TABLE OF CONTENTS

                        EXecutive Summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Scope of Report                                                                   

1.3                   Organization Structure                                                 

1.4                   Summary of Construction Works                              

1.5                   Summary of EM&A Programme Requirements        

2                      EM&A RESULTS                                                                         

2.1                   Air Quality                                                                               

2.2                   Noise Monitoring                                                                  

2.3                   Water Quality Monitoring                                              

2.4                   Dolphin Monitoring                                                            

2.5                   Post-Translocation Coral Monitoring                   

2.6                   EM&A Site Inspection                                                           

2.7                   Waste Management Status                                             

2.8                   Environmental Licenses and Permits                        

2.9                   Implementation Status of Environmental Mitigation Measures  

2.10                 Summary of Exceedances of the Environmental Quality Performance Limit                                                                                                       

2.11                 Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                         

3                      Future Key Issues                                                                

3.1                   Construction Activities for the Coming Quarter   

3.2                   Key Issues for the Coming Quarter                           

3.3                   Monitoring Schedule for the Coming Quarter   

4                      Conclusions and recommendations                         

4.1                   Conclusions                                                                           

 


List of Appendices

Appendix A

Project Organization for Environmental Works

Appendix B

Three Month Rolling Construction Programmes

Appendix C

Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D

Summary of Action and Limit Levels

Appendix E

EM&A Monitoring Schedules

Appendix F

Impact Air Quality Monitoring Results and Graphical Presentation

Appendix G

Impact Noise Monitoring Results and Graphical Presentation

Appendix H

Impact Water Quality Monitoring Results and Graphical Presentation

Appendix I

Impact Dolphin Monitoring Survey Results

Appendix J

Event Action Plan

Appendix K

Quarterly Summary of Waste Flow Table

Appendix L

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

           

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the third quarterly EM&A report presenting the EM&A works carried out during the period from 1 June to 31 August 2014 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

June 2014

Marine-based Works

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaduct B;

¡P         Piling platform installation for Viaducts B, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

July 2014

Marine-based Works

¡P         Construction of Pile caps at Viaduct B;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaducts B & D;

¡P         Piling platform installation for Viaducts B, C, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys;

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9; and

¡P         Site formation of workshop at Area 1.

August 2014

Marine-based Works

¡P         Construction of Pile caps at Viaduct B;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B, D & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaduct B;

¡P         Piling platform installation for Viaducts B, C, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                       16 sessions

1-hour TSP monitoring                                   16 sessions

Noise monitoring                                   16 sessions

Water quality monitoring                       39 sessions

Dolphin monitoring                                 6 sessions

Joint Environmental site inspection      13 sessions

Post-Translocation Coral monitoring    1 session

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Levels was recorded for air quality monitoring in the reporting period.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.

Breaches of Action and Limit Levels for Water Quality

No exceedance of Action and Limit Levels was recorded for impact water quality monitoring in the reporting period.

Impact Dolphin Monitoring

Whilst two (2) Action Level exceedances were observed for the quarterly dolphin monitoring data between June and August 2014, no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations during the dolphin monitoring in this reporting quarter.  The exceedances are considered to be the natural variation of Chinese White Dolphin ranging pattern upon further investigation.

Daily marine mammal exclusion zone monitoring was undertaken. No sighting of the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in the reporting period during the exclusion zone monitoring.

Post-Translcoation Coral Monitoring

The Third Quarterly Post-Translocation Coral Monitoring was conducted on 24 July 2014 and no exceedance of Action and Limit Levels was recorded.  The results were detailed in the Third Quarterly Post- Translocation Coral Monitoring Report and were submitted under a separate cover.

Environmental Complaints, Non-compliance & Summons

One (1) complaint was referred by the EPD on 23 June 2014 which was considered to be not related to this Contract upon further investigation. 

No notification of summons and successful prosecution was received in the reporting period.

Reporting Change

There was no reporting change required in the reporting period.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming quarter include the following:

 

September 2014

Marine Works

¡P        Construction of Pile caps at Viaduct B;

¡P        Marine piling platform installation;

¡P        Marine Piling at Viaducts B & E;

¡P        Marine piling platform installation for Viaduct D; and

¡P        Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P        Construction of pile cap superstructure of Viaduct B;

¡P        Fence installation and relocation of Works Area 2, Viaducts A, B, C & D;

¡P        Land Piling at Viaduct B and Viaduct C;

¡P        Piling platform installation for Viaducts B, C, D and E;

¡P        Additional land GI, trial pits & lab testing;

¡P        Utility surveys; and

¡P        Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

October 2014

Marine Works

¡P        Construction of Pile caps at Viaduct E;

¡P        Marine piling platform installation;

¡P        Marine Piling at Viaducts A, C, D & E; and

¡P        Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P        Land Piling at Viaducts B, C & D;

¡P        Piling platform installation for Viaducts C & D;

¡P        Additional land GI, trial pits & lab testing;

¡P        Utility surveys; and

¡P        Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

November 2014

Marine Works

¡P        Construction of Pile caps at Viaduct E;

¡P        Marine piling platform installation;

¡P        Marine Piling at Viaducts A, C, D & E; and

¡P        Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P        Fence installation and relocation of Viaducts A, B, & C;

¡P        Land Piling at Viaducts A &D;

¡P        Piling platform installation for Viaducts C & D;

¡P        Additional land GI, trial pits & lab testing;

¡P        Utility surveys; and

¡P        Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issue.


