Table of Contents

                        executive Summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Scope of Report                                                                   

1.3                   Organization Structure                                                 

1.4                   Summary of Construction Works                              

1.5                   Summary of EM&A Programme Requirements        

2                      Air quality                                                                               

2.1                   Monitoring Requirements                                               

2.2                   Monitoring Equipment                                                       

2.3                   Monitoring Locations                                                       

2.4                   Monitoring Parameters, Frequency and Duration 

2.5                   Monitoring methodology                                               

2.6                   Monitoring Schedule for the Reporting Month 

2.7                   Results and Observations                                             

3                      nOISE MONITORING                                                                  

3.1                   Monitoring Requirements                                               

3.2                   Monitoring Equipment                                                       

3.3                   Monitoring Locations                                                       

3.4                   Monitoring Parameters, Frequency and Duration 

3.5                   Monitoring Methodology                                               

3.6                   Monitoring Schedule for the Reporting Month 

3.7                   Monitoring Results                                                            

4                      Water Quality MOnitoring                                              

4.1                   Monitoring Requirements                                               

4.2                   Monitoring equipment                                                       

4.3                   Monitoring Parameters, Frequency and Duration 

4.4                   Monitoring Locations                                                       

4.5                   Monitoring methodology                                               

4.6                   Monitoring Schedule for the Reporting Month 

4.7                   Results and Observations                                             

5                      Dolphin monitoring                                                            

5.1                   monitoring requirements                                               

5.2                   monitoring equipment                                                       

5.3                   Monitoring Parameter, Frequencies and Duration

5.4                   Monitoring Location                                                          

5.5                   Monitoring Schedule for the Reporting Month 

5.6                   Results and Observations                                             

6                      Bore piling monitoring                                                     

6.1                   Monitoring Requirements                                               

6.2                   Monitoring Frequencies                                                  

6.3                   Monitoring Location                                                          

6.4                   Monitoring Methodology                                               

7                      Environmental site inspection and audit               

7.1                   Site Inspection                                                                       

7.2                   Waste Management Status                                             

7.3                   Environmental Licenses and Permits                        

7.4                   Implementation Status of Environmental Mitigation Measures  

7.5                   Summary of Exceedances of the Environmental Quality Performance Limit                                                                                                       

7.6                   Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                         

8                      Future Key Issues                                                                

8.1                   Construction Programme for the Coming Months

8.2                   Key Issues for the Coming Month                                

8.3                   Monitoring Schedule for the Coming Month        

9                      Conclusions and recommendations                         

9.1                   Conclusions                                                                           

9.2                   Recommendations                                                                

 

List of Tables

Table 1.1

Contact Information of Key Personnel

Table 2.1

Air Quality Monitoring Equipment

Table 2.2

Locations of Impact Air Quality Monitoring Stations

Table 2.3

Air Quality Monitoring Parameters, Frequency and Duration

Table 2.4

Summary of 1-hour TSP Monitoring Results in the Reporting Period

Table 3.1

Noise Monitoring Equipment

Table 3.2

Location of Impact Noise Monitoring Station

Table 3.3

Noise Monitoring Parameters, Frequency and Duration

Table 3.4

Summary of Construction Noise Monitoring Results in the Reporting Period

Table 4.1

Water Quality Monitoring Equipment

Table 4.2

Monitoring Parameters, Frequency and Duration

Table 4.3

Locations of Impact Water Quality Monitoring Stations

Table 4.4

Laboratory Analysis for Suspended Solids

Table 5.1

Dolphin Monitoring Equipment

Table 5.2

Impact Dolphin Monitoring Line Transect Co-ordinates

Table 5.3

Individual Survey Event Encounter Rates

Table 5.4

Monthly Average Encounter Rates

Table 6.1   

Bore Piling Monitoring Frequency

Table 6.2

Bore Piling Monitoring Locations

Table 7.1

Summary of Environmental Licensing and Permit Status

 

Figures

Figure 1.1

General Project Layout Plan

Figure 1.2

Location Plan and Key Plan

Figure 1.3

General Layout

Figure 1.4

Proposed Ground Investigation Plan (Sheet 1 of 8)

Figure 1.5

Proposed Ground Investigation Plan (Sheet 2 of 8)

Figure 1.6

Proposed Ground Investigation Plan (Sheet 3 of 8)

Figure 1.7

Proposed Ground Investigation Plan (Sheet 4 of 8)

Figure 1.8

Proposed Ground Investigation Plan (Sheet 5 of 8)

Figure 1.9

Proposed Ground Investigation Plan (Sheet 6 of 8)

Figure 1.10

Works Area and Hoarding Plan (Sheet 1 of 2)

Figure 1.11

Works Area and Hoarding Plan (Sheet 2 of 2)

Figure 1.12

Location of Area 4

Figure 2.1

Locations of Impact Air Quality Monitoring Stations

Figure 3.1

Locations of Impact Noise Monitoring Station

Figure 4.1

Locations of Impact Water Quality Stations

Figure 5.1

Line Transects for Impact Dolphin Monitoring Survey

Figure 5.2

Locations of Dolphin Sightings during Impact Dolphin Monitoring Survey

Figure 7.1

Environmental Complaint Handling Procedure

 

List of Appendices

Appendix A

Project Organization for Environmental Works

Appendix B

Three Month Rolling Construction Programmes

Appendix C

Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D

Summary of Action and Limit Levels

Appendix E

Calibration Certificates of Monitoring Equipments

Appendix F

EM&A Monitoring Schedules

Appendix G

Impact Air Quality Monitoring Results and Graphical Presentation

Appendix H

Meteorological Data for the Reporting Month

Appendix I

Impact Noise Monitoring Results and Graphical Presentation

Appendix J

Impact Water Quality Monitoring Results and Graphical Presentation

Appendix K

Impact Dolphin Monitoring Survey Results

Appendix L

Event Action Plan

Appendix M

Monthly Summary of Waste Flow Table

Appendix N

Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

           

           

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. .  

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the first monthly EM&A report presenting the EM&A works carried out during the period from 31 October to 30 November 2013 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

Marine-based Works

¡P      Ground investigation (GI) work at marine piers;

¡P      Survey towers erection; and

¡P      Filling platform at seawall.

Land-based Works

¡P      Additional GI fieldwork, laboratory testing and permitting;

¡P      Application for tree felling and transplanting;

¡P      Site office relocation;

¡P      Fence relocation at Viaduct A, C and D;

¡P      Site offices erection; and

¡P      Temporary access bridge (TAB).

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                       5 sessions

1-hour TSP monitoring                                   5 sessions

Noise monitoring                                   5 sessions

Impact Water Quality Monitoring                   14 sessions

Impact dolphin monitoring                     2 sessions

Joint Environmental site inspection      4 sessions

Daily marine mammal exclusion zone monitoring was undertaken.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis was recorded in November 2013 during the exclusion zone monitoring.

