1.1 Background
1.2 Scope
of Report
1.3 Organization
Structure
1.4 Summary
of Construction Works
1.5 Summary
of EM&A Programme Requirements
2.1 Air
Quality
2.2 Noise
Monitoring
2.3 Water
Quality Monitoring
2.4 Dolphin
Monitoring
2.5 Post-Translocation
Coral Monitoring
2.6 EM&A
Site Inspection
2.7 Waste
Management Status
2.8 Environmental
Licenses and Permits
2.9 Implementation
Status of Environmental Mitigation Measures
2.10 Summary
of Exceedances of the Environmental Quality Performance Limit
2.11 Summary
of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction
Activities for the Coming Quarter
3.2 Key
Issues for the Coming Quarter
3.3 Monitoring
Schedule for the Coming Quarter
4 Conclusions
and recommendations
4.1 Conclusions
List of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule
of Environmental Mitigation Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
Impact Air Quality
Monitoring Results and Graphical Presentation |
Appendix G |
|
Appendix H |
Impact Water Quality
Monitoring Results and Graphical Presentation |
Appendix I |
|
Appendix J |
|
Appendix K |
|
Appendix L |
Under
Contract No. HY/2012/07, Gammon
Construction Limited (GCL) is commissioned by the Highways Department (HyD) to
undertake the design and construction of the Southern Connection Viaduct
Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while
AECOM Asia Company Limited was appointed by HyD as the Supervising
Officer. For implementation of the
environmental monitoring and audit (EM&A) programme under the Contract,
ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker (IEC) and Environmental
Project Office (ENPO) in accordance with Environmental
Permit No. EP-354/2009/A. Another application
for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.
The
construction phase of the Contract commenced on 31 October 2013 and will be
tentatively be completed by 2018.
The impact monitoring of the EM&A programme, including air quality,
noise, water quality and marine ecological monitoring as well as environmental
site inspections, commenced on 31 October 2013.
This
is the third quarterly EM&A report presenting the EM&A works carried
out during the period from 1 June to 31 August 2014 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
June
2014
Marine-based Works
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaduct B;
¡P
Piling platform installation for Viaducts B, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
July 2014
Marine-based
Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaducts B & D;
¡P
Piling platform installation for Viaducts B, C, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys;
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9; and
¡P
Site formation of workshop at Area 1.
August 2014
Marine-based
Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B, D & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaduct B;
¡P
Piling platform installation for Viaducts B, C, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour TSP
monitoring 16
sessions
1-hour TSP
monitoring 16
sessions
Noise
monitoring 16
sessions
Water quality monitoring 39
sessions
Dolphin
monitoring 6
sessions
Joint
Environmental site inspection 13
sessions
Post-Translocation
Coral monitoring 1
session
Breaches of Action and Limit Levels for Air Quality
No exceedance
of Action and Limit Levels was recorded for air quality monitoring in the
reporting period.
Breaches of Action and Limit Levels for Noise
No exceedance
of Action and Limit Levels was recorded for construction noise monitoring in
the reporting period.
Breaches of Action and Limit Levels for Water Quality
No
exceedance of Action and Limit Levels was recorded for impact water quality
monitoring in the reporting period.
Impact Dolphin Monitoring
Whilst
two (2) Action Level exceedances were observed for the quarterly dolphin
monitoring data between June and August 2014, no unacceptable impact from the construction
activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White
Dolphins was noticeable from general observations during the dolphin monitoring
in this reporting quarter. The
exceedances are considered to be the natural variation of Chinese White Dolphin
ranging pattern upon further investigation.
Daily
marine mammal exclusion zone monitoring was undertaken. No sighting of the
Indo-Pacific humpback dolphin Sousa
chinensis (i.e. Chinese White Dolphin) was recorded in the reporting period
during the exclusion zone monitoring.
Post-Translcoation Coral Monitoring
The Third Quarterly Post-Translocation Coral
Monitoring was conducted on 24 July 2014 and no exceedance of Action and
Limit Levels was recorded. The results were detailed in the Third Quarterly Post- Translocation Coral
Monitoring Report and were submitted under a separate cover.
Environmental Complaints, Non-compliance & Summons
One
(1) complaint was referred by the EPD on 23 June 2014 which was considered to
be not related to this Contract upon further investigation.
No
notification of summons and successful prosecution was received in the
reporting period.
Reporting Change
There
was no reporting change required in the reporting period.
Upcoming Works
for the Next Reporting Period
Works
to be undertaken in the coming quarter include the following:
September
2014
Marine Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Marine piling platform installation for Viaduct D; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Works Area
2, Viaducts A, B, C & D;
¡P
Land Piling at Viaduct B and Viaduct C;
¡P
Piling platform installation for Viaducts B, C, D and
E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 &
9SE-B/F9.
October 2014
Marine
Works
¡P
Construction of Pile caps at Viaduct E;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts A, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Land Piling at Viaducts B, C & D;
¡P
Piling platform installation for Viaducts C & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
November 2014
Marine
Works
¡P
Construction of Pile caps at Viaduct E;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts A, C, D & E; and
¡P
Additional marine ground investigation (GI) and
laboratory testing.