1                                             Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number: AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.  Another application for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.

1.2                                      Scope of Report

This is the Third Quarterly EM&A Report under the Contract No. HY/2012/07 Tuen Mun ¡V Chek Lap Kok Link ¡V Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works from 1 June 2014 to 31 August 2014.

1.3                                      Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

Kingman Chan

3691 2950

3691 2899

 

ENPO / IEC

(ENVIRON Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2888

3465 2899

IEC

 

Dr. F.C. Tsang

3465 2828

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Manager

 

Brian Kam

3520 0387

3520 0486

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Jovy Tam

2271 3113

2723 5660

1.4                                      Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The rolling construction programme for the period of June to August 2014 is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

June 2014

Marine-based Works

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaduct B;

¡P         Piling platform installation for Viaducts B, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

July 2014

Marine-based Works

¡P         Construction of Pile caps at Viaduct B;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaducts B & D;

¡P         Piling platform installation for Viaducts B, C, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys;

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9; and

¡P         Site formation of workshop at Area 1.

August 2014

Marine-based Works

¡P         Construction of Pile caps at Viaduct B;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B, D & E;

¡P         Construction of rockfill platform at Viaduct D landing; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaduct B;

¡P         Piling platform installation for Viaducts B, C, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

The locations of the construction activities are shown in Figure 1.3.  The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.4.


Figure 1.3       Locations of Construction Activities in the Reporting Period


The environmental mitigation measures implementation schedule are presented in Appendix C.

1.5                                      Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

¡P         Monitoring parameters;

¡P         Monitoring schedules for the reporting months and forthcoming months;

¡P         Action and Limit levels for all environmental parameters;

¡P         Event Action Plan;

¡P         Results and observations;

¡P         Environmental mitigation measures, as recommended in the approved EIA Report; and

¡P         Environmental requirement in contract documents.

2                                             EM&A RESULTS

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                                      Air Quality

The baseline air quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡VMacao Bridge Hong Kong Projects (HKZMB) during October 2011 has included the two monitoring stations ASR9A and ASR9C for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([1]) are adopted for this Project.

2.1.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact 1-hour TSP monitoring was conducted three (3) times every six (6) days while the highest dust impact was expected.  Impact 24-hour TSP monitoring was carried out once every six (6) days.  The Action and Limit Level of the air quality monitoring is provided in Appendix D.

Air quality monitoring stations ASR9A and ASR9C in Siu Ho Wan MTRC Depot were the proposed locations in accordance with the Updated EM&A Manual.  However, authorization of getting access into Siu Ho Wan MTRC Depot is still being sought for the impact monitoring of the EM&A programme for the captioned Contract.  Air quality monitoring stations in Siu Ho Wan MTRC Depot (ASR9A and ASR9C) were relocated to Area 4 (ASR8A) and rooftop of Pak Mong Village (ASR8) respectively since November 2013.  A proposal for setting up alternative air quality monitoring stations at ASR8A (Area 4) and ASR8 (Rooftop of Pak Mong Village Watch Tower) was submitted on 13 November 2013 which was subsequently approved.  Same baseline and Action/Limit Level for air quality, as derived from the baseline monitoring data recorded at Siu Ho Wan MTRC Depot, were adopted for these temporary air quality locations (Figure 2.1; Table 2.1).

High Volume Samplers (HVSs) were used for carrying out 1-hour and 24-hr TSP monitoring during the reporting period.  The HVS meets all requirements of the Updated EM&A Manual.  Brand and model of the equipment is given in Table 2.2.

Wind data monitoring equipment has been installed at the rooftop of Pak Mong Village Watch Tower during the reporting period for logging wind speed and wind direction.  The wind sensor was setup such as it was clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.

Table 2.1        Locations of Impact Air Quality Monitoring Stations and Monitoring Dates in this Reporting Period

Monitoring Station (1)

Monitoring Period

Location

Description

Parameters & Frequency

ASR8A

3, 9, 13, 19, 25 and 30 June; 5, 11, 17, 23 and 29 July; 4, 8, 14, 20 and 26 August 2014

 

Area 4

On ground at the Area 4

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times per day every 6 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour every 6 days

ASR8

Pak Mong Village Watch Tower

Rooftop of the premise

Note: 

(1)  Air Quality Monitoring Stations ASR9A and ASR9C at Siu Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were temporarily relocated to ASR 8A and ASR8, respectively.

