1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Dolphin monitoring
2.5 Coral Monitoring
2.6 EM&A Site inspection
2.7 Waste Management Status
2.8 Environmental Licenses and
Permits
2.9 Implementation Status of
Environmental Mitigation Measures
2.10 Summary of Exceedances of the
Environmental Quality Performance Limit
2.11 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Programme for
the Coming Months
3.2 Key Issues for the Coming
Month
3.3 Monitoring Schedule for the
Coming Month
List
of Tables
Table 1.1 |
|
Table 2.1 |
|
Table
2.2 |
|
Table
2.3 |
Summary
of 1-hour TSP Monitoring Results in the Reporting Period |
Table
2.4 |
Summary
of 24-hour TSP Monitoring Results in the Reporting Period |
Table
2.5 |
|
Table 2.6 |
|
Table
2.7 |
Summary
of Construction Noise Monitoring Results in the Reporting Period |
Table 2.8 |
Locations
of Impact Water Quality Monitoring Stations and its Corresponding Monitoring Requirements |
Table 2.9 |
|
Table
2.10 |
|
Table
2.11 |
|
Table
2.12 |
|
Table
2.13 |
|
Table
2.14 |
Specific
Observations and Recommendations during the Weekly Site Inspection in this
Reporting Month |
Table
2.15 |
List
of Figures
Figure 1.1 |
|
Figure 1.2 |
|
Figure 1.3 |
|
Figure 1.4 |
|
Figure 1.5 |
|
Figure 1.6 |
|
Figure 1.7 |
|
Figure 1.8 |
|
Figure 1.9 |
|
Figure 1.10 |
|
Figure 1.11 |
|
Figure 1.12 |
|
Figure 1.13 |
Environmental Sensitive
Receivers in the Vicinity of Contract No. HY/2012/07 |
Figure 2.1 |
|
Figure 2.2 |
|
Figure 2.3 |
|
Figure 2.4 |
|
Figure 2.5 |
Locations of Dolphin
Sightings during Impact Dolphin Monitoring Survey |
Figure 2.6 |
List
of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule
of Environmental Mitigation Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
Impact Air Quality
Monitoring Results and Graphical Presentation |
Appendix H |
|
Appendix I |
|
Appendix J |
Impact Water Quality
Monitoring Results and Graphical Presentation |
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
Under Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern
Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker
(IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Another application
for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.
The
construction phase of the Contract commenced on 31 October 2013 and will be
tentatively be completed by 2018.
The impact monitoring of the EM&A programme,
including air quality, noise, water quality and marine ecological monitoring as
well as environmental site inspections, commenced on 31 October 2013.
This
is the fifth monthly EM&A report presenting the EM&A works carried out
during the period from 1 to 31 March 2014 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
Marine-based
Works
¡P Marine
piling platform installation;
¡P Marine
Piling at Viaduct B;
¡P Construction
of rockfill platform at Viaduct D landing; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Satellite
container offices erection along seawall;
¡P Fence
installation and relocation of Area 2, Viaduct A, B, C & D;
¡P Land
Piling at Viaduct B;
¡P Piling
platform installation for Viaducts B, D & E;
¡P Additional
land ground investigation (GI), trial pits & laboratory testing;
¡P Utility
surveys; and
¡P Slope
work of 9SE-B/C8 and 9SE-B/C9.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour TSP
monitoring 5
sessions
1-hour TSP
monitoring 5
sessions
Noise
monitoring 5
sessions
Impact Water
Quality Monitoring 13
sessions
Impact dolphin
monitoring 2
sessions
Joint
Environmental site inspection 4
sessions
Breaches of Action and Limit Levels for Air Quality
No exceedance of Action and Limit Levels was recorded for impact
air quality monitoring in the reporting month.
Breaches of Action and Limit Levels for Noise
No exceedance of Action and Limit Levels was recorded for
construction noise monitoring in the reporting month.
Breaches of Action and Limit Levels for Water Quality
No exceedance of Action and Limit Levels was recorded for
impact water quality monitoring in the reporting month.
Impact Dolphin Monitoring
During this
month of dolphin monitoring, no unacceptable impact from the construction activities
of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins
was noticeable from general observations.
Due to monthly
variation in dolphin occurrence within the study area, it would be more
appropriate to draw conclusion on whether any impacts on dolphins have been
detected related to the construction activities of the TM-CLKL Southern
Connection Viaduct Section in the quarterly EM&A reports, where comparison
on distribution, group size and encounter rates of dolphins between the
quarterly impact monitoring period and baseline monitoring period will be made.