Land-based
Works
¡P
Fence installation and relocation of Viaducts A, B,
& C;
¡P
Land Piling at Viaducts A &D;
¡P
Piling platform installation for Viaducts C & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the coming quarterly period are mainly associated with air quality, noise, marine
water quality, marine ecology and waste management issue.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge,
Lantau Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based
on the estimated increase in cross boundary traffic, developments in the Northwest
New Territories (NWNT), and possible developments in North Lantau, including
the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V
Zhuhai ¡V Macao Bridge (HZMB). In
order to cope with the anticipated traffic demand, two new road sections
between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen
Mun Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007)
and the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The EIA
Report was submitted under the Environmental Impact Assessment Ordinance (EIAO)
in August 2009. Subsequent to the
approval of the EIA Report (EIAO Register Number: AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL
was granted by the Director of Environmental Protection (DEP) on 4 November
2009, and EP variation (EP-354/2009A)
was issued on 8 December 2010. Another application
for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.
Under Contract No. HY/2012/07, Gammon
Construction Limited (GCL) is commissioned by the Highways Department (HyD) to
undertake the design and construction of the Southern Connection Viaduct
Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia
Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong,
Limited (ERM) has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
HyD as the Independent Environmental Checker (IEC) and Environmental Project
Office (ENPO) in accordance with Environmental
Permit No. EP-354/2009/A.
The
organization structure of the Contract is shown in Appendix A.
The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident
Engineer |
Kingman Chan |
3691 2950 |
3691 2899 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465 2888 |
3465 2899 |
IEC |
Dr. F.C.
Tsang |
3465 2828 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
June
2014
Marine-based Works
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaduct B;
¡P
Piling platform installation for Viaducts B, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
July 2014
Marine-based
Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaducts B & D;
¡P
Piling platform installation for Viaducts B, C, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys;
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9; and
¡P
Site formation of workshop at Area 1.
August 2014
Marine-based
Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B, D & E;
¡P
Construction of rockfill platform at Viaduct D landing; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Area 2, Viaducts A, B, C
& D;
¡P
Land Piling at Viaduct B;
¡P
Piling platform installation for Viaducts B, C, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
The
locations of the construction activities are shown in Figure 1.3. The Environmental Sensitive Receivers in
the vicinity of the Project are shown in Figure 1.4.
The EM&A
programme required environmental monitoring for air quality, noise, water
quality and marine ecology as well as environmental site inspections for air
quality, noise, water quality, waste management, marine ecology and landscape
and visual impacts. The EM&A
requirements and related findings for each component are described in the
following sections, which include:
¡P
Monitoring parameters;
¡P
Monitoring schedules for the reporting months and
forthcoming months;
¡P
Action and Limit levels for all environmental
parameters;
¡P
Event Action Plan;
¡P
Results and observations;
¡P
Environmental mitigation measures, as recommended in
the approved EIA Report; and
¡P
Environmental requirement in contract documents.
The EM&A
programme required environmental monitoring for air quality, noise, water
quality and marine ecology as well as environmental site inspections for air
quality, noise, water quality, waste management, marine ecology and landscape
and visual impacts. The EM&A
requirements and related findings for each component are summarized in the
following sections.
The baseline
air quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡VMacao Bridge Hong
Kong Projects (HKZMB) during October 2011 has included the two monitoring
stations ASR9A and ASR9C for this project.
Thus, the baseline monitoring results and Action/ Limit Level presented
in HKZMB Baseline Monitoring Report ([1]) are
adopted for this Project.
Wind
data monitoring equipment has been installed at the rooftop of Pak Mong Village
Watch Tower during the reporting period for logging wind speed and wind
direction. The wind sensor was
setup such as it was clear of obstructions or turbulence caused by
building. The wind data monitoring
equipment is recalibrated at least once every six months.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations and Monitoring Dates in this
Reporting Period
Monitoring Station (1) |
Monitoring Period |
Location |
Description |
Parameters & Frequency |
ASR8A |
3,
9, 13, 19, 25 and 30 June; 5, 11, 17, 23 and 29 July; 4, 8, 14, 20 and 26
August 2014 |
Area 4 |
On ground at
the Area 4 |
1-hour Total Suspended Particulates (1-hour
TSP, µg/m3), 3 times per day every 6 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour every 6 days |
ASR8 |
Pak Mong
Village Watch Tower |
Rooftop of
the premise |
Note:
(1) Air Quality Monitoring Stations ASR9A and ASR9C at Siu
Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were
temporarily relocated to ASR 8A and ASR8, respectively.
Table
2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental
Mass Flow Controlled Total Suspended Particulate
(TSP) High Volume Sampler (Model No. TE-5170) |
Wind Sensor |
Global Water (Wind
Speed Sensor: WE550; Wind Direction Sensor: WE570) |
Wind Anemometer for
calibration |
Lutron (Model No.
AM-4201) |
The Action and
Limit Levels of the air quality monitoring is provided in Appendix D. The Event and Action plan is presented
in Appendix J.
The schedules
for air quality monitoring in the reporting quarter is provided in Appendix E.
