Table of Contents

                       

                        Executive Summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Scope of Report                                                                   

1.3                   Organization Structure                                                 

1.4                   Summary of Construction Works                              

2                      EM&A Results                                                                         

2.1                   Air quality                                                                               

2.2                   Noise Monitoring                                                                  

2.3                   Water Quality Monitoring                                              

2.4                   Dolphin monitoring                                                            

2.5                   Coral Monitoring                                                                

2.6                   EM&A Site inspection                                                           

2.7                   Waste Management Status                                             

2.8                   Environmental Licenses and Permits                        

2.9                   Implementation Status of Environmental Mitigation Measures  

2.10                 Summary of Exceedances of the Environmental Quality Performance Limit                                                                                                       

2.11                 Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                         

3                      Future Key Issues                                                                

3.1                   Construction Programme for the Coming Months

3.2                   Key Issues for the Coming Month                                

3.3                   Monitoring Schedule for the Coming Month        

4                      Conclusions                                                                           

 


List of Tables

Table 1.1

Contact Information of Key Personnel

Table 2.1

Locations of Impact Air Quality Monitoring Stations

Table 2.2

Air Quality Monitoring Equipment

Table 2.3

Summary of 1-hour TSP Monitoring Results in the Reporting Period

Table 2.4

Summary of 24-hour TSP Monitoring Results in the Reporting Period

Table 2.5

Location of Impact Noise Monitoring Station

Table 2.6

Noise Monitoring Equipment

Table 2.7

Summary of Construction Noise Monitoring Results in the Reporting Period

Table 2.8

Locations of Impact Water Quality Monitoring Stations and its Corresponding Monitoring Requirements

Table 2.9

Water Quality Monitoring Equipment

Table 2.10

Dolphin Monitoring Equipment

Table 2.11

Impact Dolphin Monitoring Line Transect Co-ordinates

Table 2.12

Individual Survey Event Encounter Rates

Table 2.13

Monthly Average Encounter Rates

Table 2.14

Specific Observations and Recommendations during the Weekly Site Inspection in this Reporting Month

Table 2.15

Summary of Environmental Licensing and Permit Status



List of Figures

Figure 1.1

General Project Layout Plan

Figure 1.2

Location Plan and Key Plan

Figure 1.3

General Layout

Figure 1.4

Proposed Ground Investigation Plan (Sheet 1 of 8)

Figure 1.5

Proposed Ground Investigation Plan (Sheet 2 of 8)

Figure 1.6

Proposed Ground Investigation Plan (Sheet 3 of 8)

Figure 1.7

Proposed Ground Investigation Plan (Sheet 4 of 8)

Figure 1.8

Proposed Ground Investigation Plan (Sheet 5 of 8)

Figure 1.9

Proposed Ground Investigation Plan (Sheet 6 of 8)

Figure 1.10

Works Area and Hoarding Plan (Sheet 1 of 2)

Figure 1.11

Works Area and Hoarding Plan (Sheet 2 of 2)

Figure 1.12

Location of Area 4

Figure 1.13

Environmental Sensitive Receivers in the Vicinity of Contract No. HY/2012/07

Figure 2.1

Locations of Impact Air Quality Monitoring Stations

Figure 2.2

Locations of Impact Noise Monitoring Station

Figure 2.3

Locations of Impact Water Quality Stations

Figure 2.4

Line Transects for Impact Dolphin Monitoring Survey

Figure 2.5

Locations of Dolphin Sightings during Impact Dolphin Monitoring Survey

Figure 2.6

Environmental Complaint Handling Procedure

           

List of Appendices

Appendix A

Project Organization for Environmental Works

Appendix B

Three Month Rolling Construction Programmes

Appendix C

Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D

Summary of Action and Limit Levels

Appendix E

Calibration Certificates of Monitoring Equipment

Appendix F

EM&A Monitoring Schedules

Appendix G

Impact Air Quality Monitoring Results and Graphical Presentation

Appendix H

Meteorological Data for the Reporting Month

Appendix I

Impact Noise Monitoring Results and Graphical Presentation

Appendix J

Impact Water Quality Monitoring Results and Graphical Presentation

Appendix K

Impact Dolphin Monitoring Survey Results

Appendix L

Event Action Plan

Appendix M

Monthly Summary of Waste Flow Table

Appendix N

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

           

           

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.   Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the fifth monthly EM&A report presenting the EM&A works carried out during the period from 1 to 31 March 2014 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

Marine-based Works

¡P      Marine piling platform installation;

¡P      Marine Piling at Viaduct B;

¡P      Construction of rockfill platform at Viaduct D landing; and

¡P      Additional marine ground investigation (GI) and laboratory testing.