 

Table 2.2        Air Quality Monitoring Equipment

Equipment

Brand and Model

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Sensor

Global Water (Wind Speed Sensor: WE550; Wind Direction Sensor: WE570)

 

Wind Anemometer for calibration

Lutron (Model No. AM-4201)

2.1.2                               Action & Limit Levels

The Action and Limit Levels of the air quality monitoring is provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.1.3                               Monitoring Schedule for the Reporting Quarter

The schedules for air quality monitoring in the reporting quarter is provided in Appendix E.  


2.1.4                               Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively.  Monitoring results are presented graphically in Appendix F and detailed impact air quality monitoring results and meteorological information were reported in the Eighth to Tenth Monthly EM&A Report.     

Table 2.3        Summary of 1-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2014

ASR 8A

73

47 - 131

394

500

ASR 8

70

49 - 115

393

500

July 2014

ASR 8A

60

40 - 74

394

500

 

ASR 8

67

52 - 102

393

500

August 2014

ASR 8A

69

43 - 113

394

500

 

ASR 8

67

43 - 116

393

500

Table 2.4        Summary of 24-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2014

ASR 8A

54

39 - 69

178

260

ASR 8

53

40 - 68

178

260

July 2014

ASR 8A

43

38 - 47

178

260

 

ASR 8

42

36 - 47

178

260

August 2014

ASR 8A

41

40 - 43

178

260

 

ASR 8

43

41 - 45

178

260

The major dust sources in the reporting period include construction activities under the Contract as well as nearby traffic emissions.

In this reporting period, a total of sixteen (16) monitoring events were undertaken within the reporting period, in which no Action or Limit Level exceedances for 1-hr and 24-hr TSP for air quality were recorded during the reporting period.


2.2                                      Noise Monitoring

The baseline noise monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Projects (HKZMB) during the period of 18 October to 1 November 2011 has included the monitoring station NSR1 for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([2]) are adopted for this Project.

2.2.1                               Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact noise monitoring was conducted once per week during the construction phase of the Contract at NSR1. 

Monitoring location was set up at NSR1 in accordance with the Updated EM&A Manual.  Figure 2.2 shows the location of the monitoring station.  Table 2.5 describes the details of the monitoring station.  

Noise monitoring was performed using sound level meter at each designated monitoring station.  The sound level meters deployed comply with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Brand and model of the equipment is given in Table 2.6.

Table 2.5        Location of Impact Noise Monitoring Station and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Period

Location

Parameters & Frequency

NSR1

June 2014 to August 2014

Pak Mong Village Watch Tower

Ÿ   30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

Ÿ   At least once a week

Table 2.6        Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-31

Acoustic Calibrator

Rion NC-73

2.2.2                               Action and Limit Levels

The Action and Limit levels of the noise monitoring are provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.2.3                               Monitoring Schedule for the Reporting Quarter

The schedules for noise monitoring in the reporting quarter is provided in Appendix E.

2.2.4                               Results and Observations

The monitoring results for noise monitoring are summarized in Table 2.7.  Monitoring results are presented graphically in Appendix G and detailed impact noise monitoring results are reported in the Eighth to Tenth Monthly EM&A Report.

Table 2.7        Summary of Construction Noise Monitoring Results at NSR1 in the Reporting Period

Month

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

June 2014

58

55 - 59

75

July 2014

57

56 - 58

75

August 2014

56

54 - 57

75

 

A total of sixteen (16) monitoring events were undertaken in the reporting period with no Action Level and Limit Level exceedance recorded at all monitoring stations in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix J.

Major noise sources during the noise monitoring included construction activities, nearby traffic noise and aircraft noise.


2.3                                      Water Quality Monitoring

The baseline water quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all monitoring stations except SR4a for the Project.  Thus, the baseline monitoring results except for station SR4a and Action/Limit Level presented in HKZMB Baseline Monitoring Report ([3]) are adopted for this Project.  Baseline water quality monitoring was conducted at station SR4a from 29 August to 24 September 2013. 

2.3.1                               Monitoring Requirements and Equipment

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period at seven water quality monitoring stations in accordance with the Updated EM&A Manual (Figure 2.3; Table 2.8).  

Table 2.8        Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

¡P    SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

 

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract.

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

SR4

Sensitive receiver (Tai Ho Inlet)

814760

817867

SR4a

Sensitive receiver

815247

818067

CS(Mf)3

Control Station

809989

821117

CS(Mf)5

Control Station

817990

821129

Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Table 2.9 summarizes the equipment used in the impact water quality monitoring programme.

Table 2.9        Water Quality Monitoring Equipment

Equipment

Brand and Model

DO, Temperature meter and Salinity

YSI Pro2030

 

 

Turbidimeter

HACH Model 2100Q

 

pH meter   

HANNA HI8314

 

Positioning Equipment

Koden913MK2 with KBG-3 DGPS antenna

 

Water Depth Detector

Speedtech Instrument SM-5

 

Water Sampler

Kemmerer 1520 (1520-C25) 2.2L with messenger

2.3.2                               Action & Limit Levels

The Action and Limit Level of the water quality monitoring is provided in Appendix D.