Daily
marine mammal exclusion zone monitoring was undertaken. No sighting of the Indo-Pacific humpback
dolphin Sousa chinensis
was recorded in March 2014 during the exclusion zone monitoring.
Environmental Complaints, Non-compliance & Summons
No complaint,
notification of summons and successful prosecution was received in the
reporting month.
Reporting Change
There was no
reporting change required in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be
undertaken in the next monitoring period of April 2014 include the following:
Marine
Works
¡P Marine
piling platform installation;
¡P Marine
piling at Viaduct B;
¡P Construction
of rockfill platform at Viaduct D landing; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Satellite
container offices erection along seawall;
¡P Fence
installation and relocation of Area 2, Viaducts A, B, C & D;
¡P Land
piling at Viaduct B, C and E;
¡P Piling
platform installation for Viaducts B, D & E;
¡P Additional
land ground investigation (GI), trial pits & laboratory testing;
¡P Utility
surveys; and
¡P Slope
work at 9SE-B/C8 and 9SE-B/C9.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of April 2014 are mainly associated with dust, noise,
marine water quality, marine ecology and waste management issues.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau
Highway would be operating beyond capacity after 2016. This forecast has been based on the
estimated increase in cross boundary traffic, developments in the Northwest New
Territories (NWNT), and possible developments in North Lantau,
including the Airport developments, the Lantau
Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order to cope with the anticipated
traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun
¡V Chek Lap Kok Link
(TM-CLKL) and Tuen Mun
Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007) and
the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The
EIA Report was submitted under the Environmental Impact Assessment Ordinance
(EIAO) in August 2009. Subsequent
to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an
Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of
Environmental Protection (DEP) on 4 November 2009, and EP variation
(EP-354/2009A) was issued on 8 December 2010.
Under
Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Another application for variation of
environmental permit (VEP) (EP-354/2009/B)
was granted on 28 January 2014.
The
organization structure of the Contract is shown in Appendix A.
The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident
Engineer |
Kingman Chan |
3691 3950 |
3691 2899 |
|
|
|
|
|
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465 2888 |
3465 2899 |
IEC |
Tony Cheng |
3465 2888 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
Marine-based
Works
¡P Marine
piling platform installation;
¡P Marine
Piling at Viaduct B;
¡P Construction
of rockfill platform at Viaduct D landing; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Satellite
container offices erection along seawall;
¡P Fence
installation and relocation of Area 2, Viaduct A, B, C & D;
¡P Land
Piling at Viaduct B;
¡P Piling
platform installation for Viaducts B, D & E;
¡P Additional
land ground investigation (GI), trial pits & laboratory testing;
¡P Utility
surveys; and
¡P Slope
work of 9SE-B/C8 and 9SE-B/C9.
The EM&A programme required environmental monitoring for air
quality, noise, water quality and marine ecology as well as environmental site
inspections for air quality, noise, water quality, waste management, marine
ecology and landscape and visual impacts.
The EM&A requirements and related findings for each component are summarized
in the following sections.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
Description |
Monitoring Dates |
ASR 8 |
Pak Mong Village Watch Tower |
Rooftop of
the premise |
6, 12, 18,
24, 28 March 2014 |
ASR 8A |
Area 4 |
On ground at
the Area 4 |
Table 2.2 Air Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170) |
Wind Anemometer |
Global Water: Wind Speed Sensor WE550, Wind Direction Sensor WE570 |
Table 2.3 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
120 |
58
- 240 |
394 |
500 |
ASR
8 |
118 |
70
- 175 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
56 |
37
- 83 |
178 |
260 |
ASR
8 |
64 |
45
- 83 |
178 |
260 |
All
1-hour and 24-hour TSP results were below the Action and Limit level at all
monitoring locations in the reporting period. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Noise
monitoring was performed on 6, 12, 18, 24 and 28 March
2014 using sound level meter at the designated monitoring station NSR 1 (Figure 2.2; Table 2.5) in accordance with the
requirements stipulated in the Updated EM&A Manual. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Details of the equipment deployed are provided
in Table 2.6. Copies of the calibration certificates
for the equipment are presented in Appendix E.