The monitoring
results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4,
respectively. Monitoring results
are presented graphically in Appendix F and
detailed impact air quality monitoring results and meteorological information were
reported in the Eighth to Tenth Monthly EM&A Report.
Table
2.3 Summary
of 1-hour TSP Monitoring Results in this Reporting Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
June 2014 |
ASR 8A |
73 |
47
- 131 |
394 |
500 |
ASR 8 |
70 |
49
- 115 |
393 |
500 |
|
July 2014 |
ASR 8A |
60 |
40
- 74 |
394 |
500 |
|
ASR 8 |
67 |
52
- 102 |
393 |
500 |
August 2014 |
ASR 8A |
69 |
43
- 113 |
394 |
500 |
|
ASR 8 |
67 |
43
- 116 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in this Reporting Period
Month |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
June 2014 |
ASR
8A |
54 |
39
- 69 |
178 |
260 |
ASR
8 |
53 |
40
- 68 |
178 |
260 |
|
July 2014 |
ASR
8A |
43 |
38
- 47 |
178 |
260 |
|
ASR
8 |
42 |
36
- 47 |
178 |
260 |
August 2014 |
ASR
8A |
41 |
40
- 43 |
178 |
260 |
|
ASR
8 |
43 |
41
- 45 |
178 |
260 |
The major dust
sources in the reporting period include construction activities under the
Contract as well as nearby traffic emissions.
In this
reporting period, a total of sixteen (16) monitoring events were undertaken
within the reporting period, in which no Action or Limit Level exceedances for 1-hr
and 24-hr TSP for air quality were recorded during the reporting period.
The baseline
noise monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge Hong Kong
Projects (HKZMB) during the period of 18 October to 1 November 2011 has
included the monitoring station NSR1 for this project. Thus, the baseline monitoring results
and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([2]) are
adopted for this Project.
Monitoring
location was set up at NSR1 in accordance with the Updated EM&A
Manual. Figure 2.2 shows
the location of the monitoring station.
Table 2.5 describes the
details of the monitoring station.
Noise
monitoring was performed using sound level meter at each designated monitoring
station. The sound level meters
deployed comply with the International Electrotechnical Commission Publications
(IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Brand and model of the equipment is given in Table 2.6.
Table 2.5 Location of Impact Noise
Monitoring Station and Monitoring Dates in this Reporting Period
Monitoring Station |
Monitoring Period |
Location |
Parameters & Frequency |
NSR1 |
June 2014 to
August 2014 |
Pak Mong
Village Watch Tower |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10 and L90 would
be recorded. At
least once a week |
Table 2.6 Noise Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion NL-31 |
Acoustic
Calibrator |
Rion NC-73 |
The Action and
Limit levels of the noise monitoring are provided in Appendix D. The Event and Action plan is presented
in Appendix J.
The schedules
for noise monitoring in the reporting quarter is provided in Appendix E.
The monitoring
results for noise monitoring are summarized in Table 2.7. Monitoring
results are presented graphically in Appendix G and
detailed impact noise monitoring results are reported in the Eighth to Tenth Monthly EM&A Report.
Table 2.7 Summary of Construction Noise
Monitoring Results at NSR1 in the Reporting Period
Month |
Average , dB(A), Leq
(30mins) |
Range, dB(A), Leq
(30mins) |
Limit Level, dB(A), Leq
(30mins) |
June 2014 |
58 |
55 - 59 |
75 |
July 2014 |
57 |
56 - 58 |
75 |
August 2014 |
56 |
54 - 57 |
75 |
The baseline
water quality monitoring undertaken by the Hong Kong ¡V Zhuhai ¡V Macao Bridge
Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all
monitoring stations except SR4a for the Project. Thus, the baseline monitoring results
except for station SR4a and Action/Limit Level presented in HKZMB Baseline
Monitoring Report ([3]) are
adopted for this Project. Baseline
water quality monitoring was conducted at station SR4a from 29 August to 24
September 2013.
Table 2.8 Locations
of Water Quality Monitoring Stations and the Corresponding Monitoring
Requirements
Station ID |
Type |
Coordinates |
*Parameters, unit |
Depth |
Frequency |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH(pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) ¡P
SS (mg/L) |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth may be omitted. |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract. |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station(Close
to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
Notes: In addition to the parameters presented monitoring location/position,
time, water depth, sampling depth, tidal stages, weather conditions and any
special phenomena or works underway nearby were also recorded. |
Table 2.9 summarizes the equipment used in the impact water quality monitoring
programme.
Table
2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO, Temperature meter and Salinity |
YSI Pro2030 |
Turbidimeter |
HACH Model 2100Q |
pH meter |
HANNA HI8314 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
Water Depth Detector |
Speedtech Instrument SM-5 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
The schedules
for water quality monitoring in the reporting quarter are provided in Appendix E.
Impact water
quality monitoring was conducted at all designated monitoring stations in the
reporting period. Monitoring
results are presented graphically in Appendix H and
detailed impact water quality monitoring results were reported in the Eighth to Tenth Monthly EM&A Report.