 

Land-based Works

¡P      Satellite container offices erection along seawall;

¡P      Fence installation and relocation of Area 2, Viaduct A, B, C & D;

¡P      Land Piling at Viaduct B;

¡P      Piling platform installation for Viaducts B, D & E;

¡P      Additional land ground investigation (GI), trial pits & laboratory testing;

¡P      Utility surveys; and

¡P      Slope work of 9SE-B/C8 and 9SE-B/C9.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                       5 sessions

1-hour TSP monitoring                                   5 sessions

Noise monitoring                                   5 sessions

Impact Water Quality Monitoring                   13 sessions

Impact dolphin monitoring                     2 sessions

Joint Environmental site inspection      4 sessions

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Levels was recorded for impact air quality monitoring in the reporting month.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting month. 

Breaches of Action and Limit Levels for Water Quality

No exceedance of Action and Limit Levels was recorded for impact water quality monitoring in the reporting month. 

Impact Dolphin Monitoring

During this month of dolphin monitoring, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations.  Due to monthly variation in dolphin occurrence within the study area, it would be more appropriate to draw conclusion on whether any impacts on dolphins have been detected related to the construction activities of the TM-CLKL Southern Connection Viaduct Section in the quarterly EM&A reports, where comparison on distribution, group size and encounter rates of dolphins between the quarterly impact monitoring period and baseline monitoring period will be made.

Daily marine mammal exclusion zone monitoring was undertaken.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis was recorded in March 2014 during the exclusion zone monitoring.

Environmental Complaints, Non-compliance & Summons

No complaint, notification of summons and successful prosecution was received in the reporting month.

Reporting Change

There was no reporting change required in the reporting period.


Upcoming Works for the Next Reporting Period

Works to be undertaken in the next monitoring period of April 2014 include the following:

Marine Works

¡P      Marine piling platform installation;

¡P      Marine piling at Viaduct B;

¡P      Construction of rockfill platform at Viaduct D landing; and

¡P      Additional marine ground investigation (GI) and laboratory testing.

 

Land-based Works

¡P      Satellite container offices erection along seawall;

¡P      Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P      Land piling at Viaduct B, C and E;

¡P      Piling platform installation for Viaducts B, D & E;

¡P      Additional land ground investigation (GI), trial pits & laboratory testing;

¡P      Utility surveys; and

¡P      Slope work at 9SE-B/C8 and 9SE-B/C9.

 

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the next reporting month of April 2014 are mainly associated with dust, noise, marine water quality, marine ecology and waste management issues.


1                                             Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

1.2                                      Scope of Report

This is the fifth monthly EM&A Report under the Contract No. HY/2012/07 Tuen Mun ¡V Chek Lap Kok Link ¡V Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works in March 2014.

1.3                                      Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

Kingman Chan

3691 3950

3691 2899

 

 

 

 

 

ENPO / IEC

(ENVIRON Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2888

3465 2899

IEC

 

Tony Cheng

3465 2888

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Manager

 

Brian Kam

3520 0387

3520 0486

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Jovy Tam

2271 3113

2723 5660

1.4                                      Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The three-month rolling construction programme is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

Marine-based Works

¡P      Marine piling platform installation;

¡P      Marine Piling at Viaduct B;

¡P      Construction of rockfill platform at Viaduct D landing; and

¡P      Additional marine ground investigation (GI) and laboratory testing.

 

Land-based Works

¡P      Satellite container offices erection along seawall;

¡P      Fence installation and relocation of Area 2, Viaduct A, B, C & D;

¡P      Land Piling at Viaduct B;

¡P      Piling platform installation for Viaducts B, D & E;

¡P      Additional land ground investigation (GI), trial pits & laboratory testing;

¡P      Utility surveys; and

¡P      Slope work of 9SE-B/C8 and 9SE-B/C9.