Table 2.5 Location
of Impact Noise Monitoring Station
Monitoring Station |
Location |
Description |
Parameter |
Frequency and Duration |
Monitoring Dates |
NSR 1 |
Pak Mong Village Watch Tower |
Rooftop of
the premise |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10
and L90 would be recorded. |
At least
once per week |
6, 12, 18,
24, 28 March 2014 |
Table 2.6 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion
NL-31 |
Acoustic
Calibrator |
Rion
NC-73 |
Table 2.7 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Average , dB(A), Leq
(30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq
(30mins) |
NSR
1 |
59 |
58
- 60 |
75 |
Station ID |
Type |
Coordinates |
*Parameters, unit |
Frequency |
Depth |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH(pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) ¡P SS (mg/L) |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract |
3 water depths: 1m below
sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth will be omitted |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station(Close
to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
*Notes: |
Table
2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
DO, Temperature meter and Salinity |
YSI Pro2030 |
1 |
Turbidimeter |
HACH Model 2100Q |
1 |
pH meter |
HANNA HI8314 |
1 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
1 |
Water Depth Detector |
Speedtech Instrument SM-5 |
1 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
1 |
No
Action and Limit level exceedance was recorded at all
monitoring stations for impact water quality monitoring in the reporting month,
during which marine piling platform installation, marine piling at Viaduct B
and rockfill platform construction at Viaduct D
landing were the major marine construction works involved. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Table
2.10 Dolphin Monitoring Equipment
Equipment |
Model |
|
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single engine motor vessel with viewing platform 4.5m above
water level |
|
Table
2.11 Impact Dolphin Monitoring Line Transect
Co-ordinates
Line
No. |
Easting |
Northing |
|
Line
No. |
Easting |
Northing |
||
1 |
Start
Point |
804671 |
814577 |
|
13 |
Start
Point |
816506 |
819480 |
1 |
End
Point |
804671 |
831404 |
|
13 |
End
Point |
816506 |
824859 |
2 |
Start
Point |
805475 |
815457 |
|
14 |
Start
Point |
817537 |
820220 |
2 |
End
Point |
805477 |
826654 |
|
14 |
End
Point |
817537 |
824613 |
3 |
Start
Point |
806464 |
819435 |
|
15 |
Start
Point |
818568 |
820735 |
3 |
End
Point |
806464 |
822911 |
|
15 |
End
Point |
818568 |
824433 |
4 |
Start
Point |
807518 |
819771 |
|
16 |
Start
Point |
819532 |
821420 |
4 |
End
Point |
807518 |
829230 |
|
16 |
End
Point |
819532 |
824209 |
5 |
Start
Point |
808504 |
820220 |
|
17 |
Start
Point |
820451 |
822125 |
5 |
End
Point |
808504 |
828602 |
|
17 |
End
Point |
820451 |
823671 |
6 |
Start
Point |
809490 |
820466 |
|
18 |
Start
Point |
821504 |
822371 |
6 |
End
Point |
809490 |
825352 |
|
18 |
End
Point |
821504 |
823761 |
7 |
Start
Point |
810499 |
820690 |
|
19 |
Start
Point |
822513 |
823268 |
7 |
End
Point |
810499 |
824613 |
|
19 |
End
Point |
822513 |
824321 |
8 |
Start
Point |
811508 |
820847 |
|
20 |
Start
Point |
823477 |
823402 |
8 |
End
Point |
811508 |
824254 |
|
20 |
End
Point |
823477 |
824613 |
9 |
Start
Point |
812516 |
820892 |
|
21 |
Start
Point |
805476 |
827081 |
9 |
End
Point |
812516 |
824254 |
|
21 |
End
Point |
805476 |
830562 |
10 |
Start
Point |
813525 |
820872 |
|
22 |
Start
Point |
806464 |
824033 |
10 |
End
Point |
813525 |
824657 |
|
22 |
End
Point |
806464 |
829598 |
11 |
Start
Point |
814556 |
818449 |
|
23 |
Start
Point |
814559 |
821739 |
11 |
End
Point |
814556 |
820992 |
|
23 |
End
Point |
814559 |
824768 |
12 |
Start
Point |
815542 |
818807 |
|
|
|
|
|
12 |
End
Point |
815542 |
824882 |
|
|
|
|
|
The action and
limit levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented
in Appendix L.
A
total of 14 groups
of 43 Chinese White Dolphin sightings were recorded
during the two sets
of surveys in March 2014. All
sightings were made in NWL during the two sets of surveys in March,
with no dolphin being sighted at all in NEL. All except two sightings were
made on primary lines during on-effort search, and none of
the dolphin groups was associated with operating fishing vessel.
The
majority of these dolphin sightings in March 2014 were made at the northwestern
portion of NWL survey area, especially to the north of Lung Kwu
Chau. Another two sightings were
made at the north of the airport and between the River Trade Terminal and
airport platform respectively. The
distribution of dolphin sightings during the reporting month is shown in Figure 2.5.