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Levels was recorded for 1-hour and 24-hour TSP monitoring in the reporting month.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting month.

Breaches of Action and Limit Levels for Water Quality

One (1) exceedance of Action Level in depth-averaged SS was recorded for impact water quality monitoring in the reporting month.  The exceedance was considered not related to the construction works of this Contract upon further investigation.

Impact Dolphin Monitoring

During this month of dolphin monitoring, no adverse impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations.  Due to monthly variation in dolphin occurrence within the study area, it would be more appropriate to draw conclusion on whether any impacts on dolphins have been detected related to the construction activities of the TM-CLKL Southern Connection Viaduct Section in the quarterly EM&A reports, where comparison on distribution, group size and encounter rates of dolphins between the quarterly impact monitoring period and baseline monitoring period will be made.

Environmental Complaints, Non-compliance & Summons

One (1) complaint was referred by EPD on 12 November 2013 and was follow-up timely.  The complaint was considered to be not related to this Contract.

No notification of summons and successful prosecution was received in the reporting month.

Reporting Change

There was no reporting change required in the reporting period.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the next monitoring period of December 2013 include the following:

Marine Works

¡P      GI works at marine piers;

¡P      Filling Platform at seawall; and

¡P      Marine foundation at Viaduct E2, E5-8 and E13.

Land-based Works

¡P      Additional GI fieldwork, laboratory testing and permitting;

¡P      Fence relocation at Viaduct A, C and D; and

¡P      Site offices erection at Area 2, Area 3, Area 5 and seawall.

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the next reporting month of December 2013 are mainly associated with dust, noise, marine water quality, marine ecology and waste management issues.


 

 

1                                             Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

1.2                                      Scope of Report

This is the first monthly EM&A Report under the Contract No. HY/2012/07 Tuen Mun ¡V Chek Lap Kok Link ¡V Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works in October and November 2013.

1.3                                      Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

ENPO / IEC

(ENVIRON Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2888

3465 2899

IEC

 

Tony Cheng

3465 2888

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Manager

 

Brian Kam

2750 0118

2750 0922

Environmental Officer

 

Roy Leung

2750 0118

2750 0922

 

24-hour Complaint Hotline

 

9738 4332

 

ET (ERM-HK)

ET Leader

Jovy Tam

2271 3113

2723 5660

1.4                                      Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The three-month rolling construction programme is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

Marine-based Works

¡P      Ground investigation (GI) work at marine piers;

¡P      Survey towers erection; and

¡P      Filling platform at seawall.

Land-based Works

¡P      Additional GI fieldwork, laboratory testing and permitting;

¡P      Application for tree felling and transplanting;

¡P      Site office relocation;

¡P      Fence relocation at Viaduct A, C and D;

¡P      Site offices erection; and

¡P      Temporary access bridge (TAB).

The general layout plan of the site showing the detailed works areas is shown in Figures 1.1 to 1.12.

The environmental mitigation measures implementation schedule are presented in Appendix C.

1.5                                      Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

-       Monitoring parameters;

-       Monitoring schedules for the reporting month and forthcoming month;

-       Action and Limit levels for all environmental parameters;

-       Event/ Action Plan;

-       Results and observations;

-       Environmental mitigation measures, as recommended in the Project EIA reports; and

-       Environmental requirement in contract documents.

2                                             Air quality

2.1                                      Monitoring Requirements

In accordance with the Updated EM&A Manual, baseline 1-hour and 24-hour TSP levels at two (2) air quality monitoring stations were established.  Impact 1-hour TSP monitoring was conducted three (3) times every six (6) days while the highest dust impact was expected.  Impact 24-hour TSP monitoring was carried out once every six (6) days.  The Action and Limit Level of the air quality monitoring is provided in Appendix D.

2.2                                      Monitoring Equipment

Portable direct reading dust meters were used to carry out the 1-hour TSP monitoring on 5, 11 and 15 November 2013.  High Volume Samplers (HVSs) were used for carrying out 1-hour TSP monitoring on 21 and 27 November 2013 due to the change of monitoring locations from Siu Ho Wan MTR Depot to Pak Mong Village Watch Tower and Area 4 where more reliable power supply is available to power the HVS.  24-hour TSP air quality monitoring was performed using HVS located at each designated monitoring station.  The HVS meets all requirements of the Updated EM&A Manual.  Brand and model of the equipment is given in Table 2.1.  Copies of the calibration certificates for the equipment are presented in Appendix E.

Wind data monitoring equipment was installed at fencing close to ASR9A (Siu Ho Wan MTRC Depot) since 5 November 2013.  It was then installed at the rooftop of Pak Mong Village Watch Tower since 15 November 2013 for logging wind speed and wind direction.  The wind sensor was setup such as it was clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.

Table 2.1        Air Quality Monitoring Equipment

Equipment

Brand and Model

Portable direct reading dust meter
(1-hour TSP)

Sibata Digital Dust Monitor
(Model No. LD-3B)

 

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Sensor

Global Water WE550

2.3                                      Monitoring Locations

Monitoring locations ASR 9A and ASR 9C were set up at the proposed locations in Siu Ho Wan MTRC Depot in accordance with the Updated EM&A Manual.  However, approval for carrying out impact monitoring within MTRC Depot could not be obtained.  Air quality monitoring on 5 and 11 November 2013 was carried out just outside MTRC Depot at close proximity to the proposed locations, which was then temporarily relocated to the rooftop of Pak Mong Village Watch Tower (ASR 8) and Area 4 (ASR 8A).  Same baseline and Action Level for air quality, as derived from the baseline monitoring data recorded at Siu Ho Wan MTRC Depot, were adopted for these temporary air quality locations.

Figure 2.1 shows the locations of monitoring stations.  Table 2.2 describes the details of the monitoring stations.

Table 2.2        Locations of Impact Air Quality Monitoring Stations

Monitoring Dates

Monitoring Station

Location

Description

5, 11 November 2013

ASR 9A

Siu Ho Wan MTRC Depot

On ground near security office

ASR 9C

Siu Ho Wan MTRC Depot

On ground near staff canteen

15, 21, 27 November 2013

ASR 8

Pak Mong Village Watch Tower

Rooftop of the premise

ASR 8A

Area 4

On ground at the Area 4

 

2.4                                      Monitoring Parameters, Frequency and Duration

Table 2.3 summarized the monitoring parameters, frequency and duration of impact TSP monitoring.

Table 2.3        Air Quality Monitoring Parameters, Frequency and Duration

Parameter

Frequency and Duration

1-hour TSP

Three times every 6 days while the highest dust impact was expected

24-hour TSP

Once every 6 days

 

2.5                                      Monitoring methodology

High Volume Sampler

(a)       The HVS was installed in the vicinity of the air sensitive receivers.  The following criteria were considered in the installation of the HVS:

¡P         A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.