The general layout plan of the site showing the detailed works areas is shown in Figures 1.1 to 1.12.  The Environmental Sensitive Receivers in the vicinity of the Project is shown in Figure 1.13.

The environmental mitigation measures implementation schedule are presented in Appendix C.

2                                             EM&A Results

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                                      Air quality

2.1.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact 1-hour TSP monitoring was conducted three (3) times every six (6) days and impact 24-hour TSP monitoring was carried out once every six (6) days when the highest dust impact was expected.  The Action and Limit Level of the air quality monitoring is provided in Appendix D.

Table 2.1        Locations of Impact Air Quality Monitoring Stations

Monitoring Station

Location

Description

Monitoring Dates

ASR 8

Pak Mong Village Watch Tower

 

Rooftop of the premise

6, 12, 18, 24, 28 March 2014

ASR 8A

Area 4

On ground at the Area 4

High Volume Samplers (HVSs) were used for carrying out 1-hour and 24-hr TSP monitoring on 6, 12, 18, 24 and 28 March 2014 at ASR8 (Pak Mong Village Watch Tower) and ASR8A (Area 4) (Figure 2.1; Table 2.1) in accordance with the requirements stipulated in the Updated EM&A Manual.  Wind anemometer was installed at the rooftop of Pak Mong Village Watch Tower for logging wind speed and wind direction.  Details of the equipment deployed are given in Table 2.2.  Copies of the calibration certificates for the equipment are presented in Appendix E.

Table 2.2        Air Quality Monitoring Equipment

Equipment

Brand and Model

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Anemometer

Global Water: Wind Speed Sensor WE550, Wind Direction Sensor WE570

 

2.1.2                               Monitoring Schedule for the Reporting Month

The schedule for air quality monitoring in March 2014 is provided in Appendix F.

2.1.3                               Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4 respectively.  Detailed impact air quality monitoring results are presented in Appendix G.

Table 2.3        Summary of 1-hour TSP Monitoring Results in the Reporting Period

 

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

ASR 8A

120

58 - 240

394

500

ASR 8

118

70 - 175

393

500

 

Table 2.4        Summary of 24-hour TSP Monitoring Results in the Reporting Period

 

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

ASR 8A

56

37 - 83

178

260

ASR 8

64

45 - 83

178

260

The major dust source in the reporting period included construction activities such as excavation works under the Contract as well as nearby traffic emissions.

All 1-hour and 24-hour TSP results were below the Action and Limit level at all monitoring locations in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix L.

Meteorological information collected from the wind station, including wind speed and wind direction, is provided in Appendix H.

2.2                                      Noise Monitoring

2.2.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact noise monitoring was conducted once per week during the construction phase of the Contract.  The Action and Limit level of the noise monitoring is provided in Appendix D.

Noise monitoring was performed on 6, 12, 18, 24 and 28 March 2014 using sound level meter at the designated monitoring station NSR 1 (Figure 2.2; Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Details of the equipment deployed are provided in Table 2.6.  Copies of the calibration certificates for the equipment are presented in Appendix E.

Table 2.5        Location of Impact Noise Monitoring Station

Monitoring Station

Location

Description

Parameter

Frequency and Duration

Monitoring Dates

NSR 1

Pak Mong Village Watch Tower

Rooftop of the premise

30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

At least once per week

6, 12, 18, 24, 28 March 2014

Table 2.6        Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-31

Acoustic Calibrator

Rion NC-73

 

2.2.2                               Monitoring Schedule for the Reporting Month

The schedule for construction noise monitoring in the reporting period is provide in Appendix F.

2.2.3                               Monitoring Results

Results for noise monitoring are summarized in Table 2.7 and the monitoring data is provided in Appendix I.

Table 2.7        Summary of Construction Noise Monitoring Results in the Reporting Period

 

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

NSR 1

59

58 - 60

75

 

No noise Action Level and Limit level exceedance was recorded at all monitoring stations in the reporting month.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix L.