2.3.3                               Monitoring Schedule for the Reporting Quarter

The schedules for water quality monitoring in the reporting quarter are provided in Appendix E.

2.3.4                               Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting period.  Monitoring results are presented graphically in Appendix H and detailed impact water quality monitoring results were reported in the Eighth to Tenth Monthly EM&A Report.    

In this reporting period, a total of Thirty-nine (39) monitoring events were undertaken in which no Action or Limit Level exceedance were recorded during the reporting quarter.

2.4                                      Dolphin Monitoring

2.4.1                               Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort.

2.4.2                               Monitoring Equipment

Table 2.10 summarises the equipment used for the impact dolphin monitoring.

Table 2.10      Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                               Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                               Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.4.  The co-ordinates of all transect lines are shown in Table 2.11 below.


Table 2.11      Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

814577

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805475

815457

14

Start Point

817537

820220

2

End Point

805477

826654

14

End Point

817537

824613

3

Start Point

806464

819435

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

819771

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

820220

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

820466

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

820690

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

820847

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

820892

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

820872

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818449

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

 

 

 

 

12

End Point

815542

824882

 

 

 

 

2.4.5                               Action & Limit Levels

The action and limit levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix J.

2.4.6                               Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are shown in Appendix E.

2.4.7                               Results & Observations

A total of 894.40 km of survey effort was collected, with 93.6% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility).  Among the two areas, 343.21 km and 551.19 km of survey effort were conducted in NEL and NWL survey areas respectively.  The total survey effort conducted on primary lines was 647.96 km, while the effort on secondary lines was 246.44 km.  Both survey efforts conducted on primary and secondary lines were considered as on-effort survey data.  The survey efforts are summarized in Appendix I.

During the six sets of monitoring surveys from June to August 2014, a total of twenty eight (28) groups of ninety six (96) Chinese White Dolphins were sighted.  All except two (2) dolphin sightings were made during on-effort search.  Twenty (20) on-effort sightings were made on primary lines, while another six (6) on-effort sightings were made on secondary lines.  In this quarterly period, almost all dolphin groups were sighted in NWL, with the exception of one (1) group of four (4) dolphins being sighted in NEL.  Summary table of the dolphin sightings is shown in Appendix I.

Encounter rates of Chinese White Dolphins deduced from the survey effort and on-effort sighting data from the primary transect lines under favourable conditions (Beaufort 3 or below) in the reporting period with the results presented in Tables 2.12 and 2.13.

Table 2.12      Individual Survey Event Encounter Rates

Survey Area

Survey period

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

NEL

Set 1 (3 & 5 Jun 2014)

Set 2 (10 & 16 Jun 2014)

Set 3 (3, 9 & 10 Jul 2014)

Set 4 (14 & 21 Jul 2014)

Set 5 (5 & 6 Aug 2014)

Set 6 (15 & 19 Aug 2014)

0.0

0.0

2.54

0.0

0.0

0.0

0.0

0.0

10.16

0.0

0.0

0.0

NWL

Set 1 (3 & 5 Jun 2014)

Set 2 (10 & 16 Jun 2014)

Set 3 (3, 9 & 10 Jul 2014)

Set 4 (14 & 21 Jul 2014)

Set 5 (5 & 6 Aug 2014)

Set 6 (15 & 19 Aug 2014)

1.67

0.0

3.03

8.4

5.63

9.7

5.0

0.0

10.61

26.6

22.52

40.4

Note:  Dolphin Encounter Rates are deduced from the six sets of surveys (two surveys in each set) in the reporting period in Northeast (NEL) and Northwest Lantau (NWL)

Table 2.13      Quarterly Average Encounter Rates

Survey Area

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

June ¡V August 2014

September -November 2011

June ¡V August 2014

September -November 2011

Northeast Lantau

0.42 ¡Ó 1.04

6.00 ¡Ó 5.05

1.69 ¡Ó 4.15

22.19 ¡Ó 26.81

Northwest Lantau

4.74 ¡Ó 3.84

9.85 ¡Ó 5.85

17.52 ¡Ó 15.12

44.66 ¡Ó 29.85

Note: encounter rates deduced from the baseline monitoring period have been recalculated based only on survey effort and on-effort sighting data made along the primary transect lines under favourable conditions

Group size of Chinese White Dolphins ranged from one to eight (1 - 8) individuals per group in North Lantau region during June ¡V August 2014.  The average dolphin group sizes from these three months were compared with the ones deduced from the baseline period in September to November 2011, as shown in Table 2.14.

Table 2.14      Comparison of Quarterly Average Encounter Rates

 

Average Dolphin Group Size

June ¡V August 2014

September -November 2011

Overall

3.43 ¡Ó 1.95 (n = 28)

3.72 ¡Ó 3.13 (n = 66)

Northeast Lantau

4.00 ¡Ó 0.00 (n = 1)

3.18 ¡Ó 2.16 (n = 17)

Northwest Lantau

3.41 ¡Ó 1.99 (n = 27)

3.92 ¡Ó 3.40 (n = 49)

Whilst two (2) Action Level exceedances (one Action Level exceedance for Northeast Lantau cluster; one Action Level exceedance for Northwest Lantau social cluster) and no Limit Level exceedance were observed for the quarterly dolphin monitoring data between June and August 2014.  During this quarter of dolphin monitoring, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.  Although the dolphins infrequently occurred along the alignment of TMCLKL southern connection viaduct in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL, and many individuals have shifted away from the important habitat around the Brothers Islands.