¡P         The distance between the HVS and an obstacle, such as buildings, was at least twice the height that the obstacle protrudes above the sampler.

¡P         A minimum of 2m of separation from walls, parapets and penthouses was required for rooftop samples.

¡P         A minimum of 2m separation from any supporting structure, measured horizontally was required.

¡P         No furnaces or incineration flues were nearby.

¡P         Airflow around the sampler was unrestricted.

¡P         The samplers were more than 20m from the drip line.

¡P         Any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring.

¡P         Permission must be obtained to set up the samples and to obtain access to the monitoring stations.

¡P         A secured supply of electricity is needed to operate the samplers.

¡P         No two samplers should be placed less than 2 m apart.

 

(b)       Preparation of Filter Papers

¡P           Filter papers of size 8¡¨x 10¡¨ that were clean and without pinholes were selected. 

¡P           All filter papers were conditioned in a humidity controlled chamber for over 24-hour and be pre-weighed before use for sampling.

¡P           All filter papers were prepared and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality assurance and quality control programmes.

 

(c)       Field Monitoring

¡P           The power supply was checked to ensure the HVS works properly.

¡P           The filter holder and the area surrounding the filter were cleaned.

¡P           The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.

¡P           The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.

¡P           The swing bolts were fastened to hold the filter holder down to the frame.  The pressure applied was sufficient to avoid air leakage at the edges.

¡P           Then the shelter lid was closed and was secured with the aluminum strip.

¡P           The HVS was warmed up for about 5 minutes to establish run-temperature conditions.

¡P           A new flow rate record sheet was set into the flow recorder.

¡P           On site temperature and atmospheric pressure readings were taken and the flow rate of the HVS was checked and adjusted at around 1.1 m3/min, and complied with the range specified in the Updated EM&A Manual (i.e. 0.6 ¡V 1.7 m3/min).

¡P           The programmable digital timer was set for a sampling period of 1 hour or 24 hours, and the starting time, weather condition and the filter number were recorded.

¡P           The initial elapsed time was recorded.

¡P           At the end of sampling, on site temperature and atmospheric pressure readings were taken and the final flow rate of the HVS was checked and recorded.

¡P           The final elapsed time was recorded.

¡P           The sampled filter was removed carefully and folded in half-length so that only surfaces with collected particulate matter were in contact.

¡P           It was then placed in a clean plastic envelop and sealed.

¡P           All monitoring information was recorded on a standard data sheet.

¡P           Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.

(d)       Maintenance and Calibration

¡P           The HVS and its accessories were maintained.  Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working condition.

¡P           All HVS were calibrated (five point calibration) using Calibration Kit prior to the commencement of the baseline monitoring and thereafter at bi-monthly intervals.

Dust Meter

(a)       The measuring procedures of the 1-hour dust meter followed the Manufacturer¡¦s Instruction Manual as presented below:

¡P           Turn the power on

¡P           Close the air collecting opening cover.

¡P           Push the ¡§TIME SETTING¡¨ switch to [BG].

¡P           Push the ¡§START/STOP¡¨ switch to perform background measurement for 6 seconds.

¡P           Turn the knob at SENSI ADJ position to insert the light scattering plate.

¡P           Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨ is indicated in the display.

¡P           Push ¡§START/STOP¡¨ switch to perform automatic sensitivity adjustment.  This measurement takes 1 minute.

¡P           Pull out the knob and return it to MEASURE position.

¡P           Push the ¡§TIME SETTING¡¨ switch the time set in the display to 3 hours.

¡P           Lower down the air collection opening cover.

¡P           Push ¡§START/STOP¡¨ switch to start measurement.

 

(b)     Maintenance and Calibration

 

¡P           The 1-hour TSP meter was calibrated at 1-year interval against a continuous particulate TEOM Monitor.  Calibration certificates of the Laser Dust Monitors are provided in Appendix E.

¡P           1-hour validation checking of the TSP meter against HVS is carried out on half-year basis at the air quality monitoring locations.

2.6                                      Monitoring Schedule for the Reporting Month

The schedule for air quality monitoring in the reporting period is provided in Appendix F.

2.7                                      Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.4 and 2.5 respectively.  Detailed impact air quality monitoring results are presented in Appendix G.

Table 2.4        Summary of 1-hour TSP Monitoring Results in the Reporting Period

 

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

ASR 9A (ASR 8A)

101.5

60 - 182

394

500

ASR 9C (ASR 8)

102

63 - 156

393

500

 

Table 2.5        Summary of 24-hour TSP Monitoring Results in the Reporting Period

 

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

ASR 9A (ASR 8A)

69.2

52 - 91

178

260

ASR 9C (ASR 8)

82.6

65 - 121

178

260

The major dust source in the reporting period included construction activities under the Contract as well as nearby traffic emissions.

All 1-hour and 24-hour TSP results were below the Action and Limit level at all monitoring locations in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix L.

Meteorological information collected from the wind station, including wind speed and wind direction, is provided in Appendix H.

 

3                                             nOISE MONITORING

3.1                                      Monitoring Requirements

In accordance with the Updated EM&A Manual, impact noise monitoring was conducted once per week during the construction phase of the Contract.  The Action and Limit level of the noise monitoring is provided in Appendix D.

3.2                                      Monitoring Equipment

Noise monitoring was performed using sound level meter at each designated monitoring station.  The sound level meters deployed comply with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meters at a known sound pressure level.  Brand and model of the equipment is provided in Table 3.1.

Table 3.1        Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-31

Acoustic Calibrator

Rion NC-73

3.3                                      Monitoring Locations

Monitoring location was set up at NSR 1 in accordance with the Updated EM&A Manual.  Figure 3.1 shows the location of the monitoring station.  Table 3.2 describes the details of the monitoring station.

Table 3.2        Location of Impact Noise Monitoring Station

Monitoring Station

Location

Description

NSR 1

Pak Mong Village Watch Tower

Rooftop of the premise

3.4                                      Monitoring Parameters, Frequency and Duration

Table 3.3 summarizes the monitoring parameters, frequency and duration of impact noise monitoring.

Table 3.3        Noise Monitoring Parameters, Frequency and Duration

Parameter

Frequency and Duration

30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

At least once per week

3.5                                      Monitoring Methodology

Monitoring Procedures

¡P      The microphone head of the sound level meter was positioned 1m exterior of the noise sensitive facade and lowered sufficiently so that the building¡¦s external wall acts as a reflecting surface. 

¡P      The battery condition was checked to ensure the correct functioning of the meter.