Major noise sources during the noise monitoring included noise from crane operation and excavation works, nearby traffic noise and aircraft noise.

2.3                                      Water Quality Monitoring

2.3.1                               Monitoring Requirements and Equipment

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period in accordance with the Updated EM&A Manual.  The Action and Limit Level of the water quality monitoring is provided in Appendix D.

The locations of the monitoring stations under the Contract are shown in Figure 2.3 and Table 2.8. 

Table 2.8        Locations of Impact Water Quality Monitoring Stations and its Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Frequency

Depth

 

 

Easting

Northing

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

¡P    SS (mg/L)

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract

 

 

 

             

3 water depths: 1m below sea surface, mid-depth and 1m above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth will be omitted

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

SR4

Sensitive receiver (Tai Ho Inlet)

814760

817867

SR4a

Sensitive receiver

815247

818067

CS(Mf)3

Control Station

809989

821117

CS(Mf)5

Control Station

817990

821129

*Notes:
In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Table 2.9 summarises the equipment used in the impact water quality monitoring programme.  Copies of the calibration certificates are attached in Appendix E.

Table 2.9        Water Quality Monitoring Equipment  

Equipment

Brand and Model

Quantity

DO, Temperature meter and Salinity

YSI Pro2030

 

 

1

Turbidimeter

HACH Model 2100Q

 

1

pH meter   

HANNA HI8314

 

1

Positioning Equipment

Koden913MK2 with KBG-3 DGPS antenna

 

1

Water Depth Detector

Speedtech Instrument SM-5

 

1

Water Sampler

Kemmerer 1520 (1520-C25) 2.2L with messenger

1

 

2.3.2                               Monitoring Schedule for the Reporting Month

The schedule for water quality monitoring in March 2014 is provided in Appendix F.

2.3.3                               Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting month.  Impact water quality monitoring results and graphical presentations are provided in Appendix J.

No Action and Limit level exceedance was recorded at all monitoring stations for impact water quality monitoring in the reporting month, during which marine piling platform installation, marine piling at Viaduct B and rockfill platform construction at Viaduct D landing were the major marine construction works involved.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix L.

2.4                                      Dolphin monitoring

2.4.1                               Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort. 

2.4.2                               Monitoring equipment

Table 2.10 summarises the equipment used for the impact dolphin monitoring.

Table 2.10      Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                               Monitoring Parameter, Frequencies and Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                               Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.4.  The co-ordinates of all transect lines are shown in Table 2.11 below.

Table 2.11      Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

 

Line No.

Easting

Northing

1

Start Point

804671

814577

 

13

Start Point

816506

819480

1

End Point

804671

831404

 

13

End Point

816506

824859

2

Start Point

805475

815457

 

14

Start Point

817537

820220

2

End Point

805477

826654

 

14

End Point

817537

824613

3

Start Point

806464

819435

 

15

Start Point

818568

820735

3

End Point

806464

822911

 

15

End Point

818568

824433

4

Start Point

807518

819771

 

16

Start Point

819532

821420

4

End Point

807518

829230

 

16

End Point

819532

824209

5

Start Point

808504

820220

 

17

Start Point

820451

822125

5

End Point

808504

828602

 

17

End Point

820451

823671

6

Start Point

809490

820466

 

18

Start Point

821504

822371

6

End Point

809490

825352

 

18

End Point

821504

823761

7

Start Point

810499

820690

 

19

Start Point

822513

823268

7

End Point

810499

824613

 

19

End Point

822513

824321

8

Start Point

811508

820847

 

20

Start Point

823477

823402

8

End Point

811508

824254

 

20

End Point

823477

824613

9

Start Point

812516

820892

 

21

Start Point

805476

827081

9

End Point

812516

824254

 

21

End Point

805476

830562

10

Start Point

813525

820872

 

22

Start Point

806464

824033

10

End Point

813525

824657

 

22

End Point

806464

829598

11

Start Point

814556

818449

 

23

Start Point

814559

821739

11

End Point

814556

820992

 

23

End Point

814559

824768

12

Start Point

815542

818807

 

 

 

 

 

12

End Point

815542

824882

 

 

 

 

 

2.4.5                               Action & Limit Levels

The action and limit levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix L.