It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

2.4.8                               Marine Mammal Exclusion Zone Monitoring

Daily 250 m marine mammal exclusion zone monitoring was undertaken under this Contract.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in the reporting period during the exclusion zone monitoring.

2.5                                      Post-Translocation Coral Monitoring

The third quarterly Coral Post-Translocation Monitoring was conducted on 24 July 2014 and the results were provided in the Third Quarterly Post-Translocation Coral Monitoring Report submitted under a separate cover.  The findings indicated that the Action or Limit Levels for coral monitoring were not exceeded as increase in percentage of partial mortality was not detected for both the tagged translocated and natural coral colonies when comparing to the pre-translocation dataset.

2.6                                      EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Thirteen (13) site inspections were carried out in the reporting quarter on 4, 11, 19 and 25 June 2014; 2, 10, 16, 24 and 31 July 2014; 6, 14, 21 and 27 August 2014.

Key observations during the site inspections in this reporting period are summarized in Table 2.15.

Table 2.15      Specific Observations Identified during the Weekly Site Inspection in this Reporting Period

Inspection Date

Location & Environmental Observations

Recommendations/ Remarks

4 June 2014

Pier E9

¡P          Decoupling pad was not placed underneath the water pump and generator

Pier E10

Pier E9

¡P             The Contractor was reminded to place the decoupling pad

Pier E10

 

¡P         Chemical containers were placed at site without drip tray

¡P          Oil stain was seen underneath the crane.

¡P         The Contractor was reminded to place the chemical containers in drip tray properly

¡P          The Contractor was reminded to maintain all plants in properly and oil stain was immediately absorbed by absorbent.

11 June 2014

Pier B9

Pier B9

 

¡P         Drip tray was not plugged.

¡P         The Contractor was reminded to plug the drip tray properly

 

Seafront

Seafront

 

¡P         No acoustic decoupling pad was found for generators on platform.

 

¡P          Chemical containers were not placed in drip tray.

¡P         Drip trays for generators next to the office have no stopper

¡P         Acoustic decoupling pad was suggested to be placed underneath the generators on platform

¡P         Chemical containers at site should be placed in drip tray.

¡P         All drip trays used at site should be properly plugged.

19 June 2014

Rockfill platform at Seafront.

Rockfill platform at Seafront

 

¡P         A drip tray was found not plugged.

Barge G23

¡P          Chemical containers were not placed in drip tray

¡P          Labels of chemical waste was found dropped off

Pier B2

¡P         Drip tray was not plugged properly

¡P         The Contractor was reminded to plug the drip tray.

Barge G23

¡P          Chemical containers should be provided for chemical containers

¡P          All chemical waste containers should be well-labelled

Pier B2

¡P         The Contractor was reminded to plug drip tray properly

25 June 2014

Pier B15

Pier B15

 

¡P         Two chemical containers were placed without drip tray

¡P         General refuse was observed scattered onsite

¡P         The Contractor was advised to put them on drip tray properly

¡P         The Contractor was advised to clear off any general refuse properly

 

Pier B16

Pier B16

 

¡P         Stagnant water was observed to be present in drip tray of a generator

 

¡P         The Contractor was advised to clear away any stagnant water accumulated in drip tray in timely manner

 

¡P         Stagnant water was observed to be accumulated in pit which is for placing excavated materials

¡P         The Contractor was advised to clear away any stagnant water accumulated in pits in timely manner

2 July 2014

Area 2

¡P          Tarpaulin sheet was required for grouting.

¡P          Chemical waste was not placed in drip tray.

Pier B15

¡P         General refuse was disposed improperly.

Pier B11

¡P         More sandbags were needed to avoid runoff.

Area 1

Ÿ   A rubbish bin was label incorrectly.

Area 2

¡P          Tarpaulin sheet should be provided for grouting.

¡P          Chemical waste should be placed in drip tray.

Pier B15

¡P         General refuse should be removed.

Pier B11

¡P         More sandbags should be added.

Area 1

¡P             The label was removed immediately.

10 July 2014

Seafront

Seafront

 

¡P         Refuse was disposed improperly.

¡P         Oil stain was observed on the ground.

¡P         Chemical containers were not placed in drip tray.

¡P         A drip tray was unplugged.

¡P         The Contractor was reminded to maintain good housekeeping.

¡P         Oil stain should be removed.

¡P         Chemical containers should be placed in drip tray.

¡P         The drip tray should be plugged.

 

Barge M025

Barge M025

 

¡P         Chemical containers were not placed in drip tray.