¡P      Parameters were set as follows:

Ø   frequency weighting: A

Ø   time weighting: Fast

Ø   time measurement: Leq(30 min.) dB(A) (as six consecutive Leq, 5min readings) during non-restricted hours (i.e. 0700-1900 hrs on normal weekdays)

¡P      Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94.0 dB at 1000 Hz.  If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

¡P      During the monitoring period, the Leq, L90 and L10 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

¡P      Noise measurement was paused temporarily during periods of high intrusive noise (eg dog barking, helicopter noise) if possible and observation was recorded when intrusive noise was not avoided.

¡P      Noise monitoring was cancelled in the presence of fog, rain and wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10 m/s.  The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

Maintenance and Calibration

¡P      The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

¡P      The meter and calibrator were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.

¡P      Calibration certificates of the sound level meters and acoustic calibrators are provided in Appendix E.

3.6                                      Monitoring Schedule for the Reporting Month

The schedule for construction noise monitoring in the reporting period is provide in Appendix F.

3.7                                      Monitoring Results

Results for noise monitoring are summarized in Table 3.4 and the monitoring data is provided in Appendix I.

Table 3.4        Summary of Construction Noise Monitoring Results in the Reporting Period

 

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

NSR 1

57

56 - 59

75

 

No noise Action Level and Limit level exceedance was recorded at all monitoring stations in the reporting month.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix L.

Major noise sources during the noise monitoring included construction activities, nearby traffic noise and aircraft noise.

4                                             Water Quality MOnitoring

4.1                                      Monitoring Requirements

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period in accordance with the Updated EM&A Manual.  The Action and Limit Level of the water quality monitoring is provided in Appendix D.

4.2                                      Monitoring equipment

Table 4.1 summarises the equipment used in the impact water quality monitoring programme.

Table 4.1        Water Quality Monitoring Equipment

Equipment

Brand and Model

DO, Temperature meter and Salinity

YSI Pro2030

 

 

Turbidimeter

HACH Model 2100Q

 

pH meter   

HANNA HI8314

 

Positioning Equipment

Koden913MK2 with KBG-3 DGPS antenna

 

Water Depth Detector

Speedtech Instrument SM-5

 

Water Sampler

Kemmerer 1520 (1520-C25) 2.2L with messenger

4.3                                      Monitoring Parameters, Frequency and Duration

Table 4.2 summarizes the monitoring parameters, frequency and monitoring depths of impact water quality monitoring as required in the Updated EM&A Manual.

Table 4.2        Water Quality Monitoring Parameters and Frequency

Monitoring Stations

Parameters, unit

Frequency

Depth

Impact Stations:

IS(Mf)9

IS(Mf)16

IS8

 

Sensitive Receivers:

SR4

SR4a

 

Control Stations:

CS(Mf)3

CS(Mf)5

Ÿ Temperature(¢XC)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

Ÿ SS (mg/L)

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides (within ¡Ó1.75 hour of the predicted time) during the construction period of the Contract

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.

 

 

 

If the water depth is

less than 3m, mid-depth

sampling only.

 

 

 

If water depth less

than 6m, mid-depth

may be omitted.

4.4                                      Monitoring Locations

The locations of the monitoring stations under the Contract are shown in Figure 4.1 and detailed in Table 4.3.

Table 4.3        Locations of Impact Water Quality Monitoring Stations

Station ID

Type

Coordinates

 

 

Easting

Northing

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

SR4

Sensitive receiver (Tai Ho Inlet)

814760

817867

SR4a

Sensitive receiver

815247

818067

CS(Mf)3

Control Station

809989

821117

CS(Mf)5

Control Station

817990

821129

Notes:
DO = Dissolved Oxygen
SS = Suspended Solid

4.5                                      Monitoring methodology

4.5.1                               Instrumentation

The in-situ water quality parameters, i.e. dissolved oxygen, temperature and salinity were measured by multi-parameter Water Quality System (Model YSI Pro2030).

Turbidity and pH were measured by HACH Model 2100Q and HANNAH HI8314, respectively.

4.5.2                               Operating/ Analytical Procedures

Digital Differential Global Positioning Systems (DGPS) were used to ensure that the correct location was selected prior to sample collection.

Portable, battery-operated echo sounders were used for the determination of water depth at each designated monitoring station.

All in-situ measurements were taken at 3 water depths, 1 m below water surface, mid-depth and 1 m above sea bed, except where the water depth was less than 6 m, for which the mid-depth station was omitted.  Should the water depth be less than 3 m, only the mid-depth station was monitored.

At each sampling depth, two consecutive in-situ measurements (DO concentration and saturation, temperature, turbidity, pH and salinity) and water samples for SS were taken.  The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement.  Where the difference in the value between the first and second readings of DO or turbidity parameters was more than 25% of the value of the first reading, the reading was discarded and further readings were taken.

Duplicate samples were collected at each sampling depth for SS measurement in the laboratory.  Water samples were collected using the water samplers and the samples were stored in high-density polythene bottles.  Water samples collected were well-mixed in the water sampler prior to pre-rinsing and transferring to sample bottles.  Samples bottles were pre-rinsed with the same water samples.  The sample bottles were then packed in cool-boxes (cooled at 4¢XC) without being frozen) and delivered to ALS Technichem (HK) Pty Ltd. for the analysis of SS concentrations.  The laboratory determination work would be started within 24 hours after collection of the water samples.  ALS Technichem (HK) Pty Ltd. is a HOKLAS accredited laboratory and has comprehensive QA/QC programme.  For QA/QC procedures, one sample of every batch of 20 samples was analyzed.

The analysis method and reporting and detection limit for SS is shown in Table 4.4.

Table 4.4        Laboratory Analysis for Suspended Solids

Parameters

Instrumentation

Analytical Method

Reporting Limit

Detection Limit

Suspended Solid (SS)

Weighing

APHA 2540-D

0.5 mg/L

0.5 mg/L

 

Other relevant data were recorded, including monitoring location/ position, time, water depth, tidal stages, weather conditions and any special phenomena or work underway at the construction site in the field log sheet for information.

4.5.3                               Maintenance and Calibration

 

All in situ monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS or other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes were checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter was carried out before measurement at each monitoring event.

 

For the on-site calibration of field equipment (Multi-parameter Water Quality System), the BS 1427:2009, "Guide to on-site test methods for the analysis of waters" was observed.  Copies of the calibration certificates are attached in Appendix E.

4.6                                      Monitoring Schedule for the Reporting Month

The schedule for water quality monitoring in November 2013 is provided in Appendix F.

4.7                                      Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting month.  Impact water quality monitoring results and graphical presentations are provided in Appendix J.

Exceedances of the Action Levels of the depth-averaged SS was observed at SR4a during mid-ebb tide on 26 November 2013.  It is considered that the exceedance of depth-averaged SS level at SR4a during mid-ebb tide on 26 November 2013 was likely due to sediment disturbance caused by water sampler touching seabed, contributing to an exceedance in SS for water sampled at bottom water depth.  Thus, the observed SS exceedance was not considered to be project-related and not of environmental concern.

Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan, as provided in Appendix L should be carried out.

5                                             Dolphin monitoring

5.1                                      monitoring requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  Dolphin monitoring works by line transect methodology is required to carry out in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD¡¦s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort. 

5.2                                      monitoring equipment

Table 5.1 summarises the equipment used for the impact dolphin monitoring.

Table 5.1        Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

5.3                                      Monitoring Parameter, Frequencies and Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

5.4                                      Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 5.1.  The co-ordinates of all transect lines are shown in Table 5.2 below.

Table 5.2        Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

 

Line No.

Easting

Northing

1

Start Point

804671

814577

 

13

Start Point

816506

819480

1

End Point

804671

831404

 

13

End Point

816506

824859

2

Start Point

805475

815457

 

14

Start Point

817537

820220

2

End Point

805477

826654

 

14

End Point

817537

824613

3

Start Point

806464

819435

 

15

Start Point

818568

820735

3

End Point

806464

822911

 

15

End Point

818568

824433

4

Start Point

807518

819771

 

16

Start Point

819532

821420

4

End Point

807518

829230

 

16

End Point

819532

824209

5

Start Point

808504

820220

 

17

Start Point

820451

822125

5

End Point

808504

828602

 

17

End Point

820451

823671

6

Start Point

809490

820466

 

18

Start Point

821504

822371

6

End Point

809490

825352

 

18

End Point

821504

823761

7

Start Point

810499

820690

 

19

Start Point

822513

823268

7

End Point

810499

824613

 

19

End Point

822513

824321

8

Start Point

811508

820847

 

20

Start Point

823477

823402

8

End Point

811508

824254

 

20

End Point

823477

824613

9

Start Point

812516

820892

 

21

Start Point

805476

827081

9

End Point

812516

824254

 

21

End Point

805476

830562

10

Start Point

813525

820872

 

22

Start Point

806464

824033

10

End Point

813525

824657

 

22

End Point

806464

829598

11

Start Point

814556

818449

 

23

Start Point

814559

821739

11

End Point

814556

820992

 

23

End Point

814559

824768

12

Start Point

815542

818807

 

 

 

 

 

12

End Point

815542

824882

 

 

 

 

 

5.5                                      Monitoring Schedule for the Reporting Month

Dolphin monitoring was carried out on 1, 5, 8 and 13 November 2013.  The dolphin monitoring schedule for the reporting period is shown in Appendix F.

5.6                                      Results and Observations

Vessel-based Line-transect Survey

A total of 268.17 km of survey effort was collected, with 100% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility) during the November¡¦s surveys.  Amongst the two areas, 98.97 km and 169.20 km of survey effort were collected from NEL and NWL survey areas, respectively.  The total survey effort conducted on primary and secondary lines were 211.85 km and 56.32 km respectively.  The survey efforts are summarized in Appendix K.

A total of twenty-one groups of 102 Chinese White Dolphin sightings were recorded during the two surveys.  All sightings were made in NWL during the two sets of surveys in November, with no sightings made at all in NEL.  All except one were on-effort sightings, and 18 of these on-effort sightings were made on primary lines.  None of the dolphin groups was associated with operating fishing vessels.  

None of the 21 sightings was made in the proximity of this Project.  The distribution of dolphin sightings during the reporting month is shown in Figure 5.2.

Encounter rates of Chinese White Dolphins are deduced from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below) in November 2013 with the results presented in Tables 5.3 and 5.4.

Table 5.3        Individual Survey Event Encounter Rates

 

 

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

 

 

Primary Lines Only

Primary Lines Only

NEL

Set 1: Nov 1st/5th

0.0

0.0

 

Set 2: Nov 8th/13th

0.0

0.0

NWL

Set 1: Nov 1st/5th

10.3

50.0

 

Set 2: Nov 8th/13th

16.1

76.1

Table 5.4        Monthly Average Encounter Rates

 

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary   Lines Only

Both Primary and Secondary Lines

Primary   Lines Only

Both Primary and Secondary Lines

Northeast Lantau

0.0

0.0

0.0

0.0

Northwest Lantau

13.2

11.2

63.1

53.2

Note: Overall dolphin encounter rates (sightings per 100km of survey effort) from all four surveys are conducted in November 2013 on primary lines only as well as both primary lines and secondary lines in Northeast and Northwest Lantau

The average group size of Chinese White Dolphins in November 2013 was 4.86 individuals per group.  Twelve dolphin groups were composed of only 1-4 animals, while the other nine were larger groups with 5-11 animals per group.

Photo-identification Work

During dolphin monitoring in November 2013, 58 individual dolphins were identified and a majority of them were only sighted once in the reporting month (Appendices III and IV).  Seven (7) individuals were sighted twice and four (4) others were sighted 3-4 times during the two sets of surveys.

Five (5) well-recognized females, including NL33, NL88, NL93, NL98 and NL123 were accompanied with their calves during their re-sightings.

During this month of dolphin monitoring, no adverse impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations

Due to monthly variation in dolphin occurrence within the Study area, it would be more appropriate to draw conclusion on whether any impacts on dolphins have been detected related to the construction activities of the TM-CLKL Southern Connection Viaduct Section in the quarterly EM&A reports, where comparison on distribution, group size and encounter rates of dolphins between the quarterly impact monitoring period and baseline monitoring period will be made.

Taking into account of natural seasonal change in distribution patterns, which is also observed in baseline monitoring, it is suggested that a longer period of impact monitoring data should be obtained for comparison.

The Event Action Plan is provided in Appendix L.

6                                             Bore piling monitoring

6.1                                      Monitoring Requirements

Bore piling monitoring comprised land-based theodolite tracking, underwater noise monitoring and acoustic behavioural monitoring.  Such monitoring is undertaken by qualified dolphin specialist, who has sufficient relevant post-graduate experience and publication in the respective aspects.

6.2                                   Monitoring Frequencies

Table 6.1 summarizes the monitoring frequency of the bore piling monitoring as required in the Updated EM&A Manual.  The impact phase bored piling monitoring has not been carried out in the reporting month since no bored piling works were scheduled to be undertaken.

Table 6.1        Bore Piling Monitoring Frequency

 

Monitoring Frequency

Land-based Theodolite Tracking

As a minimum, 30 days before, 30 days during and 30 days after the bore piling works.

 

Underwater Noise Monitoring and Acoustic Behavioural Monitoring

30 days before and 30 days during the construction phase of the bore piling activities

coustic Behavioural Monitoring0 days during and 30 days after the bore piling works.ng as required in the Updated EM&A Manual.

6.3                                      Monitoring Location

Table 6.2 summarizes the monitoring locations for bore piling monitoring.