2.4.6                               Monitoring Schedule for the Reporting Month

Dolphin monitoring was carried out on 5, 11, 17 and 25 March 2014 (Appendix F).  

2.4.7                               Results and Observations

A total of 296.83 km of survey effort was collected, with 89.0% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility) during the February¡¦s surveys.  Among the two areas, 117.30 km and 179.53 km of survey effort were collected from NEL and NWL survey areas respectively.  The total survey effort conducted on primary and secondary lines were 211.71 km and 85.12 km, respectively.  The survey efforts are summarized in Appendix K.

A total of 14 groups of 43 Chinese White Dolphin sightings were recorded during the two sets of surveys in March 2014.  All sightings were made in NWL during the two sets of surveys in March, with no dolphin being sighted at all in NEL.  All except two sightings were made on primary lines during on-effort search, and none of the dolphin groups was associated with operating fishing vessel.

The majority of these dolphin sightings in March 2014 were made at the northwestern portion of NWL survey area, especially to the north of Lung Kwu Chau.  Another two sightings were made at the north of the airport and between the River Trade Terminal and airport platform respectively.  The distribution of dolphin sightings during the reporting month is shown in Figure 2.5.

Encounter rates of Chinese White Dolphins are deduced from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below with good visibility) in March 2014 with the results presented in Tables 2.12 and 2.13.

Table 2.12      Individual Survey Event Encounter Rates

 

 

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

 

 

Primary Lines Only

Primary Lines Only

NEL

Set 1: Mar 5th/ 11th   

0.0

0.0

 

Set 2: Mar 17th/ 25th  

0.0

0.0

NWL

Set 1: Mar 5th/ 11th  

6.4

23.6

 

Set 2: Mar 17th/ 25th 

13.2

24.8

Note:   Dolphin Encounter Rates are deduced from the two sets of surveys ( ie two Surveys in each set) in March 2014 in Northeast (NEL) and Northwest Lantau (NWL)

Table 2.13      Monthly Average Encounter Rates

 

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary   Lines Only

Both Primary and Secondary Lines

Primary   Lines Only

Both Primary and Secondary Lines

Northeast Lantau

0.0

0.0

0.0

0.0

Northwest Lantau

10.4

8.6

24.3

19.9

Note: Overall dolphin encounter rates (sightings per 100km of survey effort) from all four surveys are conducted in March 2014 on primary lines only as well as both primary lines and secondary lines in Northeast and Northwest Lantau

The average group size of Chinese White Dolphins in March 2014 was 3.07 individuals per group, which was lower than the previous three months of dolphin monitoring.  Most dolphin groups were composed of 1-3 animals, with only one large group of 13 animals sighted near Lung Kwu Chau.   Detailed results of dolphin monitoring in this reporting month are presented in Appendix K.

During this month of dolphin monitoring, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations

Due to monthly variation in dolphin occurrence within the Study area, it would be more appropriate to draw conclusion on whether any unacceptable impacts on dolphins have been detected related to the construction activities of the TM-CLKL Southern Connection Viaduct Section in the quarterly EM&A reports, where comparison on distribution, group size and encounter rates of dolphins between the quarterly impact monitoring period and baseline monitoring period will be made.

2.4.8                               Marine Mammal Exclusion Zone Monitoring

Daily 250 m marine mammal exclusion zone monitoring was undertaken during the period of dredging activities being undertaken.  No sighting of Indo-Pacific humpback dolphin Sousa chinensis were recorded in March 2014 during the exclusion zone monitoring.  

2.4.9                               Marine Bored Piling Monitoring

Marine bored piling monitoring programme for dolphins (ie Land-based Theodolite Tracking, Underwater Noise Monitoring and Acoustic Behavioural Monitoring) was undertaken since 3 March 2014.  No sightings of Indo-Pacific humpback dolphins Sousa chinensis were recorded during the bored piling monitoring in March 2014.  The monitoring schedule for bored piling monitoring in March 2014 is presented in Appendix F.

2.5                                      Coral Monitoring

No Post-Translocation Monitoring Exercise was conducted in the reporting month in March 2014.