In this
reporting period, a total of Thirty-nine (39) monitoring events were undertaken
in which no Action or Limit Level exceedance were recorded during the reporting
quarter.
Impact dolphin
monitoring is required to be conducted by a qualified dolphin specialist team
to evaluate whether there have been any effects on the dolphins. In order to fulfil the EM&A
requirements and make good use of available resources, the on-going impact line
transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to
avoid duplicates of survey effort.
Table 2.10 summarises the equipment used for the impact dolphin
monitoring.
Table 2.10 Dolphin Monitoring Equipment
Equipment |
Model |
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and reticules 65 foot single
engine motor vessel with viewing platform 4.5m above water level |
Dolphin
monitoring should cover all transect lines in Northeast Lantau (NEL) and the
Northwest Lantau (NWL) survey areas twice per month throughout the entire
construction period. The monitoring
data should be compatible with, and should be made available for, long-term
studies of small cetacean ecology in Hong Kong. In order to provide a suitable long-term
dataset for comparison, identical methodology and line transects employed in
baseline dolphin monitoring was followed in the impact dolphin monitoring.
The impact
dolphin monitoring was carried out in the NEL and NWL along the line transect
as depicted in Figure 2.4. The co-ordinates of all transect lines
are shown in Table 2.11 below.
Table 2.11 Impact
Dolphin Monitoring Line Transect Co-ordinates
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
814577 |
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815457 |
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820690 |
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
820847 |
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
820892 |
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818449 |
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
The action and
limit levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented
in Appendix J.
The dolphin
monitoring schedules for the reporting period are shown in Appendix E.
A total of 894.40
km of survey effort was collected, with 93.6% of the total survey effort being
conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or
below with good visibility). Among
the two areas, 343.21 km and 551.19 km of survey effort were conducted in NEL
and NWL survey areas respectively. The
total survey effort conducted on primary lines was 647.96 km, while the effort
on secondary lines was 246.44 km.
Both survey efforts conducted on primary and secondary lines were
considered as on-effort survey data. The survey efforts are summarized in Appendix I.
During the six
sets of monitoring surveys from June to August 2014, a total of twenty eight (28)
groups of ninety six (96) Chinese White Dolphins were sighted. All except two (2) dolphin sightings
were made during on-effort search. Twenty
(20) on-effort sightings were made on primary lines, while another six (6)
on-effort sightings were made on secondary lines. In this quarterly period, almost all
dolphin groups were sighted in NWL, with the exception of one (1) group of four
(4) dolphins being sighted in NEL.
Summary table of the dolphin sightings is shown in Appendix I.
Encounter
rates of Chinese White Dolphins deduced from the survey effort and on-effort
sighting data from the primary transect lines under favourable conditions (Beaufort
3 or below) in the reporting period with the results presented in Tables 2.12 and 2.13.
Table 2.12 Individual Survey Event Encounter
Rates
Survey Area |
Survey period |
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
Primary
Lines Only |
Primary
Lines Only |
||
NEL |
Set
1 (3 & 5 Jun 2014) Set
2 (10 & 16 Jun 2014) Set
3 (3, 9 & 10 Jul 2014) Set
4 (14 & 21 Jul 2014) Set
5 (5 & 6 Aug 2014) Set
6 (15 & 19 Aug 2014) |
0.0 0.0 2.54 0.0 0.0 0.0 |
0.0 0.0 10.16 0.0 0.0 0.0 |
NWL |
Set
1 (3 & 5 Jun 2014) Set
2 (10 & 16 Jun 2014) Set
3 (3, 9 & 10 Jul 2014) Set
4 (14 & 21 Jul 2014) Set
5 (5 & 6 Aug 2014) Set
6 (15 & 19 Aug 2014) |
1.67 0.0 3.03 8.4 5.63 9.7 |
5.0 0.0 10.61 26.6 22.52 40.4 |
Note: Dolphin Encounter Rates are deduced from
the six sets of surveys (two surveys in each set) in the reporting period in
Northeast (NEL) and Northwest Lantau (NWL)
Table 2.13 Quarterly Average Encounter Rates
Survey Area |
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per
100 km of survey effort) |
||
June ¡V August 2014 |
September -November 2011 |
June ¡V August 2014 |
September -November 2011 |
|
Northeast Lantau |
0.42 ¡Ó 1.04 |
6.00 ¡Ó 5.05 |
1.69 ¡Ó 4.15 |
22.19 ¡Ó 26.81 |
Northwest Lantau |
4.74 ¡Ó 3.84 |
9.85 ¡Ó 5.85 |
17.52 ¡Ó 15.12 |
44.66 ¡Ó 29.85 |
Note:
encounter rates deduced from the baseline monitoring period have been
recalculated based only on survey effort and on-effort sighting data made along
the primary transect lines under favourable conditions
Table 2.14 Comparison of Quarterly Average
Encounter Rates
|
Average Dolphin Group Size |
|
June ¡V August 2014 |
September -November 2011 |
|
Overall |
3.43 ¡Ó 1.95 (n = 28) |
3.72 ¡Ó 3.13 (n = 66) |
Northeast Lantau |
4.00 ¡Ó 0.00 (n = 1) |
3.18 ¡Ó 2.16 (n = 17) |
Northwest Lantau |
3.41 ¡Ó 1.99 (n = 27) |
3.92 ¡Ó 3.40 (n = 49) |
Daily 250 m marine
mammal exclusion zone monitoring was undertaken under this Contract. No sighting of the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White
Dolphin) was recorded in the reporting period during the exclusion zone
monitoring.