Table 6.2        Bore Piling Monitoring Locations

Monitoring Component

Monitoring Locations

Land-based Theodolite Tracking

Pak Mong Station (Figure 6.1)

 

Underwater Noise Monitoring

Pier No. B1, B2, B3, B4, B5, and B6 (Figure 6.2)

 

Acoustic Behavioural Monitoring

Dipping Hydrophone

 

 

 

 

 

 

 

Ecological Acoustics Recorders (EARs)

 

Predefined route in Northeast Lantau (overlapped with TM-CLKL alignment) and part of Northwest Lantau (Control Site) (Figure 6.3)

 

Site C1 (within 500m of TM-CLKL alignment) and Site C2 (Control Site between Sha Chau and Lung Kwu Chau) (Figure 6.3)

 

 

 

6.4                                      Monitoring Methodology

Land-based Theodolite Tracking

The methodology of the present monitoring programme generally follows the one established under the Piwetz et al. 2012 ([1]) study, which is also part of the AFCD long-term marine mammal monitoring programme (ung 2012, 2013)([2])([3])  .  On each survey day, observers will search systematically for Chinese white dolphins using the unaided eye and handheld binoculars (7 x 50) from the Pak Mong Station, overlooking the viaduct alignment to the northeast coast of Lantau Island, in particular the area around the six bored pile sites.  Notably, all six bored piling sites were monitored during baseline phase, while three of these six sites will be chosen for construction phase and post-construction phase monitoring when the initial phase of the construction schedule is confirmed.

A theodolite tracking session will be initiated when an individual dolphin or group of dolphins is located, and focal follow methods will be used to track the dolphins.  Within a group, a focal individual will be selected for the purposes of tracking the behaviour and movement of the group, based on its distinctive feature such as colouration or severe injury mark.  The focal individual will then be tracked continuously via the theodolite, with positions recorded whenever the dolphin surfaces.  If an individual cannot be positively distinguished from other members, the group will be tracked by recording positions based on a central point within the group when the dolphins surface. 

Tracking will continue until animals are lost from view, move beyond the range of reliable visibility (>5 km), or when environmental conditions obstructed visibility (e.g. intense haze).  Behavioural state data will also be recorded every 5 minutes for the focal individual or group.  This interval is long enough to allow for determination of the behavioural state, and short enough to capture behavioural responses to the bored piling activities.  Moreover, when multiple groups or individuals are present in the study area, attempts will be made to record the behaviours of all groups/individuals every 10 minutes, with spotters assisting in determining behaviour of the dolphins. 

Positions of dolphins, boats and construction activities will be measured using a Sokkisha DT5 digital theodolite with ¡Ó 5-sec precision and 30-power magnification connected to a laptop computer running the program Pythagoras Version 1.2 (Gailey and Ortega-Ortiz 2002)?as bee intervals), while it wasring mid-ebb tidemid-onfirmed that no marine works were being carried out when exceedance of dep([4]) .  This program calculates a real-time conversion of horizontal and vertical angles collected by the theodolite into geographic positions of latitude and longitude each time a fix is initiated.  Pythagoras also displays positions, movements, and distances in real-time.  When possible, the position of the focal dolphin will be recorded at every surfacing with use of Pythagoras.  The position, type, and activity of all vessels within 5 km of the focal dolphin will also be recorded.  An effort will be made to obtain at least several positions for each vessel, and additional positions will be acquired when vessels changed course or speed. 

While the primary source of human disturbance to dolphins of interest in this study is bored piling works for the TM-CLKL Project, the presence of vessels may also have an effect on the behaviour and movement patterns of dolphins.  Prior to the construction phase (i.e. baseline phase), the simultaneous tracking of dolphins and boats over time provides information on the speed and orientation of dolphins, as well as their movements in relation to vessel activities.  Other construction activities and vessel movements in relation to the bored piling works will be recorded during the construction phase monitoring, and the same theodolite tracking and behavioural procedures will be followed as during baseline phase.

Underwater Noise Monitoring Study using Dipping Hydrophone

The underwater sound recording system consists of a high-sensitivity, high-bandwidth hydrophone (International Transducer Corporation ITC-6050c) and two-channel audio recorder (Sound Devices 702T).  The hydrophone will be deployed from the stern of the research vessel, a deployment scheme sometimes referred to as a ¡§dipping hydrophone¡¨, approximately mid-water column at a depth of 5 m beneath a 2 m spar buoy.  The hydrophone cable is faired to streamline water flow around the cable, reducing pseudonoise and eliminating cable vibration.  The vessel will ¡§go quiet¡¨ (its engine, generator, bilge pump, and depth sounder turned off) and drift for the duration of each recording.  The recording system and deployment method generally follow that of another well-established study of underwater sounds in Hong Kong waters (Würsig and Greene 2002)([5]) .

The ITC-6050c is a wide-band hydrophone with a built-in, low-noise preamplifier for optimum noise performance.  Its nominal operating band is 30 Hz to 70 kHz, and its self-noise level is well below Knudsen Sea State 0 up to 20 kHz.  The hydrophone signal will be amplified as needed via a postamplifier with user-selectable gains from 0 to 60 dB in 10 dB increments. The audio recorder will be configured to sample 16-bit data received on each of its two channels at a rate of 192 kHz, thus allowing analysis of the acoustic data up to 96 kHz.  According to Section 6.4.5 of the EM&A Manual, ¡§the acoustic results of the monitoring should be analyzed in terms of both the broadband range (100 Hz to 25.6 kHz) and, also, the dolphin sensitive range (400 Hz to 12.6 kHz).¡¨  The acoustic data collected from the present underwater noise study was analyzed between 100 Hz and 50 kHz, in compliance with the EM&A Manual requirement.

Observers will log document the recording date, start and end times, hydrophone and water depths, Beaufort sea state, survey area, and postamplifier gain in each recording.  Wind speed, often directly correlated with underwater levels, will be measured and documented in the survey team¡¦s logs.  The wind speed measurements will be performed with a handheld Kestrel 1000 anemometer, containing an impeller with precision axle and low-friction bearings, providing 0.1 m/s resolution between 0.6¡V40.0 m/s and an accuracy (calculated using two standard deviations) of the larger of 3% of the reading, least significant digit, or 0.1 m/s.

Dolphin Acoustic Behavioural Study using Dipping Hydrophone

During dedicated acoustic surveys, the survey team of 2-3 HKCRP researchers will conduct systematic search for dolphins within the study area.  The survey protocol to search for dolphins is similar to the line-transect survey methodology adopted in the vessel survey under the AFCD long-term marine mammal monitoring programme (Hung 2012, 2013)([6])([7])   as well as various HZMB EM&A dolphin monitoring programmes.  For each survey, a 15-m inboard vessel with an open upper deck will be used to make observations from the flying bridge area, at a visual height of 4-5 m above water surface.  The two observers searched with unaided eyes and 7 x 50 marine binoculars ahead of the vessel (between 270o and 90o in relation to the bow, which is defined as 0o). The survey team will record effort data including time, position (latitude and longitude), weather conditions (Beaufort sea state and visibility), and distance travelled in each series (a continuous period of search effort) with the assistance of a handheld GPS.