2.6                                      EM&A Site inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  In the reporting month, five (5) site inspections were carried out on 5, 12, 19 and 26 March 2014.

Key observations and recommendations during the site inspections are summarized in Table 2.14.

Table 2.14      Specific Observations and Recommendations during the Weekly Site Inspection in this Reporting Month

Inspection Date

Observations

Remarks

5 March 2014

Ÿ   Stoppers of two drip trays were missing at seafront site.

Ÿ   Several chemical drums were not placed in drip tray.

Ÿ   The Contractor was reminded to replace the stopper.

Ÿ   The Contractor was reminded to place them properly and immediate rectification has been done accordingly.

12 March 2014

Ÿ   Some oil trace was observed around one of the bored piles with unidentified source.

Ÿ   The Contractor carried out immediate rectification action by deploying absorbent to absorb the floating oil trace.

19 March 2014

Ÿ   Watering programme was recommended to be carried out more regularly to suppress dust.

Ÿ  The Contractor was reminded to carry out watering programme or dust-suppression measures more regularly.

26 March 2014

Ÿ  Oil stain was observed underneath a vibration hammer at B1.

Ÿ   Five cans of chemicals were placed along the road of the rockfill platform without any drip trays.

Ÿ  Immediate rectification action was undertaken by the Contractor to absorb the oil stain.

Ÿ  The Contractor was reminded to place them properly in timely manner.

The Contractor has rectified all observations as identified during environmental site inspection in the reporting month. 

2.7                                      Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

As advised by the Contractor, 3223 m3 of inert C&D Materials are generated and disposed of in the reporting period and 221 m3 of inert C&D Materials are disposed of as public fill.  12.39 tonnes of general refuse were generated and disposed of in the reporting period.  Monthly summary of waste flow table is detailed in Appendix M.

The Contractor is advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor is reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

The Contractor is reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.8                                      Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.15 below.


Table 2.15      Summary of Environmental Licensing and Permit Status

Statutory Reference

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

EIAO

Environmental Permit

EP-354/2009/A

8 Dec 2010

NA

HyD

Tuen Mun- Chek Lap Kok Link

 

EIAO

Environmental Permit

EP-354/2009/B

28 Jan 2014

NA

 

HyD

Tuen Mun- Chek Lap Kok Link

 

APCO

Construction Dust Notification

361571

5 Jul 2013

NA

GCL

-

APCO

Construction Dust Notification

 

362093

17 Jul 2013

NA

GCL

for Area 23

WDO

Billing Account for Disposal

7017735

10 Jul 2013

End of Project

GCL

-

 

WDO

Chemical Waste Registration

5213-961-G2380-13

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Chemical Waste Registration

5213-961-G2380-14

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Chemical Waste Registration

5213-974-G2588-03

4 Nov 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Construction Waste Disposal Account

7017735

10 Jul 2013

NA

GCL

Waste disposal in Contract HY/2012/07

WPCO

Waste Water Discharge License

Nil

Application Ref. 368337

NA

GCL

Discharge for discharge points for Viaduct A & B

 

NCO

Construction Noise Permit

Nil

Application in process

NA

GCL

For Piling Works

NCO

Construction Noise Permit

GW-RW0660-13

27 Sep 2013

02 Feb 2014

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1129-13

31 Oct 2013

30 Apr 2014

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1186-13

23 Oct 2013

24 Dec 2013

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1187-13

24 Oct 2013

28 Feb 2014

GCL

For night

 

NCO

Construction Noise Permit

GW-RW0925-13

19 Dec 2013

17 Apr 2014

GCL

Renewal of WA5 site office erection

 

NCO

Construction Noise Permit

GW-RS1423-13

11 Dec 2013

30 Apr 2014

GCL

Renewal for marine portion

 

NCO

Construction Noise Permit

GW-RS1413-13

17 Dec 2013

26 Mar 2014

GCL

For loading and unloading on NLH near viaduct A & B

 

NCO

Construction Noise Permit

GW-RS0034-14

14 Jan 2014

29 Mar 2014

GCL

For night works and works in general holiday

 