The third quarterly
Coral Post-Translocation Monitoring was conducted on 24 July 2014 and the results
were provided in the Third Quarterly
Post-Translocation Coral Monitoring Report submitted under a separate cover. The findings indicated that the Action
or Limit Levels for coral monitoring were not exceeded as increase in
percentage of partial mortality was not detected for both the tagged translocated
and natural coral colonies when comparing to the pre-translocation dataset.
Site
inspections were carried out on a weekly basis to monitor the implementation of
proper environmental pollution control and mitigation measures under the
Contract. Thirteen (13) site
inspections were carried out in the reporting quarter on 4, 11, 19 and 25 June
2014; 2, 10, 16, 24 and 31 July 2014; 6, 14, 21 and 27 August 2014.
Key
observations during the site inspections in this reporting period are summarized
in Table 2.15.
Table 2.15 Specific
Observations Identified during the Weekly Site Inspection in this Reporting
Period
Inspection Date |
Location & Environmental Observations |
Recommendations/ Remarks |
4 June 2014 |
Pier E9 ¡P
Decoupling pad was not placed underneath the water
pump and generator Pier E10 |
Pier E9 ¡P
The Contractor was reminded to place the decoupling
pad Pier E10 |
|
¡P
Chemical containers were placed at site without drip
tray ¡P
Oil stain was seen underneath the crane. |
¡P
The Contractor was reminded to place the chemical
containers in drip tray properly ¡P
The Contractor was reminded to maintain all plants
in properly and oil stain was immediately absorbed by absorbent. |
11 June 2014 |
Pier B9 |
Pier B9 |
|
¡P
Drip tray was not plugged. |
¡P
The Contractor was reminded to plug the drip tray
properly |
|
Seafront |
Seafront |
|
¡P
No acoustic decoupling pad was found for generators
on platform. ¡P
Chemical containers were not placed in drip tray. ¡P
Drip trays for generators next to the office have no
stopper |
¡P
Acoustic decoupling pad was suggested to be placed
underneath the generators on platform ¡P
Chemical containers at site should be placed in drip
tray. ¡P
All drip trays used at site should be properly
plugged. |
19 June 2014 |
Rockfill
platform at Seafront. |
Rockfill
platform at Seafront |
|
¡P
A drip tray was found not plugged. Barge G23 ¡P
Chemical containers were not placed in drip tray ¡P
Labels of chemical waste was found dropped off Pier B2 ¡P
Drip tray was not plugged properly |
¡P
The Contractor was reminded to plug the drip tray. Barge G23 ¡P
Chemical containers should be provided for chemical
containers ¡P
All chemical waste containers should be
well-labelled Pier B2 ¡P
The Contractor was reminded to plug drip tray
properly |
25 June 2014 |
Pier B15 |
Pier B15 |
|
¡P
Two chemical containers were placed without drip
tray ¡P
General refuse was observed scattered onsite |
¡P
The Contractor was advised to put them on drip tray
properly ¡P
The Contractor was advised to clear off any general
refuse properly |
|
Pier B16 |
Pier B16 |
|
¡P
Stagnant water was observed to be present in drip
tray of a generator |
¡P
The Contractor was advised to clear away any
stagnant water accumulated in drip tray in timely manner |
|
¡P
Stagnant water was observed to be accumulated in pit
which is for placing excavated materials |
¡P
The Contractor was advised to clear away any
stagnant water accumulated in pits in timely manner |
2 July 2014 |
Area 2 ¡P
Tarpaulin sheet was required for grouting. ¡P
Chemical waste was not placed in drip tray. Pier B15 ¡P
General refuse was disposed improperly. Pier B11 ¡P
More sandbags were needed to avoid runoff. Area 1 A
rubbish bin was label incorrectly. |
Area 2 ¡P
Tarpaulin sheet should be provided for grouting. ¡P
Chemical waste should be placed in drip tray. Pier B15 ¡P
General refuse should be removed. Pier B11 ¡P
More sandbags should be added. Area 1 ¡P
The label was removed immediately. |
10 July 2014 |
Seafront |
Seafront |
|
¡P
Refuse was disposed improperly. ¡P
Oil stain was observed on the ground. ¡P
Chemical containers were not placed in drip tray. ¡P
A drip tray was unplugged. |
¡P
The Contractor was reminded to maintain good
housekeeping. ¡P
Oil stain should be removed. ¡P
Chemical containers should be placed in drip tray. ¡P
The drip tray should be plugged. |
|
Barge M025 |
Barge M025 |
|
¡P
Chemical containers were not placed in drip tray. |
¡P