¡P         Chemical containers should be placed in drip tray.

16 July 2014

Area 2

Area 2

 

¡P         Sandbags were considered insufficient.

¡P         The unpaved slope was not well cover by tarpaulin sheet.

¡P         Drainage was not fully protected from runoff.

¡P         More sandbags should be provided.

¡P         The unpaved slope should be entirely covered by tarpaulin sheet.

¡P         More sandbags should be provided to prevent runoff.

24 July 2014

Seafront

Seafront

 

¡P         Chemical containers were not placed in drip tray.

Pier E3

¡P         Dumping permit was expired.

¡P         Chemical containers should be placed in drip tray.

Pier E3

¡P         The Contractor was reminded to renew the dumping permits regularly.

31 July 2014

Pak Mong

¡P             General refuse was observed in the project area.

¡P             Sandbags were not enough to avoid surface runoff.

Pier E3

¡P             Stagnant water was observed on the platform.

¡P             The acoustic decoupling pad was not deployed properly beneath the generators.

Pier E11

¡P             The acoustic decoupling pad was not deployed properly beneath the generators.

¡P             A drip tray was found unplugged.

Pak Mong

¡P             The Contractor was reminded to maintain good housekeeping.

¡P             The Contractor was reminded to provide sufficient sandbags to prevent runoff.

Pier E3

¡P             Stagnant water was removed immediately.

¡P             The Contractor was reminded to place the acoustic decoupling pad beneath the generators properly.

Pier E11

¡P             The Contractor was reminded to place the acoustic decoupling pad beneath the generators properly.

¡P             A drip tray stopper should be provided.

6 August 2014

Site Access 9A

¡P         Chemical containers were not placed in drip tray.

¡P         A drip tray was found unplugged.

Slope next to NL1

¡P         Drainage was filled with trash.

Site Access 9B

¡P         Chemical containers were not placed in drip tray.

Slope BC8

¡P         Tarpaulin sheet for soil nail on unpaved slope was not cover properly.

Site Access 9A

¡P          Chemical Containers should be placed in drip tray.

¡P          The contractor should provide stopper to the drip tray.

¡P         Slope next to NL1

The contractor was reminded to clean up the drainage regularly.

Site Access 9B

¡P         Chemical Containers should be placed in drip tray.

Slope BC8

¡P         Soil nail on unpaved slope should be well covered.

14 August 2014

Pier B1

Pier B1

 

¡P         A drip tray was found unplugged.

¡P         Stagnant water was found in a drip tray.

Pier A,C&D1

¡P         A drip tray of generator could not be covered well by screen.

¡P         Stagnant water was found in a drip tray.

¡P         A drip tray was found unplugged.

¡P         The drip tray should be plugged.

¡P         Stagnant water in drip tray should be cleared.

Pier A,C&D1

¡P         The screen was improved immediately and able to cover the drip tray of generator properly.

¡P         Stagnant water in drip tray should be cleared.

¡P             The drip tray should be plugged.

 

Pier E4

Pier E4

 

¡P          Muddy water was accumulated on the platform.

¡P             A label of waste category label was missing.

Ÿ   Muddy water should be cleared.

Ÿ   Waste category label should be labelled properly.

21 August 2014

Pier B1

Pier B1

 

¡P         Stagnant water was accumulated in a drip tray.

Pier E10

¡P         Chemical containers were not labelled properly.

¡P         Soil and sand were accumulated on the platform.

Slope BC9

¡P             Soil and mud was observed accumulating in drainage.

¡P         Stagnant water in a drip tray should be cleared.

Pier E10

¡P         Chemical containers should be labelled properly.

¡P         Soil and sand on the platform were cleaned up immediately.

Slope BC9

¡P             Soil and mud in drainage should be cleared regularly.

27 August 2014

Slope BC9

Slope BC9

 

¡P         A chemical container was not placed in drip tray.

¡P         An unpaved slope was not covered.

¡P         Refuse was observed on the slope.

¡P         A part of bund was missing at the path on slope.

Pier B15

¡P             A drip tray was found unplugged.

¡P         The chemical container was removed intermediately.

¡P         The unpaved slope should be covered by tarpaulin sheet.

¡P         Refuse on the slope should be removed.

¡P         The Contractor was reminded to implement precautionary measures for preventing soil and sand runoff from the slope.

Pier B15

¡P         The drip tray should be plugged.


2.7                                      Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert), imported fill, recyclable materials, and marine sediments.  Reference has been made to the waste flow table prepared by the Contractor (Appendix K).  The quantities of different types of wastes are summarized in Table 2.16. 

Table 2.16      Quantities of Different Waste Generated in the Reporting Period

Month/Year

Inert Construction Waste (a) (m3)

Imported Fill (m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (tonnes)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

June 2014

357

2,457

2,503

77.29

25,480

0

338

0

July 2014

4,654

1,629

20

87.81

27,496

0

847

303

August 2014

2,441

288

2,094

98.22

22,281

0

391

164

Total

7,452

4,374

4,617

263.32

75,257

0

1,576

467

Notes:

(a)   Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)   Non-inert construction wastes include general refuse disposed at landfill.

