||||||||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. |
|||||||||||||||
The Contractor was
advised to properly maintain on site C&D materials and waste collection,
sorting and recording system, dispose of C&D materials and wastes at
designated ground and maximize reuse/ recycle of C&D materials and
wastes. The Contractor was also reminded
to properly maintain the site tidiness and dispose of the wastes accumulated on
site regularly and properly.
For chemical waste containers, the Contractor was
reminded to treat properly and store temporarily in designated chemical waste
storage area on site in accordance with the Code
of Practice on the Packaging, Labelling and Storage of Chemical Wastes.
The status of
environmental licensing and permit is summarized in Table 2.18 below.
Table
2.18 Summary of Environmental Licensing and
Permit Status
License/ Permit |
License or Permit No. |
Date of
Issue |
Date of
Expiry |
License/
Permit Holder |
Remarks |
|||||||
Environmental Permit |
EP-353/2009/K |
11-Apr-16 |
N/A |
HyD |
Hong Kong Boundary Crossing
Facilities |
|
||||||
Environmental Permit |
EP-354/2009/D |
13-Mar-15 |
N/A |
HyD |
Tuen Mun-
Chek Lap Kok Link |
|
||||||
Construction Dust Notification |
361571 |
05-Jul-13 |
N/A |
GCL |
|
|
||||||
Construction Dust Notification |
362093 |
17-Jul-13 |
N/A |
GCL |
For Area 23 |
|
||||||
Chemical Waste Registration |
5213-951-G2380-17 |
12-Jun-14 |
N/A |
GCL |
Viaducts A, B, C, D & E |
|
||||||
Chemical Waste Registration |
5213-961-G2380-13 |
10-Oct-13 |
N/A |
GCL |
Chemical waste produced in
Contract No. HY/2012/07 (Area 1
adjacent to Cheng Tung Road, Siu Ho Wan) |
|
||||||
Chemical Waste Registration |
5213-961-G2380-14 |
10-Oct-13 |
N/A |
GCL |
Chemical waste produced in
Contract No. HY/2012/07 (Area 2
adjacent to Cheung Tung Road, Pak Mong Village) |
|
||||||
Chemical Waste Registration |
5213-974-G2588-03 |
04-Nov-13 |
N/A |
GCL |
Chemical waste produced in
Contract No. HY/2012/07 (WA5 adjacent
to Cheung Tung Road, Yam O) |
|
||||||
Construction
Waste Disposal Account |
7017735 |
10-Jul-13 |
N/A |
GCL |
- |
|
||||||
Construction
Waste Disposal Account |
7019470 |
03-Mar-14 |
N/A |
GCL |
Vessel CHIT Account |
|
||||||
Waste Water Discharge License |
WT00019017-2014 |
13-May-14 |
31-May-19 |
GCL |
Discharge for marine portion |
|
||||||
Waste Water Discharge License |
WT00019018-2014 |
13-May-14 |
31-May-19 |
GCL |
Discharge for land portion |
|
||||||
Construction Noise Permit for
night works and works in general holidays |
GW-RW0708-16 |
20-Dec-16 |
18-Jun-17 |
GCL |
General works at WA5 |
|
||||||
Construction Noise Permit for
night works and works in general holidays |
GW-RW0294-17 |
19-Jun-17 |
18-Dec-17 |
GCL |
General works at WA5 |
|
||||||
Construction Noise Permit for
night works and works in general holidays |
GW-RS1309-16 |
20-Dec-16 |
19-Jun-17 |
GCL |
Broad Permit for Whole Site Areas |
|
||||||
Construction Noise Permit for
night works and works in general holidays |
GW-RS0540-17 |
20-Jun-17 |
15-Dec-17 |
GCL |
Broad
Permit for Whole Site Areas |
|
||||||
Construction Noise Permit for night works and works in general
holidays |
GW-RS0408-17 |
11-May-17 |
30-Sep-17 |
GCL |
Pre-casted pile cap shell
installation at E8-E13 |
|
||||||
Construction Noise Permit
for night works and works in general holidays |
GW-RS0668-17 |
7-Aug-17 |
6-Feb-18 |
GCL |
Pre-casted pile cap shell