When dolphins are sighted, the survey team will end the search effort, and the research vessel will be diverted from its course to slowly approach the animals for group size estimation, assessment of group composition, and behavioural observations in the initial 5-10 minutes.  The dipping hydrophone will then be deployed 3 to 7 metres below the sea surface by 2-metre long spar buoy from the stern of the research vessel, with vessel engine noise off and the vessel drifting.  Broadband dolphin recordings will be made with the same set of underwater sound recording system as mentioned in Section 2.3.1 (see previous paragraph for detailed description).  According to Section 6.4.5 of the EM&A Manual, ¡§the acoustic results of the monitoring should be analyzed in terms of both the broadband range (100 Hz to 25.6 kHz) and, also, the dolphin sensitive range (400 Hz to 12.6 kHz).¡¨  Dolphin acoustic data collected from the recording system will be analyzed from 100 Hz and up to 40 kHz, which avoided a hydrophone resonance frequency at 50 kHz.  This range would be sufficient to detect the presence of dolphin acoustic signals and their temporal parameters (e.g. click intervals), while it is also in compliance with the EM&A Manual requirement.

During the dipping hydrophone deployment, the date, start and end times, hydrophone and water depths, Beaufort sea state, survey area, locations, gain, event, and notes will be taken for each recording in five-minute intervals.  Within each corresponding five-minute interval, observers will also note variables including the group size, group composition and general behaviour during the 5-minute period (i.e. feeding, socializing, travelling, resting, milling and any aerial activity).  The number of vessels that passed within 500 m of the dolphin group will also be recorded during the same 5-minute interval, with special notes on close approaches by vessels within 100 m of dolphins, including the time of closest approach and any behavioural reaction being noted.  Distances of vessels will be gathered by hand-held laser rangefinder (Bushnell Yardage Pro 800; maximum range of detection for most objects: 720 metres; ranging accuracy ¡Ó 2 metres under most circumstances).  Also, notes will be made on the approximate distance (i.e. 0-250m, 250-500m, >500 m) of the dolphin groups to the hydrophone during the 5-minute interval.  Notably, positions of dolphin group will be recorded continuously during the entire focal follow session to examine their movements in detail, especially when they occur in the vicinity of the TM-CLKL alignment.

Passive Acoustic Monitoring using Ecological Acoustic Recorders

Two sets of EARs will be deployed at two sites in North Lantau, one near the bored piling site and another at a control site between Sha Chau and Lung Kwu Chau.  The EARs will be deployed and recovered by a professional dive team from Oceanway Corporation Limited.  During each deployment, the EAR serial number, as well as the time and date of deployment will be recorded.  Moreover, the GPS position, water depth and type of substrate at the deployment location will also be recorded.

The EARs will be programmed to record on a 20% duty cycle (1 minute ¡§on¡¨ for every 5 minutes).  Recordings will be from approximately 20 Hz at the low end to 32 kHz at the high end, which effectively covered a major part of the acoustic channel of the Chinese White Dolphins (Sims et al. 2011)([8]) .  Data from the EARs was downloaded onto a computer hard disk at the end of the baseline monitoring period, and will then be re-deployed at the same location before the start of bored piling works until the study is completed at the end of the 30 days of construction phase monitoring.

 

7                                             Environmental site inspection and audit

7.1                                      Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  In the reporting month, four (4) site inspections were carried out on 6, 13, 20 and 27 November 2013.

Particular observations during the site inspections are described below:

Air Quality

The Contractor was reminded to implement dust suppression measures more frequently, especially on water spraying at Area 5.

Noise

No adverse observation was identified in the reporting month.

Water Quality

The Contractor was recommended to set up an appropriate wastewater treatment system in the work site.

Marine Ecology

Pre-translocation survey at Yam Tsai Wan was conducted on 19 October 2013 and the subsequent coral translocation and audit survey was carried out at Tai Ho Wan and Yam Tsai Wan on 24 October 2013.  The post-translocation monitoring is scheduled in January 2014. 

Daily 250 m marine mammal exclusion zone monitoring was undertaken within the reporting month.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis were recorded in November 2013 during the exclusion zone monitoring.  In addition, acoustic decoupling monitoring and marine vessel control were implemented in this reporting month.

Chemical and Waste Management

The drip tray stopper was found missing for one of the generators in Area 5 which was then being rectified in timely-manner.

Landscape and Visual Impact

No adverse observation was identified in the reporting month.

Miscellaneous

The Environmental Permit was displayed at the site entrance. 

The Contractor has rectified most of the observations as identified during environmental site inspection in the reporting month.  Rectifications of remaining identified items are undertaken by the Contractor.  Follow-up inspections on the status on provision of mitigation measures will be conducted to ensure all identified items are mitigated properly.

7.2                                      Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

As advised by the Contractor, 560 m3 of inert C&D Materials are generated and disposed of in the reporting period and 37 m3 of inert C&D Materials are disposed of as public fill.  22.05 tonnes of general refuse were generated and disposed of in the reporting period.  Monthly summary of waste flow table is detailed in Appendix M.

The Contractor is advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor is reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

The Contractor is reminded that chemical waste containers should be properly treated and stored temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

7.3                                      Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 7.1 below.


Table 7.1        Summary of Environmental Licensing and Permit Status

Statutory Reference

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

EIAO

Environmental Permit

EP-354/2009/A

8 Dec 2010

NA

HyD

Tuen Mun- Chek Lap Kok Link

 

NCO

Construction Dust Notification

361571

5 Jul 2013

NA

GCL

-

NCO

Construction Dust Notification

 

362093

17 Jul 2013

NA

GCL

Areas 2 and 3

WDO

Chemical Waste Registration

5213-961-G2380-13

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Chemical Waste Registration

5213-961-G2380-14

10 Oct 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Chemical Waste Registration

5213-974-G2588-03

4 Nov 2013

NA

GCL

Chemical waste produced in Contract HY/2012/07

 

WDO

Construction Waste Disposal Account

7017735

10 Jul 2013

NA

GCL

Waste disposal in Contract HY/2012/07

WPCO

Waste Water Discharge License

Nil

Application in process

NA

GCL

Discharge of Construction Runoff

NCO

Construction Noise Permit

Nil

Application in process

NA

GCL

For Piling Works

NCO

Construction Noise Permit

GW-RW0660-13

27 Sep 2013

02 Feb 2014

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1129-13

31 Oct 2013

30 Apr 2014

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1186-13

23 Oct 2013

24 Dec 2013

GCL

For night works and works in general holidays

 

NCO

Construction Noise Permit

GW-RS1187-13

24 Oct 2013

28 Feb 2014

GCL

For night

7.4                                      Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

7.5                                      Summary of Exceedances of the Environmental Quality Performance Limit

Results for 1-hour and 24-hour TSP monitoring and construction noise monitoring complied with the Action/ Limit levels in the reporting period.  One (1) exceedance of Action Level for depth-averaged SS at SR4a was recorded in the reporting month.  The exceedances were considered not related to the construction works of this Contract after further investigation.