(c)    Recyclable materials include metals, paper, cardboard, plastics, timber and others.

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.8                                      Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.17 below.


Table 2.17      Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-354/2009/A

8 Dec 2010

NA

HyD

Tuen Mun- Chek Lap Kok Link

 

Environmental Permit

EP-354/2009/B

28 Jan 2014

NA

 

HyD

Tuen Mun- Chek Lap Kok Link

 

Construction Dust Notification

361571

5 Jul 2013

NA

GCL

-

Construction Dust Notification

 

362093

17 Jul 2013

NA

GCL

For Area 23

Billing Account for Disposal

7017735

10 Jul 2013

End of Project

GCL

-

 

Chemical Waste Registration

5213-961-G2380-13

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

(Area 1 adjacent to Cheng Tung Road, Siu Ho Wan)

 

Chemical Waste Registration

5213-961-G2380-14

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

(Area 2 adjacent to Cheung Tung Road, Pak Mong Village)

 

Chemical Waste Registration

5213-974-G2588-03

4 Nov 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

(WA5 adjacent to Cheung Tung Road, Yam O)

 

Construction Waste Disposal Account

7017735

10 Jul 2013

NA

GCL

Waste disposal in Contract HY/2012/07

Waste Water Discharge License

WT00019017-2014

13 May 2014

31 May 2019

GCL

Discharge for marine portion

 

Waste Water Discharge License

 

WT00019018-2014

13 May 2014

31 May 2019

GCL

Discharge for land portion

Construction Noise Permit

Nil

Application in process

NA

GCL

For Piling Works

Construction Noise Permit

GW-RS0419-14

15 May 2014

13 Nov 2014

GCL

For loading & unloading on NLH near Viaducts A & B

Construction Noise Permit

GW-RS0226-14

30 Mar 2014

29 Sep 2014

GCL

For loading & unloading on NLH near Viaduct D

 

Construction Noise Permit

GW-RS0299-14

7 Apr 2014

5 Jul 2014

GCL

Pier B8 at CEDD Access Road

Construction Noise Permit

GW-RS0331-14

4 Apr 2014

6 Jul 2014

GCL

Broad permit for works at seafront & marine piers

Construction Noise Permit

GW-RS0338-14

4 Apr 2014

3 Jun 2014

GCL

For bored piling works between Pier E13 and HKBCF

Construction Noise Permit

GW-RS1423-13

11 Dec 2013

30 Apr 2014

GCL

Renewal for marine portion

 

Construction Noise Permit

GW-RW0123-14

27 Feb 2014

27 Aug 2014

GCL

For night works and works in general holiday at WA5

 

Dumping Permit/ Loading Permit

(Type 1 ¡V Open Sea Disposal)

(4) in EP/MD/14-075

25 Sep 2013

NA

GCL

-

Marine Dumping Permit

EP/MD/14-075

28 Jan 2014

27 Jul 2014

GCL

For dumping Type I Sediment

 

Marine Dumping Permit

EP/MD/15-028

1 Jun 2014

30 Jun 2014

GCL

For dumping Type I (Dedicated Site) and Type II sediment

Chemical Waste Registration

5213-951-G2380-17

12 Jun 2014

NA

GCL

Viaducts A, B, C, D & E

Construction Noise Permit for night works and works in general holidays

GW-RS0646-14

27 Jun 2014

26 Oct 2014

GCL

Broad Permit for Works at Seafront & Marine Piers & Pier B9

Construction Noise Permit for night works and works in general holidays

GW-RS0647-14

28 Jun 2014

26 Oct 2014

GCL

Pier C7 & D8 at CEDD Access Road

Marine Dumping Permit

EP/MD/15-028

1 Jun 2014

30 Jun 2014

GCL

For dumping Type I (Dedicated Site) and Type II sediment

Construction Noise Permit

GW-RS0792-14

31 Jul 2014

24 Dec 2014

GCL

Broad Permit for Works at Seafront & Marine Piers & Pier B9

Construction Noise Permit

GW-RS0700-14

21 Jul 2014

31 Dec 2014

GCL

For loading & unloading on NLH near Viaduct A & B

Construction Noise Permit

GW-RW0640-14

28 Aug 2014

27 Feb 2015

GCL

General works at WA5

Marine Dumping Permit

EP/MD/15-065

1 Aug 2014

31 Aug 2014

GCL

For dumping Type I (Dedicated Site) and Type II sediment

2.9                                      Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

2.10                                   Summary of Exceedances of the Environmental Quality Performance Limit

Results for 1-hour TSP, 24-hour TSP, construction noise and impact water quality monitoring complied with the Action/ Limit levels in the reporting period. 
The construction impact on depth-averaged SS was assessed by comparing the quarterly mean values of depth-averaged SS with the relevant ambient mean values.  Results showed that the quarterly mean values of depth-averaged SS at all monitoring stations are well below the ambient mean values (Table 2.18), thus no further action is required in accordance with the Updated EM&A Manual. 