installation at E8-E13 |
|
||||||
Construction
Noise Permit for night works and works in general holidays |
GW-RS0456-17 |
31-May-17 |
31-Jul-17 |
GCL |
Broad
Permit for Segment Launching at Land Portion |
|
||||||
Construction
Noise Permit for night works and works in general holidays |
GW-RS0639-17 |
31-Jul-17 |
29-Sep-17 |
GCL |
Broad
Permit for Segment Launching at Land Portion |
|
||||||
Construction
Noise Permit for night works and works in general holidays |
GW-RS0688-17 |
17-Aug-17 |
31-Aug-17 |
GCL |
Contingency
plan for DN800T works at Tung Chung Seafront Road |
|
||||||
Construction
Noise Permit for percussive piling |
PP-RS0010-17 |
12-Jun-17 |
15-Sep-17 |
GCL |
Percussive piling at Portion
A |
|
||||||
Marine Dumping Permit |
EP/MD/17-153 |
01-Jan-17 |
30-Jun-17 |
GCL |
For dumping Type I sediment |
|
||||||
Marine
Dumping Permit |
EP/MD/18-031 |
01-Jul-17 |
31-Dec-17 |
GCL |
For
dumping Type I sediment |
|
||||||
Marine Dumping Permit |
EP/MD/17-196 |
01-Jul-17 |
31-Jul-17 |
GCL |
For dumping Type II sediment |
|
||||||
Marine Dumping Permit |
EP/MD/18-047 |
1-Aug-17 |
31-Aug-17 |
GCL |
For dumping Type I and Type
II sediment |
|
||||||
Thirty (30) Action Level and fourteen (14)
Limit Level of Dissolved Oxygen (DO) exceedances and one (1) Action Level of
Suspended Solids (SS) exceedances were recorded for water quality impact
monitoring in the reporting period. The exceedances were considered not related to this Contract upon further
investigation and the investigation report is presented in Appendix L.
Table 2.19 Comparison between Quarterly Mean and Ambient Mean Values of
Depth-averaged Suspended Solids
Station |
Baseline Mean |
Ambient Mean (a) |
Quarterly
Mean (June to August 2017) |
|||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|
CS(Mf)3(N) |
9.2 |
12.8 |
12.0 |
16.6 |
6.3 |
7.6 |
CS(Mf)5 |
9.2 |
11.5 |
11.9 |
14.9 |
6.0 |
5.3 |
SR4/SR4(N) |
10.3 |
12.3 |
13.4 |
16.0 |
7.8 |
9.3 |
SR4a |
9.1 |
9.8 |
11.9 |
12.7 |
9.2 |
9.9 |
IS8 |
11.3 |
13.5 |
14.6 |
17.6 |
6.9 |
8.3 |
IS(Mf)9 |
10.9 |
14.3 |
14.2 |
18.5 |
6.6 |
7.4 |
IS(Mf)16 |
11.4 |
10.3 |
14.8 |
13.4 |
7.6 |
6.1 |
Notes: |
||||||
(a) Ambient mean value is defined as a 30%
increase of the baseline mean value (b)
Water Quality
Monitoring Station CS(Mf)3 was relocated to
CS(Mf)3(N) since 2 May 2017. |
One (1) Limit Level
exceedance was recorded for impact dolphin monitoring in this reporting
quarter. Following the review of the
monitoring data and marine works details as per the procedure stipulated in the
Event and Action Plan of the Updated EM&A Manual, no unacceptable impact
was associated with the construction works under this Contract that may have
affected the dolphin usage in the North Lantau region. Investigation findings were detailed in Appendix L.
There was no
environmental complaint, notification of summons or successful prosecution
recorded in the reporting period.
Statistics on
complaint, notification of summons of successful prosecution are summarized in Appendix L.
September 2017
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Launching gantry operation;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
October 2017
Land-based Works
·
Pier construction;
·
Re-alignment of Cheung Tung Road;
·
Road works along North Lantau Highway;
·
Launching gantry operation;
·
Installation of pier head and deck segments; and
·
Slope work of Viaducts A, B & C.
