TABLE OF CONTENTS

 

EXECUTIVE SUMMARY

Introduction

Environmental Monitoring and Audit Progress

Complaint Log

Future Key Issues

1      INTRODUCTION

Purpose of the report

Structure of the report

2      CONTRACT INFORMATION

Background

Contract Organisation

Construction Programme

Summary of Construction Works Undertaken During Reporting Month

Status of Environmental Licences, Notification and Permits

3      AIR QUALITY MONITORING

Monitoring Requirements

Monitoring Location

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedure

1-hour and 24-hour TSP Air Quality Monitoring

Instrumentation

HVS Installation

Filters Preparation

Operating/Analytical Procedures

Results and Observations

Event and Action Plan

4      NOISE MONITORING

Monitoring Requirements

Monitoring Location

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedures

Maintenance and Calibration

Results and Observations

Event and Action Plan

5      WATER QUALITY MONITORING

Monitoring Requirements

Monitoring Locations

Monitoring Equipment

Monitoring Parameters, Frequency

Monitoring Methodology

Instrumentation

Operating/Analytical Procedures

Laboratory Analytical Methods

QA/QC Requirements

Maintenance and Calibration

Results and Observations

Event and Action Plan

6      DOLPHIN-RELATED MONITORING

Monitoring Requirements

DOLPHIN MONITORING (LINE-TRANSECT VESSEL SURVEY)

Monitoring Requirements

Monitoring Location

Monitoring Frequency

Monitoring Results

LAND-BASED DOLPHIN BEHAVIOUR AND MOVEMENT MONITORING AFTER BRIDGE CONSTRUCTION

Construction Program and Monitoring Period

ADDITIONAL LAND-BASED DOLPHIN BEHAVIOUR AND MOVEMENT MONITORING

7      ENVIRONMENTAL SITE INSPECTION

Site Audits

Implementation Status of Environmental Mitigation Measures

Advice on the Solid and Liquid Waste Management Status

8      ENVIRONMENTAL NON-CONFORMANCE (EXCEEDANCES)

Summary of Exceedances

Summary of Notification of Summons and Successful Prosecution

9      FUTURE KEY ISSUES

Key Issues in the Coming Month

Construction Programme for the Next Month

10    CONCLUSIONS

 

 

LIST OF TABLES

 

Table 2.1  Key Contacts of the Contract

Table 2.2  Status of Environmental Licences, Notification and Permits

Table 3.1  Location for Air Quality Monitoring Locations

Table 3.2  Air Quality Monitoring Equipment

Table 3.3  Impact Dust Monitoring Parameters, Frequency and Duration

Table 4.1  Location for Noise Monitoring Locations

Table 4.2  Noise Monitoring Equipment

Table 4.3  Noise Monitoring Parameters, Frequency and Duration

Table 5.1  Location for Marine Water Quality Monitoring Locations

Table 5.2  Water Quality Monitoring Equipment

Table 5.3  Water Quality Monitoring Parameters and Frequency

Table 5.4  Methods for Laboratory Analysis for Water Samples

Table 5.5  Summary of Post-Construction Water Quality Monitoring Results

Table 6.1  Co-ordinates of transect lines in WL survey area

Table 6.2  Summary of Land-based of Dolphin Behaviour and Movement Monitoring Requirements

Table 6.3  Major Construction Program for Contract No. HY/ 2011/09

Table 6.4  Summary of Land-based dolphin behavior and movement monitoring across the bridge alignment before, during and after bridge construction

 

 

LIST OF FIGURE

 

Figure 1a-d      Site Layout Plan

Figure 2           Project Organisation for Environmental Works

Figure 3           Locations of Air Quality, Noise and Wind Monitoring Stations

Figure 4          Locations of Water Quality Monitoring Stations

 

 

LIST OF APPENDICES

 

Appendix A    Construction Programme

Appendix B    Action and Limit Levels

Appendix C    Event Action Plans

Appendix D    Summary of Exceedance

Appendix E     Updated Environmental Mitigation Implementation Schedule

Appendix F     Waste Generation in the Reporting Month

Appendix G    Complaint Log

Appendix H    Summary of Successful Prosecutions

Appendix I      Post-Construction Water Quality Monitoring Report

Appendix J      Post-Construction Dolphin Monitoring Report (Line-transect)