NCO

Construction Noise Permit

GW-RW0123-14

27 Feb 2014

27 Aug 2014

GCL

For night works and works in general holiday

 

NCO

Construction Noise Permit

GW-RS0236-14

27 Mar 2014

14 May 2014

GCL

For loading & unloading on NLH near Viaduct A & B

 

NCO

Construction Noise Permit

GW-RS0226-14

30 Mar 2014

29 Sep 2014

GCL

For loading & unloading on NLH near Viaduct D

 

NCO

Construction Noise Permit

GW-RS0280-14

31 Mar 2014

31 May 2014

GCL

For excavation at Pier B9

 

 

 

 

 

 

 

DASO

Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal)

 

(4) in EP/MD/14-075

25 Sep 2013

NA

GCL

-

DASO

Marine Dumping Permit

EP/MD/14-075

28 January 2014

27 July 2014

GCL

For dumping Type I Sediment

 

DASO

Marine Dumping Permit

EP/MD/14-155

1 April 2014

30 April 2014

GCL

For dumping Type I (Dedicated Site) and Type II Sediment

Note:

Statutory Reference:  EIAO ¡V Environmental Impact Assessment Ordinance; NCO ¡V Noise Control Ordinance; APCO ¡V Air Pollution Control Ordinance; WDO ¡V Waste Disposal Ordinance; WPCO ¡V Water Pollution Control Ordinance; DASO ¡V Dumping At Sea Ordinance.

License/ Permit Holder:  HyD ¡V Highway Department; GCL ¡V Gammon Construction Limited.


2.9                                      Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

2.10                                Summary of Exceedances of the Environmental Quality Performance Limit

Results for 1-hour, 24-hour TSP, construction noise monitoring and impact water quality monitoring complied with the Action/ Limit levels in the reporting period. 

Cumulative statistics on exceedances is provided in Appendix N.

2.11                                Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.6.

No complaints, notification of summons and prosecution were received in the reporting period.

Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix N.

3                                             Future Key Issues

3.1                                      Construction Programme for the Coming Months

As informed by the Contractor, the major works for the Contract in April 2014 will be:

Marine Works

¡P      Marine piling platform installation;

¡P      Marine piling at Viaduct B;

¡P      Construction of rockfill platform at Viaduct D landing; and

¡P      Additional marine ground investigation (GI) and laboratory testing.

 

Land-based Works

¡P      Satellite container offices erection along seawall;

¡P      Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P      Land piling at Viaduct B, C and E;

¡P      Piling platform installation for Viaducts B, D & E;

¡P      Additional land ground investigation (GI), trial pits & laboratory testing;

¡P      Utility surveys; and

¡P      Slope work at 9SE-B/C8 and 9SE-B/C9.

3.2                                      Key Issues for the Coming Month

Potential environmental impacts arising from the above upcoming construction activities in the next reporting month of April 2014 are mainly associated with dust, noise, marine water quality, marine ecology and waste management issues.

3.3                                      Monitoring Schedule for the Coming Month

The tentative schedule for environmental monitoring in April 2014 is provided in Appendix F.

Marine bored piling monitoring programme for dolphins (ie Land-based Theodolite Tracking, Underwater Noise Monitoring and Acoustic Behavioural Monitoring) will be carried out in April 2014.  The preliminary schedule for the marine bored piling monitoring in the coming reporting month is provide in Appendix F.

 

4                                             Conclusions

This Fifth Monthly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 31 March 2014, in accordance with the Updated EM&A Manual and the requirements of EP-354/2009/A.   

Air quality (including 1-hour TSP and 24-hour TSP), noise, water quality and dolphin monitoring were carried out in the reporting period.  Results for noise, 1-hr, 24-hr TSP monitoring, noise and impact water quality monitoring complied with the Action/ Limit levels in the reporting period.

A total of fourteen (14) groups of forty-three (43) dolphin sightings were recorded during the two sets of surveys.  All sightings were made in NWL during the two sets of surveys in March, with no dolphin being sighted at all in NEL.  During this reporting period of dolphin monitoring, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations.

Environmental site inspection was carried out four (4) times in March 2014.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

No environmental complaint, notification of summons and prosecution were received in the reporting month.

The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.