Chemical containers should be placed in drip tray. |
16 July 2014 |
Area 2 |
Area 2 |
|
¡P
Sandbags were considered insufficient. ¡P
The unpaved slope was not well cover by tarpaulin
sheet. ¡P
Drainage was not fully protected from runoff. |
¡P
More sandbags should be provided. ¡P
The unpaved slope should be entirely covered by
tarpaulin sheet. ¡P
More sandbags should be provided to prevent runoff. |
24 July 2014 |
Seafront |
Seafront |
|
¡P
Chemical containers were not placed in drip tray. Pier E3 ¡P
Dumping permit was expired. |
¡P
Chemical containers should be placed in drip tray. Pier E3 ¡P
The Contractor was reminded to renew the dumping
permits regularly. |
31 July 2014 |
Pak Mong ¡P
General refuse was observed in the project area. ¡P
Sandbags were not enough to avoid surface runoff. Pier E3 ¡P
Stagnant water was observed on the platform. ¡P
The acoustic decoupling pad was not deployed
properly beneath the generators. Pier E11 ¡P
The acoustic decoupling pad was not deployed
properly beneath the generators. ¡P
A drip tray was found unplugged. |
Pak Mong ¡P
The Contractor was reminded to maintain good
housekeeping. ¡P
The Contractor was reminded to provide sufficient
sandbags to prevent runoff. Pier E3 ¡P
Stagnant water was removed immediately. ¡P
The Contractor was reminded to place the acoustic
decoupling pad beneath the generators properly. Pier E11 ¡P
The Contractor was reminded to place the acoustic
decoupling pad beneath the generators properly. ¡P
A drip tray stopper should be provided. |
6 August
2014 |
Site Access
9A ¡P
Chemical containers were not placed in drip tray. ¡P
A drip tray was found unplugged. Slope next
to NL1 ¡P
Drainage was filled with trash. Site Access
9B ¡P
Chemical containers were not placed in drip tray. Slope BC8 ¡P
Tarpaulin sheet for soil nail on unpaved slope was
not cover properly. |
Site Access
9A ¡P
Chemical Containers should be placed in drip tray. ¡P
The contractor should provide stopper to the drip
tray. ¡P
Slope next to NL1 The
contractor was reminded to clean up the drainage regularly. Site Access
9B ¡P
Chemical Containers should be placed in drip tray. Slope BC8 ¡P
Soil nail on unpaved slope should be well covered. |
14 August
2014 |
Pier B1 |
Pier B1 |
|
¡P
A drip tray was found unplugged. ¡P
Stagnant water was found in a drip tray. Pier
A,C&D1 ¡P
A drip tray of generator could not be covered well
by screen. ¡P
Stagnant water was found in a drip tray. ¡P
A drip tray was found unplugged. |
¡P
The drip tray should be plugged. ¡P
Stagnant water in drip tray should be cleared. Pier
A,C&D1 ¡P
The screen was improved immediately and able to
cover the drip tray of generator properly. ¡P
Stagnant water in drip tray should be cleared. ¡P
The drip tray should be plugged. |
|
Pier E4 |
Pier E4 |
|
¡P
Muddy water was accumulated on the platform. ¡P
A label of waste category label was missing. |
Muddy
water should be cleared. Waste
category label should be labelled properly. |
21 August
2014 |
Pier B1 |
Pier B1 |
|
¡P
Stagnant water was accumulated in a drip tray. Pier E10 ¡P
Chemical containers were not labelled properly. ¡P
Soil and sand were accumulated on the platform. Slope BC9 ¡P
Soil and mud was observed accumulating in drainage. |
¡P
Stagnant water in a drip tray should be cleared. Pier E10 ¡P
Chemical containers should be labelled properly. ¡P
Soil and sand on the platform were cleaned up
immediately. Slope BC9 ¡P
Soil and mud in drainage should be cleared
regularly. |
27 August
2014 |
Slope BC9 |
Slope BC9 |
|
¡P
A chemical container was not placed in drip tray. ¡P
An unpaved slope was not covered. ¡P
Refuse was observed on the slope. ¡P
A part of bund was missing at the path on slope. Pier B15 ¡P
A drip tray was found unplugged. |
¡P
The chemical container was removed intermediately. ¡P
The unpaved slope should be covered by tarpaulin
sheet. ¡P
Refuse on the slope should be removed. ¡P
The Contractor was reminded to implement
precautionary measures for preventing soil and sand runoff from the slope. Pier B15 ¡P
The drip tray should be plugged. |
Wastes
generated during this reporting period include mainly construction wastes
(inert and non-inert), imported fill, recyclable materials, and marine
sediments. Reference has been made
to the waste flow table prepared by the Contractor (Appendix K). The quantities of different types of
wastes are summarized in Table 2.16.