Table 2.18      Comparison between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended Solids

Station

Baseline Mean

Ambient Mean (a)

Quarterly Mean (June 2014 to August 2014)

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

CS(Mf)3

9.2

12.8

12.0

16.6

3.9

3.9

CS(Mf)5

9.2

11.5

12.0

15.0

3.8

4.2

SR4

10.3

12.3

13.4

16.0

4.0

4.1

SR4a

9.1

9.8

11.8

12.7

3.9

4.1

IS8

11.3

13.5

14.7

17.6

4.0

4.2

IS(Mf)9

10.9

14.3

14.2

18.6

4.0

4.1

IS(Mf)16

11.4

10.3

14.8

13.4

4.0

4.1

Notes:

(a) Ambient mean value is defined as a 30% increase of the baseline mean value

Two Action Level exceedances were recorded for impact dolphin monitoring in this reporting quarter.  Following the review of the monitoring data and marine works details as per the procedure stipulated in the Event and Action Plan of the Updated EM&A Manual, the recorded exceedance was considered to be due to natural variation of dolphin ranging pattern.  Investigation findings were detailed in Appendix L.

2.11                                   Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.5.
One (1) complaint was referred by EPD on 23 June 2014 regarding to the discharge of muddy water from Site Access 9A to the nearby storm drains. Complaint investigation was conducted on 25 June 2014 and the interim report was submitted to EPD on 4 July 2014.  The complaint was considered to be not related to the Contract and it was subsequently closed upon further investigation on 30 July 2014.  However, the Contractor was reminded to implement the on-site precautionary measures appropriately for handling the waste water, if any, during rainy season.  The complaint investigation findings are detailed in Appendix N of the Ninth Monthly EM&A Report.
Statistics on complaint, notification of summon of successful prosecution are summarized in Appendix L.

3                                             Future Key Issues

3.1                                      Construction Activities for the Coming Quarter

As informed by the Contractor, the major works for the Contract in the coming quarter are summarized below:

September 2014

Marine Works

¡P         Construction of Pile caps at Viaduct B;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts B & E;

¡P         Marine piling platform installation for Viaduct D; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Construction of pile cap superstructure of Viaduct B;

¡P         Fence installation and relocation of Works Area 2, Viaducts A, B, C & D;

¡P         Land Piling at Viaduct B and Viaduct C;

¡P         Piling platform installation for Viaducts B, C, D and E;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

October 2014

Marine Works

¡P         Construction of Pile caps at Viaduct E;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts A, C, D & E; and

¡P         Additional marine ground investigation (GI) and laboratory testing.

Land-based Works

¡P         Land Piling at Viaducts B, C & D;

¡P         Piling platform installation for Viaducts C & D;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.

November 2014

Marine Works

¡P         Construction of Pile caps at Viaduct E;

¡P         Marine piling platform installation;

¡P         Marine Piling at Viaducts A, C, D & E; and

¡P         Additional marine ground investigation (GI) and laboratory testing

Land-based Works

¡P         Fence installation and relocation of Viaducts A B, & C;

¡P         Land Piling at Viaducts A &D;

¡P         Piling platform installation for Viaducts C & D;

¡P         Additional land GI, trial pits & lab testing;

¡P         Utility surveys; and

¡P         Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9

3.2                                      Key Issues for the Coming Quarter

Potential environmental impacts arising from the above upcoming construction activities are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issues.

3.3                                      Monitoring Schedule for the Coming Quarter

Impact monitoring for air quality, noise, marine water quality and marine ecology (include dolphin monitoring and post-translocation coral monitoring) are scheduled to continue for the next reporting period. 

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.

4                                             Conclusions and recommendations

4.1                                      Conclusions

This Third Quarterly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 June to 31 August 2014, in accordance with the Updated EM&A Manual and the requirements of EP-354/2009/B.   

Neither Action Level nor Limit Level exceedances were observed for air quality, noise, water quality impact monitoring and post-translocation coral monitoring in this reporting period. 

A total of twenty eight (28) groups of ninety six (96) Chinese White Dolphin sightings were recorded during the six sets of surveys from June 2014 to August 2014.  Whilst two Action Level exceedances were recorded for the quarterly dolphin monitoring data between June and August 2014, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.  Although the dolphins infrequently occurred along the alignment of TMCLKL southern connection viaduct in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL, and many individuals have shifted away from the important habitat around the Brothers Islands.  It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

Environmental site inspection was carried out thirteen (13) times in the reporting period.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

One (1) environmental complaint regarding the discharge of muddy water and soil from Site Access 9A to the nearby storm drains was received on 23 June 2014 and the interim complaint investigation was undertaken on 25 June 2014.  The complaint was considered to be not related to the Contract and it was subsequently closed upon further investigation on 30 July 2014.

No summons/ prosecution were received during the reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not recommended at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.  The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.


 


([1]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([2]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([3]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.