Cumulative statistics on exceedances is provided in Appendix N.

7.6                                      Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 7.1.

One (1) complaint was referred by EPD to various parties of the HZMB projects on 12 November 2013 regarding the noise nuisance arising from the operation or towing of barges by tug boats during restricted hours, particularly during the period from 23:00 to 07:00 of next day by HZMB Projects in the waters outside Tung Chung New Development Pier and near the barging point of CEDD¡¦s construction site of Site Formation at Tung Chung Areas 53 and 54.

With reference to the Contractor¡¦s site dairy of 12 November 2013, no site activity after 18:00 was undertaken on the concerned day.  Thus, the noise complaint was considered as non-project related.

No notification of summons and prosecution was received in the reporting period.

Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix N.

8                                             Future Key Issues

8.1                                      Construction Programme for the Coming Months

As informed by the Contractor, the major works for the Contract in December 2013 and January 2014 will be:

Marine Works

¡P      GI works at marine piers;

¡P      Filling Platform at seawall; and

¡P      Marine foundation at Viaduct E2, E5-8 and E13.

Land-based Works

¡P      Additional GI fieldwork, Lab testing and permitting;

¡P      Fence relocation at Viaduct A, C and D; and

¡P      Site offices erection at Area 2, Area 3, Area 5 and seawall.

8.2                                      Key Issues for the Coming Month

Potential environmental impacts arising from the above upcoming construction activities in the next reporting month of December 2013 are mainly associated with dust, noise, marine water quality, marine ecology and waste management issues.

8.3                                      Monitoring Schedule for the Coming Month

The tentative schedule for environmental monitoring in December 2013 is provided in Appendix F.

 

9                                             Conclusions and recommendations

9.1                                      Conclusions

The construction phase of the TM-CLKL Southern Connection Viaduct Section and the associated impact phase EM&A programme of the Project commenced on 31 October 2013.

1-hour TSP, 24-hour TSP, noise, water quality and dolphin monitoring were carried out in the reporting period.

Exceedance of Action Levels for depth-averaged SS level was recorded in one monitoring event in this reporting month.  The review of monitoring data and works activities undertaken suggested that no marine works were being undertaken when exceedance was recorded and that construction activities have been proceeded in an environmentally acceptable manner.

Results for noise and air quality monitoring complied with the Action/ Limit levels in the reporting period.

A total of twenty-one dolphin s sighting were recorded during the two surveys.  All sightings were made in NWL during the two sets of surveys with no sightings made at all in NEL in November 2013.  None of the 21 sightings was made in the proximity of the TM-CLKL Southern Connection Viaduct Section.  During this reporting period of dolphin monitoring, no adverse impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations.

Environmental site inspection was carried out four (4) times in November 2013.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

One (1) environmental complaint regarding noise nuisance was followed up and was considered to be not related to the Contract works.

9.2                                      Recommendations

According to the environmental site inspections performed in the reporting month, the following recommendations were provided:

Air Quality Impact

¡P      All working plants and vessels on site should be regularly inspected and properly maintained by the Contractor to avoid dark smoke emission.

¡P      Open stockpiles should be properly covered by the Contractor.

¡P      The Contractor should provide water spraying to suppress fugitive dust for any dusty construction activity.

Construction Noise Impact

¡P      Vessels and equipment operating should be checked regularly and properly maintained by the Contractor.

Water Quality Impact

¡P      The Contractor should regularly review and maintain drainage systems to make sure they are functioning effectively.

¡P      Proper drainage channels, bunds and set-up should be provided by the Contractor at the site to collect/ intercept the surface run-off or waste water generated from works area to ensure no direct discharge from site to surrounding water bodies.

Chemical and Waste Management

¡P      All types of wastes should be collected and sorted accordingly and removed timely by the Contractor.  They should be properly stored in designated areas within the works areas temporarily.

¡P      All plants and vehicles on site should be properly maintained by the Contractor to prevent oil leakage.

¡P      All drain holes of the drip trays within the works areas should be properly plugged by the Contractor to avoid any oil and chemical waste leakage.

¡P      Oil stains on soil surface should be cleared and disposed of as chemical waste by the Contractor.

Marine Mammal Exclusion Zone Monitoring

¡P      Daily 250 m marine mammal exclusion zone monitoring was undertaken during the period in which marine works were being undertaken.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis were recorded in November 2013 during the exclusion zone monitoring.


 



([1]) Piwetz, S., Hung, S. K., Wang J. Y., Lundquist, D. and Würsig, B.  2012.  Influence of vessel traffic on movements of Indo-Pacific humpback dolphins (Sousa chinensis) off Lantau Island, Hong Kong.  Aquatic Mammals 38: 325-331.

([2]) Hung, S. K.  2012 Monitoring of Marine Mammals in Hong Kong waters: final report 2011-12). An unpublished report submitted to the Agriculture, Fisheries and Conservation Department, 171 pp.?as bee intervals), while it wasring mid-ebb tidemid-onfirmed that no marine works were being carried out when exceedance of dep

([3]) Hung, S. K.  2013.  Monitoring of Marine Mammals in Hong Kong waters: final report (2012-13). An unpublished report submitted to the Agriculture, Fisheries and Conservation Department, 168 pp.

([4]) Gailey, G. A. and Ortega-Ortiz J.  2002.  A note on a computer-based system for theodolite tracking of cetaceans. Journal of Cetacean Research and Management 4: 213-218

([5]) Würsig, B. and Greene, C. R., Jr.  2002.  Underwater sounds near a fuel receiving facility in western Hong Kong: relevance to dolphins.  Marine Environmental Research 54: 129¡V145

([6]) Hung, S. K.  2012.  Monitoring of Marine Mammals in Hong Kong waters: final report

(2011-12).  An unpublished report submitted to the Agriculture, Fisheries and Conservation Department, 171 pp.

([7]) Hung, S. K.  2013.  Monitoring of Marine Mammals in Hong Kong waters: final report

(2012-13).  An unpublished report submitted to the Agriculture, Fisheries and Conservation Department, 168 pp

([8]) Sims, P. Q., Vaughn, R., Hung, S. K. and Würsig, B.  2011.  Sounds of Indo-Pacific humpback dolphins (Sousa chinensis) in West Hong Kong: A preliminary description.  Journal of the Acoustical Society of America, EL48-EL53 (doi: 10.1121/1.3663281).