Table 2.16 Quantities
of Different Waste Generated in the Reporting Period
Month/Year |
Inert Construction Waste (a)
(m3) |
Imported Fill (m3) |
Inert Construction Waste
Re-used (m3) |
Non-inert Construction Waste (b)
(tonnes) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
|
Category L |
Category M |
|||||||
June 2014 |
357 |
2,457 |
2,503 |
77.29 |
25,480 |
0 |
338 |
0 |
July 2014 |
4,654 |
1,629 |
20 |
87.81 |
27,496 |
0 |
847 |
303 |
August 2014 |
2,441 |
288 |
2,094 |
98.22 |
22,281 |
0 |
391 |
164 |
Total |
7,452 |
4,374 |
4,617 |
263.32 |
75,257 |
0 |
1,576 |
467 |
Notes: |
||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. |
The Contractor
was advised to properly maintain on site C&D materials and waste
collection, sorting and recording system, dispose of C&D materials and
wastes at designated ground and maximize reuse/ recycle of C&D materials
and wastes. The Contractor was also
reminded to properly maintain the site tidiness and dispose of the wastes
accumulated on site regularly and properly.
For chemical
waste containers, the Contractor was reminded to treat properly and store temporarily
in designated chemical waste storage area on site in accordance with the Code
of Practice on the Packaging, Labelling and Storage of Chemical Wastes.
The status of
environmental licensing and permit is summarized in Table 2.17 below.
Table
2.17 Summary
of Environmental Licensing and Permit Status
License/
Permit |
License
or Permit No. |
Date of Issue |
Date of Expiry |
License/
Permit Holder |
Remarks |
Environmental Permit |
EP-354/2009/A |
8 Dec 2010 |
NA |
HyD |
Tuen Mun- Chek Lap Kok Link |
Environmental Permit |
EP-354/2009/B |
28 Jan 2014 |
NA |
HyD |
Tuen Mun- Chek Lap Kok Link |
Construction Dust Notification |
361571 |
5 Jul 2013 |
NA |
GCL |
- |
Construction Dust Notification |
362093 |
17 Jul 2013 |
NA |
GCL |
For Area 23 |
Billing Account for Disposal |
7017735 |
10 Jul 2013 |
End of Project |
GCL |
- |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan) |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong Village) |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 (WA5 adjacent to Cheung Tung Road, Yam O) |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
NA |
GCL |
Waste disposal in Contract HY/2012/07 |
Waste Water Discharge License |
WT00019017-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for marine portion |
Waste Water Discharge License |
WT00019018-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for land portion |
Construction Noise Permit |
Nil |
Application
in process |
NA |
GCL |
For Piling Works |
Construction Noise Permit |
GW-RS0419-14 |
15 May 2014 |
13 Nov 2014 |
GCL |
For loading & unloading on NLH near Viaducts A & B |
Construction Noise Permit |
GW-RS0226-14 |
30 Mar 2014 |
29 Sep 2014 |
GCL |
For loading & unloading on NLH near Viaduct D |
Construction Noise Permit |
GW-RS0299-14 |
7 Apr 2014 |
5 Jul 2014 |
GCL |
Pier B8 at CEDD Access Road |
Construction Noise Permit |
GW-RS0331-14 |
4 Apr 2014 |
6 Jul 2014 |
GCL |
Broad permit for works at seafront
& marine piers |
Construction Noise Permit |
GW-RS0338-14 |
4 Apr 2014 |
3 Jun 2014 |
GCL |
For bored piling works between Pier
E13 and HKBCF |
Construction Noise Permit |
GW-RS1423-13 |
11 Dec 2013 |
30 Apr 2014 |
GCL |
Renewal for marine portion |
Construction Noise Permit |
GW-RW0123-14 |
27 Feb 2014 |
27 Aug 2014 |
GCL |
For night works and works in general holiday at WA5 |
Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal) |
(4) in EP/MD/14-075 |
25 Sep 2013 |
NA |
GCL |
- |
Marine Dumping Permit |
EP/MD/14-075 |
28 Jan 2014 |
27 Jul 2014 |
GCL |
For dumping Type I Sediment |
Marine Dumping Permit |
EP/MD/15-028 |
1 Jun 2014 |
30 Jun 2014 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Chemical Waste Registration |
5213-951-G2380-17 |
12 Jun 2014 |
NA |
GCL |
Viaducts A, B, C, D & E |
Construction Noise Permit for night works and works in general
holidays |
GW-RS0646-14 |
27 Jun 2014 |
26 Oct 2014 |
GCL |
Broad Permit for Works at Seafront & Marine Piers & Pier B9 |
Construction Noise Permit for night works and works in general
holidays |
GW-RS0647-14 |
28 Jun 2014 |
26 Oct 2014 |
GCL |
Pier C7 & D8 at CEDD Access Road |
Marine Dumping Permit |
EP/MD/15-028 |
1 Jun 2014 |
30 Jun 2014 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Construction Noise Permit |
GW-RS0792-14 |
31 Jul 2014 |
24 Dec 2014 |
GCL |
Broad Permit for Works at Seafront & Marine Piers & Pier B9 |
Construction Noise Permit |
GW-RS0700-14 |
21 Jul 2014 |
31 Dec 2014 |
GCL |
For loading & unloading on NLH near Viaduct A & B |
Construction Noise Permit |
GW-RW0640-14 |
28 Aug 2014 |
27 Feb 2015 |
GCL |
General works at WA5 |
Marine Dumping Permit |
EP/MD/15-065 |
1 Aug 2014 |
31 Aug 2014 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
Table 2.18 Comparison
between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended
Solids
Station |
Baseline Mean |
Ambient Mean (a) |
Quarterly Mean (June 2014 to August
2014) |
|||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|
CS(Mf)3 |
9.2 |
12.8 |
12.0 |
16.6 |
3.9 |
3.9 |
CS(Mf)5 |
9.2 |
11.5 |
12.0 |
15.0 |
3.8 |
4.2 |
SR4 |
10.3 |
12.3 |
13.4 |
16.0 |
4.0 |
4.1 |
SR4a |
9.1 |
9.8 |
11.8 |
12.7 |
3.9 |
4.1 |
IS8 |
11.3 |
13.5 |
14.7 |
17.6 |
4.0 |
4.2 |
IS(Mf)9 |
10.9 |
14.3 |
14.2 |
18.6 |
4.0 |
4.1 |
IS(Mf)16 |
11.4 |
10.3 |
14.8 |
13.4 |
4.0 |
4.1 |
Notes: |
||||||
(a)
Ambient mean value is defined as a 30% increase of the baseline mean value |
Two Action
Level exceedances were recorded for impact dolphin monitoring in this reporting
quarter. Following the review of
the monitoring data and marine works details as per the procedure stipulated in
the Event and Action Plan of the Updated EM&A Manual, the recorded
exceedance was considered to be due to natural variation of dolphin ranging
pattern. Investigation findings
were detailed in Appendix L.