Encounter
rates of Chinese White Dolphins are deduced from the survey effort and
on-effort sighting data made under favourable
conditions (Beaufort 3 or below with good visibility) in March 2014 with the
results presented in Tables 2.12 and 2.13.
Table 2.12 Individual Survey
Event Encounter Rates
|
|
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
|
|
Primary
Lines Only |
Primary
Lines Only |
NEL |
Set 1: Mar
5th/ 11th |
0.0 |
0.0 |
|
Set 2: Mar
17th/ 25th |
0.0 |
0.0 |
NWL |
Set 1: Mar
5th/ 11th
|
6.4 |
23.6 |
|
Set 2: Mar
17th/ 25th |
13.2 |
24.8 |
Note: Dolphin
Encounter Rates are deduced from the two sets of surveys ( ie two Surveys in each set) in March 2014 in Northeast
(NEL) and Northwest Lantau (NWL) |
Table 2.13 Monthly Average
Encounter Rates
|
Encounter rate (STG)
(no. of on-effort dolphin sightings per 100 km of
survey effort) |
Encounter rate (ANI) (no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
||
Primary Lines Only |
Both Primary and Secondary
Lines |
Primary Lines Only |
Both Primary and Secondary
Lines |
|
Northeast Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest Lantau |
10.4 |
8.6 |
24.3 |
19.9 |
Note: Overall dolphin encounter rates (sightings per
100km of survey effort) from all four surveys are conducted in March 2014 on
primary lines only as well as both primary lines and secondary lines in
Northeast and Northwest Lantau
Daily 250 m marine
mammal exclusion zone monitoring was undertaken during the period of dredging
activities being undertaken. No sighting of Indo-Pacific humpback
dolphin Sousa chinensis
were recorded in March 2014 during the exclusion zone monitoring.
Marine bored
piling monitoring programme for dolphins (ie Land-based Theodolite Tracking, Underwater Noise
Monitoring and Acoustic Behavioural Monitoring) was
undertaken since 3 March 2014. No
sightings of Indo-Pacific humpback dolphins Sousa chinensis were
recorded during the bored piling monitoring in March 2014. The monitoring schedule for bored piling
monitoring in March 2014 is presented in Appendix F.
No
Post-Translocation Monitoring Exercise was conducted in the reporting month in March
2014.
Table 2.14 Specific
Observations and Recommendations during the Weekly Site Inspection in this
Reporting Month
Inspection Date |
Observations |
Remarks |
5 March 2014 |
Stoppers of two drip trays were missing at seafront
site.
Several chemical drums were not placed in drip tray. |
The
Contractor was reminded to replace the stopper. The
Contractor was reminded to place them properly and immediate rectification
has been done accordingly. |
12
March 2014 |
Some
oil trace was observed around one of the bored piles with unidentified
source. |
The
Contractor carried out immediate rectification action by deploying absorbent
to absorb the floating oil trace. |
19 March
2014 |
Watering
programme was recommended to be carried out more
regularly to suppress dust. |
The
Contractor was reminded to carry out watering programme
or dust-suppression measures more regularly. |
26
March 2014 |
Oil
stain was observed underneath a vibration hammer at B1. Five
cans of chemicals were placed along the road of the rockfill
platform without any drip trays. |
Immediate
rectification action was undertaken by the Contractor to absorb the oil
stain. The
Contractor was reminded to place them properly in timely manner. |
The Contractor
has rectified all observations as identified during environmental site inspection
in the reporting month.
The status of
environmental licensing and permit is summarized in Table 2.15 below.