November 2017
· Pier construction;
· Re-alignment of
Cheung Tung Road;
· Road works along
North Lantau Highway;
· Launching gantry
operation;
· Installation of
pier head and deck segments; and
· Slope work
of Viaducts A, B & C.
Potential
environmental impacts arising from the above upcoming construction activities are
mainly associated with air quality, noise, marine water quality, marine ecology
and waste management issues.
Impact
monitoring for air quality, noise, marine water quality and dolphin monitoring
are scheduled to continue for the next reporting period.
The monitoring programme has been reviewed and was considered as adequate
to cater for the nature of works in progress.
The Fifteenth Quarterly
EM&A Report presents the findings of the EM&A activities undertaken
during the period from 1 June to 31 August 2017, in accordance with the Updated
EM&A Manual and the requirements of the Environmental
Permits (EP-354/2009/D and EP-353/2009/K).
Neither Action
Level nor Limit Level exceedances were observed for air quality and noise
impact monitoring in this reporting period.
Thirty (30) Action
Level and fourteen (14) Limit Level of Dissolved Oxygen (DO) exceedances and
one (1) Action Level of Suspended Solids (SS) exceedances were recorded for water
quality impact monitoring in the reporting period. Investigation findings suggested the observed
water quality exceedances were not related to the works under this Contract.
A total of twelve
(12) groups of thirty-four (34) Chinese White Dolphins were sighted during the
six sets of survey from June to August 2017.
One (1) Limit Level exceedance was recorded for the quarterly dolphin
monitoring data between June and August 2017, no unacceptable impact from the
activities of this Contract on Chinese White Dolphins was noticeable from the
general observations. It is critical to
monitor the dolphin usage in North Lantau region in the upcoming quarters, to
determine whether the dolphins are continuously affected by the various
construction activities in relation to the HZMB-related works, and whether
suitable mitigation measure can be applied to revert the situation.
Environmental
site inspection was carried out 13 times in the reporting period. Recommendations on remedial actions were
given to the Contractor for the deficiencies identified during the site audits.
There was no
environmental complaint, notification of summons or successful prosecution
recorded in the reporting period.
The monitoring programme has been reviewed and was considered as adequate
to cater for the nature of works in progress.
Change to the monitoring programme was thus not recommended at this
stage. The monitoring programme will be
evaluated as appropriate in the next reporting period. The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
([1]) Results of impact water quality
monitoring were adopted from the published EM&A data of Contract No. HY/2010/02 HKBCF- Reclamation Works.
Available at: http://www.hzmbenpo.com/
([2]) Agreement No. CE 35/2011 (EP) Baseline
Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation. Baseline Environmental Monitoring Report
(Version C). Submitted on 8 March 2012
and subsequently approved by EPD.
(1) Agreement No. CE 35/2011 (EP)
Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong
Kong Projects - Investigation. Baseline
Environmental Monitoring Report (Version C).
Submitted on 8 March 2012 and subsequently approved by EPD.
([4])
Agreement No. CE 35/2011 (EP)
Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong
Kong Projects - Investigation. Baseline
Environmental Monitoring Report (Version C).
Submitted on 8 March 2012 and subsequently approved by EPD.
([5]) The Proposal of Alternative Water Quality
Monitoring Station with the verification letter from IEC was submitted to EPD on 31 March 2017, and subsequently
replied with no objection on.6 April 2017.
([6])
Published EM&A data for impact water
quality monitoring by Contract No. HY/2010/02 are available at: http://www.hzmbenpo.com/
([7])
Technical issues have been observed from
impact monitoring of the Contract and thus published information is adopted from Contract No. HY/2010/02
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Reclamation Works.
([8])
The schedules for water quality monitoring for the
period between June and July 2017 could be referred to the published Monthly EM&A
Reports of Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Reclamation
Works. Available at
http://www.hzmbenpo.com/
([9]) Published
EM&A data for impact water quality monitoring by Contract No. HY/2010/02
are available at: http://www.hzmbenpo.com/