September
2014
Marine Works
¡P
Construction of Pile caps at Viaduct B;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts B & E;
¡P
Marine piling platform installation for Viaduct D; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Construction of pile cap superstructure of Viaduct B;
¡P
Fence installation and relocation of Works Area 2, Viaducts
A, B, C & D;
¡P
Land Piling at Viaduct B and Viaduct C;
¡P
Piling platform installation for Viaducts B, C, D and E;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
October 2014
Marine
Works
¡P
Construction of Pile caps at Viaduct E;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts A, C, D & E; and
¡P
Additional marine ground investigation (GI) and laboratory
testing.
Land-based
Works
¡P
Land Piling at Viaducts B, C & D;
¡P
Piling platform installation for Viaducts C & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
November 2014
Marine
Works
¡P
Construction of Pile caps at Viaduct E;
¡P
Marine piling platform installation;
¡P
Marine Piling at Viaducts A, C, D & E; and
¡P
Additional marine ground investigation (GI) and laboratory testing
Land-based
Works
¡P
Fence installation and relocation of Viaducts A B, & C;
¡P
Land Piling at Viaducts A &D;
¡P
Piling platform installation for Viaducts C & D;
¡P
Additional land GI, trial pits & lab testing;
¡P
Utility surveys; and
¡P
Slope work of Slopes 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9
Potential
environmental impacts arising from the above upcoming construction activities are
mainly associated with air quality, noise, marine water quality, marine ecology
and waste management issues.
Impact
monitoring for air quality, noise, marine water quality and marine ecology
(include dolphin monitoring and post-translocation coral monitoring) are
scheduled to continue for the next reporting period.
The monitoring
programme has been reviewed and was considered as adequate to cater for the
nature of works in progress.
This Third Quarterly
EM&A Report presents the findings of the EM&A activities undertaken
during the period from 1 June to 31 August 2014, in accordance with the Updated
EM&A Manual and the requirements of EP-354/2009/B.
Neither Action
Level nor Limit Level exceedances were observed for air quality, noise, water
quality impact monitoring and post-translocation coral monitoring in this
reporting period.
A total of twenty
eight (28) groups of ninety six (96) Chinese White Dolphin sightings were
recorded during the six sets of surveys from June 2014 to August 2014. Whilst two Action Level exceedances were
recorded for the quarterly dolphin monitoring data between June and August 2014,
no unacceptable impact from the activities of this Contract on Chinese White
Dolphins was noticeable from the general observations. Although the dolphins infrequently occurred
along the alignment of TMCLKL southern connection viaduct in the past and
during the baseline monitoring period, it is apparent that dolphin usage has
been significantly reduced in NEL, and many individuals have shifted away from
the important habitat around the Brothers Islands. It is critical to monitor the dolphin
usage in North Lantau region in the upcoming quarters, to determine whether the
dolphins are continuously affected by the various construction activities in
relation to the HZMB-related works, and whether suitable mitigation measure can
be applied to revert the situation.
Environmental
site inspection was carried out thirteen (13) times in the reporting period. Recommendations on remedial actions were
given to the Contractor for the deficiencies identified during the site audits.
No summons/
prosecution were received during the reporting period.
The monitoring
programme has been reviewed and was considered as adequate to cater for the
nature of works in progress. Change
to the monitoring programme was thus not recommended at this stage. The monitoring programme will be
evaluated as appropriate in the next reporting period. The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
([1])
Agreement No. CE 35/2011 (EP) Baseline
Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong
Projects - Investigation.
Baseline Environmental Monitoring Report (Version C). Submitted on 8 March 2012 and
subsequently approved by EPD.