Table 2.15 Summary of Environmental Licensing and
Permit Status
Statutory Reference |
License/
Permit |
License
or Permit No. |
Date
of Issue |
Date
of Expiry |
License/ Permit Holder |
Remarks |
EIAO |
Environmental Permit |
EP-354/2009/A |
8 Dec 2010 |
NA |
HyD |
Tuen Mun- Chek Lap Kok Link |
EIAO |
Environmental Permit |
EP-354/2009/B |
28 Jan 2014 |
NA |
HyD |
Tuen Mun- Chek Lap Kok Link |
APCO |
Construction Dust Notification |
361571 |
5 Jul 2013 |
NA |
GCL |
- |
APCO |
Construction Dust Notification |
362093 |
17 Jul 2013 |
NA |
GCL |
for Area 23 |
WDO |
Billing Account for Disposal |
7017735 |
10 Jul 2013 |
End of Project |
GCL |
- |
WDO |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
NA |
GCL |
Waste disposal in Contract HY/2012/07 |
WPCO |
Waste Water Discharge License |
Nil |
Application Ref. 368337 |
NA |
GCL |
Discharge for discharge points for Viaduct A & B |
NCO |
Construction Noise Permit |
Nil |
Application in process |
NA |
GCL |
For Piling Works |
NCO |
Construction Noise Permit |
GW-RW0660-13 |
27 Sep 2013 |
02 Feb 2014 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1129-13 |
31 Oct 2013 |
30 Apr 2014 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1186-13 |
23 Oct 2013 |
24 Dec 2013 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1187-13 |
24 Oct 2013 |
28 Feb 2014 |
GCL |
For night |
NCO |
Construction Noise Permit |
GW-RW0925-13 |
19 Dec 2013 |
17 Apr 2014 |
GCL |
Renewal of WA5 site office erection |
NCO |
Construction Noise Permit |
GW-RS1423-13 |
11 Dec 2013 |
30 Apr 2014 |
GCL |
Renewal for marine portion |
NCO |
Construction Noise Permit |
GW-RS1413-13 |
17 Dec 2013 |
26 Mar 2014 |
GCL |
For loading and unloading on NLH near viaduct A & B |
NCO |
Construction Noise Permit |
GW-RS0034-14 |
14 Jan 2014 |
29 Mar 2014 |
GCL |
For night works and works in general holiday |
NCO |
Construction Noise Permit |
GW-RW0123-14 |
27 Feb 2014 |
27 Aug 2014 |
GCL |
For night works and works in general holiday |
NCO |
Construction Noise Permit |
GW-RS0236-14 |
27 Mar 2014 |
14 May 2014 |
GCL |
For loading & unloading on NLH near Viaduct A & B |
NCO |
Construction Noise Permit |
GW-RS0226-14 |
30 Mar 2014 |
29 Sep 2014 |
GCL |
For loading & unloading on NLH near Viaduct D |
NCO |
Construction Noise Permit |
GW-RS0280-14 |
31 Mar 2014 |
31 May 2014 |
GCL |
For excavation at Pier B9 |
|
|
|
|
|
|
|
DASO |
Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal) |
(4) in EP/MD/14-075 |
25 Sep 2013 |
NA |
GCL |
- |
DASO |
Marine Dumping Permit |
EP/MD/14-075 |
28 January 2014 |
27 July 2014 |
GCL |
For dumping Type I Sediment |
DASO |
Marine Dumping Permit |
EP/MD/14-155 |
1 April 2014 |
30 April 2014 |
GCL |
For dumping Type I (Dedicated Site) and Type II Sediment |
Note: Statutory Reference: EIAO
¡V Environmental Impact Assessment Ordinance; NCO ¡V Noise Control Ordinance; APCO
¡V Air Pollution Control Ordinance; WDO ¡V Waste Disposal Ordinance; WPCO ¡V
Water Pollution Control Ordinance; DASO ¡V Dumping At Sea Ordinance. License/ Permit Holder: HyD ¡V Highway Department; GCL ¡V Gammon Construction
Limited. |
Marine
Works
¡P Marine
piling platform installation;
¡P Marine
piling at Viaduct B;
¡P Construction
of rockfill platform at Viaduct D landing; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Satellite
container offices erection along seawall;
¡P Fence
installation and relocation of Area 2, Viaducts A, B, C & D;
¡P Land
piling at Viaduct B, C and E;
¡P Piling
platform installation for Viaducts B, D & E;
¡P Additional
land ground investigation (GI), trial pits & laboratory testing;
¡P Utility
surveys; and
¡P Slope
work at 9SE-B/C8 and 9SE-B/C9.
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of April 2014 are mainly associated with dust, noise,
marine water quality, marine ecology and waste management issues.
This Fifth Monthly
EM&A Report presents the findings of the EM&A activities undertaken
during the period from 1 to 31 March 2014, in accordance with the Updated
EM&A Manual and the requirements of EP-354/2009/A.
A total of fourteen
(14) groups of forty-three (43) dolphin sightings were recorded during the two sets of
surveys. All sightings were made in NWL during
the two sets of surveys in March, with no dolphin being sighted at all in NEL. During this reporting
period of dolphin monitoring, no unacceptable impact from the construction activities
of the TM-CLKL Southern Connection Viaduct Section on Chinese
White Dolphins was noticeable from general observations.
The ET will
keep track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation
measures.